A method for applying a performance form based on on-site project management by supervisors

By constructing a project performance form, obtaining project information and on-site supervision information, generating supervision evaluation results and management plans, the problem of engineering project supervision is solved and efficient and accurate project management is achieved.

CN119863219BActive Publication Date: 2025-08-01GUANGZHOU ELECTRIC POWER ENG SUPERVISION CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202510345890.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2025-03-24
Publication Date
2025-08-01
Estimated Expiration
2045-03-24

AI Technical Summary

Technical Problem

In engineering project management, it is difficult for the company to efficiently supervise multiple projects at the same time, resulting in inadequate supervision and affecting project quality and progress.

Method used

Based on the application method of the performance form of supervision on-site project management, by constructing the project performance form, obtaining project information and on-site supervision information, generating supervision evaluation results and management plans, we realize automated supervision of managed projects.

Benefits of technology

Efficient and accurate supervision of the project site has been achieved, problems have been discovered and managed in a timely manner, and negative impacts have been reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119863219B_ABST
    Figure CN119863219B_ABST
Patent Text Reader

Abstract

The present invention relates to a method for applying a performance form based on on-site project management of supervision, which is applied to the technical field of engineering project supervision. The method includes: obtaining project information of a target engineering project, where the target engineering project includes a plurality of completed standard engineering projects; constructing a project performance form based on the project information; obtaining on-site supervision information and on-site supervision responsible person information of a project to be managed; generating a supervision evaluation result of the project to be managed based on the project performance form and the on-site supervision information; generating a project management plan based on the supervision evaluation result and the on-site supervision responsible person information; and performing supervision on the project to be managed based on the project performance form and the project management plan. This application has the effect of efficiently and accurately supervising the on-site of an engineering project.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the technical field of engineering project supervision, and particularly to an application method of a performance form based on on-site project management of supervision. Background Art

[0002] An engineering project is a project carried by engineering construction, which is a one-time engineering construction task as the object to be managed.

[0003] It takes buildings or structures as the target outputs, requires a certain amount of cost, is completed according to a certain procedure within a certain period of time, and should meet the quality requirements.

[0004] In order to ensure that the engineering project can be completed on time and with quality, on-site supervision needs to be carried out when the engineering project starts, and the implementation situation needs to be recorded and managed.

[0005] However, for a company, it often undertakes several engineering projects at the same time. It is easy to have the situation of inadequate supervision during management. Due to the complex content of the supervised engineering projects and a large number of supervision records, it is difficult to discover and solve problems in a timely manner, thus having a negative impact on the engineering project. Summary of the Invention

[0006] In order to efficiently and accurately supervise the on-site of an engineering project, this application provides an application method of a performance form based on on-site project management of supervision.

[0007] In the first aspect, this application provides an application method of a performance form based on on-site project management of supervision, adopting the following technical solutions:

[0008] An application method of a performance form based on on-site project management of supervision includes:

[0009] Obtain the project information of the target engineering project, where the target engineering project includes multiple completed standard engineering projects;

[0010] Construct a project performance form based on the project information;

[0011] Obtain the on-site supervision information and on-site supervision responsible person information of the project to be managed;

[0012] Generate the supervision evaluation result of the target supervision project based on the project performance form and the on-site supervision information;

[0013] Generate a project management plan based on the supervision evaluation result and the on-site supervision responsible person information;

[0014] Supervise the project to be managed based on the project performance form and the project management plan.

[0015] By adopting the above technical solution, taking the completed and standard-compliant engineering projects as the target engineering projects, using the project information of the target engineering projects to construct a project performance form for project management, collecting on-site supervision information and on-site supervision responsible person information for the projects to be managed that do not use the project performance form, using the constructed project performance form to judge the on-site supervision information, obtaining the supervision judgment result, constructing a project management plan for managing the projects to be managed through the supervision judgment result and the on-site supervision responsible person information, and then using the project performance form and the project plan to automatically and comprehensively supervise the projects to be managed, so as to be able to efficiently and accurately supervise the engineering project site.

[0016] Optionally, constructing the project performance form based on the project information includes:

[0017] Extracting effective information from the project information to obtain project execution content;

[0018] Extracting fixed content from the project execution content to determine project fixed content and project difference content;

[0019] Extracting content keywords and type keywords of the project difference content;

[0020] Calculating the application correlation degree between the project difference contents based on the content keywords and the type keywords;

[0021] Dividing the application scope of the project difference contents based on the application correlation degree to generate an application content division result;

[0022] Generating a project operation process based on the project fixed content and the application content division result;

[0023] Obtaining project supervision requirements, and generating a project performance form based on the project supervision requirements and the project operation process.

[0024] Optionally, calculating the application correlation degree between the project difference contents based on the content keywords and the type keywords includes:

[0025] Obtaining the keyword attributes of the content keywords and the type division rules of the type keywords;

[0026] Determining the content similarity between the content keywords based on the keyword attributes;

[0027] Determining the type similarity between the type keywords based on the type division rules;

[0028] Obtaining the correlation degree calculation rule;

[0029] Determine the application correlation degree between each of the item difference contents based on the correlation degree calculation rule, the content similarity, and the type similarity.

