A suction pile jacket installation method and apparatus

By setting lifting points at both ends of the jacket structure and controlling the lifting speed and distance, and combining the lifting tower for the flipping and installation of the jacket structure, the problems of large equipment investment and high-altitude operations in traditional construction processes are solved, achieving low-cost and efficient jacket structure installation.

CN119593429BActive Publication Date: 2025-12-12FUJIAN MAWEI SHIPBUILDING
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202411708694.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-08-28
Publication Date
2025-12-12
Estimated Expiration
2040-08-28

AI Technical Summary

Technical Problem

The construction process of traditional three-pile suction cylinder jacket wind turbine foundations involves large investment in equipment, difficult splicing processes, and a lot of high-altitude work, resulting in high construction costs and low efficiency.

Method used

Lifting points are set at both ends of the horizontal jacket structure. By controlling the lifting speed and distance of the lifting points, the jacket structure can be flipped and spliced ​​as a whole. The first and second lifting towers are used to flip and install the jacket structure, reducing high-altitude operations.

Benefits of technology

It reduced equipment investment costs, improved construction accuracy and efficiency, reduced the risks of working at heights, and met the requirements for horizontal construction and overall tilting and hoisting of the jacket.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119593429B_ABST
    Figure CN119593429B_ABST
Patent Text Reader

Abstract

The present application relates to offshore engineering facilities technical field, especially to a kind of offshore wind power suction cylinder jacket installation method and device, hoisting point is respectively arranged in the opposite ends of the recumbent jacket body, the hoisting speed of each hoisting point is controlled, the jacket body is overturned to erect state, so as to facilitate the installation of suction cylinder body and jacket body, after installation, it can be directly vertical transport, solve the traditional three pile suction cylinder jacket construction process and equipment investment big problem, the initial investment of the whole device is about 25 million, far lower than the initial investment of nearly 200 million of super large gantry crane equipment;And without tensioning cable wind rope, the impact on site is minimized;Foundation treatment is simple, overall stability is good, economic benefit is high;Meet the requirements of upper jacket horizontal construction and overall rollover hoisting splicing, can realize the upper jacket horizontal construction, improve construction precision and construction efficiency, reduce the risk of high-altitude operation.
Need to check novelty before this filing date? Find Prior Art

Description

[0001] The present application is a divisional application of the parent application with the application date of August 28, 2020, the application number of CN202010885603.X, and the name of "A method and device for installing a suction pile jacket of offshore wind power". TECHNICAL FIELD

[0002] The present application relates to the technical field of offshore engineering facilities, in particular to a method and device for installing a suction pile jacket. BACKGROUND

[0003] Offshore wind turbine foundations adopt different forms of foundations such as single pile, skirt pile, gravity type, jacket, and floating type according to water depth. With the development of China's offshore wind power from shallow sea to deep sea, three-pile suction pile jacket wind turbine foundation is widely used due to its advantages of adaptability to 20m-50m water depth, short offshore construction period, and less influence of offshore operation window period. The three-pile suction pile jacket wind turbine foundation includes an upper jacket and three lower suction piles. The overall height of the jacket structure is 92m-98m, and the mass is 2300t-2600t.

[0004] Currently, there are generally two traditional processes for constructing the three-pile suction pile jacket wind turbine foundation, as follows: one is to adopt horizontal construction for the upper jacket, to use lifting equipment for turning over and splicing with the suction pile, and to be equipped with super-large gantry lifting equipment (the lifting capacity needs to be greater than 3000t, and the lifting height needs to be greater than 120m); the other is to adopt horizontal construction in stages for the upper jacket, to be equipped with lifting equipment (the lifting capacity needs to be greater than 1000t, and the lifting height needs to be greater than 120m), and then to be spliced in stages in a vertical manner. The disadvantage of the first method is that the horizontal construction requires the configuration of super-large lifting equipment for overall turning over, and the construction unit needs to invest a lot in equipment. The disadvantage of the second method is that the splicing in stages in a vertical manner is difficult, and the precision requirement for connection is high; the splicing in stages in a vertical manner involves a lot of high-altitude operations, and the safety risk coefficient is high, and the work efficiency is low. It can be seen that the two construction processes either require a large investment in equipment, or the splicing process is difficult and involves a lot of high-altitude operations, which is not conducive to the reduction of construction cost and the improvement of construction efficiency of the three-pile suction pile jacket wind turbine foundation. SUMMARY

[0005] The technical problem to be solved by the present application is to provide a method and device for installing a suction pile jacket of offshore wind power, which solves the problems of large investment in traditional three-pile suction pile jacket construction process and equipment, and difficult splicing process and a lot of high-altitude operations.

