A roof sound insulation board hoisting system and hoisting method for assembled sound barrier
By combining column top frame beams and connecting steel beam mechanisms with door-type hanging frame mechanisms in the roof sound insulation plate lifting system with fully enclosed sound barriers, the problems of large lifting radius and high tonnage in the existing technology are solved, and efficient lifting and construction efficiency of roof sound insulation plates are achieved.
Patent Information
- Application Number
- CN202510025077.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-08
- Publication Date
- 2025-03-18
- Estimated Expiration
- 2045-01-08
AI Technical Summary
When constructing roof sound barriers, the hoisting radius is too large and the tonnage requirements are high, resulting in high construction costs and difficult to meet construction conditions.
The column top frame beam and the connecting steel beam mechanism are used to form a sliding track that is compatible with the door-type hanging frame mechanism. The multiple sets of alternately telescopic support legs of the door-type hanging frame mechanism can be adjusted staggered, so that the door-type hanging frame mechanism can move across the beam, and improve the lifting efficiency of the roof sound insulation plate.
It realizes efficient lifting of roof sound insulation panels, reduces the demand for construction to occupy railway line space, reduces construction costs and material usage, and improves construction efficiency.
Smart Images

Figure CN119429983B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of assembled sound barrier construction, and in particular to a roof sound insulation board hoisting system and a hoisting method for an assembled sound barrier. Background Art
[0002] Fully enclosed sound barriers are an environmental protection facility used to reduce railway noise, especially in high-speed railways and elevated roads. Fully enclosed sound barriers significantly reduce noise transmission through their structural design. Compared with traditional upright sound barriers, fully enclosed sound barriers can more effectively reduce the impact of noise on the surrounding environment, especially for sensitive areas along the line such as schools and hospitals.
[0003] As an advanced noise reduction measure, fully enclosed sound barriers not only effectively reduce the impact of railway noise on the surrounding environment, but also show significant advantages in ecological protection and wind load bearing. With the continuous advancement of technology and the promotion of its application, fully enclosed sound barriers will play an important role in more fields in the future and contribute to the construction of a more harmonious environment.
[0004] However, the existing fully enclosed sound barriers have the following problems when constructing roof sound insulation panels:
[0005] (1) When there is space under the roof sound insulation board for heavy cranes to move and hoist into place, heavy crane lifting is undoubtedly the most convenient and direct method. However, when hoisting sound insulation boards on the roof of the existing railway line, the space under the roof sound insulation board cannot be occupied, and the hoisting can only be carried out outside the sound barrier. At this time, the hoisting radius is particularly large, and the required crane tonnage is very large, which is not only expensive, but also has strict requirements on the construction space, and it is difficult to meet the construction conditions;
[0006] (2) Traditional jacking is generally just a simple high-altitude jacking of components, which requires a larger installation platform. The jacking direction must be hoisted in place before jacking can be achieved. When the lifting radius is too large, a light crane cannot be used. When the crane tonnage and lifting radius are too large, the lifting cost is too high, which is not economical and the construction conditions are difficult to meet.
[0007] Therefore, how to propose solutions to the above problems has become an urgent problem to be solved by those skilled in the art. Summary of the invention
[0008] The technical problem to be solved by the present invention is to overcome the deficiencies in the prior art and provide a system and method for hoisting a roof sound insulation board of an assembled sound barrier. The column top frame beam and the connecting steel beam mechanism of the present invention form a high and low staggered basic track that is compatible with the sliding of the portal hanger mechanism, and then the portal hanger mechanism is adjusted by multiple groups of alternately retracted supporting legs to achieve staggered movement, so that the portal hanger mechanism can move across the beam, thereby improving the hoisting efficiency of the roof sound insulation board. During the construction of the patent, the site does not need to occupy the space of the railway line, and the construction needs can be met according to the key points of the normal existing line, and there is no need to rigidly close the railway line, which has great promotion value.
