Development well budget optimization method and system

By screening and comparing the budget information of the drilling section and identifying and optimizing the limit items, the problem of rising drilling costs is solved, reasonable financial and time goals are achieved, and budget accuracy is enhanced.

CN119476539APending Publication Date: 2025-02-18CHINA PETROLEUM & CHEMICAL CORP +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310994323.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2023-08-08
Publication Date
2025-02-18

AI Technical Summary

Technical Problem

Due to the increasing costs in drilling operations, due to diversity, technical complexity, time pressure, strict safety and environmental regulation and uncertainty, it is difficult to set reasonable financial and time goals.

Method used

By obtaining the budget information of the well sections of the target development wells in different times, filtering out a variety of material budgets and duration estimates based on preset screening indicators, and comparing them with the predefined material budget distribution and duration estimate distribution. , identify the limits and conduct expert review and updates.

Benefits of technology

Accurate optimization of drilling costs has been achieved, reasonable financial and time goals have been set, which greatly enhances the accuracy of the budget and avoids cost and progress overspending.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119476539A_ABST
    Figure CN119476539A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of drilling engineering, and provides a budget optimization method and system for a development well. The method comprises the steps of obtaining well section budget information of a target development well at different opening times, and screening out multiple material budgets and multiple duration pre-estimates corresponding to the opening times from the well section budget information on the basis of a preset screening index; comparing each material budget / duration estimation with predetermined corresponding material budget distribution / duration estimation distribution to obtain a plurality of material budget comparison results / duration estimation comparison results; and if any one of the material budget comparison results / duration estimation comparison results indicates overrun, performing expert auditing, and updating the corresponding material budget distribution / duration estimation distribution based on the material budget / duration estimation corresponding to the overrun material budget comparison result / duration estimation comparison result under the condition that the expert auditing is passed. According to the embodiment of the invention, reasonable financial and time targets can be set, and the precision of budgeting is greatly improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present disclosure relates to the technical field of drilling engineering, and in particular to a budget optimization method and system for development wells. Background Art

[0002] The quality of drilling design is very important for the successful cost budget management of drilling projects, because it contains the two keys to drilling profitable wells, namely: minimizing drilling operation problems and maximizing operation progress. Therefore, a correct and appropriate drilling design will lead to lower-cost drilling. An important step in the design process is the well construction cost budget, which is an indispensable component of economic drilling and the main tool for controlling expenditures. The cost budget ensures that sufficient funds have been approved for drilling without a shortage of funds, or avoids idle funds to achieve the best allocation of financial resources. On the contrary, the cost budget, as the most direct value response data of the drilling design, can directly present the optimization of different parts of the drilling design. By comparing with the cost budget of other wells in the block, it can feedback the parts of the design that need to be optimized.

[0003] One of the major challenges facing drilling operations engineering and management today is preventing cost and schedule overruns. The nature of drilling operations, including the diversity of different tasks involved from well design to completion, the increasing complexity of the technologies used, time pressures, increasingly stringent regulations on safety and environmental requirements, and the huge uncertainty inherent in drilling operations, has led to rising costs and difficulty in setting reasonable financial and time targets. Summary of the invention

[0004] In view of this, the embodiments of the present disclosure provide a budget optimization method and system for development wells to address the problems in the prior art of the diversity of different operational tasks from drilling design to completion, the increasingly complex technologies used, time pressure, increasingly stringent supervision of safety and environmental requirements, and the huge uncertainty of drilling operations themselves, which lead to rising costs and difficulty in setting reasonable financial and time goals.

[0005] A first aspect of an embodiment of the present disclosure provides a method for optimizing a development well budget, comprising:

[0006] Obtain the well section budget information of the target development well at different openings, and select the various material budgets and various time estimates corresponding to each opening based on the preset screening indicators;

[0007] Comparing each material budget / duration estimate with a predetermined corresponding material budget distribution / duration estimate distribution to obtain a plurality of material budget comparison results / duration estimate comparison results, wherein the material budget distribution represents a corresponding relationship between the development depth and the budget, and the duration estimate distribution represents a corresponding relationship between the development depth and the construction duration;

[0008] If any of the material budget comparison results / duration estimate comparison results indicates an excess, an expert review is conducted on the material budget comparison result / duration estimate comparison result that exceeds the limit, and if the expert review is passed, the corresponding material budget distribution / duration estimate distribution is updated based on the material budget / duration estimate corresponding to the material budget comparison result / duration estimate comparison result that exceeds the limit.

[0009] In some embodiments, the step of determining the screening index comprises:

[0010] Obtaining benchmark budget data and benchmark construction duration of target development wells at each opening, wherein the benchmark budget data includes multiple benchmark fixed budgets and multiple benchmark variable budgets, and the benchmark construction duration includes multiple benchmark construction durations;

[0011] At least one target benchmark variable budget and target benchmark construction duration are selected in descending order, wherein the sum of the at least one target benchmark variable budget accounts for a proportion of the total budget that is not less than a preset first preset value, and the sum of the at least one target benchmark construction duration accounts for a proportion of the total construction duration that is not less than a preset second preset value;

[0012] The screening index is determined according to the at least one target benchmark variable budget and the target benchmark construction duration.

[0013] In some embodiments, the step of determining the material budget distribution / time estimate distribution includes:

[0014] Acquire multiple historical well section budget information, and screen out multiple historical material budgets and multiple historical duration estimates based on the screening index, each historical material budget / historical duration estimate including multiple historical data;

[0015] A probability distribution is made for each historical material budget / historical duration estimate, and based on the preset high ratio threshold and low ratio threshold, high threshold and low threshold corresponding to each historical material budget / historical duration estimate at different depths / times are generated to obtain the material budget distribution.

[0016] In some embodiments, the upper ratio threshold value ranges from 80% to 95%, and the lower ratio threshold value ranges from 5% to 20%.

[0017] In some embodiments, if any of the material budget comparison results / time estimate comparison results indicates an over-limit, expert review is performed on the over-limit material budget comparison results / time estimate comparison results, including:

[0018] If any of the material budget comparison results / duration estimate comparison results indicates that the lower threshold is exceeded, the corresponding material budget / duration estimate will be sent to the preset excess reduction processing port for corresponding expert review.

[0019] In some embodiments, if any of the material budget comparison results / time estimate comparison results indicates an over-limit, expert review is performed on the over-limit material budget comparison results / time estimate comparison results, including:

[0020] If any of the material budget comparison results / time estimate comparison results indicates that the high threshold is exceeded, determining whether the structure of the well section budget information is the same as the existing structure;

[0021] If they are different, determining whether the well section budget information is reduced, and if reduced, indicating passing;

[0022] If it has not been reduced, the corresponding material budget / duration estimate will be sent to the preset overbudget processing port for corresponding expert review.

[0023] In some embodiments, the method further comprises:

[0024] At every preset period, historical budget data of a type corresponding to the target development well in the previous period is obtained, and the material distribution interval and time distribution interval are updated according to the historical data.

[0025] In some embodiments, the method further comprises:

[0026] In response to the display instruction, the corresponding material budget / duration estimate and the material budget distribution / duration estimate distribution corresponding to the material budget / duration estimate are combined and displayed on the target display interface.

