Recyclable monitoring integrated slope supporting system

By designing an integrated slope support system for recyclable monitoring, the combination of anchor rods, strain gauge, steel strands, connecting nodes and surface layers is used to solve the problem that slope support systems cannot be recycled and cannot be monitored in real time in the existing technology, and green construction and safety monitoring are achieved, reducing costs and significantly improving environmental protection effects.

CN119900303APending Publication Date: 2025-04-29CHINA CONSTR EIGHTH ENG BUREAU (GANSU) CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411847953.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-16
Publication Date
2025-04-29

AI Technical Summary

Technical Problem

The existing slope support system cannot be recycled after construction is completed, resulting in environmental pollution and the inability to monitor slope deformation and bearing capacity changes in real time, resulting in high usage costs.

Method used

An integrated slope support system for recycling monitoring is designed, including anchor rods, strain gauge, steel strands, connecting nodes and surface layers. Through these components, the effective combination of anchor rods and soil and real-time monitoring of slopes can be achieved, and recycling can be carried out after construction is completed.

Benefits of technology

The green construction of the slope support system is realized, ensuring safety monitoring of foundation pits, and the construction cycle is accelerated, costs are reduced, and the system can be recycled, turnover and utilized, with significant environmental protection effect.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119900303A_ABST
    Figure CN119900303A_ABST
Patent Text Reader

Abstract

The invention relates to a recoverable monitoring integrated slope supporting system, which relates to the technical field of engineering construction, is arranged on a foundation pit slope, and comprises a plurality of anchor rods embedded on the foundation pit slope at intervals, strain gauges connected to the anchor rods and embedded in the foundation pit slope, and a monitoring device connected to the strain gauges and used for monitoring the foundation pit slope. The bearing stress change of the anchor rods can be monitored through the strain gauges, the steel strands are tied to the anchor rods in the same row, the anchor rods and a soil body are effectively combined after the anchor rods are placed on a side slope, the steel strands and the anchor rods are tied together, then the steel strands are fixed through the connecting nodes, and a surface layer is laid. The steel strands, the surface layer and the anchor rods are integrated, the anchor rods and the surface layer are connected and fixed through the connecting nodes to form a supporting structure, the slope protection surface layer is firmly fixed to the side slope through the anchor rods through the steel strands penetrating through the anchor rods in a crossed mode, and therefore the waterproof and supporting effects on the side slope soil body sliding face and the side slope are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of engineering construction, and in particular to a recoverable monitoring integrated slope support system. Background Art

[0002] With the gradual improvement of public environmental awareness, the environmental protection requirements during the construction process of construction projects are also getting higher and higher. The slope support system of the foundation pit is an important safety measure in the project. During the excavation and construction process, temporary support measures such as soil nails and concrete spraying surface layer should be adopted to ensure safety. However, the existing equipment will remain in the foundation after the construction is completed, causing pollution to the soil environment. The support system cannot be recycled, and the slope deformation and bearing capacity changes cannot be monitored during the construction process, resulting in high overall use costs of the support system. Summary of the invention

[0003] The purpose of the present invention is to overcome the defects of the prior art and provide a recyclable monitoring integrated slope support system to solve the problems that the existing equipment is buried in the soil and cannot be recovered, which easily causes environmental pollution and cannot monitor slope changes during construction.

[0004] The technical solution to achieve the above purpose is: a recyclable monitoring integrated slope support system, which is arranged on the foundation pit slope, and the support system includes:

[0005] A plurality of anchor rods, wherein the anchor rods are buried at intervals on the slope of the foundation pit;

[0006] A strain gauge connected to the anchor rod and buried in the foundation pit slope, through which the bearing force change of the anchor rod can be monitored;

[0007] The steel strands tied to the same row of anchor rods;

[0008] A connection node connected to one end of the anchor rod extending out of the foundation pit slope, the connection node being connected to the corresponding steel strand;

[0009] A surface layer laid on the foundation pit slope, the surface layer being connected to corresponding connection nodes;

[0010] A displacement meter connected to the connection node can measure the change of the soil surface between the connection node and the foundation pit slope.

[0011] The technical solution of the present invention is further improved in that: the connection node includes a base plate mounted on the anchor rod, a cover plate connected to the base plate, a buckle plate mounted on the anchor rod and arranged above the cover plate, and a buckle detachably mounted on the anchor rod.

