Sampling device for bridge foundation geological exploration
By designing a sampling device for geological exploration of bridge foundations, the adjustment mechanism is used to separate loosening and sampling work, the problem of excessive load capacity of existing devices affecting battery life is solved, and more efficient sampling operations are achieved.
Patent Information
- Application Number
- CN202510001005.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-02
- Publication Date
- 2025-04-11
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing sampling device for geological surveying of bridge foundations carries two robotic arms, which increases the load capacity, affecting the device's battery life.
A sampling device including a moving mechanism, a robotic arm, a loosening mechanism and a suction mechanism is designed. By adjusting the mechanism, the position of the loosening mechanism and the suction mechanism is driven, the loosening and sampling work can be separated, and the impact on the load weight is reduced.
By reducing the impact on load weight, the endurance of the device is improved, so that only one robot arm is required to complete the loose soil and soil sampling work.
Smart Images

Figure CN119804002A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of geological exploration, and in particular to a sampling device used for geological exploration of bridge foundations. Background Art
[0002] The sampling device for geological survey is used to obtain soil and groundwater samples in order to study the characteristics of the strata, the distribution of mineral deposits and environmental conditions. In some places that cannot be reached by personnel, sampling devices that can move autonomously are required.
[0003] However, the existing vehicle sampling devices are generally equipped with a soil drilling robot arm and a suction robot arm. The soil drilling robot arm is used to loosen the soil, while the suction robot arm is used to suck up loose and broken soil. However, carrying two robots at the same time will greatly affect the load capacity of the entire device, thereby affecting the endurance of the device. Summary of the invention
[0004] In view of the above-mentioned problems existing in the existing sampling devices for geological survey of bridge foundations, the present invention is proposed.
[0005] Therefore, an object of the present invention is to provide a sampling device for geological investigation of bridge foundation.
[0006] In order to solve the above technical problems, the present invention provides the following technical solutions: a sampling device for geological survey of bridge foundation, characterized in that: it includes a moving mechanism; a mechanical arm, which is arranged on the moving mechanism; a loosening mechanism and a suction mechanism, both of which are movably arranged on the mechanical arm; and an adjustment mechanism, including a rotating pin connected to the loosening mechanism and the suction mechanism, and a driving member connected to the rotating pin; the driving member can drive the rotating pin to rotate, and the rotating pin can adjust the position of the loosening mechanism and the suction mechanism when it rotates.
[0007] As a preferred solution of the sampling device for geological survey of bridge foundation described in the present invention, wherein: the mechanical arm is provided with a first slide groove and a second slide groove parallel to each other; the loosening mechanism includes a first slide column, and the suction mechanism includes a second slide column, and the first slide column and the second slide column extend to the inside of the first slide groove and the second slide groove respectively; the rotating pin is provided with a limiting groove, and the first slide column and the second slide column both extend to the inside of the limiting groove.
[0008] As a preferred solution of the sampling device for geological exploration of bridge foundation described in the present invention, the loosening mechanism includes a first mobile platform, a drill bit installed on the first mobile platform, and a driving motor installed on the first mobile platform and connected to the drill bit; the first sliding column is arranged on the first mobile platform, and the first mobile platform is installed on the mechanical arm through the first sliding column.
[0009] As a preferred solution of the sampling device for geological survey of bridge foundation described in the present invention, the suction mechanism includes a second movable platform and a suction tube arranged on the second movable platform; the second sliding column is arranged on the second movable platform, and the second movable platform is installed on the mechanical arm through the second sliding column.
[0010] As a preferred embodiment of the sampling device for geological survey of bridge foundation described in the present invention, the suction tube includes a first tube body and a second tube body, and the first tube body is installed on the second movable platform; the suction mechanism also includes an extension frame slidably connected to the second movable platform, and an elastic member provided on the extension frame and the second movable platform; the second tube body is installed on the extension frame.
[0011] As a preferred solution of the sampling device for geological investigation of bridge foundation described in the present invention, the extension frame is provided with a friction buckle, and when the first movable platform moves, the extension frame can be driven to move by pushing the friction buckle.
