App-based power grid project feasibility research design process management system
By developing an App-based power grid engineering feasibility design process management system, the problems of delayed power grid engineering process management, lack of data, and inability to effectively control progress are solved, and efficient process management and data management are achieved.
Patent Information
- Application Number
- CN202411589259.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-08
- Publication Date
- 2025-03-25
AI Technical Summary
The existing power grid engineering process management has problems such as delay, lack of data, and ineffective progress, resulting in inefficiency.
Develop a feasibility study design process management system for power grid engineering based on app. Through mobile communication tools, wireless communication networks and backend servers, the mobile design process management system and anti-loss functions of data management are realized, which facilitates centralized management and unified control.
It achieves timely grasping the completion of work and effectively controlling the progress. At the same time, the storage and query of project data and task orders are convenient, which helps standardize process management and improve work efficiency.
Smart Images

Figure CN119692923A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the field of project process management, and in particular relates to an App-based power grid engineering feasibility study design process management system. Background Art
[0002] In a project management environment, according to plan requirements, many businesses require the participation of multiple stakeholders inside and outside the enterprise, including design review, specification input, issuance of work orders, stage acceptance, results acceptance, etc.
[0003] Under the traditional management model, these businesses are often forced to be interrupted into multiple processes, resulting in delays, missing data and other problems at the process connections. Users have to repeat the process or supervise manually, resulting in low work efficiency.
[0004] The existing distribution network engineering design task management usually involves manually filling out task sheets and placing orders manually, which results in managers being unable to grasp the completion status of work in a timely manner and unable to effectively control the progress. At the same time, there are many inconveniences in the storage and query of engineering data and task sheets.
[0005] The invention patent application with the application publication date of October 11, 2022 and the application publication number CN 115170060A discloses "A blockchain-based power grid project site visa management method and system", including: S1. Based on the existing visa business, from the three aspects of existing visa types and processes, visa participants and their permissions, and visa business management methods, combined with blockchain technology, adopt a suitable blockchain type to establish a visa contract framework; S2. Based on the basic visa framework, establish the core functional modules of the visa business, improve the contract algorithm and process, and simulate all participants with administrator permissions to conduct feasibility simulation experiments; S3. Based on the results of the feasibility simulation experiment, actually apply the visa contract algorithm to the power grid engineering business visa business, feedback optimization, adapt to various dynamic changes, adopt a contract incentive mechanism, optimize existing contracts, and propose new contracts; S4. Based on the blockchain visa process, conduct multi-dimensional traceability evaluation based on actual use cases, including execution time, cost, number of uses, participants, effect feedback, etc.
[0006] The invention patent application with the application publication date of 2021.02.19 and application publication number CN 112380549A discloses "a method for managing statistical data of power grid engineering project investment based on blockchain". By establishing a data management framework for power grid investment engineering projects based on blockchain, it can achieve decentralized data sharing and data security storage in a distributed system where distributed nodes / departments do not need to fully trust each other through the use of data certificates, data encryption, workload authentication, distributed consensus and smart contracts. It provides an effective and feasible solution to the problems of high cost and low efficiency of centralized data platforms, and provides a basis for promoting lean data management of power grid engineering projects and improving the standardization of project process management.
[0007] Although the above technical solution focuses on decentralization and data confidentiality requirements, it requires strong support from high-performance computer systems and is not suitable for operation and use by ordinary technicians, which brings certain inconveniences to its specific implementation and use. Summary of the invention
[0008] The technical problem to be solved by the present invention is to provide an App-based power grid project feasibility study design process management system. It realizes the mobility of the design process management system and the anti-loss function of data information through mobile communication tools, wireless communication networks and background servers, which is convenient for centralized management and unified control, and is used to solve the current problems of delayed process management of distribution network projects, missing data, and inability to effectively control progress, resulting in low work efficiency.