[0012] A further improvement of the technical solution of the present invention is that the buckle is U-shaped.

[0013] The technical solution of the present invention is further improved in that: a groove is provided at the bottom of the gusset plate, and the groove can allow the steel strand to pass through.

[0014] A further improvement of the technical solution of the present invention is that the groove is arranged in a cross shape.

[0015] The technical solution of the present invention is further improved in that: the cover plate is in contact with the surface layer, and the side of the bottom plate away from the cover plate is connected to the displacement meter.

[0016] A further improvement of the technical solution of the present invention is that the bottom film is in a cross shape.

[0017] The technical solution of the present invention is further improved in that: the anchor rod and the steel strand are perpendicular to each other.

[0018] The technical solution of the present invention is further improved in that: a plurality of embedding grooves are provided on the surface layer, and the embedding grooves can be used for installing photovoltaic panels, and the photovoltaic panels are electrically connected to batteries;

[0019] The storage battery is electrically connected to the strain gauge and the displacement gauge.

[0020] A construction method of a recyclable monitoring integrated slope support system comprises the following steps:

[0021] Step 1: Provide multiple anchor rods and bury them at intervals on the slope of the foundation pit;

[0022] Provide connection nodes and surface layers, install the connection nodes on the end of the anchor rod exposed outside the foundation pit slope, lay the surface layer on the foundation pit slope, and fix the surface layer on the foundation pit slope through the corresponding connection nodes;

[0023] A steel strand is provided, and the anchor rods in the same row are connected by the steel strand, and the ends of the steel strand are fixed to the structure near the slope of the foundation pit.

[0024] By using the above technical solution, the present invention has the following technical effects compared with the prior art:

[0025] The present invention provides a recoverable monitoring integrated slope support system, which realizes effective combination of the anchor rod and the soil after placing the anchor rod on the slope, and uses steel strands to pull the anchor rod together, and then uses connecting nodes to fix the steel strands and lay the surface layer, so that the steel strands, the surface layer and the anchor rod are integrated, the anchor rod and the surface layer are connected and fixed by connecting nodes to form a support structure, and the slope protection surface layer is firmly fixed to the slope by the anchor rod through the steel strands that cross the anchor rod, thereby playing a role in waterproofing and supporting the sliding surface of the slope soil and the slope.

[0026] The present invention detects the change of the bearing force of the anchor rod by means of the strain gauge arranged on the anchor rod, and detects the surface deformation of the soil on the foundation pit slope by means of the displacement gauge arranged on the negative plate. By placing monitoring components such as the strain gauge and the displacement gauge in the anchor rod and the negative plate, the synchronous monitoring of the deformation of the foundation pit slope is truly realized, and the monitoring device can be synchronously recovered with the supporting structure, thereby realizing the green construction of the foundation pit slope support, ensuring the safety monitoring of the foundation pit, speeding up the construction period, and being recyclable and circulated, saving costs and being green and environmentally friendly.

[0027] By setting up a photovoltaic power supply system on the surface to provide unit power supply for the monitoring equipment, the complex interweaving of the power supply network is avoided and a stable and reliable power supply is achieved. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 The present invention is a plan view of a recoverable monitoring integrated slope support system.

[0029] Figure 2 This is a connection diagram of anchor rods and steel strands in a recoverable monitoring integrated slope support system of the present invention.

[0030] Figure 3 This is a connection diagram of a bottom plate and a cover plate of a recoverable monitoring integrated slope support system of the present invention.

[0031] Figure 4 This is a plan view of a cover plate of a recoverable and monitoring integrated slope support system of the present invention.

[0032] Figure 5 This is a plan view of a gusset plate of a recoverable monitoring integrated slope support system of the present invention.

[0033] Figure 6 It is a buckle plan view of a recoverable monitoring integrated slope support system of the present invention.

[0034] Figure 7 This is an anchor distribution diagram of a recoverable and monitoring integrated slope support system of the present invention.

[0035] Figure 8 This is a distribution diagram of the bottom plate and cover plate of a recoverable monitoring integrated slope support system of the present invention.

[0036] Fig. 9 This is a surface plan view of a recoverable monitoring integrated slope support system of the present invention.

