Front-end equipment control method, system and equipment for intelligent linkage of transformer substation
By adopting front-end device control methods in the substation intelligent linkage system, dynamically locking and unlocking equipment, and verifying the attribution relationship of control commands, the flexibility and stability of the substation intelligent linkage control method in the case of failure is solved, and the operating efficiency and stability of the system are improved.
Patent Information
- Application Number
- CN202510049920.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-13
- Publication Date
- 2025-04-18
AI Technical Summary
The intelligent linkage control method of substations is not flexible enough in case of faults, which may lead to limited linkage function or interruption of operation, and is poor in stability and is easily disturbed by external interference.
A front-end device control method for intelligent linkage of substations is provided. By obtaining the linkage data information of the main and auxiliary monitoring systems, the inspection points and front-end devices are screened based on preset rules and policies, and the hybrid execution mode management control method is adopted to dynamically lock and unlock the front-end device, and to verify the attribution relationship of the control instructions.
The equipment management and orchestration mechanism of intelligent linkage of substations has been improved, control operations have been simplified, overall operation efficiency has been improved, the stability and continuity of the system have been ensured, and the problems of poor stability and external interference have been alleviated.
Smart Images

Figure CN119853290A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of intelligent patrol of power systems, and in particular to a front-end equipment control method, system and equipment for intelligent linkage of substations. Background Art
[0002] In the modern substation intelligent inspection system, intelligent linkage is the key means to ensure the safe and efficient operation of the system. Through intelligent linkage, various types of equipment and systems can work together, respond to and handle various abnormal situations in a timely manner, thereby ensuring the stable operation of the substation. In addition, intelligent linkage can also optimize resource allocation, improve operation and maintenance efficiency, reduce the risk of manual intervention and misoperation, and play an important role in the reliability and intelligence level of the entire substation.
[0003] However, due to the complexity of the substation system, there are some problems with the control method of intelligent linkage. In the event of a fault, the emergency handling of the traditional method is not flexible enough, which may lead to limited linkage functions or interrupted operations. At the same time, the traditional method has poor stability during the linkage process and is easily affected by external interference. These problems limit the overall performance of the intelligent patrol system. Summary of the invention
[0004] The purpose of the present invention is to provide a front-end equipment control method, system and equipment for intelligent linkage of substations in order to solve at least one of the above technical problems.
[0005] In the first aspect, an embodiment of the present invention provides a front-end equipment control method for intelligent linkage of substations, which is applied to a remote intelligent patrol system of a substation; the method comprises: obtaining the linkage data information of the main and auxiliary monitoring systems of the substation, and generating a trigger signal based on the linkage data information; based on preset rules and strategies, screening patrol points and front-end equipment corresponding to the trigger signal; based on a hybrid execution mode, managing and organizing the control method of the front-end equipment; based on the control method, dynamically locking the corresponding front-end equipment during the linkage execution period, and verifying the ownership relationship of the control instructions during the linkage execution period; and unlocking the front-end equipment when the linkage state of the front-end equipment is task completion or the locking time ends.
[0006] Furthermore, the linkage data information includes: a master device remote control preset signal, a master device position change signal, a master and auxiliary device monitoring over-limit signal, a master and auxiliary device monitoring alarm signal, and online monitoring data.
[0007] Furthermore, a trigger signal is generated based on the linkage data information, including: directly generating the trigger signal from the main device remote control preset signal, the main device position change signal, the main and auxiliary device monitoring over-limit signal, and the main and auxiliary device monitoring alarm signal; analyzing data features based on the online monitoring data and preset judgment conditions, and generating the trigger signal when the trend change of the data features exceeds a preset threshold range or the data features are abnormal.
[0008] Furthermore, the preset rules and strategies include relationship mapping and data screening; wherein, the relationship mapping includes: a many-to-many relationship between the patrol points and the front-end devices, and a one-to-one relationship or a one-to-many relationship between the trigger signal and the patrol points; the data screening includes: based on the patrol points configured with the trigger signal and the relationship mapping, screening the patrol points and front-end devices corresponding to the trigger signal.
[0009] Furthermore, the hybrid execution mode includes a serial control execution mode and a parallel control execution mode; based on the hybrid execution mode, the control method of the front-end device is managed and organized, including: when one front-end device corresponds to multiple patrol points, the execution mode of the front-end device is the serial control execution mode; when patrol points are executed between each front-end device, the execution mode of the front-end device is the parallel control execution mode.