[0009] The technical solution of the present invention is to provide an App-based power grid project feasibility study design process management system, which is characterized by:
[0010] Including engineering management app and engineering management background;
[0011] The engineering management App is connected to the engineering management backend by wireless communication;
[0012] The engineering management backend includes a system management module, a project management module, a project link management module, and a record query module;
[0013] The engineering management background is set in the server;
[0014] By sequentially creating projects, creating design tasks, managing the progress of each design node and managing files in the engineering management App, corresponding data information is generated after the above process is completed, and the corresponding data information is queried and configured by entering the engineering management background.
[0015] Specifically, the system management function module includes three submodules: user management, role management, and permission management. User management content includes user name, mobile phone number, login account name, login password, and user role; role management content includes role name, affiliated unit, and permission category of the role; permission management includes permission category and the functional permissions that can be used by the category; the above management content is uniformly created, managed, and configured by the operation and maintenance personnel. After logging in to the engineering management app, the user information of the corresponding account is obtained. The engineering app can only view but not modify.
[0016] Specifically, the project management function module includes adding projects, modifying project information, deleting project information, and project query. The project information includes: project name, project code, application unit, application date, project nature, project description, project attachments, and project notes; the project query includes: query by start date and end date, and query by user input content.
[0017] Specifically, the project management function module includes five sub-modules: line and site selection, feasibility study design, feasibility study review, feasibility study approval, and environmental impact assessment and water conservation.
[0018] Furthermore, the line selection and site selection functions include three functions: "line selection / site selection", "line selection review" and "line selection approval".
[0019] Specifically, the App-based power grid project feasibility study design process management system participates in management work and data input work including review, specification input, issuance of work orders, stage acceptance, and results acceptance through App software installed on network systems and mobile communication tools. Its management information processing process is clear, which facilitates the participation of multiple stakeholders inside and outside the enterprise.
[0020] Furthermore, after the engineering management background creates the design task, it automatically creates a line selection and site selection task based on the content of the design task. The content of the line selection and site selection task includes the associated feasibility study design number, review of the feasibility study design, review of related projects, line selection unit, line selection entrustment content, line selection entrustment letter, line selection unit person in charge and contact information, line selection task description, and completion progress information.
[0021] Specifically, the system will verify relevant information when performing various operations:
[0022] A. When logging into the Project Management App, follow these steps:
[0023] a1. The project management background verifies whether the account information exists and the account password is correct;
[0024] a2. Check whether the user's usage period has expired. If it has expired, a prompt "Account Expired" will be returned;
[0025] a3. Obtain user permission information after successful login;
[0026] B. When the project management backend receives a request to create a new project, it performs the following verification:
[0027] b1. Determine whether the project already exists. If not, insert the project information into the database. If it does exist, prompt "Project already exists" and feedback to the App user.
[0028] b2. After the project is successfully created, the project progress status is set to 0 and the result is fed back to the App to display.
[0029] C. When the engineering management background receives a request for a new feasibility study design task, it performs the following verification:
[0030] c1. Determine whether the feasibility study design task already exists for the project. If not, insert the feasibility study design information into the database. If so, prompt "Feasibility study design already exists" and feedback to the App user.
[0031] c2. After the engineering management background creates the design task, it determines whether there is a corresponding line selection and site selection task for the design. If not, the line selection and site selection information is inserted into the database. If so, it prompts "The line selection and site selection task already exists" and feedback is given to the App user.
[0032] D. When the project management backend receives the "Submit" request, it performs the following verification:
[0033] d1. Determine whether the current project progress information has changed. If it has changed, set the update time to the current time. If it has not changed, do nothing.
[0034] d2. Determine whether the received progress information is "100%". If so, further determine the current stage of the project and perform the following operations:
[0035] If the current status is "line selection and site selection", the project status is set to the "feasibility study and design" stage;
[0036] If the current status is "Feasibility Study Design", set the project status to "Feasibility Study Review" stage;
[0037] If the current status is "Feasibility Study Review", set the project status to "Feasibility Study Approval" stage;
[0038] If the current status is "Feasibility Study Approval", the project status will be set to "Environmental Assessment and Water Conservation" stage;
[0039] If the current status is "Environmental Impact Assessment and Water Conservation", set the project status to Completed.