[0037] Fig.10 This is a plan view of the cover plate and surface layer of a recoverable monitoring integrated slope support system of the present invention.

[0038] Fig.11The figure is a top view of a recoverable and monitoring integrated slope support system according to the present invention.

[0039] Fig.12 This is a connection diagram of the photovoltaic panels and batteries of a recoverable monitoring integrated slope support system of the present invention.

[0040] Fig.13 The present invention is a schematic diagram of a recoverable monitoring integrated slope support system.

[0041] Fig.14 The present invention is a flowchart for installing a recoverable monitoring integrated slope support system.

[0042] In the figure: 1. Anchor rod; 2. Strain gauge; 3. Bottom film; 4. Cover plate; 5. Surface layer; 6. Buckle plate; 7. Steel strand; 8. Buckle; 9. Displacement gauge; 10. Photovoltaic panel; 11. Battery. DETAILED DESCRIPTION

[0043] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.

[0044] The present invention provides a recyclable monitoring integrated slope support system, which is composed of a recyclable support structure (including anchor rods, surface layers, steel strands and connection nodes) and built-in monitoring equipment (including strain gauges and displacement gauges, etc.). By integrating the monitoring components into the key components and nodes of the recyclable support structure, the synchronous monitoring of the deformation of the foundation pit slope is truly realized, and the monitoring device can be synchronously recovered with the support structure, thereby realizing the green construction of the foundation pit slope support, ensuring the safety monitoring of the foundation pit, speeding up the construction cycle, and being recyclable and recyclable, saving costs and being green and environmentally friendly. The recyclable monitoring integrated slope support system is described below.

[0045] See also Figure 1 , showing a plan view of a recyclable monitoring integrated slope support system of the present invention. Fig.11 , showing a top view of a recyclable monitoring integrated slope support system of the present invention. Figures 1 to 11 , the structure of the recoverable monitoring integrated slope support system of the present invention is described.

[0046] like Figure 1 and Fig.11As shown, the present invention provides a recyclable monitoring integrated slope support system, which is arranged on the foundation pit slope, and the slope support system includes multiple anchor rods 1, strain gauges 2, displacement gauges 9, surface layers 5, steel strands 7 and connection nodes, wherein multiple anchor rods 1 are buried on the foundation pit slope at intervals; the strain gauges 2 are connected to the anchor rods 1 and buried in the foundation pit slope, and the bearing force changes of the anchor rods 1 can be monitored by the strain gauges 2; the steel strands 7 are tied to connect the same row of anchor rods 1, and the steel strands 7 are arranged in the transverse and longitudinal directions, and the transversely arranged steel strands 7 are used to tie the transverse direction The same row of anchor rods 1, the steel strand 7 passes through each anchor rod 1 on the same row, and then the two ends of the steel strand 7 are tensioned and fixed to the structure near the foundation pit slope. Similarly, the longitudinally arranged steel strand 7 pulls the same row of anchor rods 1 in the longitudinal direction; the connecting node is connected to the end of the anchor rod 1 extending out of the foundation pit slope, and the connecting node is connected to the corresponding steel strand 7; the surface layer 5 is laid on the foundation pit slope, and the surface layer 5 is connected to the corresponding connecting node; the displacement meter 9 is connected to the connecting node, and the displacement meter 9 can be used to measure the changes in the soil surface between the connecting node and the foundation pit slope.

[0047] The anchor rod 1, surface layer 9, steel strand 7 and connection nodes in the slope support system of the present invention form a recyclable slope support structure, which can be recycled and used after the structural construction in the foundation pit is completed, saving costs and being green and environmentally friendly. The strain gauge 2 and displacement gauge 9 in the slope support system of the present invention form a monitoring device, which is built into the anchor rod 1 and the connection node, realizing the synchronous construction of the support structure and the monitoring device. After the construction is completed, the stability and deformation of the slope can be synchronously monitored, thereby improving the safety of the slope support system.

[0048] Preferably, the surface layer 5 is fixed to the foundation pit slope by cooperating with the anchor rod 1 and the connection node, and then the anchor rod 1 is fixed to the structure near the foundation pit slope by the steel strand 7 tied to the anchor rod 1, thereby supporting the slope soil.