[0012] As a preferred solution of the sampling device for geological survey of bridge foundation described in the present invention, wherein: a through groove is opened on the first tube body, and a spring piece is installed in the through groove on the first tube body; a pushing body is installed in the second tube body; when the second tube body moves toward the direction of the first tube body, the pushing body can press the spring piece to bend and deform toward the axial direction of the first tube body.
[0013] As a preferred solution of the sampling device for geological exploration of bridge foundations described in the present invention, the spring piece includes a connecting portion connected to the first tube body, and an arc portion connected to the connecting portion and deflected toward the axial direction of the first tube body; the outer diameter of the first tube body is adapted to the inner diameter of the second tube body.
[0014] As a preferred solution of the sampling device for geological survey of bridge foundation described in the present invention, a bracket is also installed on the mechanical arm, and the driving member is installed on the bracket.
[0015] As a preferred solution of the sampling device for geological investigation of bridge foundation described in the present invention, a camera mechanism is also provided on the mobile mechanism.
[0016] The beneficial effects of the present invention are as follows: after the loosening is completed, the driving member drives the rotating pin to rotate, and the loosening mechanism is retracted into the inside of the mechanical arm to reach a standby state. At the same time, the suction mechanism extends from the inside of the mechanical arm to absorb and collect loose and damaged soil samples. Compared with the sampling device in the prior art, only one mechanical arm is needed to complete the work of loosening the soil and sampling the soil. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0018] Figure 1 The figure is a schematic diagram of the overall structure of the sampling device used for geological survey of bridge foundation according to the present invention.
[0019] Figure 2 It is a schematic diagram of the structure of the suction mechanism and the loosening mechanism described in the present invention.
[0020] Figure 3 It is a schematic diagram of the structure of the adjustment mechanism described in the present invention.
[0021] Figure 4 It is a schematic diagram of the structure of the adjustment mechanism and the suction mechanism described in the present invention.
[0022] Figure 5 It is a schematic diagram of the structure of the first tube body and the second tube body described in the present invention.
[0023] Figure 6 It is a schematic diagram of the movement direction of the suction mechanism and the loosening mechanism described in the present invention.
[0024] Figure 7 It is a schematic diagram of the connection between the suction tube and the air pump described in the present invention.
[0025] Figure 8 It is a schematic diagram of the structure of the pusher and the spring piece described in the present invention.
[0026] Fig. 9 It is a schematic diagram of the separation state of the first tube body and the second tube body described in the present invention.
[0027] Fig.10 It is a schematic diagram of the combined state of the first tube body and the second tube body described in the present invention. DETAILED DESCRIPTION
[0028] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the accompanying drawings.
[0029] Example 1 provides a sampling device for geological investigation of bridge foundations, such as Figure 1The sampling device includes a mobile mechanism 100, which has mobility. The mobile mechanism 100 may be a platform with wheels. More preferably, the mobile mechanism 100 is a platform with a track structure, which is convenient for traveling in the field. The mobile mechanism 100 provides mobility for the sampling device, and enables the sampling device to move to the sampling position.
[0030] The sampling device includes a mechanical arm 200, which is arranged on the moving mechanism 100. The mechanical arm 200 itself can be bent or straightened and extended.
[0031] like Figure 2 The loosening mechanism 300 and the suction mechanism 400 of the sampling device can be movably arranged on the mechanical arm 200. The mechanical arm 200 can extend the loosening mechanism 300 and the suction mechanism 400 to the soil that needs to be sampled. The loosening mechanism 300 can drill and damage the soil to loosen the soil. The suction mechanism 400 can suck the loosened soil to obtain a soil sample.
[0032] like Figure 3 The sampling device also includes an adjustment mechanism 500, including a rotating pin 501 connected to the loosening mechanism 300 and the suction mechanism 400, and a driving member 502 connected to the rotating pin 501; the driving member 502 can drive the rotating pin 501 to rotate, and the rotating pin 501 can adjust the positions of the loosening mechanism 300 and the suction mechanism 400 when rotating.