[0030] Optionally, the generating of the project operation process based on the project fixed content and the application content division result includes:

[0031] Obtain the project standard execution procedure;

[0032] Determine the fixed operation steps based on the project standard execution procedure and the project fixed content;

[0033] Perform step subdivision and arrangement on the item difference contents based on the application content division result to generate a content processing result;

[0034] Perform adjustment processing on the content processing result based on the project standard execution procedure to generate difference operation steps;

[0035] Arrange the fixed operation steps and the difference operation steps according to the project standard execution procedure to generate a project operation process.

[0036] Optionally, the generating of the supervision judgment result of the project to be managed based on the project performance form and the on-site supervision information includes:

[0037] Obtain the project planning information of the project to be managed;

[0038] Select the project performance form based on the project planning information to obtain a target performance form;

[0039] Generate a project execution plan based on the target performance form and the project planning information;

[0040] Generate a supervision performance record based on the on-site supervision information and the target performance form;

[0041] Obtain the supervision judgment rule;

[0042] Judge the project to be managed based on the supervision judgment rule, the project execution plan, and the supervision performance record to generate a supervision judgment result.

[0043] Optionally, the generating of the project management plan based on the supervision judgment result and the on-site supervision person in charge information includes:

[0044] Obtain the judgment level of the supervision judgment result;

[0045] Determine the supervision level of the project to be managed based on the judgment level and the supervision judgment rule;

[0046] Judge whether the project execution plan needs to be adjusted based on the supervision level;

[0047] If the project execution plan needs to be adjusted, adjust the project execution plan based on the target duty performance form and the supervision level to generate an adjusted execution plan;

[0048] Generate a project management plan based on the adjusted execution plan, the target duty performance form, the supervision level, and the on-site supervision person in charge information;

[0049] If the project execution plan does not need to be adjusted, generate a project management plan based on the project execution plan, the target duty performance form, the supervision level, and the on-site supervision person in charge information.

[0050] Optionally, the supervision of the project to be managed based on the project duty performance form and the project management plan includes:

[0051] Obtain the project duty performance form filling information of the project to be managed in real time;

[0052] Judge whether the project to be managed meets the preset execution plan based on the form filling information and the project management plan;

[0053] If the project to be managed meets the preset execution plan, repeat the step of obtaining the project duty performance form filling information of the project to be managed in real time;

[0054] If the project to be managed does not meet the preset execution plan, determine the project exception information based on the project duty performance form filling information and the project management plan;

[0055] Generate a supervision responsibility letter based on the project exception information and the on-site supervision person in charge information.

[0056] In a second aspect, the present application provides a duty performance form application device for project management on a supervision site, adopting the following technical solution:

[0057] A duty performance form application device for project management on a supervision site, comprising:

[0058] A project information acquisition module, configured to acquire project information of a target engineering project, where the target engineering project includes a plurality of completed standard engineering projects;

[0059] A duty performance form construction module, configured to construct a project duty performance form based on the project information;

[0060] A supervision information acquisition module, configured to acquire on-site supervision information and on-site supervision person in charge information of the project to be managed;

[0061] A supervision result generation module, configured to generate a supervision evaluation result of the project to be managed based on the project performance form and the on-site supervision information;

[0062] A management plan generation module, configured to generate a project management plan based on the supervision evaluation result and the on-site supervision person in charge information;

[0063] An engineering project supervision module, configured to supervise the project to be managed based on the project performance form and the project management plan.

[0064] By adopting the above technical solution, the completed and compliant engineering projects are used as target engineering projects, and the project information of the target engineering projects is used to construct a project performance form for project management. The on-site supervision information and the on-site supervision person in charge information of the project to be managed without using the project performance form are collected. The constructed project performance form is used to evaluate the on-site supervision information to obtain a supervision evaluation result. A project management plan for managing the project to be managed is constructed through the supervision evaluation result and the on-site supervision person in charge information. Then, the project performance form and the project plan are used to automatically and comprehensively supervise the project to be managed, so as to be able to efficiently and accurately supervise the engineering project site.

[0065] In a third aspect, the present application provides an electronic device, adopting the following technical solution:

[0066] An electronic device includes a processor, and the processor is coupled to a memory;

[0067] The processor is configured to execute a computer program stored in the memory, so that the electronic device executes the computer program of the duty form application method for supervision on-site project management according to any one of the first aspect.

[0068] In a fourth aspect, the present application provides a computer-readable storage medium, adopting the following technical solution:

[0069] A computer-readable storage medium stores a computer program that can be loaded and executed by a processor, and the computer program is the duty form application method for supervision on-site project management according to any one of the first aspect.

