Electric power engineering construction method based on BIM model

Through the BIM model-based power engineering construction method, real-time monitoring and progress tracking of the construction process are achieved, errors and inaccurate progress tracking caused by construction process problems in the existing technology are solved, construction technology is optimized and improved Construction efficiency.

CN119476784APending Publication Date: 2025-02-18CHINESE PEOPLES ARMED POLICE FORCE JIANGXI HYDRO POWER NO 2 GENERAL GRP

Patent Information

Application Number
CN202411488983.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-24
Publication Date
2025-02-18

AI Technical Summary

Technical Problem

During the construction of power engineering, it is difficult for the existing technology to achieve real-time monitoring and accurate tracking of construction progress, and it is easy to make errors due to construction process problems, resulting in the inability to accurately complete the construction.

Method used

Using the power engineering construction method based on the BIM model, through project basic data acquisition, BIM model construction, monitoring system settings and data display, data classification, calibration correction and multi-dimensional calculation are realized, and a multi-channel, high-correlation system organizational structure is constructed to carry out Real-time monitoring and progress tracking.

Benefits of technology

Real-time monitoring and progress tracking of power engineering construction have been achieved, construction technology has been optimized, construction deviation has been reduced, and project monitoring has been improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119476784A_ABST
    Figure CN119476784A_ABST
Patent Text Reader

Abstract

The invention discloses an electric power engineering construction method based on a BIM model. Compared with the prior art, the electric power engineering construction monitoring system has the advantage of realizing real-time construction monitoring on the basis of the BIM model in the real-time detection construction process through the setting of BIM model construction, and can realize real-time construction monitoring on the basis of the BIM model in the electric power engineering construction process through setting the modes of project basic data acquisition, BIM model construction, monitoring system setting and data display. Data classification, calibration and correction, multi-dimensional calculation and the like are carried out, efficient and high-quality conversion of data is achieved, operation modes are connected in series through the technological process, a multi-channel and high-correlation system organization structure is constructed, the effects of optimizing the technology, improving project monitoring comprehensiveness and being accurate in progress tracking are achieved, and the method is not only used for pre-simulation of construction, but also used for real-time construction. Moreover, the system can be used for achieving comprehensive monitoring, can reduce the deviation of construction, can achieve alarm processing when a problem occurs, achieves the comprehensive display of the whole process, and facilitates the real-time monitoring of people.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of electric power engineering model building, and in particular to an electric power engineering construction method based on a BIM model. Background Art

[0002] Power engineering refers to engineering related to the production, transmission and distribution of electric energy. In a broad sense, it also includes engineering that uses electricity as power and energy in various fields. At the same time, it can be understood as power transmission and transformation expansion engineering. With the acceleration of urbanization, energy demand is growing. In order to ensure the normal operation of the city and the quality of life of residents, the power system plays a vital role in the city. During the construction of power projects, construction workers often need to strictly follow the construction drawings to make corresponding work arrangements, including material preparation. When preparing materials, the materials contained in the construction drawings often need to be manually identified and counted. The efficiency of material preparation is very low, and due to the large quantity and variety of materials, it is easy to miss or make mistakes when manually identifying and counting.

[0003] In view of the above technical problems, a system and method for collecting and analyzing materials information of power engineering projects based on a drawing group is disclosed in the announcement number CN114170616A, which can automatically extract and count the materials data in the power engineering construction drawings through image text recognition. Compared with manual recognition, the efficiency and accuracy of material statistics are greatly improved. The influence of interference factors in the recognition process is eliminated by preprocessing the power engineering construction drawings, and the accuracy of image text recognition is further improved by cutting the images of the power engineering construction drawings. The above patent also has the following shortcomings: in the prior art, the power construction process is carried out in reference to the design drawings, and then errors may still occur during the construction process due to problems with the construction process, so that the step-by-step construction cannot be carried out accurately and the construction process cannot be monitored in real time. Summary of the invention

[0004] The purpose of the present invention is to provide a power engineering construction method based on the BIM model, which has the advantage of realizing real-time monitoring of construction based on the BIM model, and realizes efficient and high-quality data conversion by setting up project basic data collection, BIM model construction, monitoring system setting, data display, data classification, calibration and correction, multi-dimensional calculation, etc., and uses the process flow to connect the operation mode in series to build a multi-channel, highly correlated system organizational structure, so as to achieve the effect of optimizing the process, improving the comprehensiveness of project monitoring, and accurately tracking the progress, so as to solve the problems raised in the above background technology.