[0040] The App-based power grid engineering feasibility study and design process management system described in the present invention can timely grasp the work completion status and effectively control the progress. At the same time, the storage and query of engineering data and task orders are convenient, which helps to standardize process management, improve work efficiency, and solve the problems of delayed process management of distribution network projects, missing data, and ineffective progress control leading to low work efficiency.
[0041] Compared with the prior art, the advantages of the present invention are:
[0042] 1. The technical solution of the present invention participates in the management and data input work of the design review, specification input, work order issuance, stage acceptance, and results acceptance stages through the App software installed on the network system and mobile communication tools. The management information processing flow is clear, which is convenient for multiple stakeholders inside and outside the enterprise to participate. Other relevant personnel can view the corresponding project information through the App.
[0043] 2. In the technical solution of the present invention, the management content is uniformly created, managed and configured by the operation and maintenance personnel. After the user logs in to the engineering management App, the user information of the corresponding account is obtained. The engineering App can only view but not modify it, which facilitates unified management.
[0044] 3. The technical solution of the present invention can timely grasp the status of work completion and effectively control the progress. At the same time, the storage and query of engineering data and task orders are convenient, which helps to standardize process management and improve work efficiency. It solves the current problems of delayed distribution network engineering process management, missing data, and ineffective progress control leading to low work efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0045] Figure 1 It is a schematic diagram of the structure of a power grid project feasibility study design process management system based on App of the present invention;
[0046] Figure 2 It is a schematic diagram of the feasibility study design management information processing flow and personnel authority allocation of the present invention. DETAILED DESCRIPTION
[0047] The present invention will be further described below in conjunction with the accompanying drawings.
[0048] The present invention is a power grid engineering feasibility study design process management system based on App, and its structural composition diagram is shown in Figure 1 The system includes an engineering management app and an engineering management background, the engineering management app is connected to the engineering management background, and the engineering management background includes a system management module, a project management module, a project link management module, and a record query module.
[0049] By sequentially creating projects, creating design tasks, managing the progress of each design node, and managing files in the engineering management App, after the above process is completed, corresponding data information is generated, and the corresponding data information is queried and configured by entering the engineering management background. In the present invention, when the engineering management personnel enter the engineering information, other relevant personnel can view the corresponding engineering information through the App.
[0050] The project management function module in the above system includes adding projects, modifying project information, deleting project information, and project query. The project information includes: project name, project code, application unit, application date, project nature, project description, project attachments, and project notes; the project query includes: query by start date and end date, and query by user input content.
[0051] The project management functional modules described in the system include five sub-modules: line and site selection, feasibility study design, feasibility study review, feasibility study approval, and environmental impact assessment and water conservation.
[0052] The system management function module in the above system includes three sub-modules: user management, role management, and permission management. The user management content includes the user name, mobile phone number, login account name, login password, and the user's role; the role management content includes the role name, the unit to which it belongs, and the permission category to which the role belongs; the permission management includes the permission category and the functional permissions that can be used by the category. The above management content is uniformly created, managed, and configured by the operation and maintenance personnel. After logging in to the engineering management app, the user information of the corresponding account is obtained. The engineering app can only be viewed but not changed.
[0053] Specifically, Figure 2 As shown in , the creation of a project in the above system includes the following steps:
[0054] Step 101, log in to the project management app to obtain user information and permission information;
[0055] Step 102: Enter the project management module and press the “⊕” button in the lower right corner of the interface to enter the new project interface;
[0056] Step 103, fill in the applicant unit, application date, project name, project code, project nature, project description, upload project attachments, fill in project remarks information, and click the "Submit" button to initiate a request to create a project.