[0027] A second aspect of the embodiments of the present disclosure provides a budget optimization system for a development well, comprising:

[0028] The acquisition module is used to obtain the well section budget information of the target development well at different opening times, and select various material budgets and various time estimates corresponding to each opening time based on the preset screening indicators;

[0029] A comparison module is used to compare each material budget / duration estimate with a predetermined corresponding material budget distribution / duration estimate distribution to obtain a plurality of material budget comparison results / duration estimate comparison results, wherein the material budget distribution represents the corresponding relationship between the development depth and the budget, and the duration estimate distribution represents the corresponding relationship between the development depth and the construction duration;

[0030] The over-limit processing module is used to conduct expert review on the material budget comparison result / duration estimate comparison result that exceeds the limit if any of the material budget comparison results / duration estimate comparison results indicates an over-limit, and if the expert review is passed, update the corresponding material budget distribution / duration estimate distribution based on the material budget / duration estimate corresponding to the material budget comparison result / duration estimate comparison result that exceeds the limit.

[0031] In some embodiments, the step of determining the screening index comprises:

[0032] Obtaining benchmark budget data and benchmark construction duration of target development wells at each opening, wherein the benchmark budget data includes multiple benchmark fixed budgets and multiple benchmark variable budgets, and the benchmark construction duration includes multiple benchmark construction durations;

[0033] At least one target benchmark variable budget and target benchmark construction duration are selected in descending order, wherein the sum of the at least one target benchmark variable budget accounts for a proportion of the total budget that is not less than a preset first preset value, and the sum of the at least one target benchmark construction duration accounts for a proportion of the total construction duration that is not less than a preset second preset value;

[0034] The screening index is determined according to the at least one target benchmark variable budget and the target benchmark construction duration.

[0035] In some embodiments, the step of determining the material budget distribution / time estimate distribution includes:

[0036] Acquire multiple historical well section budget information, and screen out multiple historical material budgets and multiple historical duration estimates based on the screening index, each historical material budget / historical duration estimate including multiple historical data;

[0037] A probability distribution is made for each historical material budget / historical duration estimate, and based on the preset high ratio threshold and low ratio threshold, high threshold and low threshold corresponding to each historical material budget / historical duration estimate at different depths / times are generated to obtain the material budget distribution.

[0038] In some embodiments, the upper ratio threshold value ranges from 80% to 95%, and the lower ratio threshold value ranges from 5% to 20%.

[0039] In some embodiments, if any of the material budget comparison results / time estimate comparison results indicates an over-limit, expert review is performed on the over-limit material budget comparison results / time estimate comparison results, including:

[0040] If any of the material budget comparison results / duration estimate comparison results indicates that the lower threshold is exceeded, the corresponding material budget / duration estimate will be sent to the preset excess reduction processing port for corresponding expert review.

[0041] In some embodiments, if any of the material budget comparison results / time estimate comparison results indicates an over-limit, expert review is performed on the over-limit material budget comparison results / time estimate comparison results, including:

[0042] If any of the material budget comparison results / time estimate comparison results indicates that the high threshold is exceeded, determining whether the structure of the well section budget information is the same as the existing structure;

[0043] If they are different, determining whether the well section budget information is reduced, and if reduced, indicating passing;

[0044] If it has not been reduced, the corresponding material budget / duration estimate will be sent to the preset overbudget processing port for corresponding expert review.

[0045] In some embodiments, the system further comprises:

[0046] The updating module is used to obtain historical budget data of a type corresponding to the target development well in the previous cycle every preset period, and update the material distribution interval and time distribution interval according to the historical data.

[0047] In some embodiments, the system further comprises:

[0048] The display module is used to respond to the display instruction and display the corresponding material budget / duration estimate and the material budget distribution / duration estimate distribution corresponding to the material budget / duration estimate in combination on the target display interface.

[0049] According to a third aspect of the embodiments of the present disclosure, an electronic device is provided, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the steps implemented when the processor executes the computer program include:

[0050] Obtain the well section budget information of the target development well at different openings, and select the various material budgets and various time estimates corresponding to each opening based on the preset screening indicators;

[0051] Comparing each material budget / duration estimate with a predetermined corresponding material budget distribution / duration estimate distribution to obtain a plurality of material budget comparison results / duration estimate comparison results, wherein the material budget distribution represents a corresponding relationship between the development depth and the budget, and the duration estimate distribution represents a corresponding relationship between the development depth and the construction duration;

[0052] If any of the material budget comparison results / duration estimate comparison results indicates an excess, an expert review is conducted on the material budget comparison result / duration estimate comparison result that exceeds the limit, and if the expert review is passed, the corresponding material budget distribution / duration estimate distribution is updated based on the material budget / duration estimate corresponding to the material budget comparison result / duration estimate comparison result that exceeds the limit.

[0053] In some embodiments, the step of determining the screening index comprises:

[0054] Obtaining benchmark budget data and benchmark construction duration of target development wells at each opening, wherein the benchmark budget data includes multiple benchmark fixed budgets and multiple benchmark variable budgets, and the benchmark construction duration includes multiple benchmark construction durations;

[0055] At least one target benchmark variable budget and target benchmark construction duration are selected in descending order, wherein the sum of the at least one target benchmark variable budget accounts for a proportion of the total budget that is not less than a preset first preset value, and the sum of the at least one target benchmark construction duration accounts for a proportion of the total construction duration that is not less than a preset second preset value;

[0056] The screening index is determined according to the at least one target benchmark variable budget and the target benchmark construction duration.

[0057] In some embodiments, the step of determining the material budget distribution / time estimate distribution includes:

[0058] Acquire multiple historical well section budget information, and screen out multiple historical material budgets and multiple historical duration estimates based on the screening index, each historical material budget / historical duration estimate including multiple historical data;

[0059] A probability distribution is made for each historical material budget / historical duration estimate, and based on the preset high ratio threshold and low ratio threshold, high threshold and low threshold corresponding to each historical material budget / historical duration estimate at different depths / times are generated to obtain the material budget distribution.

[0060] In some embodiments, the upper ratio threshold value ranges from 80% to 95%, and the lower ratio threshold value ranges from 5% to 20%.

[0061] In some embodiments, if any of the material budget comparison results / time estimate comparison results indicates an over-limit, expert review is performed on the over-limit material budget comparison results / time estimate comparison results, including:

[0062] If any of the material budget comparison results / duration estimate comparison results indicates that the lower threshold is exceeded, the corresponding material budget / duration estimate will be sent to the preset excess reduction processing port for corresponding expert review.

[0063] In some embodiments, if any of the material budget comparison results / time estimate comparison results indicates an over-limit, expert review is performed on the over-limit material budget comparison results / time estimate comparison results, including:

[0064] If any of the material budget comparison results / time estimate comparison results indicates that the high threshold is exceeded, determining whether the structure of the well section budget information is the same as the existing structure;

[0065] If they are different, determining whether the well section budget information is reduced, and if reduced, indicating passing;

[0066] If it has not been reduced, the corresponding material budget / duration estimate will be sent to the preset overbudget processing port for corresponding expert review.

[0067] In some embodiments, the method further comprises:

[0068] At every preset period, historical budget data of a type corresponding to the target development well in the previous period is obtained, and the material distribution interval and time distribution interval are updated according to the historical data.

[0069] In some embodiments, the method further comprises:

[0070] In response to the display instruction, the corresponding material budget / duration estimate and the material budget distribution / duration estimate distribution corresponding to the material budget / duration estimate are combined and displayed on the target display interface.

