Secondary spray cooling method and device for continuous casting of square billets
By independently adjusting the spray water volume of each cooling zone in the secondary spray cooling system for continuous casting of square billets, especially the spray water volume on the inner arc side of the billet, the problem of uneven cooling on the four sides of the billet is solved, uniform cooling and dimensional stability of the four sides of the billet are achieved, and operational complexity and cost are reduced.
Patent Information
- Application Number
- CN202411967087.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-30
- Publication Date
- 2025-09-16
- Estimated Expiration
- 2044-12-30
AI Technical Summary
The existing secondary spray cooling system for continuous casting of square billets cannot achieve uniform cooling of the four sides of the billet, resulting in large dimensional deviation of the billet before it enters the straightening machine, which increases the difficulty of straightening the billet in the straightening machine.
The spray water volume is independently adjusted in each cooling zone, especially the spray water volume on the inner arc side of the billet is smaller than that on the outer arc side, left side and right side. By adjusting the spray water volume on the inner arc side of the billet, its cooling intensity is made equivalent to that of the other three sides, thereby achieving uniform cooling of the four sides of the billet.
The uniform cooling of the four sides of the billet is achieved, the dimensional deviation of the billet before entering the straightening machine is reduced, the operation is simplified and the cost is reduced.
Smart Images

Figure CN119733810B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of continuous casting in iron and steel metallurgy, and in particular relates to a method and device for secondary spray cooling during continuous casting of square billets. Background Art
[0002] The continuous casting of square billets generally adopts a full-arc model, and its secondary spray cooling system generally has 4 to 5 cooling zones arranged in sequence. Among them, the first zone is the foot roller section, which is located at the outlet of the crystallizer, and the remaining zones are arc sections. Each cooling zone uses spraying to cool the four sides of the billet; due to the different cooling intensity requirements of each cooling zone, the spray water volume of each cooling zone is controlled independently, but in each cooling zone, the spray water volume on the four sides of the billet is not independently controlled, so the four sides of the billet in each cooling zone receive basically the same amount of spray water.
[0003] Although the current secondary spray cooling system can quickly cool the ingot and prevent large bulging during production, it cannot achieve uniform cooling of the four sides of the ingot. Therefore, the actual size of the ingot before entering the straightening machine will deviate significantly from the expected size, increasing the difficulty of subsequent straightening in the straightening machine. Summary of the Invention
[0004] The purpose of the present invention is to provide a billet continuous casting secondary spray cooling method and a billet continuous casting secondary spray cooling device. The present invention can achieve uniform cooling of the four sides of the billet, with low cost and strong practicability.
[0005] The technical solution adopted in the present invention is:
[0006] A method for secondary spray cooling of continuous casting of square billets, wherein the spray water volume of each cooling zone is independently adjusted according to the different cooling intensity requirements of each cooling zone; for one or more arc-shaped cooling zones, within the same cooling zone, only the spray water volume on the inner arc side of the billet can be independently adjusted. By adjusting the spray water volume on the inner arc side of the billet, the spray water volume on the inner arc side of the billet is made smaller than the spray water volume on the outer arc side of the billet, the left side of the billet, and the right side of the billet.
[0007] Preferably, the second partition is selected so that only the amount of spray water on the inner arc side of the billet can be adjusted separately; or, the second and third partitions are selected so that only the amount of spray water on the inner arc side of the billet can be adjusted separately.
[0008] Preferably, before the continuous casting starts, a trial spray is carried out to observe whether the flow indication on the cooling zone main pipeline can reach the design value: if it can, it means that the spray water bars in the cooling zone are not blocked; if not, it means that the spray water bars in the cooling zone are blocked. Then, the pressure indications on the branch pipes of the spray water bars corresponding to the four sides of the ingot are further observed. If there is a branch pipe with a relatively significantly high pressure indication, it is determined that the spray water bars on the branch pipe are blocked. If the pressure indications on the four branch pipes are not much different, it is determined that the spray water bars on the four branch pipes are all blocked.
[0009] Preferably, after the continuous casting machine starts casting, when adjusting the amount of spray water on the inner arc side of the ingot, observe the pressure indications on the branch pipes of the spray water strips corresponding to the four sides of the ingot, compare the pressure indications on the branch pipes of the spray water strips corresponding to the inner arc side of the ingot with the pressure indications on the branch pipes of the spray water strips corresponding to the other three sides of the ingot, and make the difference within a certain range through adjustment.
