A method for measuring the volume of holes used for forced landing and correcting collapse in buildings
By using metrology devices, including metering containers and bags during the building tilt correction process, accurately measuring the collapsed hole volume of the soil extraction hole, the problem of inaccurate metrology in the prior art is solved, and precise control of the degree of building tilt correction is achieved, with significant economic and social benefits.
Patent Information
- Application Number
- CN202411935792.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-26
- Publication Date
- 2025-04-08
AI Technical Summary
During the construction of the reclining process, it is difficult to accurately measure the volume of the collapsed holes of the soil holes, which makes it difficult to determine the parameters such as the diameter and quantity of the subsequent reclining holes, which increases the uncertainty of the reclining process.
A metering device is adopted, including a metering container and a capsule connected thereto. A cushion bag is set in the soil extraction hole, and liquid is injected into the capsule so that its appearance corresponds to the original hole. When the soil extraction hole collapses, the liquid is extruded to the metering container. The change in the liquid level in the metering container is used to calculate the collapse amount.
The precise measurement of the volume of the soil extraction hole collapse is achieved, providing a basis for controlling the degree of building correction, reducing the uncertainty of the correction process, and having significant economic and social benefits.
Smart Images

Figure CN119779204A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of building deviation correction, and particularly relates to a method for measuring the volume of a hole for forced landing and correcting collapse of a building. Background Art
[0002] Existing buildings have uneven settlement due to foundation design and construction reasons, as well as collapsible soil, natural disasters, improper use and maintenance, which leads to overall tilting of the building, affecting the normal use of the building and seriously threatening personal and property safety. Measures must be taken to stop the settlement, correct the deviation, and reinforce the building to eliminate safety hazards. The forced landing method is widely used in building tilt correction, with the advantages of mature technology and low cost. The forced landing method is to drill holes in the foundation soil on one side of the tilted building to take soil, so that the building on the side with smaller settlement will be forced to settle until it is balanced with the side with larger settlement. However, during the implementation process, the soil holes cannot guarantee that the soil holes will collapse completely. The degree of collapse is affected by factors such as the arrangement of the soil holes, the characteristics of the foundation soil, and the foundation form of the building. It is difficult to accurately obtain the amount of collapse of the soil holes, which brings difficulties to determining the parameters such as the diameter and number of subsequent soil holes, which is not conducive to controlling the amount of building tilt correction and increases the uncertainty of the tilt correction process. In the prior art, there is no method and structure for accurately measuring the volume of collapsed holes. Summary of the invention
[0003] The invention provides a method for measuring the volume of a hole for forced landing and correcting collapse of a building.
[0004] The object of the present invention is achieved in the following way: a method for measuring the volume of a hole for taking soil for forced landing and correcting the collapse of a building, comprising the following steps: step one: excavating a soil taking working pit in the foundation soil on the side of the inclined building with less settlement, and drilling at least one soil taking hole in the working pit in the direction of the inclined building; the soil taking hole is an original hole in the initial stage; step two: selecting at least one representative soil taking hole, in which a measuring device is arranged; the measuring device comprises a measuring container and a bag connected to the measuring container; a section of the original hole in which the collapse amount needs to be measured is section B of the original hole, and the bag is arranged in the entire section B of the original hole; step three: adding a meter to the bag Liquid is injected into the bag so that the shape of the bag with liquid inside corresponds to the shape of the original hole; Step 4: After the designed number of soil-taking holes are set in the working pit, the foundation soil around them will produce a certain collapse deformation under the pressure of the inclined building foundation, and the original hole will be compressed into a collapsed hole after the collapse deformation; Step 5: After the original hole is compressed and deformed, the volume of the collapsed hole is smaller than that of the original hole, and the liquid in the bag is compressed and squeezed into the measuring container. The increased volume of the liquid in the measuring container is the collapse amount of section B of the original hole; Step 6: The collapse amount of other soil-taking holes is inferred from the collapse amount of the soil-taking hole with the metering device set, and the total collapse amount is calculated.
[0005] The measuring container is arranged outside the soil taking hole, and the lower end of the measuring container is connected to the bag through a connecting pipe; a water injection port is arranged at the upper end of the measuring container; in step three, liquid is injected into the measuring container, and the liquid then enters the bag; after the water injection is completed, there is liquid at the bottom of the measuring container, the connecting pipe, and the bag.