[0071] In a fourth aspect of the embodiments of the present disclosure, a computer-readable storage medium is provided, wherein the computer-readable storage medium stores a computer program, and the steps implemented when the computer program is executed by a processor include:

[0072] Obtain the well section budget information of the target development well at different openings, and select the various material budgets and various time estimates corresponding to each opening based on the preset screening indicators;

[0073] Comparing each material budget / duration estimate with a predetermined corresponding material budget distribution / duration estimate distribution to obtain a plurality of material budget comparison results / duration estimate comparison results, wherein the material budget distribution represents a corresponding relationship between the development depth and the budget, and the duration estimate distribution represents a corresponding relationship between the development depth and the construction duration;

[0074] If any of the material budget comparison results / duration estimate comparison results indicates an excess, an expert review is conducted on the material budget comparison result / duration estimate comparison result that exceeds the limit, and if the expert review is passed, the corresponding material budget distribution / duration estimate distribution is updated based on the material budget / duration estimate corresponding to the material budget comparison result / duration estimate comparison result that exceeds the limit.

[0075] In some embodiments, the step of determining the screening index comprises:

[0076] Obtaining benchmark budget data and benchmark construction duration of target development wells at each opening, wherein the benchmark budget data includes multiple benchmark fixed budgets and multiple benchmark variable budgets, and the benchmark construction duration includes multiple benchmark construction durations;

[0077] At least one target benchmark variable budget and target benchmark construction duration are selected in descending order, wherein the sum of the at least one target benchmark variable budget accounts for a proportion of the total budget that is not less than a preset first preset value, and the sum of the at least one target benchmark construction duration accounts for a proportion of the total construction duration that is not less than a preset second preset value;

[0078] The screening index is determined according to the at least one target benchmark variable budget and the target benchmark construction duration.

[0079] In some embodiments, the step of determining the material budget distribution / time estimate distribution includes:

[0080] Acquire multiple historical well section budget information, and screen out multiple historical material budgets and multiple historical duration estimates based on the screening index, each historical material budget / historical duration estimate including multiple historical data;

[0081] A probability distribution is made for each historical material budget / historical duration estimate, and based on the preset high ratio threshold and low ratio threshold, high threshold and low threshold corresponding to each historical material budget / historical duration estimate at different depths / times are generated to obtain the material budget distribution.

[0082] In some embodiments, the upper ratio threshold value ranges from 80% to 95%, and the lower ratio threshold value ranges from 5% to 20%.

[0083] In some embodiments, if any of the material budget comparison results / time estimate comparison results indicates an over-limit, expert review is performed on the over-limit material budget comparison results / time estimate comparison results, including:

[0084] If any of the material budget comparison results / duration estimate comparison results indicates that the lower threshold is exceeded, the corresponding material budget / duration estimate will be sent to the preset excess reduction processing port for corresponding expert review.

[0085] In some embodiments, if any of the material budget comparison results / time estimate comparison results indicates an over-limit, expert review is performed on the over-limit material budget comparison results / time estimate comparison results, including:

[0086] If any of the material budget comparison results / time estimate comparison results indicates that the high threshold is exceeded, determining whether the structure of the well section budget information is the same as the existing structure;

[0087] If they are different, determining whether the well section budget information is reduced, and if reduced, indicating passing;

[0088] If it has not been reduced, the corresponding material budget / duration estimate will be sent to the preset overbudget processing port for corresponding expert review.

[0089] In some embodiments, the method further comprises:

[0090] At every preset period, historical budget data of a type corresponding to the target development well in the previous period is obtained, and the material distribution interval and time distribution interval are updated according to the historical data.

[0091] In some embodiments, the method further comprises:

[0092] In response to the display instruction, the corresponding material budget / duration estimate and the material budget distribution / duration estimate distribution corresponding to the material budget / duration estimate are combined and displayed on the target display interface.

[0093] In a fifth aspect of the embodiments of the present disclosure, a computer program product is provided. The computer program product includes a computer program or an instruction. When the computer program or the instruction is executed by a processor, the steps implemented include:

[0094] Obtain the well section budget information of the target development well at different openings, and select the various material budgets and various time estimates corresponding to each opening based on the preset screening indicators;

[0095] Comparing each material budget / duration estimate with a predetermined corresponding material budget distribution / duration estimate distribution to obtain a plurality of material budget comparison results / duration estimate comparison results, wherein the material budget distribution represents a corresponding relationship between the development depth and the budget, and the duration estimate distribution represents a corresponding relationship between the development depth and the construction duration;

[0096] If any of the material budget comparison results / duration estimate comparison results indicates an excess, an expert review is conducted on the material budget comparison result / duration estimate comparison result that exceeds the limit, and if the expert review is passed, the corresponding material budget distribution / duration estimate distribution is updated based on the material budget / duration estimate corresponding to the material budget comparison result / duration estimate comparison result that exceeds the limit.

[0097] In some embodiments, the step of determining the screening index comprises:

[0098] Obtaining benchmark budget data and benchmark construction duration of target development wells at each opening, wherein the benchmark budget data includes multiple benchmark fixed budgets and multiple benchmark variable budgets, and the benchmark construction duration includes multiple benchmark construction durations;

[0099] At least one target benchmark variable budget and target benchmark construction duration are selected in descending order, wherein the sum of the at least one target benchmark variable budget accounts for a proportion of the total budget that is not less than a preset first preset value, and the sum of the at least one target benchmark construction duration accounts for a proportion of the total construction duration that is not less than a preset second preset value;

[0100] The screening index is determined according to the at least one target benchmark variable budget and the target benchmark construction duration.

[0101] In some embodiments, the step of determining the material budget distribution / time estimate distribution includes:

[0102] Acquire multiple historical well section budget information, and screen out multiple historical material budgets and multiple historical duration estimates based on the screening index, each historical material budget / historical duration estimate including multiple historical data;

[0103] A probability distribution is made for each historical material budget / historical duration estimate, and based on the preset high ratio threshold and low ratio threshold, high threshold and low threshold corresponding to each historical material budget / historical duration estimate at different depths / times are generated to obtain the material budget distribution.

[0104] In some embodiments, the upper ratio threshold value ranges from 80% to 95%, and the lower ratio threshold value ranges from 5% to 20%.

[0105] In some embodiments, if any of the material budget comparison results / time estimate comparison results indicates an over-limit, expert review is performed on the over-limit material budget comparison results / time estimate comparison results, including:

[0106] If any of the material budget comparison results / duration estimate comparison results indicates that the lower threshold is exceeded, the corresponding material budget / duration estimate will be sent to the preset excess reduction processing port for corresponding expert review.

[0107] In some embodiments, if any of the material budget comparison results / time estimate comparison results indicates an over-limit, expert review is performed on the over-limit material budget comparison results / time estimate comparison results, including:

[0108] If any of the material budget comparison results / time estimate comparison results indicates that the high threshold is exceeded, determining whether the structure of the well section budget information is the same as the existing structure;

[0109] If they are different, determining whether the well section budget information is reduced, and if reduced, indicating passing;

[0110] If it has not been reduced, the corresponding material budget / duration estimate will be sent to the preset overbudget processing port for corresponding expert review.

[0111] In some embodiments, the method further comprises:

[0112] At every preset period, historical budget data of a type corresponding to the target development well in the previous period is obtained, and the material distribution interval and time distribution interval are updated according to the historical data.

[0113] In some embodiments, the method further comprises:

[0114] In response to the display instruction, the corresponding material budget / duration estimate and the material budget distribution / duration estimate distribution corresponding to the material budget / duration estimate are combined and displayed on the target display interface.

[0115] Obtain the budget information of the target development well at each different opening, and select multiple material budgets and multiple time estimates corresponding to each opening based on preset screening indicators; compare each material budget / time estimate with the corresponding predetermined material budget distribution / time estimate distribution to obtain multiple material budget comparison results / time estimate comparison results; if any of the material budget comparison results / time estimate comparison results indicates an over-limit, conduct an expert review, and if the expert review is passed, update the corresponding material budget distribution / time estimate distribution, so that reasonable financial and time goals can be set, greatly enhancing the accuracy of the budget. BRIEF DESCRIPTION OF THE DRAWINGS

[0116] In order to more clearly illustrate the technical solutions in the embodiments of the present disclosure, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only for the embodiments, and ordinary technicians in this field can obtain other drawings based on these drawings without paying any creative work.