[0006] In order to solve the above technical problems, the technical scheme adopted by the present application is as follows: a method for installing a suction pile jacket, specifically comprising the following steps:

[0007] S1, preset a first lifting point at one end of the horizontal direction of the lying down guide pipe frame body, preset a second lifting point at the other end of the horizontal direction of the lying down guide pipe frame body, and set the line connecting the first lifting point and the second lifting point as an initial line;

[0008] S2, vertically upwardly hoist the first lifting point at a first hoisting speed, vertically upwardly hoist the second lifting point at a second hoisting speed, and simultaneously adjust the horizontal distance between the first lifting point and the second lifting point to gradually decrease until the line connecting the first lifting point and the second lifting point rotates 90° relative to the initial line;

[0009] S3, synchronously vertically upwardly hoist the first lifting point and the second lifting point to a preset installation height at a third hoisting speed, and then install the suction cylinder body vertically below the guide pipe frame body.

[0010] The application further provides a suction cylinder guide pipe frame installation device for connecting the suction cylinder body and the guide pipe frame body, comprising a first lifting tower and a second lifting tower.

[0011] The first lifting tower is used for hoisting one end of the guide pipe frame body, the second lifting tower is used for hoisting the other end of the guide pipe frame body, the lifting height of the first lifting tower is greater than the lifting height of the second lifting tower, the difference between the lifting heights of the first lifting tower and the second lifting tower is greater than or equal to the vertical height of one guide pipe frame body, the lifting height of the second lifting tower is greater than the vertical height of one suction cylinder body, and the horizontal distance between the first lifting tower and the second lifting tower is adjustable.

[0012] The application has the beneficial effects that the application provides a suction cylinder guide pipe frame installation method and device for offshore wind power, lifting points are arranged at opposite ends of a lying down guide pipe frame body, the hoisting speed of each lifting point is controlled, the guide pipe frame body is turned to a vertical state, and then the installation of the suction cylinder body and the guide pipe frame body is facilitated, and the two can be directly vertically conveyed after installation, thereby solving the problems of large investment in traditional three-pile suction cylinder guide pipe frame construction process and equipment, difficult splicing process and much high-altitude operation. BRIEF DESCRIPTION OF DRAWINGS

[0013] Figure 1 FIG. 1 is a structural schematic diagram of an offshore wind power suction cylinder guide pipe frame installation device according to an embodiment of the application;

[0014] Figure 2 FIG. 2 is another structural schematic diagram of the offshore wind power suction cylinder guide pipe frame installation device according to the embodiment of the application;

[0015] Figure 3 FIG. 3 is a partial schematic diagram of the offshore wind power suction cylinder guide pipe frame installation device according to the embodiment of the application;

[0016] Figure 4Another partial view of the offshore wind power suction pile jacket installation device of the embodiment of the present application;

[0017] Figure 5 Another structural view of the offshore wind power suction pile jacket installation device of the embodiment of the present application;

[0018] Figure 6 A top view of the offshore wind power suction pile jacket installation device of the embodiment of the present application;

[0019] Figure 7 Another structural view of the offshore wind power suction pile jacket installation device of the embodiment of the present application;

[0020] Figure 8 Another structural view of the offshore wind power suction pile jacket installation device of the embodiment of the present application;

[0021] Figure 9 Another structural view of the offshore wind power suction pile jacket installation device of the embodiment of the present application;

[0022] Figure 10 Another structural view of the offshore wind power suction pile jacket installation device of the embodiment of the present application;

[0023] Figure 11 Another structural view of the offshore wind power suction pile jacket installation device of the embodiment of the present application;

[0024] Label explanation:

[0025] 1, suction pile main body;

[0026] 2, jacket main body;