[0006] The section of the original hole that does not need to measure collapse is section A of the original hole; a protective tube is installed in section A of the original hole; the part of the connecting tube located in the original hole and the end of the bag close to the connecting end are located in the protective tube.
[0007] The measuring container is a straight tube container, on which a scale for measuring is arranged.
[0008] The shape of the original hole is circular.
[0009] Compared with the prior art, the present invention installs a metering device in the soil taking hole for building foundation correction, and calculates the volume of the collapsed hole by the change of the liquid level in the measuring container, so as to achieve the purpose of controlling the degree of building correction according to the amount of soil taken. It has the advantages of accurate measurement and easy implementation, provides a basis for accurately controlling the amount of collapse, and has more significant economic and social benefits. BRIEF DESCRIPTION OF THE DRAWINGS
[0010] Figure 1 It is a schematic diagram of excavating a working pit according to the present invention.
[0011] Figure 2 It is a schematic diagram of the arrangement of the metering device of the present invention.
[0012] Figure 3 It is a schematic diagram of filling water into the metering device of the present invention.
[0013] Figure 4 It is a schematic cross-sectional view of the soil sampling hole in its original hole state.
[0014] Figure 5 It is a schematic diagram of the collapse compression bag of the soil hole in the present invention.
[0015] Figure 6 It is a cross-sectional diagram of the collapsed hole formed after the borrow hole collapses.
[0016] Figure 7 This is a schematic diagram of the building after restoration.
[0017] Among them, 1 is the inclined building, 2 is the foundation soil, 3 is the working pit, 4 is the soil hole, 41 is the original hole, 42 is the collapsed hole, 5 is the metering device, 51 is the metering container, 52 is the bag, 53 is the connecting pipe, and 6 is the protective pipe. DETAILED DESCRIPTION
[0018] In the present invention, unless otherwise clearly specified and limited, the technical terms used in this application shall be the common meanings understood by the technicians of the present invention. The terms "connected", "connected", "fixed", "set", etc. should be understood in a broad sense, and may be fixedly connected, detachably connected, or integrated; may be directly connected, or indirectly connected through an intermediate medium; may be mechanically connected or electrically connected. Unless otherwise clearly specified and limited, the first feature "on" or "below" the second feature may be that the first and second features are in direct contact, or indirectly in contact through an intermediate medium. Moreover, the first feature "above" or "above" or "above" the second feature may be that the first feature is directly above or obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. The first feature "below" or "below" or "below" the second feature may be that the first feature is directly below or obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature. Relational terms such as first, second, etc. are used only to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. The terms used in the description, such as "center", "lateral", "longitudinal", "length", "width", "thickness", "height", "front", "back", "left", "right", "up", "down", "vertical", "horizontal", "top", "bottom", "inside", "outside", "axial", "radial", "circumferential", "clockwise", "counterclockwise", etc., to indicate orientations or positional relationships are based on the orientations or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or component referred to must have a specific orientation, be constructed and operated in a specific orientation.
[0019] The following will provide a clear and complete description of the technical solution of the present invention in conjunction with the accompanying drawings and specific embodiments. Figure 1-7As shown, a method for measuring the volume of a hole for taking soil for forced landing and correcting the collapse of a building comprises the following steps: Step 1: excavating a soil taking working pit 3 in the foundation soil 2 on the side of the inclined building 1 with less settlement, and drilling at least one soil taking hole 4 in the working pit 3 in the direction of the inclined building 1; the soil taking hole 4 is an original hole 41 at the initial stage; Step 2: selecting at least one representative soil taking hole 4, in which a measuring device 5 is arranged; the measuring device 5 comprises a measuring container 51 and a bag 52 connected to the measuring container 51; a section of the original hole 41 for which the collapse amount needs to be measured is section B of the original hole 41, and the bag 52 is arranged in the entire section B of the original hole 41; Step 3: injecting liquid into the bag 52 until the collapse amount is measured. The shape of the bag 52 with liquid set inside corresponds to the shape of the original hole 41; Step 4: After setting the designed number of soil holes 4 in the working pit 3, the surrounding foundation soil 2 will produce a certain collapse deformation under the foundation pressure of the inclined building 1, and the original hole 41 will be compressed into a collapsed hole 42 after the collapse deformation; Step 5: After the original hole 41 is compressed and deformed, the volume of the collapsed hole 42 is smaller than that of the original hole 41, and the liquid in the bag 52 is compressed and squeezed into the measuring container 51. The increased volume of the liquid in the measuring container 51 is the collapse amount of the original hole 41B section; Step 6: The collapse amount of other soil holes 4 is inferred from the collapse amount of the soil hole 4 with the metering device 5, and the total collapse amount is calculated.