[0010] Furthermore, verifying the ownership of the control instructions during linkage execution includes: when executing the control instructions of the front-end device, checking the locking state of the front-end device and the InstanceID of the control instructions; if the front-end device is in a locked state, verifying whether the InstanceID of the control instruction belongs to the smart linkage instance; if so, allowing the control instruction to execute, if not, refusing to execute the control instruction.
[0011] Furthermore, the method also includes: if the linkage module of the remote intelligent patrol system fails or crashes, unlocking the front-end device.
[0012] In the second aspect, an embodiment of the present invention also provides a front-end equipment control system for intelligent linkage of substations, which is applied to the remote intelligent patrol system of substations; it includes: a monitoring and analysis module, a policy analysis module, a management and organization module, a locking and verification module, and an unlocking control module; wherein the monitoring and analysis module is used to obtain the linkage data information of the main and auxiliary monitoring systems of the substation, and generate a trigger signal based on the linkage data information; the policy analysis module is used to screen the patrol points and front-end equipment corresponding to the trigger signal based on preset rules and policies; the management and organization module is used to manage and organize the control mode of the front-end equipment based on a mixed execution mode; the locking and verification module is used to dynamically lock the corresponding front-end equipment during the linkage execution period based on the control mode, and verify the ownership relationship of the control instructions during the linkage execution period; the unlocking control module is used to unlock the front-end equipment when the linkage state of the front-end equipment is task completion or the locking time ends.
[0013] Furthermore, the unlocking control module is also used to unlock the front-end device if the linkage module of the remote intelligent patrol system fails or crashes.
[0014] In a third aspect, an embodiment of the present invention further provides an electronic device, comprising: a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the method provided in the embodiment of the present invention when executing the computer program.
[0015] The present invention provides a front-end equipment control method, system and equipment for intelligent linkage of substations, which have efficient equipment management and scheduling mechanisms, simplify control operations, and improve overall operating efficiency; at the same time, they have the function of autonomously locking and unlocking equipment to ensure the stability and continuity of the system, alleviating the technical problems of poor stability and susceptibility to external interference in the prior art. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to more clearly illustrate the implementation methods of the present application or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0017] Figure 1 A flow chart of a front-end device control method for intelligent linkage of substations provided by an embodiment of the present invention;
[0018] Figure 2 A data trend comparison configuration diagram provided by an embodiment of the present invention;
[0019] Figure 3 A schematic diagram of a front-end equipment control system for intelligent linkage of a substation provided by an embodiment of the present invention;
[0020] Figure 4 A registration-heartbeat request response flow chart provided in an embodiment of the present invention;
[0021] Figure 5 A front schematic diagram of a front-end device control device for intelligent linkage of a substation provided by an embodiment of the present invention;
[0022] Figure 6 A top view of a front-end device control device for intelligent linkage of a substation provided by an embodiment of the present invention;
[0023] Figure 7 A schematic diagram of the back side of a front-end device control device for intelligent linkage of substations provided in an embodiment of the present invention. DETAILED DESCRIPTION
[0024] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0025] Embodiment 1
[0026] Figure 1 1 is a flow chart of a front-end device control method for intelligent linkage of a substation provided according to an embodiment of the present invention, and the method is applied to a remote intelligent patrol system of a substation. Figure 1 As shown, the method specifically comprises the following steps:
[0027] Step S102: acquiring linkage data information of the primary and secondary monitoring systems of the substation, and generating a trigger signal based on the linkage data information.
[0028] Step S104, based on preset rules and strategies, screening the patrol points and front-end devices corresponding to the trigger signal.
[0029] Step S106, managing and organizing the control mode of the front-end device based on the hybrid execution mode.
[0030] Step S108, based on the control mode, dynamically lock the corresponding front-end device during the linkage execution, and verify the ownership relationship of the control instructions during the linkage execution.
[0031] Step S110, when the linkage status of the front-end device is task completion or locking time is over, unlocking the front-end device.
[0032] Optionally, in the embodiment of the present invention, the front-end device includes: an integrated camera system or a front-end video host and peripheral devices, a camera and a pan / tilt device, etc. It mainly realizes the functions of information collection, two-way transmission, control, etc. of audio, video, data, alarm and status.