[0027] 3, first lifting tower;

[0028] 4, second lifting tower;

[0029] 5, first lifting assembly;

[0030] 6, second lifting assembly;

[0031] 7, concrete base;

[0032] 8, tower body;

[0033] 9, bottom section;

[0034] 10, standard section;

[0035] 11, top section;

[0036] 12, girder;

[0037] 13, winch;

[0038] 14. A block and tackle;

[0039] 15. A balance cable;

[0040] 16. A tie rod set;

[0041] 17. A balance beam;

[0042] 18. A walking trolley;

[0043] 19. An axle line vehicle. DETAILED DESCRIPTION

[0044] To make the technical content of the present application, the purposes and effects achieved more clear, the following will be described in detail in combination with the embodiments and the accompanying drawings.

[0045] Please refer to Figures 1 to 11 A method for installing a suction pile jacket of offshore wind power, specifically comprising the following steps:

[0046] S1, presetting a first lifting point at one end of the horizontal direction of the lying down jacket body, and presetting a second lifting point at the other end of the horizontal direction of the lying down jacket body, and setting the line connecting the first lifting point and the second lifting point as an initial line;

[0047] S2, vertically lifting the first lifting point at a first lifting speed, and vertically lifting the second lifting point at a second lifting speed, while gradually reducing the horizontal distance between the first lifting point and the second lifting point, until the line connecting the first lifting point and the second lifting point is rotated 90° relative to the initial line;

[0048] S3, synchronously vertically lifting the first lifting point and the second lifting point to a preset installation height at a third lifting speed, and then installing the suction pile body vertically below the jacket body.

[0049] From the above description, the beneficial effects of the present application are as follows: first, two lifting points are respectively arranged at the two ends of the lying down jacket body, then the two lifting points are vertically lifted at different speeds, so that the lying down jacket body is lifted and turned at the same time, until the turning angle reaches 90°, then the two lifting points are lifted upward at the same speed, and finally the suction pile body is installed vertically below the jacket body. The present application adopts the method of lying down construction of the upper jacket and overall turning and lifting and splicing, realizes the lying down construction of the upper jacket, improves the construction precision and construction efficiency, and reduces the risk of high-altitude operation through turning and lifting and splicing.

[0050] A device for installing a suction pile jacket of offshore wind power is used to connect a suction pile body and a jacket body, comprising a first lifting tower and a second lifting tower;

[0051] The first lifting tower is used to hoist one end of the jacket body, the second lifting tower is used to hoist the other end of the jacket body, the lifting height of the first lifting tower is greater than the lifting height of the second lifting tower, the difference between the lifting heights of the first lifting tower and the second lifting tower is greater than or equal to the vertical height of one jacket body, the lifting height of the second lifting tower is greater than the vertical height of one suction cylinder body, and the horizontal distance between the first lifting tower and the second lifting tower is adjustable.

[0052] From the above description, the beneficial effects of the present application are that: when in use, the first lifting tower and the second lifting tower are respectively arranged on both sides of the jacket body, the difference between the lifting heights of the first lifting tower and the second lifting tower is at least the vertical height of one jacket body, thereby ensuring the smooth overturning of the jacket body, the first lifting tower and the second lifting tower gradually approach while lifting the jacket body, the lifting height of the second lifting tower is at least the vertical height of one suction cylinder body, thereby facilitating the installation of the suction cylinder body from below the jacket body, reducing the amount of high-altitude work, and the advantages of the tower structure are low investment cost, the initial investment of the entire device is about 25 million, which is much lower than the initial investment of nearly 200 million of the super-large gantry crane equipment; without tensioning cable wind ropes, the impact on the site is minimized; the foundation treatment is simple, the overall stability is good, the economic benefit is high; meet the requirements of horizontal construction and overall overturning and hoisting splicing of the upper jacket, the horizontal construction of the upper jacket can be realized, the construction precision and efficiency are improved, and the risk of high-altitude work is reduced.

[0053] Further, the first lifting tower is provided with a first lifting assembly, the first lifting assembly is connected with one end of the jacket body, the second lifting tower is provided with a second lifting assembly, and the second lifting assembly is connected with the other end of the jacket body.