[0057] Step 104: After receiving the request to create a project, the project management background inserts the newly created project information into the project record table and updates the project information in the "project list".
[0058] The creation of the design task in the above system includes the following steps:
[0059] Step 201: Log in to the project management app to obtain user information and permission information;
[0060] Step 202: Enter the project management module, enter the feasibility study design sub-function interface, press the "⊕" button in the lower right corner of the interface, and enter the new design task interface;
[0061] Step 203, fill in the design number, commissioning unit, application date, person in charge of the commissioning unit and telephone number, select the design unit to obtain the design unit profile, person in charge and telephone information, select the project to obtain the project code and project nature information, select the deadline, fill in the design basis, upload basic information, fill in the main content of the design, fill in the project notes, select the project geophysical information, click the "Submit" button to initiate a request to create a design task, or click the "Save" button to temporarily store the filled in information without performing the project creation operation.
[0062] Step 204: After receiving the request to create a design task, the engineering management background inserts the newly created project information into the design task record table and updates the project information in the "design task list".
[0063] Step 205. After the engineering management background creates the design task, it will automatically create a line selection and site selection task based on the content of the design task. The content of the line selection and site selection task includes the associated feasibility study design number, viewing the feasibility study design, viewing the associated projects, the line selection unit, the line selection entrustment content, the line selection entrustment letter, the person in charge of the line selection unit and contact information, the line selection task description, and the completion progress information.
[0064] The progress management and file management of each design node in the above system includes the following steps:
[0065] Step 301, after entering the project link management module, click "line selection and site selection" to enter the corresponding sub-function module, the sub-functions include "line selection / site selection", "line selection review", and "line selection approval".
[0066] Step 302, under the "Line Selection / Site Selection" submodule, click the "Line Selection / Site Selection" button to obtain background data, and display all the project contents in the "Line Selection / Site Selection" stage. The displayed content includes: design number, related project name, overall project progress percentage, and search and filter by start date, end date and user input content.
[0067] Step 303, after screening, select the corresponding project information to be operated, enter the line selection / site selection information editing operation, after the user edits the line selection / site selection information, click the "Submit" button to initiate a request to modify the line selection / site selection information, or click the "Save" button to temporarily store the filled information without modifying the line selection / site selection information. When the user sets the line selection / site selection progress information to 100%, the interface will prompt the user to enter the person in charge and contact information for the next stage. When the user enters this information and clicks the "Submit" button, the project will enter the line selection review stage, and send a project progress notification to all other users. The notification content includes: project name, project stage, date, and person in charge of the next stage.
[0068] Step 304, under the "Line Selection and Site Selection" submodule, click the "Line Selection and Review" button to obtain background data, and display all the project contents in the "Line Selection and Review" stage. The displayed content includes: design number, related project name, overall project progress percentage, and search and filter by start date, end date and user input content.
[0069] Step 305: After screening, select the corresponding project information to be operated, and enter the line selection and review information editing operation. After the user edits the line selection and review information, click the "Submit" button to initiate a request to modify the line selection and review information. You can also click the "Save" button to temporarily store the filled information without modifying the line selection and review information. When the user sets the line selection and review progress information to 100%, the interface will prompt the user to enter the person in charge and contact information for the next stage. When the user enters this information and clicks the "Submit" button, the project will enter the line selection approval stage and send a project progress notification to all other users. The notification content includes: project name, project stage, date, and person in charge of the next stage.
[0070] Step 306. Under the "Line Selection and Site Selection" submodule, click the "Line Selection Approval" button to obtain background data, and display all the project contents in the "Line Selection Approval" stage. The displayed content includes: design number, related project name, and overall project progress percentage, and search and filter by start date, end date, and user input content.