[0070] In summary, the present application includes at least one of the following beneficial technical effects:

[0071] Take the completed and compliant engineering projects as target engineering projects, use the project information of the target engineering projects to construct a project performance form for project management, collect on-site supervision information and on-site supervision responsible person information for the projects to be managed that have not used the project performance form, use the constructed project performance form to judge the on-site supervision information, obtain the supervision judgment result, construct a project management plan for managing the projects to be managed through the supervision judgment result and the on-site supervision responsible person information, and then use the project performance form and the project plan to automatically and comprehensively supervise the projects to be managed, so as to be able to efficiently and accurately supervise the engineering project site. Description of the Drawings

[0072] Figure 1 It is a schematic flowchart of a method for applying a performance form based on on-site project management of supervision provided by an embodiment of the present application.

[0073] Figure 2 It is a structural block diagram of a device for applying a performance form based on on-site project management of supervision provided by an embodiment of the present application.

[0074] Figure 3 It is a structural block diagram of an electronic device provided by an embodiment of the present application. Detailed Description of the Embodiment

[0075] The following further describes the present application in detail with reference to the drawings.

[0076] An embodiment of the present application provides a method for applying a performance form based on on-site project management of supervision. The method for applying a performance form based on on-site project management of supervision can be executed by an electronic device, and the electronic device can be a server or a terminal device. Among them, the server can be an independent physical server, a server cluster or a distributed system composed of multiple physical servers, or a cloud server providing cloud computing services.

[0077] The terminal device can be a smart phone, a tablet computer, a desktop computer, etc., but is not limited thereto.

[0078] Figure 1 It is a schematic flowchart of a method for applying a performance form based on on-site project management of supervision provided by an embodiment of the present application.

[0079] As Figure 1 shown, the main processes of the method are described as follows (Steps S101 - S106):

[0080] Step S101, obtain the project information of the target engineering project, where the target engineering project includes multiple completed standard engineering projects.

[0081] In this embodiment, in order to make the performance forms created subsequently more standardized, it is necessary to collect a large number of completed standard engineering projects, use all the collected completed standard engineering projects as target engineering projects, extract the project information in the target engineering projects, and obtain the project information to be used subsequently. The project information includes a series of content directly related to project implementation, such as project name, project creation time, project end time, project type, project implementation location, project execution records, etc.

[0082] It should be noted that the target engineering projects need to include all types of projects, such as electrical projects, non-production patent projects, distribution network projects, equipment supervision projects, civil engineering projects, line projects, new energy projects, comprehensive management projects, etc. Standard engineering projects refer to engineering projects that are completed within the specified time with guaranteed quality and quantity without any unexpected events.

[0083] Step S102: construct a project performance form based on the project information.

[0084] For step S102, effective information is extracted from the project information to obtain the project execution content; fixed content is extracted from the project execution content to determine the project fixed content and project difference content; content keywords and type keywords of the project difference content are extracted; the application correlation between the project difference contents is calculated based on the content keywords and type keywords; the application scope of the project difference content is divided based on the application correlation to generate the application content division result; the project operation process is generated based on the project fixed content and application content division results; the project supervision requirements are obtained, and a project performance form is generated based on the project supervision requirements and the project operation process.

[0085] In this embodiment, in addition to the valid information that can be used to construct the project performance form, the project information also includes modal particles, content descriptions unrelated to the project, and descriptions of useless situations such as region, environment and weather. These contents are not only irrelevant to the construction of the project performance form, but also increase the processing pressure of the computer. Therefore, it is necessary to remove these useless contents or extract the content other than these useless contents to obtain valid information, and use the obtained valid information as the project execution content.

[0086] After obtaining the project execution content, it is necessary to further extract the project execution content, that is, to extract the content that all projects in the project execution content need to execute uniformly, and use this part of the content as the project fixed content, and the remaining part as the project difference content. Among them, the project fixed content includes the start node record at the beginning of the project, the mid-term inventory of the project, the final verification of the project, etc., while the project difference content includes different nodes corresponding to different projects. For example, in the civil engineering project, there are material purchase nodes, foundation construction nodes, and frame construction nodes, etc. In the power distribution network project, there are network cable procurement nodes, regional power distribution network nodes, and network cable laying nodes, etc. Extract keywords from the project difference content to obtain two types of keywords: content keywords and type keywords. Among them, the content keywords mainly reflect the main work content of the project, such as laying the foundation, laying network cables, and power configuration, etc., while the type keywords mainly reflect the main types of the project, such as the construction of power distribution network steel pipe racks, the construction of bridges, the installation of distribution transformers, etc., to obtain two types of keywords.

[0087] It should be noted that the setting of content keywords and type keywords needs to be set according to the actual engineering project content. The above keyword content is only for illustrative purposes and is not a specific limitation.

[0088] After obtaining the content keywords and type keywords, calculate the application correlation degree between the project difference contents according to the content keywords and type keywords, and set the corresponding correlation degree threshold. Divide the project difference contents with the application correlation degree greater than or equal to the correlation degree threshold into one application scope, and divide the project difference contents less than the correlation degree threshold into separate application scopes respectively, so as to obtain the final content division result. Create the project operation process according to the project fixed content and the application division result, and construct a project performance form for project supervision according to the created project operation process and project supervision requirements.