[0020] Among them, a representative soil hole 4 is selected as the soil hole 4 for placing the metering device 5. This representativeness is set according to needs. For example, there may be soil holes 4 of various lengths, inclination angles, diameters, different positions, and different settlement degrees in the working pit 3, and one or several of each type are selected as representatives, so as to infer the collapse amount of other soil holes 4 of the same type. The selection of representative soil holes 4 is determined according to actual needs and different working conditions. In step three, the shape of the sac 52 with liquid arranged inside corresponds to the shape of the original hole 41; here, the shape of the sac 52 and the original hole 41 are as close as possible, so as to ensure that the liquid squeezed out after collapse is the same as the collapse amount, and to ensure that the volume measurement process is as accurate as possible. There are many ways to connect the metering container 51 with the sac, which can be directly connected or indirectly connected. The sac 52 can be made of a material such as plastic that can hold liquid, and the shape of the object held will change when subjected to force or held. In addition, the liquid injected into the sac 52 in step three is preferably water, or other liquids. The soil hole 4 in the present invention is set obliquely downward, and the end is located below the building. The spacing between the soil holes 4, the inclination angles and sizes of the soil holes 4 are set as required. In the present invention, the purpose of forced landing of the tilted building 1 is achieved by the overall sinking of the foundation soil 2. In step six, after calculating the total collapse amount of this settlement, the soil volume for subsequent settlement is compared with the designed soil volume, which also provides a basis for the form and number of subsequent soil holes 4. The present invention measures the collapsed hole volume of the soil holes 4 for correcting the tilt of the building by the forced landing method, so that the control of the straightening rate of the tilted building 1 is more accurate, and potential safety hazards are eliminated. It is a safe, reliable, simple, intuitive, efficient and low-cost process for measuring the collapsed hole volume of the soil holes 4, and has significant economic and social benefits.
[0021] The metering container 51 is arranged outside the soil-boring hole 4, and the lower end of the metering container 51 is connected to the sac 52 through a connecting pipe 53; a water injection port is arranged at the upper end of the metering container 51; in step three, liquid is injected into the metering container 51, and the liquid then enters the sac 52; after the water injection is completed, there is liquid at the bottom of the metering container 51, the connecting pipe 53, and the sac 52. The metering container 51 can be arranged in the soil-boring pit or on the ground. The connecting pipe 53 can be a hard pipe or a soft pipe. After the water injection is completed, there is liquid at the bottom of the metering container 51, and after the original hole 41 collapses, the liquid level in the metering container 51 rises, and the volume reduction of the collapsed hole 42 is calculated according to the rising height of the liquid level. After the water injection is completed, the water injection port can be closed to form a closed metering device 5. Among them, the sac 52 of each soil-boring hole 4 can be connected to its own metering container 51. The bags of multiple soil-boring holes 4 may also be connected to the same measuring container 51. In this case, the increased liquid volume in the measuring container 51 is the collapse volume of the multiple soil-boring holes 4, which may be averaged.
[0022] The section of the original hole 41 that does not need to measure the collapse is section A of the original hole 41; a protective tube 6 is installed in section A of the original hole 41; the connecting tube 53 and the end of the bag 52 close to the connecting end are located in the protective tube 6. The protective tube 6 is provided to protect the connecting tube 53 and the end of the bag 52 in section A of the original hole 41 from being squeezed and deformed. It is ensured that the parts that are squeezed and deformed are all located in section B where the amount of soil taken needs to be measured, thereby ensuring the accuracy of the metering structure. Section B generally includes and is greater than the length of the original hole 41 that will collapse after settlement, ensuring the accuracy of the amount of soil taken. Section A is located in the length from the outlet of the original hole 41 to section B, that is, the remaining length outside section B is removed.
[0023] The measuring container 51 is a straight tube container, on which a scale for measuring is set.
