Post-tensioning method for prefabricating small box girder and construction method thereof
By using a straight second duct that forms an angle with the web in the post-tensioned precast small box girder, the problems of complex duct positioning and prestress loss in traditional precast small box girders are solved, achieving efficient construction and prestress durability, and reducing project costs.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- ROAD & BRIDGE INT CO LTD
- Filing Date
- 2024-12-09
- Publication Date
- 2026-05-29
AI Technical Summary
In traditional post-tensioned precast small box girders, the positioning of prestressed ducts in curved sections is complex, the construction accuracy requirements are high, the grouting is not dense, and the prestress loss is serious, which affects the structural performance and service life of the beam.
A straight second duct is set at a certain angle to the web, and the second prestressed tendon passes through the straight duct to reduce friction, simplify positioning, improve grouting quality, and reduce prestress loss.
It simplifies pipeline positioning, improves construction accuracy and production efficiency, ensures the durability of prestressing and the safety of beam structure, and saves project costs.