[0009] The present invention is achieved through the following technical solutions:
[0010] A roof sound insulation board hoisting system of an assembled sound barrier, the assembled sound barrier comprises columns, sound insulation wall panels, column top frame beams, roof truss beams and roof sound insulation boards, the columns are symmetrically arranged on the left and right sides of a double-track railway, and the lower ends of the columns are fixedly connected to the foundation, the sound insulation wall panels are arranged on the outer side of the columns, the column top frame beams are fixedly connected to the upper ends of the columns, the lower side of the roof truss beams are connected to the column top frame beams, the roof sound insulation boards are fixedly laid on the upper surface of the roof truss beams, and the roof sound insulation board hoisting system is used for hoisting and constructing the roof sound insulation boards, and comprises a door-type hanger mechanism, a connecting steel beam mechanism and a jacking mechanism, wherein;
[0011] The gantry hanger mechanism includes two groups of symmetrically arranged gantry units, multiple groups of transverse support beams arranged in the vertical direction of the track, and multiple groups of sliding lifting assemblies. The gantry unit includes a longitudinal support beam arranged along the track and multiple groups of alternately telescopic support legs. The transverse support beam is vertically fixedly connected to the longitudinal support beam, the upper end of the support leg is vertically fixedly connected to the end of the longitudinal support beam, the lower end of the support leg is against the column top frame beam or the connecting steel beam mechanism, and the lower end of the support leg moves along the upper surface of the column top frame beam or the connecting steel beam mechanism, the sliding lifting assembly is slidably connected to the transverse support beam, and the sliding lifting assembly is used for hoisting and constructing the roof sound insulation board;
[0012] The connecting steel beam mechanism includes a plurality of connecting steel beam assemblies, which are fixedly arranged between two groups of roof beams, and the upper surface of the connecting steel beam assembly is provided with a guide rail unit adapted to the lower end of the supporting leg;
[0013] The jacking mechanism includes two sets of jacking assemblies symmetrically arranged on the column top frame beams, multiple sets of roof truss beams hoisted in place, roof sound insulation panels laid on the roof truss beams and multiple sets of connecting steel beam assemblies as a whole to form a jacking structure. The two sets of jacking assemblies cooperate to drive the jacking structure to the installation position.
[0014] It can be seen that in the above technical scheme, the column top frame beam and the connecting steel beam mechanism of the present invention form a high and low staggered basic track that is compatible with the sliding of the portal hanger mechanism, and then the multiple groups of alternately retractable supporting legs of the portal hanger mechanism are used to achieve staggered movement and adjustment, so that the portal hanger mechanism can move across the beam, thereby improving the hoisting efficiency of the roof sound insulation board; this patent includes multiple groups of transverse support beams arranged in the vertical direction of the track, so that multi-point bidirectional simultaneous lifting can be achieved, thereby improving the hoisting efficiency and meeting the requirements of short hoisting time for existing lines; during the construction of this patent, the site does not need to occupy the space of the railway line, and it is unnecessary to carry out large-area formwork structure support. The amount of turnover materials and the number of operating workers are small. The construction needs can be met by constructing according to the key points of the normal existing line, and there is no need to rigidly close the railway line.
[0015] According to the above technical solution, preferably, it also includes a push monitoring subsystem, which includes multiple groups of pressure sensors, signal transmitters, signal receivers, processing terminals and alarms, wherein;
[0016] The pressure sensor is arranged on the connecting steel beam assembly, and is used to sense the deformation of the connecting steel beam assembly to generate a deformation numerical variable, and send it to the signal receiver through the signal transmitter;
[0017] The signal receiver is electrically connected to the processing terminal, and a safety monitoring model is built into the processing terminal. When the fluctuation range of the deformation value variable exceeds a set threshold, an alarm signal is generated;
[0018] The alarm is electrically connected to the processing terminal, and the alarm sounds an alarm according to the alarm signal.