[0024] The shape of the original hole 41 is circular. It can also be other shapes, determined according to needs. After the overall settlement work is completed, the building tilt correction is completed, the metering device 5 is taken out, and the working pit 3 is backfilled until the ground returns to its original appearance.
[0025] The present invention also provides a volume measuring device 5 for taking soil for forced landing and correcting collapse of a building, comprising a working pit 3 arranged in the foundation soil 2 on the side of the inclined building 1 with less settlement, at least one taking soil hole 4 being arranged in the working pit 3 in the direction of the inclined building 1; a bag 52 connected to a measuring container 51 outside the taking soil hole 4 being arranged in at least one taking soil hole 4; the bag 52 after being injected with liquid is fitted with section B of the taking soil hole 4 where the collapse amount needs to be measured.
[0026] The lower end of the metering container 51 is connected to the bag 52 through a connecting pipe 53; a protective pipe 6 is arranged in section A of the soil borrowing hole 4 where collapse measurement is not required, and the connecting pipe 53 is located in the part of the soil borrowing hole 4 and the end of the bag 52 close to the connecting end is located in the protective pipe 6.
[0027] The present invention installs a metering device 5 in a soil taking hole 4 for building foundation correction, and calculates the volume of the collapsed hole by the change of the liquid level in the metering container 51, so as to achieve the purpose of controlling the degree of building correction according to the amount of soil taken. The invention has the advantages of accurate measurement and easy realization, provides a basis for accurately controlling the amount of collapse, and has relatively significant economic and social benefits.
[0028] The technical features of the above-mentioned embodiments can be combined arbitrarily, and as long as there is no contradiction in the combination of these technical features, they should be considered as the scope of this specification. Without departing from the overall concept of the present invention, the technical solution of the present invention and the equivalent replacement or change, as well as the changes and improvements made, should also be regarded as the protection scope of the present invention.
Claims
1. A method for measuring the volume of holes for forced landing and correcting collapse in construction, characterized in that: The method comprises the following steps: step 1: excavating a soil-taking working pit in the foundation soil on the side of the inclined building with less settlement, and drilling at least one soil-taking hole in the working pit in the direction of the inclined building; the soil-taking hole is an original hole in the initial stage; step 2: selecting at least one representative soil-taking hole, in which a metering device is arranged; the metering device comprises a metering container and a bag connected to the metering container; a section of the original hole in which the collapse amount needs to be measured is section B of the original hole, and the bag is arranged in the entire section B of the original hole; step 3: injecting liquid into the bag so that the bag with the liquid inside The shape of the bag corresponds to the shape of the original hole; Step 4: After setting the designed number of soil-taking holes in the working pit, the foundation soil around them will produce a certain collapse deformation under the pressure of the inclined building foundation, and the original hole will be compressed into a collapsed hole after the collapse deformation; Step 5: After the original hole is compressed and deformed, the volume of the collapsed hole is smaller than that of the original hole, and the liquid in the bag is compressed and squeezed into the measuring container. The increased volume of the liquid in the measuring container is the collapse amount of section B of the original hole; Step 6: The collapse amount of other soil-taking holes is inferred from the collapse amount of the soil-taking hole with the metering device, and the total collapse amount is calculated.
2. According to claim 1, a method for measuring the volume of a hole for forced landing and correcting collapse in a building, characterized in that: The measuring container is arranged outside the soil taking hole, and the lower end of the measuring container is connected to the bag through a connecting pipe; a water injection port is arranged at the upper end of the measuring container; in step three, liquid is injected into the measuring container, and the liquid then enters the bag; after the water injection is completed, there is liquid at the bottom of the measuring container, the connecting pipe, and the bag.
3. According to claim 2, a method for measuring the volume of a hole for forced landing and correcting collapse in a building, characterized in that: The section of the original hole that does not need to measure collapse is section A of the original hole; a protective tube is installed in section A of the original hole; the part of the connecting tube located in the original hole and the end of the bag close to the connecting end are located in the protective tube.
4. According to claim 3, a method for measuring the volume of a hole for forced landing and correcting collapse in a building, characterized in that: The measuring container is a straight tube container, on which a scale for measuring is arranged.
5. According to claim 1, a method for measuring the volume of a hole for forced landing and correcting collapse in a building, characterized in that: The shape of the original hole is circular.