[0089] The headers of the constructed project performance form set according to the project supervision requirements include serial number, operation name, supervision control points, behavior type, output, and supervision basis; the risk-related continuation form set according to the operation risks in the process includes serial number, operation tasks (primary tasks, secondary tasks, and tertiary tasks), risk name, risk type, risk level, risk control measures, and supervision control measures; then determine the number of form rows of the project performance form and the operation nodes that need to use the risk-related continuation form according to the project operation process.

[0090] Further, calculating the application correlation degree between project difference contents using content keywords and type keywords mainly includes: obtaining the keyword attributes of content keywords and the type division rules of type keywords; determining the content similarity between content keywords based on the keyword attributes; determining the type similarity between type keywords based on the type division rules; obtaining the correlation degree calculation rules; and determining the application correlation degree between each project difference content based on the correlation degree calculation rules, content similarity, and type similarity.

[0091] In this embodiment, the keyword attribute of a content keyword is the category to which the content keyword belongs. For example, the keyword attribute of "foundation construction" is "land excavation and construction", and the keyword attribute of "distributor installation" is "electrical equipment configuration", etc. The purpose of setting the keyword attribute is to further distinguish keywords through the keyword attribute when the keyword names are relatively similar, to avoid the situation of classifying keywords with similar names but different meanings as the same keyword.

[0092] By comparing the keyword attributes of content keywords, the content similarity of content keywords with the same keyword attribute meaning is set to the highest value, otherwise it is divided into the lowest value. The average value is calculated based on the number of content keywords and the similarity value between two project difference contents to obtain the final result. At the same time, the type keywords are compared to obtain the content similarity, and then the type similarity between type keywords is determined through the type division rules. The type division rules are to set a same-type form, in which all types of type keywords are set, and type similarity relationships are set. Different type similarity relationships correspond to different scores. If two type keywords are synonyms or near-synonyms, the corresponding score is set to the highest value. If two type keywords belong to the same major category but different minor categories, the corresponding score is set to a value one level lower than the highest value. Among them, the division of major categories, minor categories, the highest value, and the score level needs to be set separately according to the actual engineering implementation requirements and different engineering types, as long as the above division idea is satisfied, and the specific content of the same-type form setting is not specifically limited here.

[0093] Finally, through the correlation degree calculation rules, the final application correlation degree is calculated. The correlation degree calculation rules are to set the ratio of content similarity and type similarity. Calculate the first similarity based on the ratio of content similarity and content similarity, calculate the second similarity based on the ratio of type similarity and type similarity, add the first similarity and the second similarity and convert it into a percentage value. The finally calculated percentage value is the application correlation degree. Among them, the ratio of content similarity and type similarity needs to be set according to the actual application requirements, and the percentage value is rounded to two decimal places according to the principle of rounding.

[0094] Further, the main process of creating a project operation process using the project fixed content and the application content division result is as follows: obtain the project standard execution procedure; determine the fixed operation steps based on the project standard execution procedure and the project fixed content; perform step subdivision and arrangement on the project difference content based on the application content division result to generate a content processing result; perform adjustment processing on the content processing result based on the project standard execution procedure to generate difference operation steps; arrange the fixed operation steps and the difference operation steps according to the project standard execution procedure to generate a project operation process.

[0095] In this embodiment, the project standard execution procedure is a procedure that enables the project to proceed smoothly and completely without adjusting the sequence of project nodes during project implementation. The project standard procedure includes the project execution sequence, node contents that can be carried out simultaneously in parallel, or execution restrictions, etc. Moreover, for different types of projects, the processing methods for the project difference content in the project standard execution procedure are also different. Therefore, when constructing the project operation process, it is necessary to first determine the fixed operation steps based on the project standard execution procedure and the project fixed content, that is, the operation sequence of the project fixed content. After that, determine the specific steps and execution sequence of the application content during project implementation through the application content division result, use the specific steps and execution sequence to subdivide the steps of the project difference content corresponding to the application content division result to obtain multiple execution steps, and arrange the execution steps according to the required execution sequence to obtain a content processing result. In the obtained content processing result, there may be conflicts in the sequence or contents that can be executed simultaneously. Therefore, use the project standard value performance procedure to adjust the content processing result to obtain difference operation steps, and insert the difference operation steps into the above-determined fixed operation steps according to the project execution standard to obtain the final project operation process.

[0096] Step S103, obtain the on-site supervision information and the on-site supervision person-in-charge information of the project to be managed.

[0097] In this embodiment, the project to be managed is a construction project that is about to be implemented or is already in the process of implementation. The on-site supervision information includes information such as the project implementation status, project implementation results, project implementation progress, and problems and accidents generated during the project implementation process. This on-site supervision information mainly records the relevant content of the implementation of the project to be managed, while the on-site supervision person-in-charge information includes the name of the person in charge, gender of the person in charge, main supervision content of the person in charge, position of the person in charge, and contact information of the person in charge, etc.

[0098] It should be noted that the on-site supervision information and the on-site supervision person-in-charge information include but are not limited to the above content, and can also be increased or adjusted according to the actual supervision requirements and the situation of the project to be managed, and no specific limitations are made here.

[0099] Step S104: Generate the supervision evaluation result of the target supervision project based on the project performance form and on-site supervision information.