[0010] Preferably, after the continuous casting machine starts casting, the bulging of the left and right sides and the inner and outer arc surfaces of the ingot is measured offline. If the difference between the bulging amount of the left and right sides and the bulging amount of the inner and outer arc surfaces increases, the amount of water sprayed on the inner arc side of the ingot is further reduced until the difference between the bulging amount of the left and right sides and the bulging amount of the inner and outer arc surfaces is within a certain range.
[0011] A secondary spray cooling device for continuous casting of square billets comprises several cooling zones arranged in sequence, each cooling zone is equipped with a spray water strip for spray cooling the four sides of the billet, four branch pipes for supplying water to the spray water strips corresponding to the four sides of the billet, a main pipe for supplying water to the four branch pipes, and a main regulating valve arranged on the main pipe, wherein the main regulating valve is used to adjust the overall cooling intensity of the cooling zone; for the cooling zones with one or more arc segments, a branch regulating valve is provided on the branch pipe of the spray water strip corresponding to the inner arc side of the billet, and the branch regulating valve is used to adjust the amount of spray water on the inner arc side of the billet, so that the amount of spray water on the inner arc side of the billet in the same cooling zone is less than the amount of spray water on the outer arc side, the left side of the billet and the right side of the billet.
[0012] Preferably, a sub-regulating valve is set on the branch pipe of the spray water strip corresponding to the inner arc side of the casting blank in the second partition; or, a sub-regulating valve is set on the branch pipe of the spray water strip corresponding to the inner arc side of the casting blank in the second and third partitions.
[0013] Preferably, the main pipeline is further provided with a manual valve, a flow detection component and a pressure detection component, and each branch pipeline is also provided with a pressure detection component.
[0014] Preferably, the sub-regulating valves and pressure detection components on each sub-pipeline are arranged outside the secondary cooling chamber.
[0015] Preferably, the sub-regulating valve is remotely controlled or manually controlled on site.
[0016] The beneficial effects of the present invention are:
[0017] In the cooling zone of the arc section, the length of the outer arc side of the billet is longer than that of the inner arc side (the thicker the billet, the more obvious it is). Therefore, the cooling area of the inner arc side of the billet is the smallest. Moreover, due to gravity, the water sprayed on the inner arc side can more easily reach the surface of the billet and stay on the billet than the water sprayed on the other three sides (the wider the billet, the longer the stay time). Therefore, under the same amount of spray water, the cooling effect of the inner arc side of the billet is the best, and the cooling effects of the other three sides of the billet are almost the same. Furthermore, the present application allows the amount of spray water on the inner arc side of the billet to be separately adjustable and less than the amount of spray water on the other three sides of the billet, so that the cooling intensity of the inner arc side of the billet is equivalent to the cooling intensity of the outer arc side, the left side and the right side of the billet, thereby achieving uniform cooling of the four sides of the billet. Moreover, the present invention hardly increases the configuration of the continuous casting machine (only valves need to be added to the original pipeline), achieving low cost, simple operation and strong practicability. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 The present invention is a schematic diagram of a spray water circuit for cooling zones with sub-regulating valves in a secondary spray cooling device for continuous casting of square billets according to an embodiment of the present invention.
[0019] Figure 2 This is a schematic diagram of the second to fifth zones in the billet continuous casting secondary spray cooling device according to an embodiment of the present invention. For ease of observation, only the spray water line of the second zone is shown.
[0020] In the figure: 1-main pipeline; 2-branch pipeline; 3-main regulating valve; 4-branch regulating valve; 5-flow detection component; 6-pressure detection component; 7-manual valve; 8-casting billet; 9-second cooling chamber; 10-water distribution chamber. DETAILED DESCRIPTION
[0021] The present application will be further described below with reference to the accompanying drawings and examples.