[0054] From the above description, the first lifting tower and the second lifting tower are provided with lifting assemblies, the lifting assemblies are used for lifting the jacket body, control is convenient, and the cost is low.

[0055] Further, the number of the first lifting assemblies is two, the horizontal heights of the two first lifting assemblies are equal, the number of the second lifting assembly is one, and the distances between each first lifting assembly and the second lifting assembly are equal.

[0056] From the above description, such design makes the three lifting assemblies form an isosceles triangle, thereby ensuring the stability and accuracy of the lifting operation.

[0057] Further, the first lifting tower and the second lifting tower each comprise a concrete base and a tower body, the concrete base is arranged on the ground, the tower body is installed on the concrete base, the first lifting assembly is arranged on the tower body of the first lifting tower, and the second lifting assembly is arranged on the tower body of the second lifting tower.

[0058] As can be seen from the above description, the concrete base is arranged on the ground and plays a supporting and fixing role, and the tower body is arranged on the concrete base and is stable in structure and convenient to install.

[0059] Further, the tower body of the first lifting tower and the tower body of the second lifting tower each comprise a bottom section, a standard section, a top section and a girder, the bottom section is installed on the concrete base, two or more groups of the standard sections are sequentially spliced, one end of the two or more groups of the standard sections after splicing is connected with the bottom section, the top section is connected with the other end of the two or more groups of the standard sections after splicing, the girder is arranged on the top section, the first lifting assembly is arranged on the girder of the first lifting tower, and the second lifting assembly is arranged on the girder of the second lifting tower.

[0060] As can be seen from the above description, the tower body comprises a bottom section, a standard section, a top section and a girder, the bottom section, the standard section and the top section can be selected according to the construction height requirement, the girder is installed on the top section after splicing and installation, and the girder is used to install the lifting assembly to ensure the stability of the lifting structure.

[0061] Further, the first lifting assembly and the second lifting assembly each comprise a winch and a trolley group, the winch and the trolley group are connected with each other, the winch of the first lifting assembly is installed on the concrete base of the first lifting tower, the trolley group of the first lifting assembly is installed on the girder of the first lifting tower, the winch of the second lifting assembly is installed on the concrete base of the second lifting tower, and the trolley group of the second lifting assembly is installed on the girder of the second lifting tower.

[0062] As can be seen from the above description, the lifting assembly comprises a winch and a trolley group, the winch is used for winding and unwinding the hoisting rope, and the trolley group is used for traction and guidance, so as to ensure the hoisting efficiency and precision.

[0063] Further, the tower body of the first lifting tower and the tower body of the second lifting tower each comprise a balance cable, a pull rod group and a balance beam, one end of the balance cable is connected with the concrete base, the pull rod group is arranged on the girder, the other end of the balance cable is connected with one end of the pull rod group, the other end of the pull rod group is used to fix the first lifting assembly or the second lifting assembly, and the first lifting assembly and the second lifting assembly are connected with the guide pipe rack body through the balance beam.

[0064] From the above description, the tower body further comprises a balance cable, a pull rod group and a balance beam, and the combination of the three enhances the stability of the jacket main body lifting structure.

[0065] Further, the second lifting tower further comprises a walking trolley, and the tower body of the second lifting tower is arranged on the walking trolley.

[0066] From the above description, the walking trolley is used to realize the movement of the second lifting tower, so as to adjust the distance between the two lifting towers according to the lifting state.

[0067] Further, the offshore wind power suction cylinder jacket installation device further comprises an axis vehicle, and the axis vehicle is provided with a tool seat used to install the suction cylinder main body.

[0068] From the above description, the axis vehicle installs the suction cylinder main body through the tool seat, after the jacket main body is lifted to the specified position, the axis vehicle sends the suction cylinder main body to the installation area below the jacket main body, and then welding assembly is performed, and after installation, the axis vehicle drives the whole assembly to send out the installation area.