[0100] Regarding step S104, obtain the project planning information of the project to be managed; select the project performance form based on the project planning information to obtain the target performance form; generate a project execution plan based on the target performance form and the project planning information; generate a supervision performance record based on the on-site supervision information and the target performance form; obtain the supervision evaluation rules; evaluate the project to be managed based on the supervision evaluation rules, the project execution plan, and the supervision performance record to generate the supervision evaluation result.

[0101] In this embodiment, the project planning information of the project to be managed includes the project plan, the project start time, the project implementation location, etc. According to the project plan among them, the project type of the project to be managed can be determined. After the project performance form is created, according to the result of the application content division of the project performance form, the project application type of the project performance form is determined. The project type is determined according to the project plan, and the project type is matched with the project application type. The project performance form corresponding to the project application type that matches the project type is used as the target performance form. Obtain the project operation process of the target performance form, and fill in the project planning information into the project operation process to obtain the project execution plan.

[0102] Fill in the collected on-site supervision information into the target performance form to obtain the supervision performance record. Obtain the abnormal part in the supervision performance record, and compare the abnormal part with the supervision evaluation rules to obtain the supervision evaluation result. The supervision evaluation rules are to set a scoring table for multiple project performance forms. First, determine the supervision evaluation rules used this time according to the project execution plan constructed based on the project operation process corresponding to the target performance form. Compare the abnormal part in the supervision performance record with the supervision evaluation rules to determine the score of each abnormal part. And there are grades corresponding to the scores set in the supervision evaluation rules. Add up all the scores to get the final total score. Determine the evaluation grade according to the total score, and bind the total score with the evaluation grade to obtain the final supervision evaluation result.

[0103] Step S105: Generate a project management plan based on the supervision evaluation result and the on-site supervision person in charge information.

[0104] For step S105, obtain the evaluation level of the supervision evaluation result; determine the supervision level of the project to be managed based on the evaluation level and the supervision evaluation rules; determine whether the project implementation plan needs to be adjusted based on the supervision level; if the project implementation plan needs to be adjusted, then adjust the project implementation plan based on the target performance form and the supervision level to generate an adjusted implementation plan; generate a project management plan based on the adjusted implementation plan, the target performance form, the supervision level, and the information of the on-site supervision person in charge; if the project implementation plan does not need to be adjusted, then generate a project management plan based on the project implementation plan, the target performance form, the supervision level, and the information of the on-site supervision person in charge.

[0105] In this embodiment, a numerical range of evaluation levels is also set in the supervision evaluation rules, and each numerical range of evaluation levels corresponds to a supervision level. When determining the supervision level of the project to be managed, use the evaluation level to determine the numerical range of evaluation levels it belongs to, and thus use the supervision level corresponding to the numerical range of evaluation levels it belongs to as the supervision level of the project to be managed. A level threshold is set to determine whether the supervision level is not greater than the level threshold. If the supervision level is not greater than the level threshold, it is determined that the project implementation plan does not need to be adjusted, and directly bind the project implementation plan, the target performance form, the supervision level, and the information of the on-site supervision person in charge to generate a project management plan. If the supervision level is greater than the level threshold, it is determined that the project implementation plan needs to be adjusted, and use the target performance form and the supervision level to adjust the project implementation plan to obtain an adjusted implementation plan, and bind the adjusted implementation plan, the target performance form, the supervision level, and the information of the on-site supervision person in charge to generate a project management plan.

[0106] When adjusting the project implementation plan to generate an adjusted implementation plan, determine the node position in the project implementation plan that needs to be adjusted according to the project performance form, determine the execution information in this node position, and adjust it based on the specific execution information with the supervision level as the benchmark to obtain the final adjusted implementation plan. The project execution information includes execution progress and execution error content, etc. When the content to be adjusted is the execution progress, determine the progress that needs to be supplemented according to the actual execution progress, and determine the execution duration of the progress that needs to be supplemented according to the supervision level. The higher the supervision level, the shorter the execution duration that needs to be supplemented. The specific duration needs to set a corresponding table according to the actual project situation, so as to query and determine according to the supervision level, the node position, and the project execution information. Other project execution information is adjusted in the same way by querying the adjustment table.

[0107] Step S106, conduct supervision on the project to be managed based on the project performance form and the project management plan.

[0108] For step S106, obtain the information filled in the project performance form of the project to be managed in real time; determine whether the project to be managed meets the preset execution plan based on the form filling information and the project management plan; if the project to be managed meets the preset execution plan, repeat the step of obtaining the information filled in the project performance form of the project to be managed in real time; if the project to be managed does not meet the preset execution plan, determine the project exception information based on the form filling information and the project management plan; generate a supervision responsibility letter based on the project exception information and the on-site supervision person in charge information.

