Method and system for generating tunnel section grouting model
By generating a tunnel section grouting model, the problem of difficulty in accurately analyzing the grouting effect in the prior art is solved, and efficient and safe grouting analysis is achieved.
Patent Information
- Application Number
- CN202510178858.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-02-18
- Publication Date
- 2025-06-06
- Estimated Expiration
- 2045-02-18
AI Technical Summary
The prior art is difficult to accurately analyze the mountain situation after grouting on the tunnel rupture surface, and there are safety hazards.
By obtaining the three-dimensional coordinates of multiple grouting holes in the tunnel section, multiple cylindrical models are generated, and by boolean collection of these cylindrical models, a grouting model of the tunnel section is generated, thereby improving the accuracy and efficiency of analyzing grouting effects.
The grouting effect of tunnel rupture surface is visualized, the analysis accuracy and work efficiency are improved, and the safety of staff is enhanced.
Smart Images

Figure CN120105546A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of construction engineering, and in particular to a method and system for generating a tunnel section grouting model. Background Art
[0002] In the current tunnel excavation process, it is often encountered that due to the breakage or cracks in the mountain inside the tunnel, water or stones suddenly gush out of the tunnel, which creates great resistance to the construction of the tunnel and poses a great threat to the safety of the construction workers.
[0003] In the prior art, grouting is usually used to reinforce the fractured surface of the tunnel and after the grouting is completed, the prior art often uses advanced geological reports, seismographs and the characteristics of electromagnetic waves to analyze the condition of the mountain after grouting. However, the above methods cannot accurately analyze the condition of the mountain after grouting, and when applying the prior art, workers need to go to the construction site for measurement and analysis, and there are certain safety issues.
[0004] Therefore, how to improve the accuracy of analyzing the grouting effect of mountain fracture surfaces has become a problem that needs to be solved. Summary of the invention
[0005] The present application provides a method and system for generating a tunnel cross-section grouting model. By establishing a tunnel cross-section grouting model, the accuracy of analyzing the grouting effect of a mountain fracture surface can be improved.
[0006] In a first aspect, the present application provides a method for generating a grouting model of a tunnel section, comprising: obtaining three-dimensional coordinates of multiple grouting holes in a tunnel section, wherein the three-dimensional coordinates of each of the multiple grouting holes include the three-dimensional coordinates of the grouting hole mouth and the three-dimensional coordinates of the grouting hole bottom, wherein the three-dimensional coordinates of the hole mouth of each grouting hole corresponds to a three-dimensional coordinate of the hole bottom; generating multiple cylindrical models based on the hole mouth coordinates and hole bottom coordinates of the multiple grouting holes; and generating a grouting model of the tunnel section based on the multiple cylindrical models.
[0007] The method for generating a tunnel section grouting model provided in the embodiment of the present application generates multiple cylindrical models using the three-dimensional coordinates of the grouting holes of the tunnel section, and generates a grouting model of the tunnel section based on the multiple cylindrical models. The grouting effect on the tunnel rupture surface can be intuitively seen through the grouting model. Compared with the prior art, there is no need to manually monitor the grouting mountain on site using a seismograph or an electromagnetic instrument, thereby improving the accuracy and efficiency of analyzing the grouting effect and being able to improve the safety of workers.
[0008] In one possible implementation, a cross-sectional contour model of the tunnel is established based on the two-dimensional coordinates of the tunnel section, and the cross-sectional contour model is a two-dimensional model; the relative position of the cross-sectional contour model and the grouting model is determined based on the grouting model; an excavation body model is generated based on the preset excavation length of the tunnel section and the cross-sectional contour model, and the excavation body model is a three-dimensional model; a grouting blind area model is generated based on the grouting model and the excavation body model.
[0009] By adopting the above technical scheme, a three-dimensional excavation model is generated through the tunnel section contour model and the preset excavation length of the tunnel section, so that the tunnel excavation work can be visualized. The grouting blind area model is generated by combining the excavation body model and the grouting model. According to the grouting blind area model, the grouting area can be intuitively seen during the grouting process. According to the range of the area that has not been grouted, it can be determined whether to grout again or expand the grouting range, which can improve the work efficiency of grouting on the tunnel fracture surface.
[0010] In a possible implementation, multiple cylindrical models are generated based on the hole mouth coordinates and hole bottom coordinates of multiple grouting holes, including: taking the hole mouths of the multiple grouting holes as the first circle center and based on a preset hole mouth radius, multiple first circles are generated; taking the hole bottoms of the multiple grouting holes as the second circle center and based on a preset hole bottom radius, multiple second circles are generated; each of the multiple first circles corresponds to a second circle; and multiple cylindrical models are generated based on the multiple first circles, the multiple second circles, the three-dimensional coordinates of the hole mouth and the three-dimensional coordinates of the hole bottom.