[0005] To achieve the above object, the present invention provides the following technical solution: a power engineering construction method based on BIM model, comprising the following steps: Step 1: Collect basic project data on the bill of quantities, equipment specifications and installation locations in the construction project, then obtain a data set and build a BIM model through the data set; Step 2: Set up several monitoring nodes, alarm nodes and display nodes on the BIM model, and connect the BIM model to the monitoring system; Step 3: When the monitoring node detects an abnormal situation in the construction process, the alarm node notifies the construction personnel to take measures, and the display node displays the data during the monitoring process; Step 4: Classify, calibrate and correct the data after data display, and perform multi-dimensional calculations, and then display the processed data again.

[0006] Exemplarily, during the data collection, the project construction drawings, construction plans and measurement data of the construction site are collected and integrated to form a data set.

[0007] Exemplarily, in the construction of the BIM model, based on the collected information and data, the building elements are drawn using BIM software and parameterized; The BIM model was constructed using Autodesk Revit software.

[0008] Exemplarily, among the monitoring nodes, temperature sensors, humidity sensors, vibration physical quantity measuring equipment, and safety equipment such as fire detectors and carbon dioxide concentration detectors suitable for the construction and application scenarios are selected; The transmission between sensors and devices is achieved through wireless communication technology or wired network; In the alarm node, using an interactive visual interface, construction personnel can intuitively understand the safety status of the construction location; When an alarm is triggered, an alarm notification is automatically sent so that construction personnel can take timely response measures; In the display node, real rendering technology is used, and a more realistic visual effect can be presented through physical engine rendering and lighting simulation; It can also use 3D visualization technology to allow construction workers to intuitively understand the structure and component layout of the project; At the same time, based on animation production, the operating status of the equipment and the construction sequence work are demonstrated; Information on components, pipelines, and lines is highlighted using different colors, fonts, and icons.

[0009] Exemplarily, the monitoring system includes functions of real-time data collection, remote control and alarm; Through the monitoring system, various information about the project is obtained, including the status, progress, and environmental conditions of the components, so that corresponding adjustments and optimizations can be made. The Python script in the automation tool is used to automatically extract and convert data, analyze the existing data sources, find out possible duplicate, invalid or outdated data, and eliminate them. According to the update frequency of the model, the data collection cycle is set without manual intervention. Adopt MQTT distributed data collection technology to enable fast data transmission between devices and platforms, use the path with the least network delay, use the global positioning system (GPS) for precise positioning to improve the accuracy of data transmission, and synchronize data regularly to ensure that all data is consistent with the latest version of the BIM model. Use the AES encryption algorithm to encrypt sensitive data to prevent data leakage, monitor the data transmission process, guard against hacker attacks, ensure that data is not tampered with during transmission, and provide an API interface to facilitate integration with SCADA and Internet of Things systems.

[0010] Exemplarily, the remote control uses Web technology to implement a Web-based remote monitoring system, and through Web technology, online viewing, editing and control of model data are realized, and data is exchanged using RESTful API. RESTful API is a lightweight Web service architecture for power engineering construction methods based on BIM models, which enables model data to be shared and accessed between different applications, and can define a set of API interfaces for adding, modifying and deleting operations.

[0011] Exemplarily, the alarm in the monitoring system sets the alarm threshold of each parameter according to the actual project requirements, and sets appropriate thresholds for different parameters according to the importance and safety standard factors of the building. When a parameter exceeds the threshold, the system promptly issues an alarm; When an alarm is triggered, the system should take immediate action and automatically send it to the project leader and technical team. It should also visually display the alarm information on the map in the form of charts, heat maps, etc., while supporting multi-dimensional comparative analysis.

[0012] Exemplarily, the physical simulation technology is applied to the BIM model in the display node to make the node display more realistic, the Riello structural analysis software is used to simulate the structural performance under different load conditions, and the fluid dynamics (CFD) technology is introduced into the BIM model to simulate the air flow around the node, so as to truly show the performance of the node in the actual project; By introducing animation, the dynamic interactivity of the model can be increased, and a node model with rotation action can be created, so that the changes of the node in different states can be intuitively observed.