[0109] In this embodiment, when using the project performance form and the project management plan to supervise the project to be managed, it is necessary to collect the information filled in the project rate index form of the project to be managed in real time to obtain the information filled in the project performance form of the project to be managed. The form filling information includes the form filling time, the form filling node, and the form filling content. Compare the above three contents with the project management plan to check whether they are consistent or within the allowable range of differences. If they are consistent or within the allowable range of differences, repeat the steps of obtaining and comparing until a problem occurs or the project ends; if they are inconsistent or outside the allowable range of differences, compare the form filling information of the project performance form with the project management plan to determine the project exception information, bind the project exception information with the on-site supervision person in charge information, generate a supervision responsibility letter, and hold the person responsible for the exception problem through the supervision responsibility letter. Therefore, when a problem occurs in the project, the key to the problem can be determined in time, and remedies can be made in time through the method of holding the person responsible, reducing the negative impact on the overall project.

[0110] Figure 2 It is a structural block diagram of a device 200 for applying a performance form based on on-site project management of supervision for the application example.

[0111] As Figure 2 shown, the device 200 for applying a performance form based on on-site project management of supervision mainly includes:

[0112] A project information acquisition module 201, configured to acquire project information of a target engineering project, where the target engineering project includes multiple completed standard engineering projects;

[0113] A performance form construction module 202, configured to construct a project performance form based on the project information;

[0114] A supervision information acquisition module 203, configured to acquire on-site supervision information and on-site supervision person in charge information of the project to be managed;

[0115] A supervision result generation module 204, configured to generate a supervision evaluation result of the project to be managed based on the project performance form and the on-site supervision information;

[0116] A management plan generation module 205, configured to generate a project management plan based on the supervision evaluation result and the information of the on-site supervision person in charge;

[0117] An engineering project supervision module 206, configured to supervise the project to be managed based on the project performance form and the project management plan.

[0118] As an optional implementation manner of this embodiment, the performance form construction module 202 includes:

[0119] An execution content extraction module, configured to extract effective information from the project information to obtain the project execution content;

[0120] A project content determination module, configured to extract fixed content from the project execution content to determine the project fixed content and the project difference content;

[0121] A keyword extraction module, configured to extract the content keywords and type keywords of the project difference content;

[0122] An application correlation degree calculation module, configured to calculate the application correlation degree between the project difference contents based on the content keywords and the type keywords;

[0123] A division result generation module, configured to divide the application scope of the project difference content based on the application correlation degree to generate an application content division result;

[0124] An operation process generation module, configured to generate a project operation process based on the project fixed content and the application content division result;

[0125] A performance form generation module, configured to obtain the project supervision requirements, and generate a project performance form based on the project supervision requirements and the project operation process.

[0126] In this optional embodiment, the application correlation degree calculation module is specifically configured to obtain the keyword attributes of the content keywords and the type division rules of the type keywords; determine the content similarity between the content keywords based on the keyword attributes; determine the type similarity between the type keywords based on the type division rules; obtain the correlation degree calculation rules; and determine the application correlation degree between each project difference content based on the correlation degree calculation rules, the content similarity, and the type similarity.

[0127] In this optional embodiment, the operation process generation module is specifically configured to obtain the project standard execution procedure; determine the fixed operation steps based on the project standard execution procedure and the project fixed content; perform step subdivision and arrangement on the project difference content based on the application content division result to generate a content processing result; perform adjustment processing on the content processing result based on the project standard execution procedure to generate difference operation steps; and arrange the fixed operation steps and the difference operation steps according to the project standard execution procedure to generate a project operation process.

[0128] As an alternative implementation of this embodiment, the supervision result generation module 204 is specifically configured to obtain the project planning information of the project to be managed; select the project performance form based on the project planning information to obtain the target performance form; generate a project execution plan based on the target performance form and the project planning information; generate a supervision performance record based on the on-site supervision information and the target performance form; obtain the supervision evaluation rules; evaluate the project to be managed based on the supervision evaluation rules, the project execution plan, and the supervision performance record, and generate a supervision evaluation result.

[0129] As an alternative implementation of this embodiment, the management plan generation module 205 is specifically configured to obtain the evaluation level of the supervision evaluation result; determine the supervision level of the project to be managed based on the evaluation level and the supervision evaluation rules; determine whether the project execution plan needs to be adjusted based on the supervision level; if the project execution plan needs to be adjusted, adjust the project execution plan based on the target performance form and the supervision level to generate an adjusted execution plan; generate a project management plan based on the adjusted execution plan, the target performance form, the supervision level, and the on-site supervision leader information; if the project execution plan does not need to be adjusted, generate a project management plan based on the project execution plan, the target performance form, the supervision level, and the on-site supervision leader information.

[0130] As an alternative implementation of this embodiment, the engineering project supervision module 206 is specifically configured to obtain the project performance form filling information of the project to be managed in real time; determine whether the project to be managed meets the preset execution plan based on the form filling information and the project management plan; if the project to be managed meets the preset execution plan, repeat the step of obtaining the project performance form filling information of the project to be managed in real time; if the project to be managed does not meet the preset execution plan, determine the project exception information based on the project performance form filling information and the project management plan; generate a supervision responsibility letter based on the project exception information and the on-site supervision leader information.