[0071] Step 307, after screening, select the corresponding project information to be operated, enter the line selection approval information editing operation, after the user edits the line selection approval information, click the "Submit" button to initiate a request to modify the line selection approval information, or click the "Save" button to temporarily store the filled information without modifying the line selection approval information. When the user sets the line selection review progress information to 100%, the interface will prompt the user to enter the person in charge and contact information for the next stage. When the user enters this information and clicks the "Submit" button, the project will enter the feasibility study design stage, and send a project progress notification to all other users. The notification content includes: project name, project stage, date, and person in charge of the next stage.
[0072] Step 308: After entering the project phase management module, click the "Feasibility Study and Design" button to obtain background data and display all the project contents in the feasibility study and design phase. The displayed content includes: design number, related project name, and overall project progress percentage, and search and filter by start date, end date, and user input content.
[0073] Step 309, after screening, select the corresponding project information to be operated, enter the feasibility study design information editing operation, after the user edits the feasibility study design information, click the "Submit" button to initiate a request to modify the feasibility study design information, or click the "Save" button to temporarily store the filled information without modifying the feasibility study design information. When the user sets the feasibility study design progress information to 100%, the interface will prompt the user to enter the person in charge and contact information for the next stage. When the user enters this information and clicks the "Submit" button, the project will enter the feasibility study review stage, and a project progress notification will be issued to all other users. The notification content includes: project name, project stage, date, and person in charge of the next stage.
[0074] Step 310, after entering the project phase management module, click the "Feasibility Study Review" button to obtain background data, and display all the project contents in the feasibility study review phase. The displayed content includes: design number, related project name, overall project progress percentage, and search and filter by start date, end date and user input content.
[0075] Step 311, after screening, select the corresponding project information to be operated, enter the feasibility study review information editing operation, after the user edits the feasibility study review information, click the "Submit" button to initiate a request to modify the feasibility study review information, or click the "Save" button to temporarily store the filled information without modifying the feasibility study review information. When the user sets the feasibility study review progress information to 100%, the interface will prompt the user to enter the person in charge and contact information for the next stage. When the user enters this information and clicks the "Submit" button, the project will enter the feasibility study approval stage, and a project progress notification will be issued to all other users. The notification content includes: project name, project stage, date, and person in charge of the next stage.
[0076] Step 312, after entering the project phase management module, click the "Feasibility Study Approval" button to obtain background data, and display all the project contents in the feasibility study review phase. The displayed content includes: design number, related project name, overall project progress percentage, and search and filter by start date, end date and user input content.
[0077] Step 313, after screening, select the corresponding project information to be operated, enter the feasibility study approval information editing operation, after the user edits the feasibility study approval information, click the "Submit" button to initiate a request to modify the feasibility study approval information, or click the "Save" button to temporarily store the filled information without modifying the feasibility study approval information. When the user sets the feasibility study approval progress information to 100%, the interface will prompt the user to enter the person in charge and contact information for the next stage. When the user enters this information and clicks the "Submit" button, the project will enter the environmental impact assessment and water conservation stage, and send a project progress notification to all other users. The notification content includes: project name, project stage, date, and person in charge of the next stage.
[0078] Step 314, after entering the project link management module, click the "Environmental Assessment / Soil and Water Conservation" button to obtain background data, and display all the project contents in the environmental assessment / water and water conservation link. The displayed content includes: design number, related project name, overall project progress percentage, and search and filter by start date, end date and user input content.
[0079] Step 315, after screening, select the corresponding project information to be operated, enter the environmental assessment / water and soil conservation information editing operation, after the user edits the environmental assessment / water and soil conservation information, click the "Submit" button to initiate a request to modify the environmental assessment / water and soil conservation information, or click the "Save" button to temporarily store the filled information without modifying the environmental assessment / water and soil conservation information. When the user sets the environmental assessment / water and soil conservation progress information to 100%, the interface will prompt the user to enter the person in charge and contact information for the next stage. When the user enters this information and clicks the "Submit" button, the project will be marked as completed, and a project progress notification will be issued to all other users. The notification content includes: project name, project completion status, and date.