[0013] Exemplarily, the data after data display is classified, calibrated, and processed by multi-dimensional calculation, and the processed data is displayed again, and the objects in the model are divided into different categories according to attributes and uses; Classification allows similar objects to be grouped together; Grouping is to classify objects into different groups according to their type, location or properties. Use the classification tools of ArchiCAD or Revit or Navisworks software to classify the objects in the model. Calibration and correction is the process of manipulating data in the BIM model to ensure accuracy and consistency. Calibration and correction operations can be easily performed using Leica LiDATs, Trimble SketchUp or Zoller & Partners software. Multidimensional computing is a tool used to analyze and simulate BIM models, including calculating parameters such as volume, area, weight, and analyzing the interaction between different building components. High-dimensional computing tools include Autodesk Simulation, ArchiCAD or Revit.

[0014] Exemplarily, the processed data is presented again using Navisworks, Graphisoft and Revit software to present the data in various ways, which can be clearly displayed in the form of 2D boards, 3D modeling and timelines.

[0015] Compared with the prior art, the present invention has the following beneficial effects: Through the setting of BIM model construction, the present invention has the advantage of realizing real-time monitoring of construction based on BIM model in power engineering construction company. Through setting project basic data collection, BIM model construction, monitoring system setting, data display mode, data classification, calibration and correction, multi-dimensional calculation, etc., efficient and high-quality data conversion is realized, and the operation mode is connected in series by using process flow to build a multi-channel and highly correlated system organizational structure, so as to achieve the effect of optimizing process, improving comprehensiveness of project monitoring and accurate progress tracking. It is not only used for pre-simulation of construction, but also can be used to realize comprehensive monitoring, and at the same time can reduce the deviation in construction. When problems occur, alarm processing can also be realized. The whole process is fully displayed, which is conducive to people's constant monitoring.

[0016] Other features and advantages of the present invention will be described in the following description, and partly become obvious from the description, or be understood by implementing the present invention. The purpose and other advantages of the present invention can be realized and obtained by the structures pointed out in the description and the drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 The present invention is a flowchart of the power engineering construction method of the BIM model. DETAILED DESCRIPTION

[0018] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0019] The present invention provides a power engineering construction method based on a BIM model, comprising the following steps: Step 1: Collect basic project data on the bill of quantities, equipment specifications and installation locations in the construction project, then obtain a data set and build a BIM model through the data set; Step 2: Set up several monitoring nodes, alarm nodes and display nodes on the BIM model, and connect the BIM model to the monitoring system; Step 3: When the monitoring node detects an abnormal situation in the construction process, the alarm node notifies the construction personnel to take measures, and the display node displays the data during the monitoring process; Step 4: Classify, calibrate and correct the data after data display, and perform multi-dimensional calculations, and then display the processed data again.

[0020] It has the advantage of enabling real-time monitoring of construction based on the BIM model.

[0021] Furthermore, during data collection, the project construction drawings, construction plans and measurement data of the construction site are collected and integrated to form a data set.

[0022] Among them, in constructing the BIM model, based on the collected information and data, the building elements are drawn using BIM software and parameterized; The BIM model was constructed using Autodesk Revit software.

[0023] First, existing data including drawings, plans and data generated by measurements are collected, and then organized into a data set or database. The above method is not limited to the above method. At this time, the building is drawn through the existing BIM software to form parameter values, and then the BIM model is constructed by Autodesk Revit software.

[0024] In addition, in the monitoring nodes, select temperature sensors, humidity sensors, vibration physical quantity measurement equipment, and safety equipment such as fire detectors and carbon dioxide concentration detectors that are suitable for the construction and application scenarios; The transmission between sensors and devices is achieved through wireless communication technology or wired network; In the alarm node, using an interactive visual interface, construction personnel can intuitively understand the safety status of the construction location; When an alarm is triggered, an alarm notification is automatically sent so that construction personnel can take timely response measures; In the display node, real rendering technology is used, and a more realistic visual effect can be presented through physical engine rendering and lighting simulation; It can also use 3D visualization technology to allow construction workers to intuitively understand the structure and component layout of the project; At the same time, based on animation production, the operating status of the equipment and the construction sequence work are demonstrated; Information on components, pipelines, and lines is highlighted using different colors, fonts, and icons.

[0025] The monitoring process includes temperature, humidity, vibration and measurement methods for detection, but is not limited to the above detection methods. It can also be viewed using a visual interface, that is, a display method, and an alarm method is used to remind monitoring problems.