[0117] Figure 1 It is a schematic diagram of an application scenario of the budget optimization method for development wells provided in accordance with an embodiment of the present disclosure;

[0118] Figure 2 is a flowchart of some embodiments of a method for optimizing a development well budget provided according to an embodiment of the present disclosure;

[0119] Figure 3 is a flow chart of some other embodiments of another method for optimizing the budget of a development well provided according to an embodiment of the present disclosure;

[0120] Figure 4 It is a simplified structural schematic diagram of a budget optimization system for a development well provided according to an embodiment of the present disclosure;

[0121] Figure 5 is a schematic diagram of an electronic device provided according to an embodiment of the present disclosure;

[0122] Figure 6 It is a schematic diagram of casing casing budget and casing budget distribution provided according to an embodiment of the present disclosure. DETAILED DESCRIPTION

[0123] Embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. Although certain embodiments of the present disclosure are shown in the accompanying drawings, it should be understood that the present disclosure can be implemented in various forms and should not be construed as being limited to the embodiments set forth herein. On the contrary, these embodiments are provided to provide a more thorough and complete understanding of the present disclosure. It should be understood that the drawings and embodiments of the present disclosure are only for exemplary purposes and are not intended to limit the scope of protection of the present disclosure.

[0124] It should also be noted that, for ease of description, only the parts related to the present disclosure are shown in the drawings. In the absence of conflict, the embodiments and features in the embodiments of the present disclosure can be combined with each other.

[0125] It should be noted that the concepts such as "first" and "second" mentioned in the present disclosure are only used to distinguish different systems, devices, modules or units, and are not used to limit the order or interdependence of the functions performed by these systems, devices, modules or units.

[0126] It should be noted that the modifications of "one" and "plurality" mentioned in the present disclosure are illustrative rather than restrictive, and those skilled in the art should understand that unless otherwise clearly indicated in the context, it should be understood as "one or more".

[0127] The names of the messages or information exchanged between multiple systems in the embodiments of the present disclosure are only used for illustrative purposes, and are not used to limit the scope of these messages or information.

[0128] The present disclosure will be described in detail below with reference to the accompanying drawings and in conjunction with embodiments.

[0129] Embodiment 1:

[0130] Figure 1 It is a schematic diagram of an application scenario of the budget optimization method for development wells according to the first embodiment of the present disclosure.

[0131] exist Figure 1 In the application scenario, first, the computing device 101 can obtain the well section budget information 102 of the target development well at different openings, and filter out multiple material budgets 104 and multiple duration estimates 105 corresponding to each opening based on the preset screening index 103.

[0132] Secondly, the computing device 101 may compare each material budget 104 / duration estimate 105 with a predetermined corresponding material budget distribution 106 / duration estimate distribution 107 to obtain a plurality of material budget comparison results 108 / duration estimate comparison results 109, wherein the material budget distribution 106 is related to the depth of the development well, and the duration estimate distribution 107 is related to the construction time of the development well;

[0133] Preferably, if any of the material budget comparison results 108 / duration estimate comparison results 109 indicates an over-limit, the computing device 101 can conduct an expert review on the over-limit material budget comparison result 108 / duration estimate comparison result 109, and if the expert review is passed, update the corresponding material budget distribution 106 / duration estimate distribution 107 based on the material budget 104 / duration estimate 105 corresponding to the over-limit material budget comparison result 108 / duration estimate comparison result 109.

[0134] It should be noted that the computing device 101 can be hardware or software. When the computing device is hardware, it can be implemented as a distributed cluster consisting of multiple servers or terminal devices, or as a single server or a single terminal device. When the computing device is embodied as software, it can be installed in the hardware devices listed above. It can be implemented as multiple software or software modules for providing distributed services, or as a single software or software module. No specific limitation is made here.

[0135] It should be understood that Figure 1 The number of computing devices in the embodiment is only illustrative. Any number of computing devices may be provided according to implementation requirements.

[0136] Embodiment 2:

[0137] Continue to refer Figure 2 , shows a process 200 of the second embodiment of the budget optimization method for developing wells according to the present disclosure. The method can be Figure 1 The method for optimizing the budget of a development well comprises the following steps:

[0138] Step 201, obtain the well section budget information of the target development well at different opening times, and filter out multiple material budgets and multiple time estimates corresponding to each opening time based on preset screening indicators.

[0139] In some embodiments, the execution entity of the budget optimization method for developing wells (such as Figure 1 The computing device 101 shown can be connected to the target device through a wired connection or a wireless connection, and then the well section budget information of the target development well at different openings is obtained, and the various material budgets and various time estimates corresponding to each opening are screened out based on the preset screening indicators. Development wells can refer to drilling in the development stage. Development wells have different opening stages during the drilling process. As an example, the first opening can refer to the drilling process of drilling and opening the surface cover before the surface cover is lowered, the second opening can refer to the drilling process of drilling the surface cover cement plug after the surface cover is lowered, and the third opening can refer to the drilling process of drilling the technical casing cement plug after the technical casing is safely lowered into the wellbore at a certain depth in a special formation to stabilize it. Therefore, different openings can refer to any of the above three openings. The budget of the development well includes multiple categories of budgets, such as relocation budget, land leveling budget, land collection budget, drilling budget, logging budget, drilling fluid budget, drill bit budget, casing budget, labor budget, etc. However, some budgets are fixed expenses, and some budgets are variable items. As an example, a fixed budget may include a relocation budget, a land leveling budget, a land expropriation budget, etc.; a variable budget may include a drilling fluid budget, a drill bit budget, a casing budget, etc. The present disclosure mainly regulates and optimizes variable items. A material budget may refer to a budget related to materials, which is correlated with the depth of the development well. A duration estimate may refer to an estimate related to a construction period, which is also correlated with the depth of the development well. A screening index may refer to a pre-set index for screening out the budget categories (types) and construction duration categories that need to be processed from the budget.

[0140] In some optional implementations, the step of determining the screening index includes: obtaining the benchmark budget data and benchmark construction duration of the target development well at each opening, the benchmark budget data includes multiple benchmark fixed budgets and multiple benchmark variable budgets, and the benchmark construction duration includes multiple benchmark construction durations; screening out at least one target benchmark variable budget and target benchmark construction duration in order from large to small, wherein the sum of the at least one target benchmark variable budget accounts for a proportion of the total budget that is not less than a preset first preset value, and the sum of the at least one target benchmark construction duration accounts for a proportion of the total construction duration that is not less than a preset second preset value; determining the screening index according to the at least one target benchmark variable budget and the target benchmark construction duration. The benchmark budget data may refer to relevant data as a standard budget structure for development wells of this type. The benchmark fixed budget may refer to a fixed budget in the benchmark budget. The benchmark variable budget may refer to a variable budget in the benchmark budget. The first preset value may be between 80% and 90%, and may be set as required. Preferably, the first preset value may be set to 80%.

[0141] It should be noted that the above-mentioned wireless connection methods may include but are not limited to 3G / 4G / 5G connection, WiFi connection, Bluetooth connection, WiMAX connection, Zigbee connection, UWB (ultra wideband) connection, and other wireless connection methods currently known or developed in the future.