[0022] Example 1
[0023] This embodiment discloses a method for secondary spray cooling of continuous casting of square billets: the spray water volume of each cooling zone is independently adjusted according to the different cooling intensity requirements of each cooling zone; for the cooling zones of one or more arc segments, within the same cooling zone, only the spray water volume on the inner arc side of the billet can be adjusted separately, and by adjusting the spray water volume on the inner arc side of the billet, the spray water volume on the inner arc side of the billet is made smaller than the spray water volume on the outer arc side of the billet, the left side of the billet and the right side of the billet. In the cooling zone of the arc section, the length of the outer arc side of the billet is longer than the length of the inner arc side (the thicker the billet, the more obvious it is). Therefore, the cooling area of the inner arc side of the billet is the smallest. Moreover, due to gravity, the water sprayed on the inner arc side can more easily reach the surface of the billet and stay on the billet than the water sprayed on the other three sides (the wider the billet, the longer the stay time). Therefore, under the same amount of spray water, the cooling effect of the inner arc side of the billet is the best, and the cooling effects of the other three sides of the billet are almost the same. Furthermore, this embodiment allows the amount of spray water on the inner arc side of the billet to be individually adjustable and less than the amount of spray water on the other three sides of the billet, so that the cooling intensity of the inner arc side of the billet is equivalent to the cooling intensity of the outer arc side, the left side of the billet and the right side of the billet, thereby achieving uniform cooling of the four sides of the billet, and almost no increase in the configuration of the continuous casting machine (only valves need to be added to the original pipeline), achieving low cost, simple operation and strong practicability.
[0024] The second partition is the first arc segment, and its influence on the overall cooling effect is greater than that of other arc segments. Therefore, the second partition is selected so that only the spray water volume on the inner arc side of the billet can be adjusted separately. In order to further ensure the cooling uniformity, the third partition can also be added so that only the spray water volume on the inner arc side of the billet can be adjusted separately.
[0025] Before continuous casting begins, a test spray is performed to observe whether the flow indication on the cooling zone main pipeline can reach the design value: if it can, it means that the spray water bars in the cooling zone are not blocked; if not, it means that the spray water bars in the cooling zone are blocked. Then further observe the pressure indications on the branch pipes of the spray water bars corresponding to the four sides of the ingot. If there is a branch pipe with a relatively significantly higher pressure indication, it is determined that the spray water bars on the branch pipe are blocked. If the pressure indications on the four branch pipes are not much different, it is determined that the spray water bars on the four branch pipes are all blocked. The spray water bars are prone to blockage under long-term work. If they are not discovered in time, insufficient cooling will result. This method determines the blockage of the spray water bars and finds the specific blockage location by observing the flow indication on the main pipeline and the pressure indication on each branch pipe. It can quickly and conveniently find the blockage location, and can be directly cleaned after finding it.
[0026] After the continuous casting machine starts casting, when adjusting the amount of spray water on the inner arc side of the billet, observe the pressure readings on the branch pipes of the spray water strips corresponding to the four sides of the billet, compare the difference between the pressure readings on the branch pipes of the spray water strips corresponding to the inner arc side of the billet and the pressure readings on the branch pipes of the spray water strips corresponding to the other three sides of the billet, and adjust the difference so that the difference is within a certain range. This method adjusts the amount of spray water on the inner arc side of the billet by pressure comparison, so that the difference between the pressure on the branch pipes of the spray water strips corresponding to the inner arc side of the billet and the pressure on the branch pipes of the spray water strips corresponding to the other three sides of the billet is within a certain range, thereby ensuring cooling uniformity and preventing the difference from increasing and affecting the cooling effect.
[0027] After the continuous casting machine starts casting, the bulging of the left and right sides and the inner and outer arc surfaces of the billet is measured offline. If the difference between the bulging amount of the left and right sides and the bulging amount of the inner and outer arc surfaces increases, the amount of spray water on the inner arc side of the billet is further reduced until the difference between the bulging amount of the left and right sides and the bulging amount of the inner and outer arc surfaces is within a certain range. Square billets will bulge during high-speed production. By measuring the size of the billet before entering the straightening machine, it is found that the bulging amount of the inner and outer arc surfaces is slightly smaller than the bulging amount of the left and right sides, indicating that bulging is more likely to occur on the left and right sides of the billet, and after the straightening machine is pressed down for straightening, the difference between the bulging amount of the left and right sides and the bulging amount of the inner and outer arc surfaces will be further aggravated. When this method initially reduces the amount of spray water on the inner arc side of the billet, the amount of spray water on the other three sides can be increased. In this way, the total amount of spray water on the left and right sides will be higher than the total amount of spray water on the inner and outer arcs, which relatively improves the cooling intensity on the left and right sides of the billet. degree, so that a sufficiently thick billet shell can be formed on the left and right sides of the billet to resist bulging deformation, thereby reducing the bulging amount of the left and right sides; when the difference between the bulging amount of the left and right sides and the bulging amount of the inner and outer arc surfaces increases, it means that the cooling intensity of the left and right sides of the billet is insufficient. Therefore, the spraying water amount on the inner arc side of the billet can be further reduced, and the spraying water amount on the other three sides can be further increased. In this way, the total amount of spraying water on the left and right sides will be further higher than the total amount of spraying water on the inner and outer arcs, which further improves the cooling intensity of the left and right sides of the billet and can further reduce the bulging amount of the left and right sides.