[0131] In one example, the modules in any of the above devices may be one or more integrated circuits configured to implement the above methods. For example: one or more application specific integrated circuits (ASICs), or, one or more digital signal processors (DSPs), or, one or more field programmable gate arrays (FPGAs), or a combination of at least two of these integrated circuit forms.

[0132] For another example, when the modules in the device can be implemented in the form of a processing element scheduler, the processing element can be a general-purpose processor, such as a central processing unit (CPU) or other processors that can call programs.

[0133] For another example, these modules can be integrated together and implemented in the form of a system-on-a-chip (SOC).

[0134] Those skilled in the art can clearly understand that for the convenience and conciseness of description, the specific working processes of the above-described device and modules can refer to the corresponding processes in the foregoing method embodiments, and will not be elaborated herein.

[0135] Figure 3 It is a structural block diagram of the electronic device 300 provided by the embodiment of the present application.

[0136] As Figure 3 shown, the electronic device 300 includes a processor 301 and a memory 302, and may further include one or more of an information input / output (I / O) interface 303, a communication component 304, and a communication bus 305.

[0137] Among them, the processor 301 is used to control the overall operation of the electronic device 300 to complete all or part of the steps of the above-mentioned method for applying the duty form based on supervision on-site project management; the memory 302 is used to store various types of data to support the operation of the electronic device 300, and these data may include, for example, instructions for any application program or method operating on the electronic device 300, and data related to the application program.

[0138] The memory 302 can be implemented by any type of volatile or non-volatile storage device or a combination thereof, such as static random access memory (SRAM), electrically erasable programmable read-only memory (EEPROM), erasable programmable read-only memory (EPROM), programmable read-only memory (PROM), read-only memory (ROM), magnetic memory, flash memory, a magnetic disk, or an optical disc.

[0139] The I / O interface 303 provides an interface between the processor 301 and other interface modules, and the other interface modules may be a keyboard, a mouse, buttons, etc. These buttons can be virtual buttons or physical buttons.

[0140] The communication component 304 is used for the electronic device 300 to communicate with other devices in a wired or wireless manner.

[0141] Wireless communication, such as Wi-Fi, Bluetooth, Near Field Communication (NFC), 2G, 3G or 4G, or a combination of one or more of them. Accordingly, the communication component 304 may include: a Wi-Fi component, a Bluetooth component, an NFC component.

[0142] The electronic device 300 can be implemented by one or more Application Specific Integrated Circuits (ASICs), Digital Signal Processors (DSPs), Digital Signal Processing Devices (DSPDs), Programmable Logic Devices (PLDs), Field Programmable Gate Arrays (FPGAs), controllers, microcontrollers, microprocessors or other electronic components, and is used to execute the method for applying a duty form based on supervision on-site project management given in the above embodiments.

[0143] The communication bus 305 may include a path for transmitting information between the above components.

[0144] The communication bus 305 may be a PCI (Peripheral Component Interconnect) bus or an EISA (Extended Industry Standard Architecture) bus, etc.

[0145] The communication bus 305 can be divided into an address bus, a data bus, a control bus, etc.

[0146] The electronic device 300 may include, but is not limited to, mobile terminals such as mobile phones, laptop computers, digital broadcast receivers, PDAs (Personal Digital Assistants), PADs (Tablet PCs), PMPs (Portable Multimedia Players), in-vehicle terminals (such as in-vehicle navigation terminals), etc., and fixed terminals such as digital TVs, desktop computers, etc., and may also be a server, etc.

[0147] The present application also provides a computer-readable storage medium, on which a computer program is stored. When the computer program is executed by a processor, the steps of the above-mentioned method for applying a performance form based on supervision on-site project management are implemented.

[0148] The computer-readable storage medium may include: various media that can store program codes, such as a USB flash drive, a mobile hard disk, a read-only memory (ROM), a random access memory (RAM), a magnetic disk, or an optical disc.

[0149] The term "comprising", "including" or any other variant thereof is intended to cover non-exclusive inclusion, such that a process, method, article or device comprising a series of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such process, method, article or device.

[0150] The above description is only a preferred embodiment of the present application and an explanation of the applied technical principle.

[0151] Those skilled in the art should understand that the scope of the application involved in the present application is not limited to the technical solution formed by the specific combination of the above technical features, and should also cover other technical solutions formed by any combination of the above technical features or their equivalent features without departing from the aforementioned application concept.

[0152] For example, a technical solution formed by mutually replacing the above features with (but not limited to) technical features having similar functions applied in the present application.

Claims

1. A method for applying a performance form based on on-site project management by supervision, characterized in that, Including: Obtain the project information of the target engineering project, where the target engineering project includes multiple completed standard engineering projects; Construct a project performance form based on the project information; Obtain the on-site supervision information and the on-site supervision responsible person information of the project to be managed; Generate a supervision evaluation result of the target supervision project based on the project performance form and the on-site supervision information; Generate a project management plan based on the supervision evaluation result and the on-site supervision responsible person information; Supervise the project to be managed based on the project performance form and the project management plan; The constructing a project performance form based on the project information includes: Extract effective information from the project information to obtain project execution content; Extract fixed content from the project execution content to determine project fixed content and project difference content; Extract content keywords and type keywords of the project difference content; Calculate the application correlation degree between the project difference contents based on the content keywords and the type keywords; Divide the application scope of the project difference content based on the application correlation degree to generate an application content division result; Generate a project operation process based on the project fixed content and the application content division result; Obtain project supervision requirements, and generate a project performance form based on the project supervision requirements and the project operation process.