[0049] Furthermore, if Fig.13 As shown, the slope support system of the present invention also includes a wireless signal system, which includes a wireless network transmitting device and a monitoring data receiving device. The wireless network transmitting device provides a wireless network for the monitoring equipment (strain gauge 2 and displacement gauge 9), and receives data collected by the monitoring equipment through the monitoring data receiving device. The monitoring data receiving device is connected to the strain gauge 2 and the displacement gauge 9 for communication, and can receive the monitoring data collected by the strain gauge 2 and the displacement gauge 9. The present invention realizes the wireless collection of discrete monitoring data in the support area through the wireless signal system, avoiding the interference of a large number of data collection lines with the construction of the support structure and the influence of line damage during construction on data collection.

[0050] The strain gauge 2 of the present invention is built into the middle section of the anchor rod 1 and is arranged close to the inner side of the anchor rod 1 along the length direction. The strain gauge 2 and the displacement gauge 9 are arranged on the anchor rod 1 and the connection node, so that the strain gauge 2 and the displacement gauge 9 can be installed synchronously with the anchor rod 1 and the connection node, and the strain gauge 2 and the displacement gauge 9 can be wirelessly connected to the external terminal through communication, so that the external terminal can receive the monitoring data information collected by the monitoring equipment.

[0051] Furthermore, the anchor rods 1 passing through the same row are connected by steel strands 7, so that the anchor rods 1 are pressed on the surface of the foundation pit slope. The steel strands 7 can pass through the holes on the corresponding anchor rods 1, and two steel strands 7 are passed through the upper end of the same anchor rod 1, one of which is arranged horizontally and the other is arranged longitudinally.

[0052] Furthermore, the surface layer 5 is a flexible felt-like material, generally in strip shape, and adhesive strips are provided on both sides of the surface layer 5, which can be connected as a whole through the adhesive strips to achieve a repairable effect. A waterproof adhesive strip is provided on the inside of the adhesive strip to ensure that the surface layer 5 does not leak after being bonded as a whole.

[0053] See also Figure 1 In a specific embodiment of the present invention, the connection node includes a bottom film 3 mounted on the anchor rod, a cover plate 4 connected to the bottom film 3, a buckle plate 6 mounted on the anchor rod 1 and arranged above the cover plate 4, and a buckle 8 detachably mounted on the anchor rod 1. The surface layer 5 is sandwiched between the bottom film 3 and the buckle plate 6, wherein the cover plate 4 is embedded in the surface layer 5, and the surface layer 5 is provided with a through hole corresponding to the anchor rod 1. The surface layer 5 is mounted on the anchor rod 1 through the through hole, and the cover plate 4 is embedded in the through hole. During installation, the through hole of the surface layer 5 can be mounted on the corresponding anchor rod 1 first, and then the cover plate 4 can be mounted on the anchor rod 1, and then the cover plate 4 can be moved downward to embed the cover plate 4 into the corresponding through hole on the surface layer 5, and ensure that the cover plate 4 is buckled with the bottom film 3. Fig.10 As shown, four through holes are drilled on the surface layer 5 , and the surface layer 5 can be sleeved on four anchor rods 1 .

[0054] Preferably, if Figure 1 As shown, the bottom sheet 3, the cover plate 4, the gusset plate 6 and the buckle 8 are movable so that they can be installed and disassembled on the anchor rod 1. When recycling, the buckle 8, the gusset plate 6 and the steel strand 7 are removed from the anchor rod 1, and then the surface layer 5 is rolled up for recovery, and the bottom sheet 3 and the cover plate 4 are removed from the anchor rod 1, so as to achieve the recycling effect. During installation, the gusset plate 6 is fastened by the buckle 8, so that the gusset plate 6 and the bottom sheet 3 clamp the corresponding part of the surface layer 5 together, and the gusset plate 6 presses the corresponding part of the steel strand 7, thereby forming a reliable support structure system.

[0055] See also Figure 6 In a specific embodiment of the present invention, the buckle 8 is U-shaped.

[0056] Furthermore, if Figure 6 As shown, by setting the buckle 8 into a U shape, when it contacts the anchor rod 1, the rounded inner surface of the buckle 8 contacts the anchor rod better, and the buckle 8 is fastened to the anchor rod 1 by rotation to form a whole, and the connectivity is stronger.