[0033] The loosening mechanism 300 and the suction mechanism 400 both have two states. When extended out of the mechanical arm 200, the loosening mechanism 300 and the suction mechanism 400 are in a working state. When retracted into the mechanical arm 200, the loosening mechanism 300 and the suction mechanism 400 are in a standby state. The function of the adjustment mechanism 500 is to adjust the states of the loosening mechanism 300 and the suction mechanism 400. When the loosening mechanism 300 is in a working state, the suction mechanism 400 is in a standby state. After the loosening mechanism 300 has finished working, the loosening mechanism 300 is retracted into the mechanical arm 200 and converted to a standby state, and the suction mechanism 400 is extended out of the mechanical arm 200 to reach a working state. In this way, when the loosening mechanism 300 is working, the suction mechanism 400 will not extend out to cause obstruction. When the suction mechanism 400 is working, the loosening mechanism 300 can be retracted and will not affect the sampling work of the suction mechanism 400. The driving member 502 is a motor.
[0034] Specifically, Figure 2 and Figure 3 The mobile mechanism 100 is also provided with a camera mechanism 600 , which can be a camera that can record the situation at the sampling site. The mechanical arm 200 is also equipped with a bracket 503 , and the driving member 502 is installed on the bracket 503 .
[0035] like Figure 3 and Figure 4 The robot arm 200 is provided with a first slide groove 201 and a second slide groove 202 which are parallel to each other; the loosening mechanism 300 includes a first slide column 301, and the suction mechanism 400 includes a second slide column 401, and the first slide column 301 and the second slide column 401 extend to the inside of the first slide groove 201 and the second slide groove 202 respectively; a limiting groove 5011 is provided on the rotating pin 501, and the first slide column 301 and the second slide column 401 both extend to the inside of the limiting groove 5011.
[0036] When the rotating pin 501 rotates clockwise, the position of the entire limiting groove 5011 also rotates clockwise. Under the limitation of the first slide groove 201, the limiting groove 5011 rotates clockwise to push the first slide column 301 inside the first slide groove 201 to move toward the robot arm 200. At the same time, under the limitation of the second slide groove 202, the limiting groove 5011 rotates clockwise to push the second slide column 401 inside the second slide groove 202 to move away from the robot arm 200, so that the loosening mechanism 300 is retracted into the interior of the robot arm 200 to reach a standby state, and the suction mechanism 400 is extended to the outside of the robot arm 200 to reach a working state.
[0037] Similarly, when the rotating pin 501 rotates counterclockwise, the loosening mechanism 300 can be extended to the outside of the mechanical arm 200 to reach a working state, and the suction mechanism 400 is retracted into the inside of the mechanical arm 200 to reach a standby state.
[0038] like Figure 3 The loosening mechanism 300 includes a first moving platform 302, a drill bit 303 mounted on the first moving platform 302, and a driving motor 304 mounted on the first moving platform 302 and connected to the drill bit 303; the driving motor 304 can reach the drill bit 303 to rotate, and when the drill bit 303 rotates, it can approach the soil to break the soil, and the first sliding column 301 is arranged on the first moving platform 302, and the first moving platform 302 is installed on the mechanical arm 200 through the first sliding column 301. In this embodiment, the number of the first sliding columns 301 is two, and at the same time, the number of the first sliding grooves 201 opened on the mechanical arm 200 is two, and the two first sliding columns 301 are respectively installed on both sides of the first moving platform 302, and the two first sliding columns 301 extend to the inside of the two first sliding grooves 201, respectively. Therefore, when the rotating pin 501 rotates and pushes the first sliding column 301 to move, the first moving platform 302 can be driven to move.