2. The method according to claim 1, wherein The calculating the application correlation degree between the project difference contents based on the content keywords and the type keywords includes: Obtain the keyword attributes of the content keywords and the type division rules of the type keywords; Determine the content similarity between the content keywords based on the keyword attributes; Determine the type similarity between the type keywords based on the type division rules; Obtain a correlation degree calculation rule; Determine the application correlation degree between each project difference content based on the correlation degree calculation rule, the content similarity, and the type similarity.

3. The method according to claim 1, characterized in that The generating a project operation process based on the project fixed content and the application content division result includes: Obtain the project standard execution procedure; Determine fixed operation steps based on the project standard execution procedure and the project fixed content; Perform step subdivision and arrangement on the project difference content based on the application content division result to generate a content processing result; Perform adjustment processing on the content processing result based on the project standard execution procedure to generate difference operation steps; Arrange the fixed operation steps and the difference operation steps according to the project standard execution procedure to generate a project operation process.

4. The method according to claim 1, wherein The generating a supervision evaluation result of the project to be managed based on the project performance form and the on-site supervision information includes: Obtain the project planning information of the project to be managed; Select the project performance form based on the project planning information to obtain a target performance form; Generate a project execution plan based on the target performance form and the project planning information; Generate a supervision performance record based on the on-site supervision information and the target performance form; Obtain a supervision evaluation rule; Judge the project to be managed based on the supervision judgment rules, the project implementation plan, and the supervision performance records to generate a supervision judgment result.

5. The method according to claim 4, wherein The generation of the project management plan based on the supervision judgment result and the on-site supervision person in charge information includes: Obtain the judgment level of the supervision judgment result; Determine the supervision level of the project to be managed based on the judgment level and the supervision judgment rules; Judge whether the project implementation plan needs to be adjusted based on the supervision level; If the project implementation plan needs to be adjusted, adjust the project implementation plan based on the target performance form and the supervision level to generate an adjusted implementation plan; Generate a project management plan based on the adjusted implementation plan, the target performance form, the supervision level, and the on-site supervision person in charge information; If the project implementation plan does not need to be adjusted, generate a project management plan based on the project implementation plan, the target performance form, the supervision level, and the on-site supervision person in charge information.

6. The method according to claim 1, wherein The supervision of the project to be managed based on the project performance form and the project management plan includes: Obtain the project performance form filling information of the project to be managed in real time; Judge whether the project to be managed meets the preset implementation plan based on the form filling information and the project management plan; If the project to be managed meets the preset implementation plan, repeat the step of obtaining the project performance form filling information of the project to be managed in real time; If the project to be managed does not meet the preset implementation plan, determine project exception information based on the project performance form filling information and the project management plan; Generate a supervision responsibility letter based on the project exception information and the on-site supervision person in charge information.

7. An application device for performance forms based on on-site project management by supervisors, characterized in that, Includes: A project information acquisition module for acquiring the project information of the target engineering project, where the target engineering project includes multiple completed standard engineering projects; A performance form construction module for constructing a project performance form based on the project information; A supervision information acquisition module for acquiring the on-site supervision information and the on-site supervision person in charge information of the project to be managed; A supervision result generation module for generating a supervision judgment result of the project to be managed based on the project performance form and the on-site supervision information; A management plan generation module for generating a project management plan based on the supervision judgment result and the on-site supervision person in charge information; An engineering project supervision module for supervising the project to be managed based on the project performance form and the project management plan; The performance form construction module includes: An execution content extraction module for extracting effective information from the project information to obtain the project execution content; A project content determination module for extracting fixed content from the project execution content to determine the project fixed content and the project difference content; A keyword extraction module for extracting content keywords and type keywords of the project difference content; An application correlation degree calculation module for calculating the application correlation degree between the project difference contents based on the content keywords and the type keywords; A division result generation module, configured to perform an application scope division on project difference content based on application relevance, and generate an application content division result; An operation process generation module, configured to generate a project operation process based on project fixed content and the application content division result; A performance form generation module, configured to obtain project supervision requirements, and generate a project performance form based on the project supervision requirements and the project operation process.

8. An electronic device, characterized in that, It includes a processor, and the processor is coupled to a memory; The processor is configured to execute a computer program stored in the memory, so that the electronic device executes the method according to any one of claims 1 to 6.

9. A computer-readable storage medium, characterized in that, It includes a computer program or instruction, and when the computer program or instruction runs on a computer, the computer is caused to execute the method according to any one of claims 1 to 6.

Citation Information

Patent Citations

  • Engineering construction whole process digital management method, device, equipment and medium

    CN117575518A

  • Multi-source data check-based supervision service digital management and control method and system

    CN117611079A