[0019] It can be seen that in the above technical solution, during normal jacking construction, the jacking assembly gradually applies pressure to the connecting steel beam assembly until the jacking structure begins to slide gradually. At this time, the connecting steel beam assembly gradually tends to a stable range. When there are structural changes in the jacking structure, the connecting steel beam assembly at this time will fluctuate accordingly. By setting up a safety monitoring model, the accuracy and timeliness of existing human eye observation can be effectively improved, which facilitates early adjustments and improves construction safety.
[0020] According to the above technical solution, preferably, the transverse support beam extends along the vertical track to the outside of the column, and the sliding lifting assembly can slide to the outside of the assembled sound barrier to hoist the roof sound insulation board.
[0021] It can be seen that in the above technical solution, the sliding lifting assembly can slide to the outside of the assembled sound barrier to hoist the roof sound insulation board, thereby greatly improving the hoisting efficiency.
[0022] According to the above technical solution, preferably, the sliding lifting assembly is an electric hoist or a hand hoist.
[0023] According to the above technical solution, preferably, the supporting legs are hydraulic telescopic columns or electric telescopic columns.
[0024] According to the above technical solution, preferably, the two ends of the connecting steel beam assembly are detachably fixedly connected to the side surfaces of the roof truss beam.
[0025] According to the above technical solution, preferably, the lower end of each group of supporting legs is provided with a roller and a driving motor that resists the guide rail unit, the roller is rotatably connected to the lower end of the supporting leg, the driving motor is externally fixed on the outside of the supporting leg, and the driving motor drives the roller to rotate.
[0026] The present invention also discloses a method for hoisting a roof sound insulation board of an assembled sound barrier, which adopts the above-mentioned roof sound insulation board hoisting system of the assembled sound barrier, and comprises the following steps:
[0027] Step 1, hoisting roof beams: in the hoisting construction area, hoist multiple groups of roof beams onto the column top frame beams, and the design spacing of adjacent roof beams is set to the space spacing of a single group of roof beams, and the ends of the roof beams are slidably connected to the column top frame beams;
[0028] Step 2, assembling the connecting steel beam mechanism: assembling the connecting steel beam assembly between adjacent roof truss beams, with both ends of the connecting steel beam assembly against the roof truss beam, and the lower end of the connecting steel beam assembly being slidably connected to the column top frame beam, at this time, multiple groups of connecting steel beam assemblies and multiple groups of roof truss beams form an integral structure that can be slidably connected to the column top frame beam;
[0029] Step 3, the portal hanger mechanism is adjusted to be directly above the roof beam on which the roof sound insulation board is to be hoisted: multiple groups of support legs of the portal unit move along the upper surface of the column top frame beam or the connecting steel beam mechanism, and the support legs are alternately telescopically adjusted, so that the portal hanger mechanism is adjusted to be directly above the roof beam on which the roof sound insulation board is to be hoisted;
[0030] Step 4, hoisting the roof sound insulation board onto the roof beam: the sliding lifting assembly hoists the roof sound insulation board, and the sliding lifting assembly drives the roof sound insulation board to slide along the transverse support beam until the hoisting of multiple groups of roof sound insulation boards is completed. At this time, the roof sound insulation board is not hoisted in the connecting steel beam assembly area. The multiple groups of roof beams hoisted in place, the roof sound insulation boards laid on the roof beams, and the multiple groups of connecting steel beam assemblies form a top-pushing structure as a whole;
[0031] Step 5, the gantry hanger mechanism is adjusted to leave the jacking structure: the support legs of the gantry unit are adjusted to be telescopic alternately, and the gantry hanger mechanism is translated along the column top frame beam, so that the gantry hanger mechanism is adjusted to leave the top of the jacking structure in step 4;
[0032] Step 6, jacking construction of jacking mechanism: two jacking components of the jacking mechanism are installed on the column top frame beam. At this time, the two jacking components cooperate to drive the jacking structure of step 4 to the installation position. At this time, a space spacing of a single set of roof truss beams is left between the two sets of jacking structures in place;
[0033] Step 7, the portal hanger mechanism is adjusted and moved to the top of the single set of roof beams reserved in step 6: the supporting legs of the portal unit are adjusted and extended alternately, and the portal hanger mechanism is translated along the column top frame beam, so that the portal hanger mechanism is adjusted and moved to the top of the single set of roof beams reserved in step 6;
[0034] Step 8: Hoist the roof sound insulation board: Use the sliding lifting assembly to hoist the roof sound insulation board so that both ends of the roof sound insulation board are fixed on the edge of the top-pushing structure to complete the hoisting construction of the roof sound insulation board.