[0028] Example 2
[0029] This embodiment discloses a billet continuous casting secondary spray cooling device, such as Figure 1 and Figure 2As shown, it includes several cooling zones arranged in sequence, each cooling zone is equipped with a spray water strip for spray cooling the four sides of the ingot 8, four branch pipes 2 for supplying water to the spray water strips corresponding to the four sides of the ingot 8, a main pipe 1 for supplying water to the four branch pipes 2, and a main regulating valve 3 arranged on the main pipe 1, and the main regulating valve 3 is used to adjust the overall cooling intensity of the cooling zone; for the cooling zones with one or more arc segments, a branch regulating valve 4 is provided on the branch pipe 2 of the spray water strip corresponding to the inner arc side of the ingot 8, and the branch regulating valve 4 is used to adjust the amount of spray water on the inner arc side of the ingot 8, so that the amount of spray water on the inner arc side of the ingot 8 in the same cooling zone is less than the amount of spray water on the outer arc side of the ingot 8, the left side of the ingot 8 and the right side of the ingot 8. In the cooling zone of the arc section, the length of the outer arc side of the billet 8 is longer than that of the inner arc side (the thicker the billet 8, the more obvious it is). Therefore, the cooling area of the inner arc side of the billet 8 is the smallest. Moreover, due to gravity, the spray water on the inner arc side can more easily reach the surface of the billet 8 and stay on the billet 8 than the spray water on the other three sides (the wider the billet 8, the longer the stay time). Therefore, under the same amount of spray water, the cooling effect of the inner arc side of the billet 8 is the best, and the cooling effects of the other three sides of the billet 8 are almost the same. Furthermore, in this embodiment, the amount of spray water on the inner arc side of the billet 8 is independently adjustable and smaller than the amount of spray water on the other three sides of the billet 8, so that the cooling intensity of the inner arc side of the billet 8 is equivalent to the cooling intensity of the outer arc side of the billet 8, the left side of the billet 8 and the right side of the billet 8, thereby achieving uniform cooling of the four sides of the billet 8, and almost no increase in the configuration of the continuous casting machine (only valves need to be added to the original pipeline), achieving low cost, simple operation and strong practicability.
[0030] Optionally, install a sub-regulating valve 4 on the branch pipe 2 of the spray water strip corresponding to the inner arc side of the billet 8 in the second zone; alternatively, install sub-regulating valves 4 on the branch pipes 2 of the spray water strip corresponding to the inner arc side of the billet 8 in both the second and third zones. The second zone is the first arc segment and has a greater impact on the overall cooling effect than other arc segments. Therefore, select the second zone to allow for independent adjustment of the spray water volume only on the inner arc side of the billet 8. To further ensure cooling uniformity, add a third zone to allow for independent adjustment of the spray water volume only on the inner arc side of the billet 8.
[0031] like Figure 1 and Figure 2As shown: the main pipeline 1 is also provided with a manual valve 7, a flow detection component 5 (such as a flow meter) and a pressure detection component 6 (such as a pressure gauge or a remote pressure transmitter), and each branch pipeline 2 is also provided with a pressure detection component 6 (such as a pressure gauge or a remote pressure transmitter); the main regulating valve 3, manual valve 7, flow detection component 5 (flow meter) and pressure detection component 6 on the main pipeline 1 are located in the water distribution chamber 10, and the sub-regulating valves 4 and pressure detection components 6 on each branch pipeline 2 are located outside the secondary cooling chamber 9 to avoid high-temperature damage to the ingot 8 and to facilitate operation and observation by personnel; the main regulating valve 3 on the main pipeline 1 is controlled in linkage with the flow detection component 5, and the sub-regulating valves 4 are remotely controlled or manually controlled on site.