[0069] Embodiment one of the present application is an offshore wind power suction cylinder jacket installation method, which specifically comprises the following steps:

[0070] Please refer to Figures 1 to 6 , S1, a first lifting point is preset at one end of the horizontal direction of the lying jacket main body 2, a second lifting point is preset at the other end of the horizontal direction of the lying jacket main body 2, and the line connecting the first lifting point and the second lifting point is set as an initial line;

[0071] Please refer to Figure 7 , 8 , S2, the first lifting point is lifted vertically upward at a first lifting speed, the second lifting point is lifted vertically upward at a second lifting speed, and the horizontal distance between the first lifting point and the second lifting point is gradually reduced at the same time, until the line connecting the first lifting point and the second lifting point is rotated by 90° relative to the initial line;

[0072] Please refer to Figures 9 to 11 , S3, the first lifting point and the second lifting point are synchronously lifted vertically upward to a preset installation height at a third lifting speed, and then the suction cylinder main body 1 is installed vertically below the jacket main body 2.

[0073] Please refer to Figures 1 to 11 , embodiment two of the present application is an offshore wind power suction cylinder jacket installation device, which is used to connect the suction cylinder main body 1 and the jacket main body 2, and comprises a first lifting tower 3 and a second lifting tower 4.

[0074] The first lifting tower 3 is used to hoist one end of the jacket body 2, the second lifting tower 4 is used to hoist the other end of the jacket body 2, the lifting height of the first lifting tower 3 is greater than the lifting height of the second lifting tower 4, the difference between the lifting heights of the first lifting tower 3 and the second lifting tower 4 is greater than or equal to the vertical height of one jacket body 2, the lifting height of the second lifting tower 4 is greater than the vertical height of one suction cylinder body 1, and the horizontal distance between the first lifting tower 3 and the second lifting tower 4 is adjustable.