[0026] Furthermore, the monitoring system includes the functions of real-time data collection, remote control and alarm; Through the monitoring system, various information about the project is obtained, including the status, progress, and environmental conditions of the components, so that corresponding adjustments and optimizations can be made. The Python script in the automation tool is used to automatically extract and convert data, analyze the existing data sources, find out possible duplicate, invalid or outdated data, and eliminate them. According to the update frequency of the model, the data collection cycle is set without manual intervention. Adopt MQTT distributed data collection technology to enable fast data transmission between devices and platforms, use the path with the least network delay, use the global positioning system (GPS) for precise positioning to improve the accuracy of data transmission, and synchronize data regularly to ensure that all data is consistent with the latest version of the BIM model. Use the AES encryption algorithm to encrypt sensitive data to prevent data leakage, monitor the data transmission process, guard against hacker attacks, ensure that data is not tampered with during transmission, and provide an API interface to facilitate integration with SCADA and Internet of Things systems.

[0027] During the monitoring process, real-time collection and remote control are used to perform real-time monitoring operations.

[0028] Furthermore, remote control uses Web technology to implement a Web-based remote monitoring system. Through Web technology, online viewing, editing and control of model data can be achieved, and data exchange can be performed using RESTful API. RESTful API is a lightweight Web service architecture based on the BIM model. It enables model data to be shared and accessed between different applications, and can define a set of API interfaces for adding, modifying and deleting operations.

[0029] Among them, the alarm in the monitoring system sets the alarm threshold of each parameter according to the actual project requirements. According to the importance of the building and safety standard factors, appropriate thresholds are set for different parameters. When a parameter exceeds the threshold, the system will issue an alarm in time; When an alarm is triggered, the system should take immediate action and automatically send it to the project leader and technical team. It should also visually display the alarm information on the map in the form of charts, heat maps, etc., while supporting multi-dimensional comparative analysis.

[0030] In addition, physical simulation technology is applied to the BIM model in the display nodes to make the node display more realistic. Riello structural analysis software is used to simulate the structural performance under different load conditions. Fluid dynamics (CFD) technology is introduced into the BIM model to simulate the air flow around the nodes, truly showing the performance of the nodes in actual projects. By introducing animation, the dynamic interactivity of the model can be increased, and a node model with rotation action can be created, so that the changes of the node in different states can be intuitively observed.

[0031] Among them, the data after data display is classified, calibrated and corrected, and multi-dimensionally calculated, and the processed data is displayed again, and the objects in the model are divided into different categories according to their attributes and uses; Classification allows similar objects to be grouped together; Grouping is to classify objects into different groups according to their type, location or properties. Use the classification tools of ArchiCAD or Revit or Navisworks software to classify the objects in the model. Calibration and correction is the process of manipulating data in the BIM model to ensure accuracy and consistency. Calibration and correction operations can be easily performed using Leica LiDATs, Trimble SketchUp or Zoller & Partners software. Multidimensional computing is a tool used to analyze and simulate BIM models, including calculating parameters such as volume, area, weight, and analyzing the interaction between different building components. High-dimensional computing tools include Autodesk Simulation, ArchiCAD or Revit.

[0032] Finally, the processed data is presented again using Navisworks, Graphisoft and Revit software to present the data in various ways, which can be clearly displayed in the form of 2D boards, 3D modeling and timelines.

[0033] Based on the above, by setting up the project-based data collection, BIM model construction, monitoring system settings, data display, and then classifying, calibrating and correcting the data, and multi-dimensional calculation, efficient and high-quality data conversion can be achieved, and new process steps are used in series to build a multi-channel, highly correlated system organizational structure to achieve the effects of optimizing the process, improving the comprehensiveness of project monitoring, and accurately tracking progress. Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A power engineering construction method based on BIM model, characterized in that: The following steps are involved: Step 1: Collect basic project data on the bill of quantities, equipment specifications and installation locations in the construction project, then obtain a data set and build a BIM model through the data set; Step 2: Set up several monitoring nodes, alarm nodes and display nodes on the BIM model, and connect the BIM model to the monitoring system; Step 3: When the monitoring node detects an abnormal situation in the construction process, the alarm node notifies the construction personnel to take measures, and the display node displays the data during the monitoring process; Step 4: Classify, calibrate and correct the data after data display, and perform multi-dimensional calculations, and then display the processed data again.

2. The power engineering construction method based on the BIM model according to claim 1, characterized in that: During the data collection, the project construction drawings, construction plans and measurement data of the construction site are collected and integrated to form a data set.

3. The power engineering construction method based on the BIM model according to claim 1, characterized in that: In the construction of the BIM model, based on the collected information and data, the building elements are drawn using BIM software and parameterized. The BIM model was constructed using Autodesk Revit software.