[0033] Optionally, in an embodiment of the present invention, the front-end device related controls include: pan / tilt control, preset position control, video control, image acquisition control and audio control, etc.
[0034] In an optional implementation manner provided by the present embodiment, the linkage data information includes: a master device remote control preset signal, a master device position change signal, a master and auxiliary device monitoring over-limit signal, a master and auxiliary device monitoring alarm signal, and online monitoring data.
[0035] Specifically, the main equipment linkage information includes: remote control preset linkage information of primary equipment; position change signal linkage information of primary equipment such as circuit breakers, isolating switches, and grounding switches; non-electrical quantity alarm signal linkage information of primary equipment such as main transformers and circuit breakers; total alarm signal linkage information after the fusion of single primary equipment; protection action tripping signal linkage information.
[0036] The linkage information of auxiliary equipment includes: remote control start command linkage information of lighting, fans, air conditioners, water pumps and other equipment; remote signal change signal linkage information of fire protection, security electronic fence, access control failure and other equipment; various online monitoring, SF6, oxygen and other telemetry alarm signal linkage information.
[0037] Specifically, step S102 also includes the following steps:
[0038] Step S1021, directly generating a trigger signal for the master device remote control preset signal, the master device position change signal, the master and auxiliary device monitoring over-limit signal, and the master and auxiliary device monitoring alarm signal;
[0039] Step S1022, analyzing data features based on online monitoring data and preset judgment conditions, and generating a trigger signal when the trend change of the data features exceeds a preset threshold range or the data features are abnormal.
[0040] Specifically, a trend analysis is performed on the online monitoring data, and the defect trend, fault characteristics and defect nature are analyzed based on the input data and the preset judgment conditions set in advance, and then a linkage trigger signal is generated; a comprehensive analysis is performed on the online monitoring data, as well as the input data and the preset judgment conditions set in advance, and the characteristics of the online monitoring data are analyzed. If the trend change exceeds a certain threshold range or there is an obvious abnormality, a linkage trigger signal is generated.
[0041] In an optional implementation provided by an embodiment of the present invention, the preset judgment condition includes using historical data for trend analysis to determine the status and performance changes of the front-end device. Data comparison items can be customized based on the number of comparisons with historical data. For example, Figure 2 is a data trend comparison configuration diagram provided according to an embodiment of the present invention, such as Figure 2 As shown, the comparison rules include greater than, greater than or equal to, equal to, less than, and less than or equal to.
[0042] Specifically, the preset rules and strategies include relationship mapping and data screening;
[0043] Relationship mapping includes: a many-to-many relationship between patrol points and front-end devices, and a one-to-one relationship or a one-to-many relationship between trigger signals and patrol points.
[0044] In the embodiment of the present invention, one linkage trigger signal can establish one or more patrol points; one front-end device can establish multiple patrol points, and at the same time, one patrol point can correspond to multiple front-end devices for patrol inspection. The present invention automatically sorts out the relationship between the patrol points and front-end devices that have been set, and the linkage trigger signal and the patrol points.
[0045] Data screening includes: based on the patrol points and relationship mapping configured by the trigger signal, screening the patrol points and front-end devices corresponding to the trigger signal.
[0046] In the embodiment of the present invention, the hybrid execution mode includes a serial control execution mode and a parallel control execution mode. Specifically, step S106 also includes the following steps:
[0047] Step S1061, when one front-end device corresponds to multiple patrol points, the execution mode of the front-end device is a serial control execution mode;
[0048] Step S1062, when each front-end device performs patrol point, the execution mode of the front-end device is the parallel control execution mode.
[0049] In the embodiment of the present invention, the efficiency of linkage control can be improved through a hybrid execution mode of serial and parallel execution. The hybrid mode allows multiple tasks to be executed simultaneously, while retaining the flexibility of executing tasks in sequence, thereby better meeting the needs of different linkage operations and improving the overall response speed and performance of the system.
[0050] Specifically, in step S108, the related front-end devices during the linkage execution are dynamically locked, including: dynamically locking the related front-end devices during the linkage execution according to the corresponding hybrid mode.
[0051] Specifically, when it comes to executing patrol equipment, a lock signal and lock time are sent to prevent other control interference.