[0075] Please refer to Figures 1 to 11The embodiment three of the present application is different from the embodiment two in that the first lifting tower 3 is provided with a first lifting assembly 5 connected with one end of the jacket body 2, and the second lifting tower 4 is provided with a second lifting assembly 6 connected with the other end of the jacket body 2. The number of the first lifting assembly 5 is two, the horizontal height of the two first lifting assemblies 5 is equal, the number of the second lifting assembly 6 is one, and the distance between each first lifting assembly 5 and the second lifting assembly 6 is equal. The first lifting tower 3 is a 3200t frame type hoisting system (main hoist), namely a double hoisting point type frame lifting tower, which comprises one pair of 2.4m lifting towers and one pair of 4.2m lifting towers which are spliced with each other. The second lifting tower 4 is a 3200t frame type hoisting system (tail), namely a single hoisting point type frame tail lifting tower, which comprises two pairs of 2.4m lifting towers which are spliced with each other. The first lifting tower 3 and the second lifting tower 4 both comprise a concrete base 7 and a tower body 8, the concrete base 7 is arranged on the ground, the tower body 8 is installed on the concrete base 7, the first lifting assembly 5 is arranged on the tower body 8 of the first lifting tower 3, and the second lifting assembly 6 is arranged on the tower body 8 of the second lifting tower 4. The tower body 8 of the first lifting tower 3 and the tower body 8 of the second lifting tower 4 both comprise a bottom section 9, a standard section 10, a top section 11 and a girder 12, the bottom section 9 is installed on the concrete base 7, two or more groups of the standard sections 10 are spliced in sequence, one end of the two or more groups of the standard sections 10 after splicing is connected with the bottom section 9, the top section 11 is connected with the other end of the two or more groups of the standard sections 10 after splicing, the girder 12 is arranged on the top section 11, the first lifting assembly 5 is arranged on the girder 12 of the first lifting tower 3, and the second lifting assembly 6 is arranged on the girder 12 of the second lifting tower 4. The number of the standard section 10 of the first lifting tower 3 is 15, and the top of the girder 12 is 101.26m away from the ground. The number of the standard section 10 of the second lifting tower 4 is 5, and the top of the girder 12 is 36.18m away from the ground. The bottom section 94.5m, the standard section 106m, the top section 114.13m and the girder 12 2.63m high of the first lifting tower 3 meet the hoisting requirements of the largest specification suction cylinder jacket (h=94.8m). The bottom section 93m, the standard section 106m x 4 sections + 3m x 1 section, the top section 112.1m and the girder 12 2.63m high of the second lifting tower 4 meet the hoisting requirements.The first lifting assembly 5 and the second lifting assembly 6 each comprise a winch 13 and a block 14, the winch 13 and the block 14 are connected with each other, the winch 13 of the first lifting assembly 5 is installed on the concrete base 7 of the first lifting tower 3, the block 14 of the first lifting assembly 5 is installed on the girder 12 of the first lifting tower 3, the winch 13 of the second lifting assembly 6 is installed on the concrete base 7 of the second lifting tower 4, and the block 14 of the second lifting assembly 6 is installed on the girder 12 of the second lifting tower 4. The first lifting assembly 5 is provided with two sets of 800t hoisting blocks 14, and the hoisting capacity is 1600t; the second lifting assembly 6 is provided with two sets of 500t hoisting blocks 14, and the hoisting capacity is 1000t; the hoisting block 14 of the first lifting tower 3 and the hoisting block 14 of the second lifting tower 4 are both 2m high. The block 14 is provided with a traction steel wire rope. The total number of ropes of a single set of 800t block 14 is 36, the number of wheels is 36, and there are a total of two sets. The maximum stress of a single set of pulley block is 1141 / 2*1.2 (non-uniform coefficient) = 684.6 tons. The tower body 8 of the first lifting tower 3 and the tower body 8 of the second lifting tower 4 each comprise a balance cable 15, a pull rod group 16 and a balance beam 17, one end of the balance cable 15 is connected with the concrete base 7, the pull rod group 16 is arranged on the girder 12, the other end of the balance cable 15 is connected with one end of the pull rod group 16, the other end of the pull rod group 16 is used to fix the first lifting assembly 5 or the second lifting assembly 6, and the first lifting assembly 5 and the second lifting assembly 6 are connected with the jacket main body 2 through the balance beam 17. The second lifting tower 4 further comprises a walking trolley 18, and the tower body 8 of the second lifting tower 4 is arranged on the walking trolley 18. The walking trolley 18 is 1.45m high, and is provided with four groups and two tracks. The offshore wind power suction cylinder jacket installation device further comprises an axis vehicle 19, and the axis vehicle 19 is provided with a tool seat used for installing the suction cylinder main body 1. The axis vehicle 19 is an SPMT axis vehicle 19. The block 14 on the first lifting tower 3 and the second lifting tower 4 comprises a fixed block and a movable block, the fixed block is installed on the girder 12 and connected with the movable block through a hoisting rope, the fixed block of the first lifting tower 3 is H800*18D, the movable block is H500*18D, meets the needs of the project, the total lifting capacity of two groups of lifting points is 1600t, meets the needs of the project, the hoisting capacity utilization coefficient is 71% considering the maximum hoisting weight 1141t, and the safety of hoisting is ensured. The fixed block of the second lifting tower 4 is H500*13D, the movable block is H500*13D, the total lifting capacity of two groups of lifting points is 1000t, meets the needs of the project, the hoisting capacity utilization coefficient is 58% considering the maximum hoisting weight 581t, and the safety of hoisting is ensured.The tie rod assembly 16 includes a front tie rod, a column, and a rear tie rod. The front tie rod and the rear tie rod are arranged in a triangle, and the column is connected to the vertex of the triangle, which improves the stability of the hoisting structure.

[0076] The working principle of this embodiment is as follows:

[0077] Please refer to Figures 1 to 6 First, the SPMT axle cart 19 is used to transport the jacket frame body 2 to the designated location. First and second lifting points are pre-set on the jacket frame body 2. After installing the lifting slings, the jacket frame is lifted as a whole using the cooperation of the first lifting assembly 5. The SPMT axle cart 19 then leaves the site. Please refer to... Figure 7 , 8 Then, with the cooperation of the first lifting assembly 5 and the second lifting tower 4, the main body 2 of the jacket frame is lifted to an upright position. During the lifting process, the second lifting tower 4 is delivered via the bottom traveling trolley 18, ensuring that the rigging of both lifting systems remains vertical at all times. Please refer to... Figures 9 to 11 Next, using two sets of frame-type hoisting systems, the main body 2 of the jacket frame is hoisted to the specified elevation. Using SPMT axle truck 19, the three suction cylinder bodies 1 at the bottom of the main body 2 are transported to the vertical position below the main body 2 for alignment and welding. After installation, the suction cylinder jacket frame is loaded onto a vehicle using SPMT axle truck 19. The second lifting tower 4 is returned to the initial area, and the suction cylinder jacket frame is driven out of the hoisting area for loading onto a ship and shipping, in preparation for the next set of jacket frame main bodies 2 to be turned over and assembled.