[0035] The beneficial effects of the present invention are:
[0036] (1) The column top frame beam and the connecting steel beam mechanism of the present invention form a high and low staggered basic track that is compatible with the sliding of the portal hanger mechanism, and then the portal hanger mechanism can be staggered and adjusted through multiple groups of alternately retracted support legs, so that the portal hanger mechanism can move across the beam, thereby improving the hoisting efficiency of the roof sound insulation board;
[0037] (2) This patent includes multiple sets of transverse support beams arranged perpendicular to the rails, which can achieve multi-point bidirectional simultaneous lifting, thereby improving the lifting efficiency and meeting the requirement of short lifting time for existing lines;
[0038] (3) During the construction of this patent, there is no need to occupy the railway line space on site, and there is no need to carry out large-scale formwork structure support. The amount of turnover materials and the number of operating workers are small. The construction needs can be met by following the key points of the normal existing line, and there is no need to rigidly close the railway line. BRIEF DESCRIPTION OF THE DRAWINGS
[0039] Figure 1 It shows an isometric structural schematic diagram of an embodiment of the present invention when working;
[0040] Figure 2 It shows a front view schematic diagram of the structure when working according to an embodiment of the present invention;
[0041] Figure 3 It shows a schematic diagram of a top view of the structure when working according to an embodiment of the present invention;
[0042] Figure 4 A logical schematic diagram of a push monitoring subsystem according to an embodiment of the present invention is shown;
[0043] Description of reference numerals:
[0044] 1. Column; 2. Sound insulation wall panel; 3. Column top frame beam; 4. Roof truss beam; 5. Roof sound insulation board; 6. Door-type hanger mechanism; 7. Connecting steel beam mechanism; 8. Connecting steel beam assembly; 9. Door frame unit; 10. Transverse support beam; 11. Sliding lifting assembly; 12. Longitudinal support beam; 13. Support leg. DETAILED DESCRIPTION
[0045] In order to enable those skilled in the art to better understand the technical solution of the present invention, the present invention is further described in detail below in conjunction with the accompanying drawings and the best embodiment. Based on the embodiments in the invention, all other embodiments obtained by ordinary technicians in the field without making creative work are within the scope of protection of the invention.
[0046] In the description of the invention, it should be noted that the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside" and "outside" etc. indicating directions or positional relationships are based on the directions or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, they cannot be understood as limitations on the invention.