[0057] See also Figure 5 In a specific embodiment of the present invention, a groove is provided at the bottom of the gusset plate 6, and the groove can allow the steel strand 7 to pass through. Preferably, the groove is cross-shaped. By setting the groove in a cross shape, it is possible to fix the steel strand 7 set in different directions.

[0058] See also Figure 3 and Fig.10 In a specific embodiment of the present invention, the cover plate 4 is in contact with the surface layer 5 , and the side of the bottom film 3 away from the cover plate 4 is connected to the displacement meter 9 .

[0059] Furthermore, when the displacement meter 9 on the bottom film 3 is installed, the displacement meter 9 is debugged in advance and replaced in time when an abnormal signal occurs. By setting a perforation on the surface layer 5, it is convenient to put the surface layer 5 on the cover plate 4.

[0060] See also Figure 3 , the bottom sheet 3 is in a cross shape. Further, the cross-shaped arrangement of the bottom sheet 3 can provide a more stable support for the cover plate 4, so that the cover plate 4 is not prone to deviation after installation.

[0061] See also Figure 2 In a specific embodiment of the present invention, the anchor rod 1 and the steel strand 7 are perpendicular to each other.

[0062] Furthermore, if Figure 2 As shown, the anchor rods 1 are vertically arranged with the steel strands 7, and the anchor rods 1 in the same row are tied together by the arranged steel strands 7.

[0063] See also Fig.12 In a specific embodiment of the present invention, a plurality of embedding grooves are provided on the surface layer 5, and the embedding grooves can be used for installing the photovoltaic panel 10. The photovoltaic panel 10 is electrically connected to the battery 11, and the battery 11 is electrically connected to the strain gauge 2 and the displacement gauge 9.

[0064] Furthermore, if Fig.12 As shown, by providing an embedding groove on the surface of the surface layer 5, the photovoltaic panel 10 can be embedded in the groove, and the wires corresponding to the photovoltaic panel 10 can also be fixed on its surface. By setting the photovoltaic panel 10 to convert heat energy into electricity, photovoltaic power generation can provide a stable power supply for the strain gauge 2 and the displacement gauge 9. Fig.13As shown, the photovoltaic panel 10 and the storage battery 11 of the present invention form a photovoltaic power supply system, which provides unit power supply for the monitoring equipment, avoids the complex interweaving of the power supply network, and realizes stable and reliable power supply. The embedded photovoltaic panel 10 can provide power to the monitoring equipment such as the strain gauge 2, displacement meter 9 and the wireless signal system nearby through a simple plug-in line connection.

[0065] like Fig.14 As shown, the construction process of the recyclable monitoring integrated slope support system of the present invention is described below.

[0066] After the foundation pit is excavated in layers, the slope is cleaned and then the slope support system construction begins. The specific steps are as follows:

[0067] Step 1: Determine the monitoring points and layout of the power supply units. Based on the foundation pit slope support and monitoring requirements, equipment power, monitoring cycle and actual on-site conditions, determine the monitoring points and layout of the power supply units through comprehensive analysis.

[0068] Step 2: Install recyclable slope support structure.

[0069] 1. Measure, locate, and lay out to determine the position of anchor 1 on the slope;

[0070] 2. Debug the strain gauge 2 built into the anchor rod 1; (replace the strain gauge 2 with abnormal signal feedback)

[0071] 3. Install anchor rod 1;

[0072] 4. Install the cross-shaped bottom plate 3 with the perforated sleeve ring of the surface layer 5 of the connection node at the end of the anchor rod 1 through the central circular hole, and make it close to the slope (the node bottom plate 3 with the displacement meter 9 should also be debugged in advance, and the abnormal signal should be replaced in time);

[0073] 5. Lay the repairable flexible surface layer 5 from top to bottom along the slope, adjust the side edges of the surface layer 5 to align, and bond them together as a whole with adhesive strips;

[0074] 6. Drill a hole in the repairable flexible surface layer 5 at the anchor rod 1 using a special tool, so that the anchor rod 1 passes through the surface layer 5 from the drilled hole;

[0075] 7. Insert the cover plate 4 of the perforated collar of the surface layer 5 into the end of the anchor rod 1 and buckle it with the bottom plate 3 to ensure that the anchor rod 1 passes through the surface layer 5 smoothly;