[0039] like Figure 4The suction mechanism 400 includes a second movable platform 402 and a suction tube 403 arranged on the second movable platform 402; a second slide column 401 is arranged on the second movable platform 402, and the second movable platform 402 is installed on the robot arm 200 through the second slide column 401. The same thing is that the number of the second slide columns 401 is two, and the two second slide columns 401 are respectively installed on both sides of the second movable platform 402, and the number of the second slide grooves 202 is two, and the two second slide columns 401 extend to the inside of the two second slide grooves 202 respectively.
[0040] An air pump and a sampling box are installed on the mobile mechanism 100. The air pump is connected to the sampling box, and the sampling box is connected to the suction tube 403. The air pump can suck the air inside the sampling box to reduce the air pressure inside the sampling box. The suction tube 403 sucks external air and soil into the interior of the sampling box.
[0041] Through the scheme in this embodiment, when loosening and breaking the soil, the loosening mechanism 300 maintains a working state and extends to the outside of the mechanical arm 200, and the suction mechanism 400 is stored in the inside of the mechanical arm 200 and does not extend out. At this time, the loosening of the soil by the loosening mechanism 300 will not be affected by the suction mechanism 400. When the loosening is completed, the driving member 502 drives the rotating pin 501 to rotate, and the loosening mechanism 300 is retracted into the inside of the mechanical arm 200 to reach a standby state. At the same time, the suction mechanism 400 extends from the inside of the mechanical arm 200, and can absorb and collect loosened and damaged soil samples. Compared with the sampling device in the prior art, only one mechanical arm 200 is needed to complete the work of loosening the soil and sampling the soil.
[0042] Embodiment 2, as Figure 5 This embodiment is different from the first embodiment in that: in order to avoid the problem of the suction tube 403 being blocked, the suction tube 403 includes a first tube body 404 and a second tube body 405, and the first tube body 404 is installed on the second movable platform 402; the suction mechanism 400 also includes an extension frame 406 slidably connected to the second movable platform 402, and an elastic member 407 provided on the extension frame 406 and the second movable platform 402; the second tube body 405 is installed on the extension frame 406.
[0043] like Figure 5 and Figure 6In the standby state, the first tube body 404 and the second tube body 405 are in a separated state. When the working state is reached, the first tube body 404 and the second tube body 405 reach a docking state. When the rotating pin 501 rotates clockwise, it can push the first movable platform 302 to move in the X direction, and the second movable platform 402 moves in the Y direction. During the movement of the second movable platform 402 in the Y direction, the first tube body 404 can move in the Y direction synchronously. At the same time, the second movable platform 402 can push the extension frame 406 to move in the Y direction through the elastic member 407, so that the second tube body 405 also moves in the Y direction.
[0044] The extension frame 406 is provided with a contact buckle 408. When the first movable platform 302 moves, the extension frame 406 can be driven to move by pushing the contact buckle 408. In the above process, when the first movable platform 302 moves in the X direction and contacts the contact buckle 408 moving in the Y direction, the first movable platform 302 can push the contact buckle 408, so that the moving direction of the contact buckle 408 is changed and it moves in the X direction, so that the contact buckle 408 pulls the extension frame 406, and the extension frame 406 pulls the second tube body 405, so that the first tube body 404 moves in the Y direction, and the second tube body 405 moves in the X direction, so that the first tube body 404 enters the interior of the second tube body 405, and the docking work of the first tube body 404 and the second tube body 405 is completed.
[0045] After the sampling work is completed, the rotating pin rotates counterclockwise, and the first tube body 404 moves in the X direction, and the first moving platform 302 moves in the Y direction. Under the action of the elastic member 407, the second tube body 405 will first move a distance in the Y direction, so that the first tube body 404 and the second tube body 405 are separated, and a gap is generated between them, so that large-volume debris sucked into the first tube body 404 can be discharged.
[0046] The first tube 404 can discharge the debris by sending gas to the first tube 404 through the air pump to push the debris away. Figure 7 The entire sampling device has two air pumps, namely a first air pump 700 and a second air pump 800. The first air pump 700 is connected to a collecting box 900 and is used to extract the air inside the collecting box 900, so as to achieve the purpose of sucking samples. The second air pump 800 is connected to the pipeline between the suction tube 403 and the collecting box 900 and is used to supply air to the suction tube 403, so as to blow out the debris inside the first tube body 404 and avoid the problem of sampling failure caused by debris blocking the suction tube 403.