[0142] Step 202, compare each material budget / duration estimate with a predetermined corresponding material budget distribution / duration estimate distribution to obtain multiple material budget comparison results / duration estimate comparison results, wherein the material budget distribution represents the corresponding relationship between the depth of development and the budget, and the duration estimate distribution represents the corresponding relationship between the depth of development and the construction duration.

[0143] In some embodiments, the execution subject may compare each material budget with a predetermined corresponding material budget distribution to obtain a plurality of material budget comparison results; and compare each duration estimate with a predetermined corresponding duration estimate distribution to obtain a plurality of duration estimate comparison results. Material budget distribution indicates the corresponding relationship between development depth and budget, that is, different depths correspond to different budgets for each material. Duration estimate distribution indicates that duration estimate distribution indicates the corresponding relationship between development depth and construction duration, that is, different depths correspond to different estimated construction lengths. Material budget distribution / duration estimate distribution may refer to a preset range of relevant budgets / construction durations according to different depths for development wells of similar types to the target development well generated based on historical data. Material budget comparison results / duration estimate comparison results may refer to comparison results related to material budgets and comparison results related to duration estimates obtained based on comparison, respectively. The comparison results may include three states: passing, exceeding upper limit, and exceeding lower limit. Passing means being in the distribution interval, exceeding upper limit means that the budget exceeds the high threshold of the distribution interval, and exceeding lower limit means that the budget is lower than the low threshold of the distribution interval. Exceeding upper limit and exceeding lower limit may be collectively referred to as exceeding limit.

[0144] In some optional implementations, the step of determining the material budget distribution / time estimate distribution includes: obtaining multiple historical well section budget information, and screening out multiple historical material budgets and multiple historical time estimates based on the screening index, each historical material budget / historical time estimate includes multiple historical data; performing probability distribution on each historical material budget / historical time estimate, generating high thresholds and low thresholds corresponding to each historical material budget / historical time estimate at different depths / times based on preset high ratio thresholds and low ratio thresholds, and obtaining the material budget / time estimate distribution. The historical well section budget information may refer to relevant information on the budget data and construction time data of similar type development wells that have been completed and operated normally. Since multiple budget data are obtained, there are multiple discretely distributed data for each depth / time. Perform probability distribution on multiple discretely distributed data, and set high ratio thresholds (e.g., 80%-95%) and low ratio thresholds (e.g., 5%-20%), so as to calculate the corresponding high thresholds and low thresholds. As an example, a certain depth corresponds to 136 data (i.e., 136 historical budget data are obtained), and 20%-80% is set as the ratio threshold (high ratio threshold 80%, low ratio threshold 20%), and 514.3 (low threshold) and 1865.15 (high threshold) can be calculated. Preferably, the high ratio threshold can be 90%, and the low ratio threshold can be 10%.

[0145] It should be noted that each material budget and each duration estimate corresponds to its own budget distribution. As an example, the drilling fluid budget in the material budget needs to be compared with the corresponding drilling fluid budget distribution, the drill bit budget needs to be compared with the corresponding drill bit budget distribution, and the casing budget needs to be compared with the corresponding casing budget distribution. The duration estimate is similar to the material budget, except that the budget corresponding to different depths is converted into the construction duration corresponding to different depths, which will not be repeated here.

[0146] In some optional implementations, in response to a display instruction, the corresponding material budget / duration estimate and the material budget distribution / duration estimate distribution corresponding to the material budget / duration estimate are combined and displayed on the target display interface.

[0147] For the convenience of display, each budget and the corresponding budget distribution can be combined and displayed on the corresponding display interface. Figure 6 As shown in the figure, a schematic diagram of casing budget and casing budget distribution is shown. The casing budget distribution can refer to the interval formed between the high threshold and the low threshold in the figure. The duration estimation is similar to it, and the horizontal axis can be changed to the construction duration, and no more examples are given.

[0148] Step 203, if any of the material budget comparison results / duration estimate comparison results indicates an over-limit, an expert review is conducted on the material budget comparison result / duration estimate comparison result that exceeds the limit, and if the expert review is passed, the corresponding material budget distribution / duration estimate distribution is updated based on the material budget / duration estimate corresponding to the material budget comparison result / duration estimate comparison result that exceeds the limit.

[0149] In some embodiments, the above-mentioned executive entity may process different material budget comparison results / duration estimate comparison results separately. If the above-mentioned budget comparison result indicates a pass, the budget comparison result may be sent to a processing module corresponding to the pass. If the above-mentioned budget comparison result indicates an over-limit (exceeding the upper limit or exceeding the lower limit), the above-mentioned executive entity may subject the over-limit material budget comparison result / duration estimate comparison result to an expert review. If the expert review fails, the application will be rejected. If the expert review passes, it means that there are parts of the budget that can be improved. Therefore, the corresponding material budget distribution / duration estimate distribution may be updated based on the material budget / duration estimate corresponding to the over-limit material budget comparison result / duration estimate comparison result. For the specific separate processing of exceeding the upper limit and exceeding the lower limit, the following steps may be referred to for processing:

[0150] If any of the material budget comparison results / time estimate comparison results indicates that the lower threshold is exceeded, the corresponding material budget / time estimate will be sent to the preset excess reduction processing port for corresponding expert review. Exceeding the lower limit indicates that the budget has been structurally improved, and the structural improvement can greatly reduce costs. Therefore, after such results are reviewed and approved by experts, the experience can be shared with other development wells, and the budget distribution of the development wells can be updated.

[0151] If any of the material budget comparison results / duration estimate comparison results indicates that it exceeds the high threshold, determine whether the structure of the well section budget information is the same as the existing structure; if different, determine whether the well section budget information is reduced, if reduced, it means passed; if not reduced, send the corresponding material budget / duration estimate to the preset excess budget processing port for corresponding expert review. Since each material budget / duration estimate must be compared separately, if one budget exceeds the standard, but the overall budget is reduced, and the budget structure is different from the existing structure, it can be said that the structure of the budget is designed to be better, and the budget distribution of the development well can be updated based on this.

[0152] In addition, the budget distribution of development wells can be updated at preset intervals.

[0153] In some optional implementations, historical budget data of the type corresponding to the target development well in the previous period is obtained at every preset period, and the material distribution interval and time distribution interval are updated according to the historical data. The preset period may be 3 months, 6 months or 12 months, etc. Since the development cycle of the development well is relatively long, the update period matches the development cycle, and the update frequency is generally more than 3 months, which is set as needed and is not specifically limited here.

[0154] Obtain the budget information of the target development well at each different opening, and select multiple material budgets and multiple time estimates corresponding to each opening based on preset screening indicators; compare each material budget / time estimate with the corresponding predetermined material budget distribution / time estimate distribution to obtain multiple material budget comparison results / time estimate comparison results; if any of the material budget comparison results / time estimate comparison results indicates an over-limit, conduct an expert review, and if the expert review is passed, update the corresponding material budget distribution / time estimate distribution, so that reasonable financial and time goals can be set, greatly enhancing the accuracy of the budget.

[0155] Embodiment three:

[0156] Continue to refer Figure 3 , shows a process 300 of the third embodiment of the budget optimization method for development wells according to the present disclosure, which can be performed by Figure 1The budget optimization method for the development well includes:

[0157] Step 301, obtain the well section budget information of the target development well at different openings, and filter out multiple material budgets and multiple time estimates corresponding to each opening based on preset screening indicators.

[0158] Step 302, the step of determining the screening index includes: obtaining the benchmark budget data and benchmark construction duration of the target development well at each opening, the benchmark budget data includes multiple benchmark fixed budgets and multiple benchmark variable budgets, and the benchmark construction duration includes multiple benchmark construction durations.