[0080] The above system will perform the following information verification when performing various operations:
[0081] When the Engineering Management App logs in, follow these steps:
[0082] a1. The project management background verifies whether the account information exists and the account password is correct;
[0083] a2. Check whether the user's usage period has expired. If it has expired, a prompt "Account Expired" will be returned;
[0084] a3. Obtain user permission information after successful login;
[0085] When the project management background receives a request to create a new project, it performs the following verification:
[0086] b1. Determine whether the project already exists. If not, insert the project information into the database. If it does exist, prompt "Project already exists" and feedback to the App user.
[0087] b2. After the project is successfully created, the project progress status is set to 0 and the result is fed back to the App to display.
[0088] When the project management background receives a request for a new feasibility study design task, it performs the following verification processing:
[0089] c1. Determine whether the feasibility study design task already exists for the project. If not, insert the feasibility study design information into the database. If so, prompt "Feasibility study design already exists" and feedback to the App user.
[0090] c2. After the engineering management background creates the design task, it determines whether there is a corresponding line selection and site selection task for the design. If not, the line selection and site selection information is inserted into the database. If so, it prompts "The line selection and site selection task already exists" and feedback is given to the App user.
[0091] When the project management backend receives the "Submit" request, it performs the following verification:
[0092] d1. Determine whether the current project progress information has changed. If it has changed, set the update time to the current time. If it has not changed, do nothing.
[0093] d2. Determine whether the received progress information is "100%". If so, further determine the current stage of the project and perform the following operations:
[0094] If the current status is "line selection and site selection", the project status is set to the "feasibility study and design" stage;
[0095] If the current status is "Feasibility Study Design", set the project status to "Feasibility Study Review" stage;
[0096] If the current status is "Feasibility Study Review", set the project status to "Feasibility Study Approval" stage;
[0097] If the current status is "Feasibility Study Approval", the project status will be set to "Environmental Assessment and Water Conservation" stage;
[0098] If the current status is "Environmental Impact Assessment and Water Conservation", set the project status to Completed.
[0099] The record query module of the above system includes query by project record, query by feasibility study and design record, query by project link, query by date, and query by user input content.
[0100] The technical solution of the present invention is to create projects, create design tasks, manage the progress of each design node and manage files in the engineering management App in sequence. After the above processes are completed, corresponding data information is generated, and the corresponding data information is queried and configured by entering the engineering management background. It realizes the mobility of the design process management system and the anti-loss function of data information through mobile communication tools, wireless communication networks and background servers, which is convenient for centralized management and unified control.
[0101] The present invention can be widely used in the management field of electric power design process systems.
Claims
1. An App-based power grid project feasibility study design process management system, characterized by: Including engineering management app and engineering management background; The engineering management App is connected to the engineering management backend by wireless communication; The engineering management backend includes a system management module, a project management module, a project link management module, and a record query module; The engineering management background is set in the server; By sequentially creating projects, creating design tasks, managing the progress of each design node and managing files in the engineering management App, corresponding data information is generated after the above process is completed, and the corresponding data information is queried and configured by entering the engineering management background.
2. The App-based power grid project feasibility study design process management system according to claim 1 is characterized by: The system management function module includes three sub-modules: user management, role management, and permission management. The user management content includes the user name, mobile phone number, login account name, login password, and the user's role; the role management content includes the role name, the unit to which it belongs, and the permission category to which the role belongs; the permission management includes the permission category and the functional permissions that can be used by the category; the above management content is uniformly created, managed, and configured by the operation and maintenance personnel. After logging in to the engineering management app, the user information of the corresponding account is obtained. The engineering app can only view but not modify.
3. The App-based power grid project feasibility study design process management system according to claim 1 is characterized by: The project management function module includes adding projects, modifying project information, deleting project information, and project query. The project information includes: project name, project code, application unit, application date, project nature, project description, project attachments, and project notes; the project query includes: query by start date and end date, and query by user input content.