[0047] Example 1
[0048] As shown in the figure, the present invention provides a roof sound insulation board hoisting system of an assembled sound barrier, the assembled sound barrier comprises a column 1, a sound insulation wallboard 2, a column top frame beam 3, a roof truss beam 4 and a roof sound insulation board 5, the column 1 is symmetrically arranged on the left and right sides of the double-track railway, and the lower end of the column 1 is fixedly connected to the foundation, the sound insulation wallboard 2 is arranged on the outer side of the column 1, the column top frame beam 3 is fixedly connected to the upper end of the column 1, the lower side of the roof truss beam 4 is slidably connected to the column top frame beam 3, the roof sound insulation board 5 is fixedly laid on the upper surface of the roof truss beam 4, and the roof sound insulation board 5 hoisting system is used for hoisting and constructing the roof sound insulation board 5, including a door-type hanger mechanism 6, a connecting steel beam mechanism 7 and a jacking mechanism (not shown in the figure), wherein;
[0049] The gantry hanger mechanism 6 includes two groups of symmetrically arranged gantry units 9, multiple groups of transverse support beams 10 arranged in the vertical direction of the track, and multiple groups of sliding lifting components 11. The gantry unit 9 includes a longitudinal support beam 12 arranged along the track and multiple groups of alternately telescopic support legs 13. The gantry unit 9 of this embodiment includes four groups of alternately telescopic support legs 13, and two groups of support legs 13 are respectively provided on the front and rear sides of the longitudinal support beam 12. The transverse support beam 10 is vertically fixedly connected to the longitudinal support beam 12, and the upper end of the support leg 13 is vertically fixedly connected to the end of the longitudinal support beam 12, and the lower end of the support leg 13 is against the column top frame beam 3 or the connecting steel beam Mechanism 7, and the lower end of the supporting leg 13 moves along the upper surface of the column top frame beam 3 or the connecting steel beam mechanism 7. For safety reasons, an anti-overturning structure can be added to the lower side of the supporting leg 13. The sliding lifting component 11 is slidably connected to the transverse supporting beam 10. The sliding lifting component 11 is used to hoist the construction roof sound insulation board 5, and the sliding lifting component 11 is an electric hoist or a hand hoist. The supporting leg 13 is a hydraulic telescopic column or an electric telescopic column. The lower end of the supporting leg 13 is provided with a roller and a driving motor that resists the guide rail unit. The roller is rotatably connected to the lower end of the supporting leg. The driving motor can be externally arranged on the outside of the supporting leg 13, and the driving motor drives the roller to rotate.
[0050] The connecting steel beam mechanism 7 includes a plurality of connecting steel beam assemblies 8, which are fixedly arranged between two groups of roof beams 4, and the upper surface of the connecting steel beam assembly 8 is provided with a guide rail unit adapted to the lower end of the supporting leg 13;
[0051] The jacking mechanism includes two groups of jacking assemblies symmetrically arranged on the column top frame beam 3, multiple groups of roof truss beams 4 hoisted in place, roof sound insulation panels 5 laid on the roof truss beams 4, and multiple groups of connecting steel beam assemblies 8 as a whole constitute a jacking structure. The two groups of jacking assemblies cooperate to drive the jacking structure to the installation position. The jacking assemblies can use hydraulic cylinders.
[0052] The column top frame beam 3 and the connecting steel beam mechanism 7 of the present invention form a high and low staggered basic track that is compatible with the sliding of the portal hanger mechanism 6, and then the portal hanger mechanism 6 can be staggered and adjusted through multiple groups of alternately telescopic support legs 13, so that the portal hanger mechanism 6 can move across the beam, thereby improving the lifting efficiency of the roof sound insulation board 5; the patent includes multiple groups of transverse support beams 10 arranged in the vertical direction of the track, thereby realizing multi-point bidirectional simultaneous lifting, thereby improving the lifting efficiency and meeting the requirement of short lifting time for existing lines; during the construction of the patent, the site does not need to occupy the space of the railway line, and it is free from large-area formwork structure support, the amount of turnover materials and the number of operating workers are small, and the construction according to the normal existing line key points can meet the construction needs, and there is no need to rigidly close the railway line.
[0053] Optionally, in a possible implementation, it further includes a push monitoring subsystem, which includes multiple groups of pressure sensors, signal transmitters, signal receivers, processing terminals and alarms, wherein;
[0054] The pressure sensor is arranged on the connecting steel beam component 8, and is used to sense the deformation of the connecting steel beam component 8 to generate a deformation numerical variable, and send it to the signal receiver through the signal transmitter;
[0055] The signal receiver is electrically connected to the processing terminal, and a safety monitoring model is built into the processing terminal. When the fluctuation range of the deformation value variable exceeds a set threshold, an alarm signal is generated;
[0056] The alarm is electrically connected to the processing terminal, and the alarm sounds an alarm according to the alarm signal.