[0032] The working process of the billet continuous casting secondary spray cooling device is:
[0033] Before continuous casting, test spraying is carried out, and the main regulating valve 3 and the sub-regulating valve 4 are fully opened to observe whether the flow rate reading on the cooling zone main pipeline 1 can reach the design value: if it can, it means that the spray water strips in the cooling zone are not blocked; if not, it means that the spray water strips in the cooling zone are blocked. Then further observe the pressure readings on the sub-pipes 2 of the spray water strips corresponding to the four sides of the ingot 8. If there is a sub-pipe 2 with a relatively high pressure reading, it is determined that the spray water strips on the sub-pipe 2 are blocked. If the pressure readings on the four sub-pipes 2 are relatively high, it is determined that the spray water strips on the sub-pipe 2 are blocked. If the pressure indications are not much different, it is determined that the spray water strips on the four branch pipes 2 are all blocked, and the blocked spray water strips can be directly cleaned until the spray water strips in each cooling zone are checked to be unblocked, and the continuous casting machine is started; the spray water strips are prone to blockage under long-term work. If they are not discovered in time, insufficient cooling will result. This method determines the blockage of the spray water strips and finds the specific blockage location by observing the flow indication on the main pipe 1 and the pressure indications on each branch pipe 2, and can quickly and conveniently find the blockage location.
[0034] After the continuous casting machine starts casting, the amount of spray water on the inner arc side of the ingot 8 is adjusted by the sub-regulating valve 3, and the pressure indications on the sub-pipelines 2 of the spray water strips corresponding to the four sides of the ingot 8 are observed, and the difference between the pressure indications on the sub-pipelines 2 of the spray water strips corresponding to the inner arc side of the ingot 8 and the pressure indications on the sub-pipelines 2 of the spray water strips corresponding to the other three sides of the ingot 8 are compared, and the sub-regulating valve 3 is adjusted to make the difference within a certain range; this method adjusts the amount of spray water on the inner arc side of the ingot 8 by pressure comparison, so that the difference between the pressure on the sub-pipeline 2 of the spray water strips corresponding to the inner arc side of the ingot 8 and the pressure on the sub-pipeline 2 of the spray water strips corresponding to the other three sides of the ingot 8 is within a certain range, which not only ensures the cooling uniformity, but also avoids the expansion of the difference and affects the cooling effect.
[0035] The bulging of the left and right sides and the inner and outer arc surfaces of the billet 8 is measured offline. If the difference between the bulging amount of the left and right sides and the bulging amount of the inner and outer arc surfaces increases, the amount of spray water on the inner arc side of the billet 8 is further reduced through the regulating valve 3 until the difference between the bulging amount of the left and right sides and the bulging amount of the inner and outer arc surfaces is within a certain range; the billet 8 will bulge during high-speed drawing production. By measuring the size of the billet 8 before entering the straightening machine, it is found that the bulging amount of the inner and outer arc surfaces is slightly smaller than that of the left and right sides, indicating that bulging is more likely to occur on the left and right sides of the billet 8, and after the straightening machine is pressed down to straighten, the difference between the bulging amount of the left and right sides and the bulging amount of the inner and outer arc surfaces will be further aggravated. When this method initially reduces the amount of spray water on the inner arc side of the billet 8, it can increase the amount of spray water on the other three sides. The amount of spray water on the left and right sides will be higher than the total amount of spray water on the inner and outer arcs, which will relatively improve the cooling intensity on the left and right sides of the billet 8. In this way, sufficiently thick billet shells can be formed on the left and right sides of the billet 8 to resist bulging deformation, thereby reducing the bulging amount of the left and right sides. When the difference between the bulging amount of the left and right sides and the bulging amount of the inner and outer arc surfaces increases, it means that the cooling intensity on the left and right sides of the billet 8 is insufficient. Therefore, further reducing the amount of spray water on the inner arc side of the billet 8 can further increase the amount of spray water on the other three sides. In this way, the total amount of spray water on the left and right sides will be further higher than the total amount of spray water on the inner and outer arcs, which will further improve the cooling intensity on the left and right sides of the billet 8, and can further reduce the bulging amount of the left and right sides.
[0036] The embodiments described above are part of the embodiments of the present application, rather than all of the embodiments. The detailed description of the embodiments of the present application is not intended to limit the scope of the present application for protection, but merely represents selected embodiments of the present application. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative efforts are within the scope of protection of this application.