[0052] Modules transmit messages through the message bus. The interactive content is in JSON format. The sending device lockout is specified as follows:
[0053] {
[0054] "CommandType":"Request",
[0055] "SessionID":"000024",
[0056] "InstanceID":"00002",
[0057] "From":"WebService",
[0058] "To":"SrvVideoCtl",
[0059] "Time":"20240527140401997",
[0060] "Command":"LinkageLock",
[0061] "Body":{
[0062] "DeviceID":"17126256272771",
[0063] "Duration":"60"
[0064] }
[0065] }
[0066] Equipment not involved in the patrol remains unlocked to ensure optimal use of system resources.
[0067] Specifically, in step S108, the attribution relationship of the control instructions during the linkage execution is verified, and the following steps are also included:
[0068] Step S1081, when executing the control instruction of the front-end device, checking the locking state of the front-end device and the InstanceID of the control instruction;
[0069] Step S1082, if the front-end device is in a locked state, check whether the InstanceID of the control instruction belongs to the intelligent linkage instance; if yes, allow the control instruction to execute, if not, refuse to execute the control instruction.
[0070] Specifically, first control and record the InstanceID of each control module; when executing the control instruction of the front-end device, first check the blocking state. If the front-end device is in the blocking state, further verify whether the InstanceID of the control instruction belongs to the intelligent linkage instance. If the verification passes and it belongs to the linkage task, it is allowed to execute; otherwise, it is rejected.
[0071] Optionally, if the front-end device is not in a locked state, the control function can be executed regardless of the InstanceID of the control instruction.
[0072] Specifically, when the linkage state of the front-end device is task completion or the locking time is over, the front-end device is unlocked to restore it to a normal operating state.
[0073] In an optional implementation provided by an embodiment of the present invention, the control instruction for actively unlocking the front-end device is sent as follows:
[0074] {
[0075] "CommandType":"Request",
[0076] "SessionID":"000024",
[0077] "InstanceID":"00002",
[0078] "From":"WebService",
[0079] "To":"SrvVideoCtl",
[0080] "Time":"20240527140401997",
[0081] "Command":"LinkageUnLock",
[0082] "Body":{
[0083] "DeviceID":"17126256272771"
[0084] }
[0085] Optionally, the method provided by the embodiment of the present invention further includes: if the linkage module of the remote intelligent patrol system fails or crashes, unlocking the front-end device.
[0086] From the above description, it can be seen that the present invention provides a front-end device control method for intelligent linkage of substations, which has an efficient device management and scheduling mechanism, simplifies control operations, and improves overall operating efficiency; at the same time, it has the function of autonomously locking and unlocking devices to ensure the stability and continuity of the system. Through the present invention, the intelligent linkage front-end device control method has efficient data processing capabilities, flexible emergency handling mechanisms and stable linkage operation characteristics. The present invention alleviates the technical problems of poor stability and susceptibility to external interference in the prior art.
[0087] Embodiment 2
[0088] Figure 3 Schematic diagram of a front-end equipment control system for intelligent linkage of substations provided according to an embodiment of the present invention, which is applied to a remote intelligent patrol system of a substation. Figure 3 As shown, the system includes: a monitoring and analysis module 10, a policy parsing module 20, a management and organization module 30, a locking and verification module 40, and an unlocking control module 50.
[0089] Specifically, the monitoring and analysis module 10 is used to obtain linkage data information of the main and auxiliary monitoring systems of the substation, and generate a trigger signal based on the linkage data information.
[0090] The strategy analysis module 20 is used to screen the patrol points and front-end devices corresponding to the trigger signal based on preset rules and strategies.
[0091] The management and organization module 30 is used to manage and organize the control mode of the front-end device based on the hybrid execution mode.
[0092] The locking and verification module 40 is used to dynamically lock the corresponding front-end device during the linkage execution based on the control mode, and to verify the ownership relationship of the control instructions during the linkage execution.
[0093] The unlocking control module 50 is used to unlock the front-end device when the linkage state of the front-end device is task completion or locking time is over.
[0094] Specifically, the unlocking control module 50 is also used to unlock the front-end device if the linkage module of the remote intelligent patrol system fails or crashes.
[0095] Optionally, the system provided by the embodiment of the present invention further includes a central control module 60 for overall coordination and control.
[0096] In an optional implementation provided by an embodiment of the present invention, inter-module message communication adopts the Kafka publish-subscribe mode, which is suitable for one-to-many communication and is often used in scenarios such as event processing, logging, and real-time notification.