[0076] 8. Arrange the steel strands 7 in a cross-shaped manner along the anchor rod 1 (i.e., arrange them in a cross-shaped manner in the horizontal and vertical directions), insert the clamp plate 6 of the anchor rod 1 into the end of the anchor rod 1, and let the steel strands 7 pass through the bottom groove thereof; tighten the horizontal and vertical steel strands from top to bottom and from the middle to both ends respectively;

[0077] 9. Insert the U-shaped buckle 8 of the anchor rod 1 chuck into the end of the anchor rod 1, press it against the anchor rod 1 chuck plate 6, and lock the U-shaped buckle 8, so that the anchor rod 1 and the repairable surface layer 5 form a reliable support structure system through the steel strand 7; the recyclable support structure is installed.

[0078] Step 3: Install the photovoltaic power supply system.

[0079] 1. According to the layout diagram of the power supply unit, embed the photovoltaic panel 10 and the connecting wires on the corresponding repairable surface layer 5;

[0080] 2. Configure the battery 11;

[0081] 3. Connect the photovoltaic panel 10, the battery 11 and the monitoring equipment through wires, and debug and monitor whether the power supply is normal. The photovoltaic power supply system is installed

[0082] Step 4: Install the data receiving device and debug the wireless signal acquisition system.

[0083] 1. Install the data receiving device;

[0084] 2. Debug the received data to ensure that all data are normal. Installation is complete.

[0085] After the excavation of the foundation pit is completed and the construction of the structure in the pit is completed, the power supply network lines of the power supply system and the wireless network transmitters and other equipment and lines of the signal system can be dismantled first, and then the steel strands 7 fixing the slope protection surface layer can be loosened, and then the easily repaired surface layer 5 can be gradually dismantled, and the anchor rod 1 can be retracted, so as to realize the effective recovery of the entire system of photovoltaic power supply system, wireless signal system, monitoring equipment and support structure.

[0086] Specifically, the recovery method of the recoverable monitoring integrated slope support system includes the following steps:

[0087] Step 1: Dismantle and recycle the power supply system:

[0088] 1. Stop the operation of the data receiving device;

[0089] 2. Disconnect the wire connection point;

[0090] 3. Remove and recycle the photovoltaic panels 10 and wires embedded in the surface layer 5;

[0091] 4. Dismantle and recycle the battery.

[0092] Step 2: Dismantle and recycle the wireless signal system;

[0093] Step 3: Dismantle and recycle the support structure:

[0094] 1. Loosen the vertical and horizontal steel strands layer by layer from both sides to the middle and from bottom to top;

[0095] 2. Loosen the U-shaped buckle 8, uncover the anchor rod 1 clamping plate 6, and collect and pack;

[0096] 3. Take out the steel strands 7 in sequence, coil them and tie them neatly;

[0097] 4. Loosen the cover plate 4 of the surface perforated ring and collect and pack them by categories;

[0098] 5. From both sides to the middle, from bottom to top, roll up each slope protection surface layer 5 and take it back;

[0099] 6. The cross-shaped bottom sheet 3 of the perforated collar of the surface layer 5 connecting the nodes is taken out from the end of the anchor rod 1 and collected and packaged;

[0100] 7. Recover anchor rod 1;

[0101] 8. Clean up the site and complete the dismantling and recycling.

[0102] The present invention also provides a construction method of a recoverable monitoring integrated slope support system, which is described below.

[0103] The construction method of the present invention comprises the following steps:

[0104] Step 1: provide a plurality of anchor rods 1, measure and locate the intervals of the buried anchor rods 1 on the foundation pit slope, and debug the strain gauges 2 on the anchor rods 1;

[0105] Provide a connection node and a surface layer 5, install the connection node on the end of the anchor rod 1 exposed outside the foundation pit slope, lay the surface layer 5 on the foundation pit slope, and fix the surface layer 5 on the foundation pit slope through the corresponding connection node;

[0106] Provide a steel strand 7, use the telescopic steel strand 7 to connect the anchor rods 1 in the same row, and fix the end of the steel strand 7 to the structure adjacent to the foundation pit slope.