[0159] Step 303, select at least one target benchmark variable budget and target benchmark construction duration in order from large to small, wherein the sum of the at least one target benchmark variable budget as a percentage of the total budget is not less than a preset first preset value, and the sum of the at least one target benchmark construction duration as a percentage of the total construction duration is not less than a preset second preset value.

[0160] Step 304: Determine the screening index according to the at least one target benchmark variable budget and the target benchmark construction duration.

[0161] Step 305, compare each material budget / duration estimate with a predetermined corresponding material budget distribution / duration estimate distribution to obtain multiple material budget comparison results / duration estimate comparison results, wherein the material budget distribution represents the corresponding relationship between the development depth and the budget, and the duration estimate distribution represents the corresponding relationship between the development depth and the construction duration.

[0162] Step 306, the step of determining the material budget distribution / time estimate distribution includes: obtaining multiple historical well section budget information, and filtering out multiple historical material budgets and multiple historical time estimates based on the screening indicators, each historical material budget / historical time estimate includes multiple historical data.

[0163] Step 307, make a probability distribution for each historical material budget / historical duration estimate, generate a high threshold and a low threshold corresponding to each historical material budget / historical duration estimate at different depths / times based on the preset high ratio threshold and the low ratio threshold, and obtain the material budget distribution, wherein the high ratio threshold value ranges from 80% to 95%, and the low ratio threshold value ranges from 5% to 20%.

[0164] Step 308, if any of the material budget comparison results / duration estimate comparison results indicates an over-limit, an expert review is conducted on the material budget comparison result / duration estimate comparison result that exceeds the limit, and if the expert review is passed, the corresponding material budget distribution / duration estimate distribution is updated based on the material budget / duration estimate corresponding to the material budget comparison result / duration estimate comparison result that exceeds the limit.

[0165] In some optional implementations, the specific implementation of steps 301-308 and the technical effects brought about can be referred to Figure 2 The corresponding steps in the second embodiment are not described again here.

[0166] All the above optional technical solutions can be combined in any way to form optional implementation methods of the present application, and will not be described in detail here.

[0167] Embodiment 4:

[0168] The following are system embodiments of the present disclosure, which can be used to execute the method embodiments of the present disclosure. For details not disclosed in the system embodiments of the present disclosure, please refer to the method embodiments of the present disclosure.

[0169] Further references Figure 4 As an implementation of the above methods in the above figures, the present disclosure provides an embodiment of a budget optimization system for development wells. The system embodiment is similar to Figure 2 The above-mentioned embodiment 2 corresponds.

[0170] like Figure 4 As shown, the budget optimization system 400 for development wells of this embodiment includes:

[0171] The acquisition module 401 is used to obtain the well section budget information of the target development well at different opening times, and select various material budgets and various time estimates corresponding to each opening time based on the preset screening index;

[0172] A comparison module 402 is used to compare each material budget / duration estimate with a predetermined corresponding material budget distribution / duration estimate distribution to obtain a plurality of material budget comparison results / duration estimate comparison results, wherein the material budget distribution represents the corresponding relationship between the development depth and the budget, and the duration estimate distribution represents the corresponding relationship between the development depth and the construction duration;

[0173] The over-limit processing module 403 is used to conduct an expert review on the material budget comparison result / duration estimate comparison result that exceeds the limit if any of the material budget comparison results / duration estimate comparison results indicates an over-limit, and if the expert review is passed, update the corresponding material budget distribution / duration estimate distribution based on the material budget / duration estimate corresponding to the over-limit material budget comparison result / duration estimate comparison result.

[0174] In some optional implementations of some embodiments, the step of determining the screening index includes:

[0175] Obtaining benchmark budget data and benchmark construction duration of target development wells at each opening, wherein the benchmark budget data includes multiple benchmark fixed budgets and multiple benchmark variable budgets, and the benchmark construction duration includes multiple benchmark construction durations;

[0176] At least one target benchmark variable budget and target benchmark construction duration are selected in descending order, wherein the sum of the at least one target benchmark variable budget accounts for a proportion of the total budget that is not less than a preset first preset value, and the sum of the at least one target benchmark construction duration accounts for a proportion of the total construction duration that is not less than a preset second preset value;

[0177] The screening index is determined according to the at least one target benchmark variable budget and the target benchmark construction duration.

[0178] In some optional implementations of some embodiments, the step of determining the material budget distribution / duration estimate distribution includes:

[0179] Acquire multiple historical well section budget information, and screen out multiple historical material budgets and multiple historical duration estimates based on the screening index, each historical material budget / historical duration estimate including multiple historical data;

[0180] A probability distribution is made for each historical material budget / historical duration estimate, and based on the preset high ratio threshold and low ratio threshold, high threshold and low threshold corresponding to each historical material budget / historical duration estimate at different depths / times are generated to obtain the material budget distribution.

[0181] In some optional implementations of some embodiments, the value range of the high ratio threshold is between 80% and 95%, and the value range of the low ratio threshold is between 5% and 20%.

[0182] In some optional implementations of some embodiments, if any of the material budget comparison results / duration estimate comparison results indicates an over-limit, expert review is performed on the over-limit material budget comparison results / duration estimate comparison results, including:

[0183] If any of the material budget comparison results / duration estimate comparison results indicates that the lower threshold is exceeded, the corresponding material budget / duration estimate will be sent to the preset excess reduction processing port for corresponding expert review.

[0184] In some optional implementations of some embodiments, if any of the material budget comparison results / duration estimate comparison results indicates an over-limit, expert review is performed on the over-limit material budget comparison results / duration estimate comparison results, including:

[0185] If any of the material budget comparison results / time estimate comparison results indicates that the high threshold is exceeded, determining whether the structure of the well section budget information is the same as the existing structure;

[0186] If they are different, determining whether the well section budget information is reduced, and if reduced, indicating passing;

[0187] If it has not been reduced, the corresponding material budget / duration estimate will be sent to the preset overbudget processing port for corresponding expert review.

[0188] In some optional implementations of some embodiments, the system further includes:

[0189] The updating module is used to obtain historical budget data of a type corresponding to the target development well in the previous cycle every preset period, and update the material distribution interval and time distribution interval according to the historical data.

[0190] In some optional implementations of some embodiments, the system further includes:

[0191] The display module is used to respond to the display instruction and display the corresponding material budget / duration estimate and the material budget distribution / duration estimate distribution corresponding to the material budget / duration estimate in combination on the target display interface.

[0192] It is understood that the modules described in the system 400 are similar to those described in the reference Figure 2 Therefore, the operations, features and beneficial effects described above for the method are also applicable to the system 400 and the modules included therein, and will not be described in detail here.

[0193] Embodiment five:

[0194] like Figure 5 As shown, the electronic device 500 may include a processing device (e.g., a central processing unit, a graphics processing unit, etc.) 501, which can perform various appropriate actions and processes according to a program stored in a read-only memory (ROM) 502 or a program loaded from a storage device 508 into a random access memory (RAM) 503. In the RAM 503, various programs and data required for the operation of the electronic device 500 are also stored. The processing device 501, the ROM 502, and the RAM 503 are connected to each other via a bus 504. An input / output (I / O) interface 505 is also connected to the bus 504.