Claims
1. A method for secondary spray cooling of continuous casting billets, wherein the spray water volume of each cooling zone is independently adjusted according to the different cooling intensity requirements of each cooling zone; characterized in that: For one or more arc-shaped cooling zones, within the same cooling zone, only the spray water volume on the inner arc side of the billet can be adjusted separately. By adjusting the spray water volume on the inner arc side of the billet, the spray water volume on the inner arc side of the billet is made smaller than the spray water volume on the outer arc side of the billet, the left side of the billet and the right side of the billet.
2. The billet continuous casting secondary spray cooling method according to claim 1, characterized in that: Selecting the 2nd zone allows only the spray water volume on the inner arc side of the billet to be adjusted individually; or selecting the 2nd and 3rd zones allows only the spray water volume on the inner arc side of the billet to be adjusted individually.
3. The billet continuous casting secondary spray cooling method according to claim 1, characterized in that: Before continuous casting begins, a test spray is carried out to observe whether the flow indication on the cooling zone main pipeline can reach the design value: if it can, it means that the spray water bars in the cooling zone are not blocked; if not, it means that the spray water bars in the cooling zone are blocked. Then further observe the pressure indications on the branch pipes of the spray water bars corresponding to the four sides of the ingot. If there is a branch pipe with a relatively significantly high pressure indication, it is determined that the spray water bar on the branch pipe is blocked. If the pressure indications on the four branch pipes are not much different, it is determined that the spray water bars on the four branch pipes are all blocked.
4. The billet continuous casting secondary spray cooling method according to claim 1, wherein: After the continuous casting machine starts casting, when adjusting the amount of spray water on the inner arc side of the ingot, observe the pressure indications on the branch pipes of the spray water strips corresponding to the four sides of the ingot, and compare the difference between the pressure indications on the branch pipes of the spray water strips corresponding to the inner arc side of the ingot and the pressure indications on the branch pipes of the spray water strips corresponding to the other three sides of the ingot. Adjust the difference so that it is within a certain range.
5. The billet continuous casting secondary spray cooling method according to claim 1, characterized in that: After the continuous casting machine starts casting, the bulging of the left and right sides and the inner and outer arc surfaces of the ingot is measured offline. If the difference between the bulging amount of the left and right sides and the bulging amount of the inner and outer arc surfaces increases, the amount of water sprayed on the inner arc side of the ingot is further reduced until the difference between the bulging amount of the left and right sides and the bulging amount of the inner and outer arc surfaces is within a certain range.
6. A secondary spray cooling device for continuous casting of square billets, comprising a plurality of sequentially arranged cooling zones, each equipped with a spray water bar for spray cooling the four sides of the billet, four branch pipes for supplying water to the spray water bars corresponding to the four sides of the billet, a main pipe supplying water to the four branch pipes, and a main regulating valve provided on the main pipe for adjusting the overall cooling intensity of the cooling zone; characterized in that: For one or more of the cooling zones of the arc-shaped segments, a sub-regulating valve is provided on the branch pipeline of the spray water strip corresponding to the inner arc side of the ingot, and the sub-regulating valve is used to adjust the amount of spray water on the inner arc side of the ingot, so that the amount of spray water on the inner arc side of the ingot in the same cooling zone is less than the amount of spray water on the outer arc side of the ingot, the left side of the ingot and the right side of the ingot.
7. The billet continuous casting secondary spray cooling device according to claim 6, characterized in that: Optionally, install a sub-regulating valve on the branch pipe of the spray water strip corresponding to the inner arc side of the casting blank in the second partition; or, optionably, install a sub-regulating valve on the branch pipe of the spray water strip corresponding to the inner arc side of the casting blank in the second and third partitions.
8. The billet continuous casting secondary spray cooling device according to claim 6, characterized in that: The main pipeline is also equipped with a manual valve, flow detection device and pressure detection device, and each branch pipeline is also equipped with a pressure detection device.
9. The billet continuous casting secondary spray cooling device according to claim 8, characterized in that: The sub-regulating valves and pressure detection components on each branch pipeline are installed outside the secondary cooling chamber.
10. The billet continuous casting secondary spray cooling device according to claim 6, characterized in that: The regulating valve is remotely controlled or manually controlled locally.
Citation Information
Patent Citations
Tinplate base material used for low-defect-rate bottle cap and reduction production technology
CN106868401A
Secondary cooling water spraying frame of continuous casting machine
CN216938339U