[0047] The rest of the structure is the same as that of Example 1.
[0048] Example 3, reference Figure 8This embodiment is different from the above embodiments in that: a through groove 4041 is opened on the first tube body 404, and a spring piece 4042 is installed in the through groove 4041 on the first tube body 404; a pushing body 4051 is installed in the second tube body 405; when the second tube body 405 moves toward the first tube body 404, the pushing body 4051 can press the spring piece 4042 to bend and deform toward the axial direction of the first tube body 404.
[0049] refer to Fig. 9 and Fig.10 When the first tube 404 moves in the Y direction and the second tube 405 moves in the X direction, the pushing body 4051 can enter the interior of the second tube 405 and contact the spring sheet 4042, so that the spring sheet 4042 is deformed, so that the spring sheet 4042 can extend to the interior of the first tube 404 to form a blocking structure. During the sampling process, when large-volume debris enters the interior of the first tube 404, the spring sheet 4042 can block the debris. After the sampling is completed or when it is found that the first tube 404 is blocked, the first tube 404 moves in the X direction and the second tube 405 moves in the Y direction by rotating the rotating pin 501 counterclockwise, and the pushing body 4051 and the spring sheet 4042 are separated. During this process, the spring sheet 4042 can push the debris to move to the gap between the first tube 404 and the second tube 405, so that it is easier to clean the debris out of the interior of the first tube 404.
[0050] Specifically, Figure 8 The spring piece 4042 includes a connecting portion 4043 connected to the first tube body 404 , and an arc portion 4044 connected to the connecting portion 4043 and deflected toward the axial direction of the first tube body 404 ; the outer diameter of the first tube body 404 is adapted to the inner diameter of the second tube body 405 .
[0051] The connecting portion 4043 of the spring piece 4042 is fixedly connected to the first tube body 404, and the arc portion 4044 is located at the end of the connecting portion 4043 away from the connection between the connecting portion 4043 and the first tube body 404. When the pushing body 4051 presses the spring piece 4042, the arc portion 4044 of the spring piece 4042 is pressed, so that the arc portion 4044 deflects toward the axial direction of the first tube body 404, so that the spring piece 4042 can form a blocking structure inside the first tube body 404.
[0052] The pushing body 4051 is composed of two parts, one is a positioning structure 4052 connected to the second tube body 405, and the other is a contact structure 4053 fixed on the positioning structure 4052. In this embodiment, the through groove 4041 penetrates to the axial end of the first tube body 404 close to the second tube body 405, and the position of the positioning structure 4052 corresponds to the position of the through groove 4041. When the second tube body 405 moves toward the first tube body 404, the positioning mechanism can enter the interior of the through groove 4041. At the same time, the contact structure 4053 is an arc-shaped structure, which can fit the inner wall of the first tube body 404 when entering the interior of the first tube body 404. It should also be noted that the arc-shaped portion 4044 partially extends into the interior of the first tube body 404 in a natural state, so that the contact structure 4053 can ensure that the pressure side 4045 of the arc-shaped portion 4044 can contact the arc-shaped portion 4044, so that the spring piece 4042 is deformed toward the center of the first tube body 404.
[0053] In order to improve the blocking effect of the spring piece 4042 , more structural extensions may be provided at the end of the spring piece 4042 where the arc portion 4044 extends into the interior of the first tube 404 , which will not be described in detail herein.
[0054] Through the scheme in this embodiment, when the first tube body 404 and the second tube body 405 are combined, the spring piece 4042 on the first tube body 404 can form a blocking structure inside the first tube body 404 to prevent large debris from penetrating into the first tube body 404 and causing blockage. When the second tube body 405 and the first tube body 404 are separated, the spring piece 4042 recovers under the action of its own elasticity. During this process, the debris blocked by the spring piece 4042 is pushed into the gap between the first tube body 404 and the second tube body 405, thereby making it easier to clean the debris out of the first tube body 404.