[0195] Typically, the following devices may be connected to the I / O interface 505: an input device 506 including, for example, a touch screen, a touch pad, a keyboard, a mouse, a camera, a microphone, an accelerometer, a gyroscope, etc.; an output device 507 including, for example, a liquid crystal display (LCD), a speaker, a vibrator, etc.; a storage device 508 including, for example, a magnetic tape, a hard disk, etc.; and a communication device 509. The communication device 509 may allow the electronic device 500 to communicate with other devices wirelessly or by wire to exchange data. Although Figure 5 The electronic device 500 is shown with various devices, but it should be understood that it is not required to implement or possess all the devices shown. More or fewer devices may be implemented or possessed instead. Figure 5 Each block shown in the figure may represent one device, or may represent multiple devices as required.

[0196] In particular, according to this embodiment, the process described above with reference to the flowchart can be implemented as a computer software program. For example, this embodiment includes a computer program product, which includes a computer program or instructions carried on a computer-readable medium, and the computer program or instructions contain program codes for executing the method shown in the flowchart. In this embodiment, the computer program can be downloaded and installed from the network through the communication device 509, or installed from the storage device 508, or installed from the ROM 502. When the computer program is executed by the processing device 501, the following steps can be performed:

[0197] Obtain the well section budget information of the target development well at different openings, and select the various material budgets and various time estimates corresponding to each opening based on the preset screening indicators;

[0198] Comparing each material budget / duration estimate with a predetermined corresponding material budget distribution / duration estimate distribution to obtain a plurality of material budget comparison results / duration estimate comparison results, wherein the material budget distribution represents a corresponding relationship between the development depth and the budget, and the duration estimate distribution represents a corresponding relationship between the development depth and the construction duration;

[0199] If any of the material budget comparison results / duration estimate comparison results indicates an excess, an expert review is conducted on the material budget comparison result / duration estimate comparison result that exceeds the limit, and if the expert review is passed, the corresponding material budget distribution / duration estimate distribution is updated based on the material budget / duration estimate corresponding to the material budget comparison result / duration estimate comparison result that exceeds the limit.

[0200] It should be noted that the computer-readable medium in the present embodiment may be a computer-readable signal medium or a computer-readable storage medium or any combination of the two. The computer-readable storage medium may be, for example, but not limited to, an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor system, device or device, or any combination of the above. More specific examples of computer-readable storage media may include, but are not limited to: an electrical connection with one or more wires, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the above. In the present embodiment, the computer-readable storage medium may be any tangible medium containing or storing a program that may be used by or in combination with an instruction execution system, device or device. In the present embodiment, the computer-readable signal medium may include a data signal propagated in a baseband or as part of a carrier wave, which carries a computer-readable program code. This propagated data signal may take a variety of forms, including but not limited to electromagnetic signals, optical signals, or any suitable combination of the above. The computer readable signal medium may also be any computer readable medium other than a computer readable storage medium, which may send, propagate or transmit a program for use by or in conjunction with an instruction execution system, apparatus or device. The program code contained on the computer readable medium may be transmitted using any suitable medium, including but not limited to: wires, optical cables, RF (radio frequency), etc., or any suitable combination of the above.

[0201] In some embodiments, the client and the server may communicate using any currently known or future developed network protocol such as HTTP (HyperText Transfer Protocol), and may be interconnected with any form or medium of digital data communication (e.g., a communication network). Examples of communication networks include a local area network ("LAN"), a wide area network ("WAN"), an internet (e.g., the Internet), and a peer-to-peer network (e.g., an ad hoc peer-to-peer network), as well as any currently known or future developed network.

[0202] The computer-readable medium may be included in the device, or may exist independently without being installed in the electronic device. The computer-readable medium carries one or more programs. When the one or more programs are executed by the electronic device, the electronic device performs the following steps:

[0203] Obtain the well section budget information of the target development well at different openings, and select the various material budgets and various time estimates corresponding to each opening based on the preset screening indicators;

[0204] Comparing each material budget / duration estimate with a predetermined corresponding material budget distribution / duration estimate distribution to obtain a plurality of material budget comparison results / duration estimate comparison results, wherein the material budget distribution represents a corresponding relationship between the development depth and the budget, and the duration estimate distribution represents a corresponding relationship between the development depth and the construction duration;

[0205] If any of the material budget comparison results / duration estimate comparison results indicates an excess, an expert review is conducted on the material budget comparison result / duration estimate comparison result that exceeds the limit, and if the expert review is passed, the corresponding material budget distribution / duration estimate distribution is updated based on the material budget / duration estimate corresponding to the material budget comparison result / duration estimate comparison result that exceeds the limit.

[0206] Obtain the well section budget information of the target development well at different openings, and select the various material budgets and various time estimates corresponding to each opening based on the preset screening indicators;

[0207] Comparing each material budget / duration estimate with a predetermined corresponding material budget distribution / duration estimate distribution to obtain a plurality of material budget comparison results / duration estimate comparison results, wherein the material budget distribution represents a corresponding relationship between the development depth and the budget, and the duration estimate distribution represents a corresponding relationship between the development depth and the construction duration;

[0208] If any of the material budget comparison results / duration estimate comparison results indicates an excess, an expert review is conducted on the material budget comparison result / duration estimate comparison result that exceeds the limit, and if the expert review is passed, the corresponding material budget distribution / duration estimate distribution is updated based on the material budget / duration estimate corresponding to the material budget comparison result / duration estimate comparison result that exceeds the limit.

[0209] In some embodiments, the step of determining the screening index comprises:

[0210] Obtaining benchmark budget data and benchmark construction duration of target development wells at each opening, wherein the benchmark budget data includes multiple benchmark fixed budgets and multiple benchmark variable budgets, and the benchmark construction duration includes multiple benchmark construction durations;

[0211] At least one target benchmark variable budget and target benchmark construction duration are selected in descending order, wherein the sum of the at least one target benchmark variable budget accounts for a proportion of the total budget that is not less than a preset first preset value, and the sum of the at least one target benchmark construction duration accounts for a proportion of the total construction duration that is not less than a preset second preset value;

[0212] The screening index is determined according to the at least one target benchmark variable budget and the target benchmark construction duration.

[0213] In some embodiments, the step of determining the material budget distribution / time estimate distribution includes:

[0214] Acquire multiple historical well section budget information, and screen out multiple historical material budgets and multiple historical duration estimates based on the screening index, each historical material budget / historical duration estimate including multiple historical data;

[0215] A probability distribution is made for each historical material budget / historical duration estimate, and based on the preset high ratio threshold and low ratio threshold, high threshold and low threshold corresponding to each historical material budget / historical duration estimate at different depths / times are generated to obtain the material budget distribution.

[0216] In some embodiments, the upper ratio threshold value ranges from 80% to 95%, and the lower ratio threshold value ranges from 5% to 20%.

[0217] In some embodiments, if any of the material budget comparison results / time estimate comparison results indicates an over-limit, expert review is performed on the over-limit material budget comparison results / time estimate comparison results, including:

[0218] If any of the material budget comparison results / duration estimate comparison results indicates that the lower threshold is exceeded, the corresponding material budget / duration estimate will be sent to the preset excess reduction processing port for corresponding expert review.

[0219] In some embodiments, if any of the material budget comparison results / time estimate comparison results indicates an over-limit, expert review is performed on the over-limit material budget comparison results / time estimate comparison results, including:

[0220] If any of the material budget comparison results / time estimate comparison results indicates that the high threshold is exceeded, determining whether the structure of the well section budget information is the same as the existing structure;

[0221] If they are different, determining whether the well section budget information is reduced, and if reduced, indicating passing;

[0222] If it has not been reduced, the corresponding material budget / duration estimate will be sent to the preset overbudget processing port for corresponding expert review.

[0223] In some embodiments, the method further comprises:

[0224] At every preset period, historical budget data of a type corresponding to the target development well in the previous period is obtained, and the material distribution interval and time distribution interval are updated according to the historical data.