4. The power engineering construction method based on the BIM model according to claim 1, characterized in that: Among the monitoring nodes, select temperature sensors, humidity sensors, vibration physical quantity measuring equipment, and safety equipment such as fire detectors and carbon dioxide concentration detectors that are suitable for the construction and application scenarios; The transmission between sensors and devices is achieved through wireless communication technology or wired network; In the alarm node, using an interactive visual interface, construction personnel can intuitively understand the safety status of the construction location; When an alarm is triggered, an alarm notification is automatically sent so that construction personnel can take timely response measures; In the display node, real rendering technology is used, and a more realistic visual effect can be presented through physical engine rendering and lighting simulation; It can also use 3D visualization technology to allow construction workers to intuitively understand the structure and component layout of the project; At the same time, based on animation production, the operating status of the equipment and the construction sequence work are demonstrated; Information on components, pipelines, and lines is highlighted using different colors, fonts, and icons.

5. The power engineering construction method based on the BIM model according to claim 1, characterized in that: The monitoring system includes functions of real-time data collection, remote control and alarm; Through the monitoring system, various information about the project is obtained, including the status, progress, and environmental conditions of the components, so that corresponding adjustments and optimizations can be made. The Python script in the automation tool is used to automatically extract and convert data, analyze the existing data sources, find out possible duplicate, invalid or outdated data, and eliminate them. According to the update frequency of the model, the data collection cycle is set without manual intervention. Adopt MQTT distributed data collection technology to enable fast data transmission between devices and platforms, use the path with the least network delay, use the global positioning system (GPS) for precise positioning to improve the accuracy of data transmission, and synchronize data regularly to ensure that all data is consistent with the latest version of the BIM model. Use the AES encryption algorithm to encrypt sensitive data to prevent data leakage, monitor the data transmission process, guard against hacker attacks, ensure that data is not tampered with during transmission, and provide an API interface to facilitate integration with SCADA and Internet of Things systems.

6. The power engineering construction method based on the BIM model according to claim 5 is characterized by: The remote control uses Web technology to implement a Web-based remote monitoring system. Through Web technology, online viewing, editing and control of model data are realized, and data is exchanged using RESTful API. RESTful API is a lightweight Web service architecture for power engineering construction methods based on BIM models. It enables model data to be shared and accessed between different applications, and can define a set of API interfaces for adding, modifying and deleting operations.

7. The power engineering construction method based on the BIM model according to claim 6 is characterized by: The alarm in the monitoring system is based on the actual project requirements, and the alarm thresholds of various parameters are set. According to the importance of the building and safety standard factors, appropriate thresholds are set for different parameters. When a parameter exceeds the threshold, the system will issue an alarm in time; When an alarm is triggered, the system should take immediate action and automatically send it to the project leader and technical team. It should also visually display the alarm information on the map in the form of charts, heat maps, etc., while supporting multi-dimensional comparative analysis.

8. The power engineering construction method based on the BIM model according to claim 1, characterized in that: In the display nodes, physical simulation technology is applied to the BIM model to make the node display more realistic. Riello structural analysis software is used to simulate the structural performance under different load conditions. Fluid dynamics (CFD) technology is introduced into the BIM model to simulate the air flow around the nodes, truly showing the performance of the nodes in actual projects. By introducing animation, the dynamic interactivity of the model can be increased, and a node model with rotation action can be created, so that the changes of the node in different states can be intuitively observed.

9. The power engineering construction method based on the BIM model according to claim 1, characterized in that: The data after data display is classified, calibrated, and multi-dimensionally calculated, and the processed data is displayed again, and the objects in the model are divided into different categories according to their attributes and uses; Classification allows similar objects to be grouped together; Grouping is to classify objects into different groups according to their type, location or properties. Use the classification tools of ArchiCAD or Revit or Navisworks software to classify the objects in the model. Calibration and rectification is the process of manipulating data in a BIM model to ensure accuracy and consistency. Calibration and rectification operations can be easily performed using Leica LiDATS, Trimble SketchUp or Zoller & Partners software. Multidimensional computing is a tool used to analyze and simulate BIM models, including calculating parameters such as volume, area, weight, and analyzing the interaction between different building components. High-dimensional computing tools include Autodesk Simulation, ArchiCAD or Revit.

10. The power engineering construction method based on the BIM model according to claim 9, characterized in that: The processed data is presented again using Navisworks, Graphisoft and Revit software to present the data in various ways, which can be clearly displayed in the form of 2D boards, 3D modeling and timelines.

Citation Information

Patent Citations

  • Electric power engineering material information acquisition and analysis system and method based on drawing group