[0055] The rest of the structure is the same as that of Example 2.
Claims
1. A sampling device for geological exploration of bridge foundation, characterized in that: include, Moving mechanism (100); A mechanical arm (200) disposed on the moving mechanism (100); The loosening mechanism (300) and the suction mechanism (400) are both movably arranged on the mechanical arm (200); and, The adjusting mechanism (500) comprises a rotating pin (501) connected to the loosening mechanism (300) and the suction mechanism (400), and a driving member (502) connected to the rotating pin (501); The driving member (502) can drive the rotating pin (501) to rotate, and the rotating pin (501) can adjust the positions of the loosening mechanism (300) and the suction mechanism (400) when rotating.
2. The sampling device for geological investigation of bridge foundation according to claim 1, characterized in that: The mechanical arm (200) is provided with a first sliding groove (201) and a second sliding groove (202) which are parallel to each other; The loosening mechanism (300) includes a first sliding column (301), and the suction mechanism (400) includes a second sliding column (401), wherein the first sliding column (301) and the second sliding column (401) extend to the inside of the first sliding groove (201) and the second sliding groove (202) respectively; The rotating pin (501) is provided with a limiting groove (5011), and the first sliding column (301) and the second sliding column (401) both extend into the limiting groove (5011).
3. The sampling device for geological investigation of bridge foundation according to claim 2, characterized in that: The loosening mechanism (300) comprises a first mobile platform (302), a drill bit (303) mounted on the first mobile platform (302), and a drive motor (304) mounted on the first mobile platform (302) and connected to the drill bit (303); The first sliding column (301) is arranged on the first moving platform (302), and the first moving platform (302) is installed on the mechanical arm (200) through the first sliding column (301).
4. The sampling device for bridge foundation geological survey according to claim 3, characterized in that: The suction mechanism (400) comprises a second movable platform (402) and a suction tube (403) arranged on the second movable platform (402); The second sliding column (401) is arranged on the second moving platform (402), and the second moving platform (402) is installed on the mechanical arm (200) through the second sliding column (401).
5. The sampling device for bridge foundation geological survey according to claim 4, characterized in that: The suction tube (403) comprises a first tube body (404) and a second tube body (405), wherein the first tube body (404) is installed on the second moving platform (402); The suction mechanism (400) further comprises an extension frame (406) slidably connected to the second movable platform (402), and an elastic member (407) arranged on the extension frame (406) and the second movable platform (402); The second tube (405) is installed on the extension frame (406).
6. The sampling device for bridge foundation geological survey according to claim 5, characterized in that: The extension frame (406) is provided with a contact buckle (408), and when the first movable platform (302) moves, the extension frame (406) can be driven to move by pushing the contact buckle (408).
7. The sampling device for bridge foundation geological survey according to claim 5 or 6, characterized in that: The first tube body (404) is provided with a through slot (4041), and a spring piece (4042) is installed in the through slot (4041) on the first tube body (404); A pushing body (4051) is installed in the second tube body (405); When the second tube (405) moves toward the first tube (404), the pusher (4051) can press the spring sheet (4042) to bend and deform toward the axial direction of the first tube (404).
8. The sampling device for bridge foundation geological survey according to claim 7, characterized in that: The spring piece (4042) comprises a connecting portion (4043) connected to the first tube body (404), and an arc-shaped portion (4044) connected to the connecting portion (4043) and deflected toward the axial direction of the first tube body (404); The outer diameter of the first tube (404) matches the inner diameter of the second tube (405).
9. The sampling device for bridge foundation geological survey according to claim 1, 6 or 8, characterized in that: The mechanical arm (200) is also provided with a bracket (503), and the driving member (502) is installed on the bracket (503).
10. The sampling device for geological investigation of bridge foundation according to claim 9, characterized in that: The moving mechanism (100) is also provided with a camera mechanism (600).