[0225] In some embodiments, the method further comprises:

[0226] In response to the display instruction, the corresponding material budget / duration estimate and the material budget distribution / duration estimate distribution corresponding to the material budget / duration estimate are combined and displayed on the target display interface.

[0227] The computer program code for performing the operation of the present embodiment can be written in one or more programming languages ​​or a combination thereof, including object-oriented programming languages, such as Java, Smalltalk, C++, and conventional procedural programming languages, such as "C" language or similar programming languages. The program code can be executed entirely on the user's computer, partially on the user's computer, as an independent software package, partially on the user's computer and partially on a remote computer, or entirely on a remote computer or server. In the case of a remote computer, the remote computer can be connected to the user's computer through any type of network, including a local area network (LAN) or a wide area network (WAN), or can be connected to an external computer (e.g., using an Internet service provider to connect through the Internet).

[0228] The flow chart and block diagram in the accompanying drawings illustrate the possible architecture, function and operation of the system, method and computer program product according to various embodiments of the present disclosure. In this regard, each square box in the flow chart or block diagram can represent a module, a program segment or a part of a code, and the module, the program segment or a part of the code contains one or more executable instructions for realizing the specified logical function. It should also be noted that in some implementations as replacements, the functions marked in the square box can also occur in a sequence different from that marked in the accompanying drawings. For example, two square boxes represented in succession can actually be executed substantially in parallel, and they can sometimes be executed in the opposite order, depending on the functions involved. It should also be noted that each square box in the block diagram and / or flow chart, and the combination of the square boxes in the block diagram and / or flow chart can be implemented with a dedicated hardware-based system that performs the specified function or operation, or can be implemented with a combination of dedicated hardware and computer instructions.

[0229] The modules described in this embodiment may be implemented by software or hardware. The modules described may also be set in a processor, for example, may be described as:

[0230] Acquisition module, comparison module and over-limit processing module. For example, the acquisition module can also be described as "a module for acquiring the well section budget information of the target development well at different openings, and filtering out the various material budgets and various time estimates corresponding to each opening based on the preset screening indicators."

[0231] The functions described above herein may be performed at least in part by one or more hardware logic components. For example, without limitation, exemplary types of hardware logic components that may be used include: field programmable gate arrays (FPGAs), application specific integrated circuits (ASICs), application specific standard products (ASSPs), systems on chips (SOCs), complex programmable logic devices (CPLDs), and the like.

[0232] The above descriptions are only some preferred embodiments of the present disclosure and an explanation of the technical principles used. Those skilled in the art should understand that the scope of the invention involved in the embodiments of the present disclosure is not limited to the technical solutions formed by a specific combination of the above-mentioned technical features, but should also cover other technical solutions formed by any combination of the above-mentioned technical features or their equivalent features without departing from the above-mentioned inventive concept. For example, the above-mentioned features are replaced with the technical features with similar functions disclosed in the embodiments of the present disclosure (but not limited to) and the technical solutions formed.

Claims

1. A budget optimization method for development wells, characterized in that: include: Obtain the well section budget information of the target development well at different openings, and select the various material budgets and various time estimates corresponding to each opening based on the preset screening indicators; Comparing each material budget / duration estimate with a predetermined corresponding material budget distribution / duration estimate distribution to obtain a plurality of material budget comparison results / duration estimate comparison results, wherein the material budget distribution represents a corresponding relationship between the development depth and the budget, and the duration estimate distribution represents a corresponding relationship between the development depth and the construction duration; If any of the material budget comparison results / duration estimate comparison results indicates an excess, an expert review is conducted on the material budget comparison result / duration estimate comparison result that exceeds the limit, and if the expert review is passed, the corresponding material budget distribution / duration estimate distribution is updated based on the material budget / duration estimate corresponding to the material budget comparison result / duration estimate comparison result that exceeds the limit.

2. The method according to claim 1, characterized in that The step of determining the screening index comprises: Obtaining benchmark budget data and benchmark construction duration of target development wells at each opening, wherein the benchmark budget data includes multiple benchmark fixed budgets and multiple benchmark variable budgets, and the benchmark construction duration includes multiple benchmark construction durations; At least one target benchmark variable budget and target benchmark construction duration are selected in descending order, wherein the sum of the at least one target benchmark variable budget accounts for a proportion of the total budget that is not less than a preset first preset value, and the sum of the at least one target benchmark construction duration accounts for a proportion of the total construction duration that is not less than a preset second preset value; The screening index is determined according to the at least one target benchmark variable budget and the target benchmark construction duration.

3. The method according to claim 2, characterized in that The steps of determining the material budget distribution / time estimate distribution include: Acquire multiple historical well section budget information, and screen out multiple historical material budgets and multiple historical duration estimates based on the screening index, each historical material budget / historical duration estimate including multiple historical data; A probability distribution is made for each historical material budget / historical duration estimate, and based on the preset high ratio threshold and low ratio threshold, high threshold and low threshold corresponding to each historical material budget / historical duration estimate at different depths / times are generated to obtain the material budget distribution.

4. The method according to claim 3, characterized in that The value range of the high ratio threshold is between 80% and 95%, and the value range of the low ratio threshold is between 5% and 20%.

5. The method according to claim 4, characterized in that If any of the material budget comparison results / time estimate comparison results indicates an over-limit, an expert review is conducted on the over-limit material budget comparison results / time estimate comparison results, including: If any of the material budget comparison results / duration estimate comparison results indicates that the lower threshold is exceeded, the corresponding material budget / duration estimate will be sent to the preset excess reduction processing port for corresponding expert review.

6. The method according to claim 4, characterized in that If any of the material budget comparison results / time estimate comparison results indicates an over-limit, an expert review is conducted on the over-limit material budget comparison results / time estimate comparison results, including: If any of the material budget comparison results / time estimate comparison results indicates that the high threshold is exceeded, determining whether the structure of the well section budget information is the same as the existing structure; If they are different, determining whether the well section budget information is reduced, and if reduced, indicating passing; If it has not been reduced, the corresponding material budget / duration estimate will be sent to the preset overbudget processing port for corresponding expert review.

7. The method according to any one of claims 1 to 6, characterized in that: The method further comprises: At every preset period, historical budget data of a type corresponding to the target development well in the previous period is obtained, and the material distribution interval and time distribution interval are updated according to the historical data.

8. The method according to any one of claims 1 to 6, characterized in that: The method further comprises: In response to the display instruction, the corresponding material budget / duration estimate and the material budget distribution / duration estimate distribution corresponding to the material budget / duration estimate are combined and displayed on the target display interface.

9. A budget optimization system for development wells, characterized in that: include: Obtain the well section budget information of the target development well at different openings, and select the various material budgets and various time estimates corresponding to each opening based on the preset screening indicators; Comparing each material budget / duration estimate with a predetermined corresponding material budget distribution / duration estimate distribution to obtain a plurality of material budget comparison results / duration estimate comparison results, wherein the material budget distribution represents a corresponding relationship between the development depth and the budget, and the duration estimate distribution represents a corresponding relationship between the development depth and the construction duration; If any of the material budget comparison results / duration estimate comparison results indicates an excess, an expert review is conducted on the material budget comparison result / duration estimate comparison result that exceeds the limit, and if the expert review is passed, the corresponding material budget distribution / duration estimate distribution is updated based on the material budget / duration estimate corresponding to the material budget comparison result / duration estimate comparison result that exceeds the limit.

10. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the computer program, the steps of the method according to any one of claims 1 to 8 are implemented.

11. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 8 are implemented.