[0107] The beneficial effects of the recyclable monitoring integrated slope support system of the present invention are:

[0108] 1. By placing anchor rods on the slope, the anchor rods are effectively combined with the soil, and the steel strands are used to tie the anchor rods together. The steel strands are then fixed using the connection nodes and the surface layer is laid, so that the steel strands, surface layer and anchor rods are integrated. The anchor rods and surface layer are connected and fixed through the connection nodes to form a support structure. The steel strands that cross the anchor rods make the slope protection surface layer firmly fixed to the slope by the anchor rods, thereby playing a role in waterproofing and supporting the sliding surface of the slope soil and the slope.

[0109] 2. The strain gauge installed on the anchor rod is used to detect the change of the bearing force on the anchor rod, and the displacement meter installed on the negative film is used to detect the deformation of the soil surface on the foundation pit slope. By placing monitoring components such as strain gauges and displacement meters in the anchor rod and the negative film, the synchronous monitoring of the deformation of the foundation pit slope is truly realized, and the monitoring device can be recovered synchronously with the supporting structure, thereby realizing the green construction of the foundation pit slope support, ensuring the safety monitoring of the foundation pit, speeding up the construction period, and being recyclable and circulated, saving costs and being green and environmentally friendly.

[0110] 3. By setting up a photovoltaic power supply system on the surface layer to provide unit power supply for the monitoring equipment, the complex interweaving of the power supply network is avoided and a stable and reliable power supply is achieved.

[0111] The present invention is described in detail above in conjunction with the embodiments of the drawings, and those skilled in the art can make various variations of the present invention according to the above description. Therefore, certain details in the embodiments should not constitute limitations of the present invention, and the scope of protection of the present invention shall be defined by the scope of the attached claims.

Claims

1. A recyclable monitoring integrated slope support system, arranged on the slope of a foundation pit, characterized in that: The support system comprises: A plurality of anchor rods, wherein the anchor rods are buried at intervals on the slope of the foundation pit; A strain gauge connected to the anchor rod and buried in the foundation pit slope, through which the bearing force change of the anchor rod can be monitored; The steel strands tied to the same row of anchor rods; A connection node connected to one end of the anchor rod extending out of the foundation pit slope, the connection node being connected to the corresponding steel strand; A surface layer laid on the foundation pit slope, the surface layer being connected to corresponding connection nodes; A displacement meter connected to the connection node can measure the change of the soil surface between the connection node and the foundation pit slope.

2. The recoverable monitoring integrated slope support system according to claim 1 is characterized by: The connection node comprises a bottom plate sleeved on the anchor rod, a cover plate connected to the bottom plate, a buckle plate sleeved on the anchor rod and arranged above the cover plate, and a buckle detachably mounted on the anchor rod.

3. The recoverable monitoring integrated slope support system according to claim 2 is characterized by: The buckle is U-shaped.

4. The recoverable monitoring integrated slope support system according to claim 2 is characterized in that: A groove is provided at the bottom of the gusset plate, and the steel strand can pass through the groove.

5. The recoverable monitoring integrated slope support system according to claim 2 is characterized by: The groove is arranged in a cross shape.

6. The recoverable monitoring integrated slope support system according to claim 2 is characterized by: The cover plate is in contact with the surface layer, and a side of the bottom plate away from the cover plate is connected to the displacement meter.

7. The recoverable monitoring integrated slope support system according to claim 2 is characterized by: The bottom film is in a cross shape.

8. The recoverable monitoring integrated slope support system according to claim 1 is characterized by: The anchor rod and the steel strand are perpendicular to each other.

9. The recoverable monitoring integrated slope support system according to claim 1, characterized in that: The surface layer is provided with a plurality of embedding grooves, wherein the embedding grooves can be used for installing photovoltaic panels, and the photovoltaic panels are electrically connected to batteries; The storage battery is electrically connected to the strain gauge and the displacement gauge.

10. The construction method of the recoverable monitoring integrated slope support system according to claim 1, characterized in that: The following steps are involved: Step 1: Provide multiple anchor rods and bury them at intervals on the slope of the foundation pit; Provide connection nodes and surface layers, install the connection nodes on the end of the anchor rod exposed outside the foundation pit slope, lay the surface layer on the foundation pit slope, and fix the surface layer on the foundation pit slope through the corresponding connection nodes; Provide steel strands, use telescopic steel strands to tie and connect the anchor rods in the same row, and fix the ends of the steel strands to the structure adjacent to the foundation pit slope.