[0078] In summary, the present application provides a kind of offshore wind power suction cylinder jacket installation method, first in the two ends of the horizontal guide frame body respectively two lifting points are set, then two lifting points are hoisted vertically at different speeds, so that the horizontal guide frame body is hoisted while being turned over, until the turning angle reaches 90 °, two lifting points are hoisted upward again at the same speed, finally suction cylinder body is installed below the vertical guide frame body.The present application adopts the method of upper guide frame horizontal construction and overall turning over hoisting and splicing, realizes the horizontal construction of upper guide frame, improves the construction precision and construction efficiency, and reduces the risk of high-altitude operation.The present application also provides a kind of offshore wind power suction cylinder guide frame installation device, when using, first lifting tower and second lifting tower are respectively set on the two sides of guide frame body, the lifting height difference of first lifting tower and second lifting tower is at least the vertical height of one guide frame body, so as to ensure the smooth turning over of guide frame body, first lifting tower and second lifting tower gradually approach while lifting guide frame body, the lifting height of second lifting tower is at least the vertical height of one suction cylinder body, so as to facilitate the installation of suction cylinder body from below guide frame body, reduce high-altitude operation amount, the advantage of tower structure is low investment cost, the initial investment of the whole device is about 25 million, which is far lower than the initial investment of nearly 200 million of super large gantry crane equipment;Without tensioning cable wind rope, the impact on site is minimized;Foundation treatment is simple, overall stability is good, economic benefit is high;Meet the requirements of upper guide frame horizontal construction and overall turning over hoisting and splicing, can realize the horizontal construction of upper guide frame, improve the construction precision and construction efficiency, and reduce the risk of high-altitude operation.Each of first lifting tower and second lifting tower is provided with lifting assembly, and lifting assembly is used for lifting guide frame body, which is convenient to control and low in cost.This design makes three lifting assemblies form an isosceles triangle, ensuring the stability and accuracy of lifting operation.Concrete base is set on the ground to play the role of supporting and fixing, tower body is set above concrete base, and the structure is stable and convenient to install.Tower body includes bottom section, standard section, top section and girder, bottom section, standard section and top section can be selected according to construction height requirement, girder is installed on top section after splicing and installation, and girder is used to install lifting assembly to ensure the stability of lifting structure.Lifting assembly includes winch and trolley group, winch is used for winding and unwinding lifting rope, and trolley group is used for pulling and guiding to ensure hoisting efficiency and accuracy.Tower body also includes balance cable, pull rod group and balance beam, and the stability of guide frame body lifting structure is enhanced by the combination of the three.Trolley is used to realize the movement of second lifting tower, so as to adjust the distance between two lifting towers according to hoisting state.Axial vehicle is used to install suction cylinder body, after guide frame body is hoisted to specified position, axial vehicle sends suction cylinder body to the installation area below guide frame body, welding and assembly are carried out, and after installation, axial vehicle drives the whole assembly out of installation area.

[0079] The above merely illustrates the embodiments of the present application, and is not intended to limit the patent scope of the present application. Any equivalent transformation or direct or indirect application in the related technical field based on the content of the present application specification and drawings is also included in the patent protection scope of the present application.