[0057] During normal jacking construction, the jacking assembly gradually applies pressure to the connecting steel beam assembly 8 until the jacking structure begins to slide gradually. At this time, the connecting steel beam assembly 8 gradually tends to a stable range. When there are structural changes in the jacking structure, the connecting steel beam assembly 8 at this time will fluctuate accordingly. By setting up a safety monitoring model, the accuracy and timeliness of existing human eye observation can be effectively improved, which facilitates early adjustments and improves construction safety.
[0058] Optionally, in a possible implementation, the transverse support beam 10 extends along the vertical track to the outside of the column 1, and the sliding lifting assembly 11 can slide to the outside of the assembled sound barrier to hoist the roof sound insulation board 5, thereby greatly improving the hoisting efficiency.
[0059] Optionally, in a possible implementation manner, both ends of the connecting steel beam assembly 8 are detachably fixedly connected to the side surfaces of the roof truss beam 4 .
[0060] Optionally, in a possible implementation, the hoisting system can also be used to hoist building components such as sound insulation wall panels to improve construction efficiency.
[0061] Example 2
[0062] The present invention also discloses a method for hoisting a roof sound insulation board of an assembled sound barrier, which adopts the hoisting system for the roof sound insulation board of the assembled sound barrier of the above-mentioned embodiment 1, and comprises the following steps:
[0063] Step 1, hoisting the roof beam 4: in the hoisting construction area, hoist multiple groups of roof beams 4 onto the column top frame beams 3, and the design spacing of adjacent roof beams 4 is set to the space spacing of a single group of roof beams 4, and the ends of the roof beams 4 are slidably connected to the column top frame beams 3;
[0064] Step 2, assembling the connecting steel beam mechanism 7: assembling the connecting steel beam assembly 8 between adjacent roof truss beams 4, with both ends of the connecting steel beam assembly 8 against the roof truss beam 4, and the lower end of the connecting steel beam assembly 8 being slidably connected to the column top frame beam 3, at this time, multiple groups of connecting steel beam assemblies 8 and multiple groups of roof truss beams 4 form an integral structure that can be slidably connected to the column top frame beam 3;
[0065] Step 3, the gantry hanger mechanism 6 is adjusted to be directly above the roof truss beam 4 on which the roof sound insulation board 5 is to be hoisted: the multiple groups of support legs 13 of the gantry unit 9 move along the column top frame beam 3 or the upper surface of the connecting steel beam mechanism 7, and the support legs 13 are alternately telescopically adjusted, so that the gantry hanger mechanism 6 is adjusted to be directly above the roof truss beam 4 on which the roof sound insulation board 5 is to be hoisted;
[0066] Step 4, hoisting the roof sound insulation board 5 onto the roof beam 4: after the door-type hanger mechanism 6 moves into place, the sliding lifting assembly 11 hoists the roof sound insulation board 5 again, and the sliding lifting assembly 11 drives the roof sound insulation board 5 to slide along the transverse support beam 10 until the hoisting of multiple groups of roof sound insulation boards 5 is completed. At this time, the roof sound insulation board 5 is not hoisted in the area of the connecting steel beam assembly 8. The multiple groups of roof beams 4 hoisted in place, the roof sound insulation boards 5 laid on the roof beams 4, and the multiple groups of connecting steel beam assemblies 8 form a top-pushing structure as a whole;
[0067] Step 5, the door-type hanger mechanism 6 is adjusted to leave the jacking structure: the support legs 13 of the door frame unit 9 are adjusted to be telescopic alternately, and the door-type hanger mechanism 6 is translated along the column top frame beam 3, so that the door-type hanger mechanism 6 is adjusted to leave the top of the jacking structure in step 4;
[0068] Step 6, jacking construction of the jacking mechanism: two sets of jacking components of the jacking mechanism are installed on the column top frame beam 3. At this time, the two sets of jacking components cooperate to drive the jacking structure of step 4 to the installation position. At this time, a space spacing of a single set of roof truss beams 4 is left between the two sets of jacking structures in place;
[0069] Step 7, the gantry hanger mechanism 6 is adjusted and moved to the top of the single set of roof beams 4 reserved in step 6: the support legs 13 of the gantry unit 9 are adjusted and extended alternately, and the gantry hanger mechanism 6 is translated along the column top frame beam 3, so that the gantry hanger mechanism 6 is adjusted and moved to the top of the single set of roof beams 4 reserved in step 6;
[0070] Step 8, hoisting the roof sound insulation board 5: the sliding lifting assembly 11 hoists the roof sound insulation board 5 so that both ends of the roof sound insulation board 5 are erected and fixed on the edge of the jacking structure, and the hoisting construction of the roof sound insulation board 5 is completed.