[0097] Furthermore, the inter-module message communication mode helps decouple modules and improve the scalability and maintainability of the system.
[0098] Specifically, the communication process defines:
[0099] Each module communicates messages between modules through subscription and publishing channels.
[0100] Through the publish-subscribe model, each module can flexibly subscribe and publish messages to achieve one-to-many communication.
[0101] Message transmission adopts the Kafka publish-subscribe model, which supports large-scale, high-throughput message publishing and subscription.
[0102] Structured messages are encapsulated in a unified JSON format to ensure the uniformity, readability, and ease of parsing of the messages.
[0103] Optionally, in an embodiment of the present invention, the structured message is encapsulated in a unified JSON format to ensure uniformity, readability and ease of parsing of the message.
[0104] Specifically, the use of the JSON format enables messages to maintain a consistent structure and format when transmitted between modules, making it easier for different modules to parse and process data, thereby improving the reliability and maintainability of the system.
[0105] Specifically, the application protocol definition is shown in Table 1:
[0106] Table 1 Application protocol definition table
[0107]
[0108]
[0109] Specifically, the application protocol parameters are explained:
[0110] Command type: According to the message function, JSON can be divided into the following categories: message request (Request), message response (Response), emergency report (Message), and heartbeat interaction (Heartbeat).
[0111] Instance number: the instance ID of the module. The instance ID is allocated and managed by the central control module 60. The unit module sends the instance ID of the registration message to the central control module 60. When the service is interrupted, it needs to be re-acquired.
[0112] Session sequence number: The request message is incremented by 1 each time, and the response message needs to bring back the session sequence number in the request message to identify the request and response transactions.
[0113] Command instruction name: Different command instructions are specified according to different control functions.
[0114] Time: The time when the message is sent, in the format of "yyyyMMddHHmmssZZZ".
[0115] Specifically, the Json protocol format:
[0116] {
[0117] "CommandType":"Request",
[0118] "InstanceID":"00001",
[0119] "SessionID":"00001",
[0120] "From":"xxx",
[0121] "To":"xxx",
[0122] "Command":"xxx",
[0123] "Time":"yyyyMMddHHmmssZZZ",
[0124] "Body":{
[0125] "param1":"value1",
[0126] "param2":"value2"
[0127] },
[0128] "ResBody":{
[0129] "param3":"value3",
[0130] "param4":"value4"
[0131] },
[0132] "Result":true,
[0133] "ResultCode":200
[0134] }
[0135] Table 2 Response result coding definition table
[0136] Response result code definition 100 Need to resend 200 success 400 reject 500 mistake
[0137] Optionally, in an embodiment of the present invention, each unit module sends registration, heartbeat and other interactive information to the central control module 60, and the central control module 60 responds after receiving the message. The registration-heartbeat request response process is as follows: Figure 4 shown.
[0138] Specifically, each unit module sends registration information to the central control module 60, and the central control module 60 provides a unique instance ID as an identifier. At the same time, a registration success or failure message is returned.
[0139] If the registration is successful, each unit module will carry the instance ID and send heartbeat information to the central control module 60 at regular intervals to indicate that the module is operating normally.
[0140] The central control module 60 is responsible for real-time management of the instance ID. If the heartbeat message is not sent for three times, it is considered that the link of the unit module is interrupted and the unit module needs to be re-authenticated and registered.
[0141] Optionally, in the embodiment of the present invention, the unit module performs message interaction through the assigned instance ID in daily operation. All messages adopt the standard JSON protocol format, including message request, response, burst report and heartbeat interaction.
[0142] The communication between the modules is more standardized and efficient. At the same time, the central control module 60 can flexibly manage and coordinate the working status of each unit module to ensure the stability and continuity of the system.
[0143] Embodiment 3
[0144] Figure 5 is a front view schematic diagram of a front-end device control device for intelligent linkage of a substation provided according to an embodiment of the present invention, Figure 6 is a top view of a front-end device control device for intelligent linkage of a substation provided according to an embodiment of the present invention, Figure 7 1 is a schematic diagram of the back side of a front-end device control device for intelligent linkage of a substation provided according to an embodiment of the present invention. Figure 5-Figure 7 As shown, the device includes: a housing 1, a switch button 2, an HDMI video output interface 3, a DC power interface 4, a rear panel USB3.0 interface 5, and a Gigabit network port 6. A main control chip and an SSD storage device are arranged inside the housing 1, and the main control chip is electrically connected to the SSD storage device and the Gigabit network port 6.