4. The App-based power grid project feasibility study design process management system according to claim 1 is characterized by: The project management function module includes five sub-modules: line selection and site selection, feasibility study design, feasibility study review, feasibility study approval, and environmental impact assessment and water conservation.
5. The App-based power grid project feasibility study design process management system according to claim 4, characterized in that The line selection and site selection functions include three functions: "line selection / site selection", "line selection review" and "line selection approval".
6. The App-based power grid project feasibility study design process management system according to claim 1 is characterized by: The App-based power grid project feasibility study design process management system participates in management work and data input work including review, specification input, issuance of work orders, stage acceptance, and results acceptance through App software installed on network systems and mobile communication tools. Its management information processing process is clear, which is convenient for multiple stakeholders inside and outside the enterprise to participate.
7. The App-based power grid project feasibility study design process management system according to claim 1 is characterized by: After the engineering management background creates the design task, it automatically creates the line selection and site selection task based on the content of the design task. The content of the line selection and site selection task includes the associated feasibility study design number, viewing the feasibility study design, viewing the associated projects, the line selection unit, the line selection entrustment content, the line selection entrustment letter, the person in charge of the line selection unit and contact information, the line selection task description, and the completion progress information.
8. The App-based power grid project feasibility study design process management system according to claim 1 is characterized by: The system will verify relevant information when performing various operations.
9. The App-based power grid project feasibility study design process management system according to claim 8 is characterized by: A. When logging into the Project Management App, follow these steps: a1. The project management background verifies whether the account information exists and the account password is correct; a2. Check whether the user's usage period has expired. If it has expired, a prompt "Account Expired" will be returned; a3. Obtain user permission information after successful login; B. When the project management backend receives a request to create a new project, it performs the following verification: b1. Determine whether the project already exists. If not, insert the project information into the database. If it does exist, prompt "Project already exists" and feedback to the App user. b2. After the project is successfully created, the project progress status is set to 0 and the result is fed back to the App to display. C. When the engineering management background receives a request for a new feasibility study design task, it performs the following verification: c1. Determine whether the feasibility study design task already exists in the project. If not, insert the feasibility study design information into the database. If it exists, prompt "Feasibility study design already exists" and feedback to the App user. c2. After the engineering management background creates the design task, it determines whether there is a corresponding line selection and site selection task for the design. If not, the line selection and site selection information is inserted into the database. If so, it prompts "The line selection and site selection task already exists" and feedback is given to the App user. D. When the project management backend receives the "Submit" request, it performs the following verification: d1. Determine whether the current project progress information has changed. If it has changed, set the update time to the current time. If it has not changed, do nothing. d2. Determine whether the received progress information is "100%". If so, further determine the current stage of the project and perform the following operations: If the current status is "Line Selection and Site Selection", the project status is set to "Feasibility Study and Design" stage; If the current status is "Feasibility Study Design", set the project status to "Feasibility Study Review" stage; If the current status is "Feasibility Study Review", set the project status to "Feasibility Study Approval" stage; If the current status is "Feasibility Study Approval", set the project status to "Environmental Assessment and Water Conservation" stage; If the current status is "Environmental Impact Assessment and Water Conservation", set the project status to Completed.
10. The App-based power grid project feasibility study design process management system according to claim 1, characterized in that The App-based power grid project feasibility study and design process management system can timely grasp the work completion status and effectively control the progress. At the same time, the storage and query of engineering data and task orders are convenient, which helps to standardize process management, improve work efficiency, and solve the problems of delayed distribution network project process management, missing data, and ineffective progress control leading to low work efficiency.
Citation Information
Patent Citations
Power grid engineering project investment statistical data management method based on blockchain
CN112380549A
Power grid project field visa management method and system based on block chain
CN115170060A
Electric power engineering project review system
CN109858751A
Solution system for managing engineering based on engineering app
CN110189109A
Medium and low voltage power distribution network project review management system and method
CN114997814A