Claims

1. A method for installing a suction cylinder guide frame, characterized in that, The suction cylinder guide frame installation device is used to connect the suction cylinder body and the guide frame body. The suction cylinder guide frame installation device includes a first lifting tower and a second lifting tower. The first lifting tower is used to hoist one end of the jacket frame body, and the second lifting tower is used to hoist the other end of the jacket frame body. The lifting height of the first lifting tower is greater than the lifting height of the second lifting tower. The difference between the lifting heights of the first lifting tower and the second lifting tower is greater than or equal to the vertical height of one jacket frame body. The lifting height of the second lifting tower is greater than the vertical height of one suction cylinder body. The horizontal distance between the first lifting tower and the second lifting tower is adjustable. The installation method for the suction cylinder guide frame includes the following steps: S1. A first suspension point is preset at one end of the horizontal direction of the lying-down jacket main body, and a second suspension point is preset at the other end of the horizontal direction of the lying-down jacket main body. The line connecting the first suspension point and the second suspension point is set as the initial line. S2. Lift the first lifting point vertically upward at the first lifting speed, and lift the second lifting point vertically upward at the second lifting speed. At the same time, adjust the horizontal distance between the first and second lifting points to gradually decrease until the line connecting the first and second lifting points rotates 90° relative to the initial line. S3. Simultaneously lift the first and second lifting points vertically upwards to the preset installation height at the third lifting speed, and then install the suction cylinder body vertically below the main body of the guide frame.

2. A suction cylinder guide frame mounting device for connecting the suction cylinder body and the guide frame body, characterized in that, Including the first lifting tower and the second lifting tower; The first lifting tower is used to hoist one end of the jacket frame body, and the second lifting tower is used to hoist the other end of the jacket frame body. The lifting height of the first lifting tower is greater than the lifting height of the second lifting tower. The difference between the lifting heights of the first lifting tower and the second lifting tower is greater than or equal to the vertical height of one jacket frame body. The lifting height of the second lifting tower is greater than the vertical height of one suction cylinder body. The horizontal distance between the first lifting tower and the second lifting tower is adjustable. The first lifting tower is provided with a first lifting component, which is connected to one end of the jacket main body; the second lifting tower is provided with a second lifting component, which is connected to the other end of the jacket main body. There are two first lifting components, and the two first lifting components are at the same horizontal height. There is one second lifting component, and the distance between each first lifting component and each second lifting component is equal. Both the first lifting tower and the second lifting tower include a concrete base and a tower body. The concrete base is set on the ground, and the tower body is installed on the concrete base. The first lifting component is set on the tower body of the first lifting tower, and the second lifting component is set on the tower body of the second lifting tower.

3. The suction cylinder guide frame installation device according to claim 2, characterized in that, The tower body of the first lifting tower and the tower body of the second lifting tower both include a bottom section, a standard section, a top section, and a main beam. The bottom section is installed on a concrete base. Two or more sets of the standard sections are spliced ​​together in sequence. One end of the spliced ​​two or more sets of the standard sections is connected to the bottom section. The top section is connected to the other end of the spliced ​​two or more sets of the standard sections. The main beam is set on the top section. The first lifting assembly is set on the main beam of the first lifting tower, and the second lifting assembly is set on the main beam of the second lifting tower.

4. The suction cylinder guide frame installation device according to claim 3, characterized in that, Both the first lifting assembly and the second lifting assembly include a winch and a pulley block, which are connected to each other. The winch of the first lifting assembly is installed on the concrete base of the first lifting tower, and the pulley block of the first lifting assembly is installed on the main beam of the first lifting tower. The winch of the second lifting assembly is installed on the concrete base of the second lifting tower, and the pulley block of the second lifting assembly is installed on the main beam of the second lifting tower.

5. The suction cylinder guide frame installation device according to claim 3, characterized in that, The tower body of the first lifting tower and the tower body of the second lifting tower both include a balance cable, a tie rod assembly and a balance beam. One end of the balance cable is connected to the concrete base. The tie rod assembly is set on the main beam. The other end of the balance cable is connected to one end of the tie rod assembly. The other end of the tie rod assembly is used to fix the first lifting component or the second lifting component. Both the first lifting component and the second lifting component are connected to the main body of the guide frame through the balance beam.

6. The suction cylinder guide frame installation device according to claim 2, characterized in that, The second lifting tower also includes a traveling trolley, on which the tower body of the second lifting tower is mounted.

7. The suction cylinder guide frame installation device according to claim 2, characterized in that, The suction cylinder guide frame installation device also includes an axle trolley, which is equipped with a tooling seat for installing the suction cylinder body.

Citation Information

Patent Citations

  • A method and device for installing an offshore wind power suction tube pipe frame

    CN112064662B

  • Offshore wind power suction cylinder jacket mounting device

    CN212612602U