[0071] Obviously, the above embodiments are merely examples for the purpose of clear explanation, and are not intended to limit the implementation methods. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived therefrom are still within the scope of protection of the invention.
Claims
1. A roof sound insulation board hoisting system for an assembled sound barrier, characterized in that: The assembled sound barrier includes columns, sound insulation wall panels, column top frame beams, roof truss beams and roof sound insulation panels. The columns are symmetrically arranged on the left and right sides of the double-track railway, and the lower ends of the columns are fixedly connected to the foundation. The sound insulation wall panels are arranged on the outer side of the columns, the column top frame beams are fixedly connected to the upper ends of the columns, the lower side of the roof truss beams are connected to the column top frame beams, and the roof sound insulation panels are fixedly laid on the upper surface of the roof truss beams. The roof sound insulation panel hoisting system is used for hoisting and constructing the roof sound insulation panels, including a door-type hanger mechanism, a connecting steel beam mechanism and a jacking mechanism, wherein; The portal hanger mechanism includes two groups of portal units symmetrically arranged on the left and right, multiple groups of transverse support beams arranged in the vertical direction of the track, and multiple groups of sliding lifting assemblies. The portal unit includes a longitudinal support beam arranged along the track and multiple groups of alternately telescopic support legs. The transverse support beam is vertically fixedly connected to the longitudinal support beam, the upper end of the support leg is vertically fixedly connected to the end of the longitudinal support beam, the lower end of the support leg is against the column top frame beam or the connecting steel beam mechanism, and the lower end of the support leg moves along the upper surface of the column top frame beam or the connecting steel beam mechanism, the sliding lifting assembly is slidably connected to the transverse support beam, and the sliding lifting assembly is used for hoisting and constructing roof sound insulation panels; The connecting steel beam mechanism comprises a plurality of connecting steel beam assemblies, wherein the connecting steel beam assemblies are fixedly arranged between two groups of roof truss beams, and the upper surface of the connecting steel beam assemblies is provided with a guide rail unit adapted to the lower end of the supporting leg; The pushing mechanism includes two groups of pushing components symmetrically arranged on the column top frame beams, multiple groups of roof truss beams hoisted in place, roof sound insulation panels laid on the roof truss beams and multiple groups of connecting steel beam components as a whole to form a pushing structure, and the two groups of pushing components cooperate to drive the pushing structure to the installation position.
2. The roof sound insulation board hoisting system of the assembled sound barrier according to claim 1 is characterized in that: It also includes a push monitoring subsystem, which includes multiple groups of pressure sensors, signal transmitters, signal receivers, processing terminals and alarms, wherein; The pressure sensor is arranged on the connecting steel beam assembly, and is used to sense the deformation of the connecting steel beam assembly to generate a deformation numerical variable, and send it to the signal receiver through the signal transmitter; The signal receiver is electrically connected to the processing terminal, and a safety monitoring model is built into the processing terminal, which generates an alarm signal when the fluctuation range of the deformation numerical variable exceeds a set threshold; The alarm is electrically connected to the processing terminal, and the alarm sounds an alarm according to an alarm signal.
3. The roof sound insulation board hoisting system of the assembled sound barrier according to claim 1 is characterized in that: The transverse support beam extends along the vertical track to the outside of the column, and the sliding lifting assembly can slide to the outside of the assembled sound barrier to hoist the roof sound insulation board.