[0145] Specifically, in the embodiment of the present invention, the Gigabit network port 6 adopts an enhanced surge protection design; the Gigabit network port 6 forms a local area network through a switch and a substation patrol system.
[0146] The processor on the main control chip is used to operate according to the instructions to execute the steps of the method of embodiment 1.
[0147] The present invention further provides an electronic device, comprising: a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the method provided in the embodiment of the present invention when executing the computer program.
[0148] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.
[0149] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A front-end equipment control method for intelligent linkage of substations, characterized in that: A remote intelligent patrol system applied to a substation; the method comprises: Acquire linkage data information of the main and auxiliary monitoring systems of the substation, and generate a trigger signal based on the linkage data information; Based on preset rules and strategies, screening patrol points and front-end devices corresponding to the trigger signal; Based on the hybrid execution mode, manage and organize the control mode of the front-end device; Based on the control mode, dynamically lock the corresponding front-end device during the linkage execution, and verify the ownership relationship of the control instructions during the linkage execution; When the linkage state of the front-end device is task completion or locking time is over, the front-end device is unlocked.
2. The method according to claim 1, characterized in that: The linkage data information includes: a master device remote control preset signal, a master device position change signal, a master and auxiliary device monitoring over-limit signal, a master and auxiliary device monitoring alarm signal, and online monitoring data.
3. The method according to claim 2, characterized in that: Generating a trigger signal based on the linkage data information includes: Directly generating the trigger signal from the master device remote control preset signal, the master device position change signal, the master and auxiliary device monitoring over-limit signal, and the master and auxiliary device monitoring alarm signal; The data feature is analyzed based on the online monitoring data and preset judgment conditions, and the trigger signal is generated when the trend change of the data feature exceeds a preset threshold range or the data feature is abnormal.
4. The method according to claim 1, characterized in that: The preset rules and strategies include relationship mapping and data screening; wherein, The relationship mapping includes: a many-to-many relationship between the patrol points and the front-end devices, and a one-to-one relationship or a one-to-many relationship between the trigger signal and the patrol points; The data screening includes: based on the patrol points configured by the trigger signal and the relationship mapping, screening the patrol points and front-end devices corresponding to the trigger signal.
5. The method according to claim 1, characterized in that: The hybrid execution mode includes a serial control execution mode and a parallel control execution mode; Based on the hybrid execution mode, the control mode of the front-end device is managed and organized, including: When one front-end device corresponds to multiple patrol points, the execution mode of the front-end device is the serial control execution mode; When patrolling points between each front-end device, the execution mode of the front-end device is the parallel control execution mode.
6. The method according to claim 1, characterized in that: Verify the ownership of control instructions during linkage execution, including: When executing a control instruction of a front-end device, checking the locking state of the front-end device and the InstanceID of the control instruction; If the front-end device is in a locked state, it is checked whether the InstanceID of the control instruction belongs to an intelligent linkage instance; if yes, the control instruction is allowed to be executed; if no, the control instruction is rejected to be executed.
7. The method according to claim 1, characterized in that: The method further comprises: if the linkage module of the remote intelligent patrol system fails or crashes, unlocking the front-end device.
8. A front-end equipment control system for intelligent linkage of substations, characterized in that: The remote intelligent patrol system applied to the substation includes: monitoring and analysis module, strategy analysis module, management and organization module, locking and verification module, and unlocking control module. The monitoring and analysis module is used to obtain linkage data information of the main and auxiliary monitoring systems of the substation, and generate a trigger signal based on the linkage data information; The strategy analysis module is used to screen the patrol points and front-end devices corresponding to the trigger signal based on preset rules and strategies; The management and organization module is used to manage and organize the control mode of the front-end device based on the hybrid execution mode; The locking and verification module is used to dynamically lock the corresponding front-end device during the linkage execution based on the control mode, and verify the ownership relationship of the control instructions during the linkage execution; The unlocking control module is used to unlock the front-end device when the linkage state of the front-end device is task completion or locking time is over.
9. The system according to claim 8, characterized in that: The unlocking control module is also used to unlock the front-end device if the linkage module of the remote intelligent patrol system fails or crashes.
10. An electronic device, characterized in that: include: A memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the method according to any one of claims 1 to 7 when executing the computer program.