4. The roof sound insulation board hoisting system of the assembled sound barrier according to claim 1 is characterized in that: The sliding lifting component is an electric hoist or a hand chain hoist.
5. The roof sound insulation board hoisting system of the assembled sound barrier according to claim 1 is characterized in that: The supporting legs are hydraulic telescopic columns or electric telescopic columns.
6. The roof sound insulation board hoisting system of the assembled sound barrier according to claim 1 is characterized in that: The two ends of the connecting steel beam assembly are detachably fixedly connected to the side surfaces of the roof truss beam.
7. The roof sound insulation board hoisting system of the assembled sound barrier according to claim 1 is characterized in that: The lower end of each group of supporting legs is provided with a roller that abuts against the guide rail unit and a driving motor, the roller is rotatably connected to the lower end of the supporting leg, the driving motor is externally fixed on the outer side of the supporting leg, and the driving motor drives the roller to rotate.
8. A method for hoisting a roof sound insulation board of an assembled sound barrier, characterized in that: The roof sound insulation board hoisting system using the assembled sound barrier according to claim 1 comprises the following steps: Step 1, hoisting roof beams: in the hoisting construction area, hoist multiple groups of roof beams onto the column top frame beams, and the design spacing of adjacent roof beams is set to the space spacing of a single group of roof beams, and the ends of the roof beams are slidably connected to the column top frame beams; Step 2, assembling the connecting steel beam mechanism: assembling the connecting steel beam assembly between adjacent roof truss beams, with both ends of the connecting steel beam assembly against the roof truss beam, and the lower end of the connecting steel beam assembly being slidably connected to the column top frame beam, at this time, multiple groups of connecting steel beam assemblies and multiple groups of roof truss beams form an integral structure that can be slidably connected to the column top frame beam; Step 3, the portal hanger mechanism is adjusted to be directly above the roof beam on which the roof sound insulation board is to be hoisted: multiple groups of support legs of the portal unit move along the upper surface of the column top frame beam or the connecting steel beam mechanism, and the support legs are alternately telescopically adjusted, so that the portal hanger mechanism is adjusted to be directly above the roof beam on which the roof sound insulation board is to be hoisted; Step 4, hoisting the roof sound insulation board onto the roof beam: the sliding lifting assembly hoists the roof sound insulation board, and the sliding lifting assembly drives the roof sound insulation board to slide along the transverse support beam until the hoisting of multiple groups of roof sound insulation boards is completed. At this time, the roof sound insulation board is not hoisted in the connecting steel beam assembly area. The multiple groups of roof beams hoisted in place, the roof sound insulation boards laid on the roof beams, and the multiple groups of connecting steel beam assemblies form a top-pushing structure as a whole; Step 5, the gantry hanger mechanism is adjusted to leave the jacking structure: the support legs of the gantry unit are adjusted to be telescopic alternately, and the gantry hanger mechanism is translated along the column top frame beam, so that the gantry hanger mechanism is adjusted to leave the top of the jacking structure in step 4; Step 6, jacking construction of jacking mechanism: two jacking components of the jacking mechanism are installed on the column top frame beam. At this time, the two jacking components cooperate to drive the jacking structure of step 4 to the installation position. At this time, a space spacing of a single set of roof truss beams is left between the two sets of jacking structures in place; Step 7, the portal hanger mechanism is adjusted and moved to the top of the single set of roof beams reserved in step 6: the supporting legs of the portal unit are adjusted and extended alternately, and the portal hanger mechanism is translated along the column top frame beam, so that the portal hanger mechanism is adjusted and moved to the top of the single set of roof beams reserved in step 6; Step 8: Hoist the roof sound insulation board: Use the sliding lifting assembly to hoist the roof sound insulation board so that both ends of the roof sound insulation board are fixed on the edge of the top-pushing structure to complete the hoisting construction of the roof sound insulation board.
Citation Information
Patent Citations
Construction device and method for assembly type building
CN110498347A
Special device for integral lifting and mounting construction of prefabricated curtain wall and using method
CN112320606A