[0011] By adopting the above technical solution, multiple cylindrical models are generated through the grouting hole mouth coordinates and the grouting hole bottom coordinates, which can improve the accuracy of the generated model.
[0012] In a possible implementation, a grouting model of a tunnel section is generated based on a plurality of cylindrical models, including: performing Boolean union of the plurality of cylindrical models to generate the grouting model of the tunnel section.
[0013] By adopting the above technical solution and performing Boolean union on multiple cylinder models, the overlapping parts between the multiple cylinders can be reduced, thereby improving the accuracy of the generated grouting model.
[0014] In a possible implementation, the volumes of multiple cylindrical models are obtained based on the three-dimensional coordinates of the bottom of multiple grouting holes, the three-dimensional coordinates of the hole mouths, the preset hole mouth radius and the preset hole bottom radius; the volumes of the multiple cylindrical models are Boolean unioned to obtain the volume of the tunnel section grouting model.
[0015] By adopting the above technical solution, the volumes of multiple cylindrical models are obtained according to the three-dimensional coordinates of the grouting hole, the preset radius of the hole mouth and the preset radius of the hole bottom, and then the accuracy of the grouting model volume is improved by performing Boolean union on the volumes of the multiple cylindrical models.
[0016] In a possible implementation, a grouting blind area model is generated based on a grouting model and an excavation body model of a tunnel, including: performing Boolean difference between the excavation body model and the grouting model to generate the grouting blind area model.
[0017] By adopting the above technical solution, a Boolean difference is performed between the excavation model and the grouting model to obtain a grouting blind area model, so that the ungrouted area in the mountain after grouting can be visualized.
[0018] In a possible implementation, the volume of the excavation model is obtained based on the two-dimensional coordinates of the tunnel section and the preset excavation length of the tunnel section; the volume of the grouting blind area model is obtained based on the volume of the excavation model and the volume of the grouting model.
[0019] By adopting the above technical solution and performing Boolean difference on the excavation body model and the grouting model, the volume of the grouting blind area model is made more accurate.
[0020] In a second aspect, an embodiment of the present application provides a device for generating a tunnel section grouting model, the device comprising: an acquisition module, for acquiring three-dimensional coordinates of a plurality of grouting holes in a tunnel section, wherein the three-dimensional coordinates of each of the plurality of grouting holes include the three-dimensional coordinates of a grouting hole mouth and the three-dimensional coordinates of a grouting hole bottom, wherein the three-dimensional coordinates of the hole mouth of each grouting hole correspond to a three-dimensional coordinate of a hole bottom; A first generation module generates a plurality of cylindrical models based on the hole mouth coordinates and hole bottom coordinates of the plurality of grouting holes; The second generation module generates a grouting model of the tunnel section based on multiple cylindrical models.
[0021] In a possible implementation, the first generation module is specifically used to: generate multiple first circles with the orifices of multiple grouting holes as the first center and based on a preset orifice radius; generate multiple second circles with the bottoms of multiple grouting holes as the second center and based on a preset bottom radius; each of the multiple first circles corresponds to a second circle; and generate multiple cylindrical models based on the multiple first circles, the multiple second circles, the three-dimensional coordinates of the orifices and the three-dimensional coordinates of the bottoms.
[0022] In a possible implementation, the second generation module is specifically used to perform Boolean union of multiple cylindrical models to generate a grouting model of the tunnel section.
[0023] In a possible implementation, the first generation module also includes: a first generation submodule, which is used to obtain the volume of multiple cylindrical models based on the three-dimensional coordinates of the bottom of multiple grouting holes, the three-dimensional coordinates of the hole mouth, the preset hole mouth radius and the preset hole bottom radius.
[0024] In a possible implementation, the second generation module further includes: a second generation submodule, configured to perform Boolean union of volumes of a plurality of cylindrical models to obtain the volume of the tunnel section grouting model.
[0025] In a possible implementation, the device for generating a tunnel section grouting model also includes a third generation module, which is used to establish a cross-sectional contour model of the tunnel based on the two-dimensional coordinates of the tunnel section, and the cross-sectional contour model is a two-dimensional model; based on the grouting model, determine the relative position of the cross-sectional contour model and the grouting model; based on the preset excavation length of the tunnel section and the cross-sectional contour model, generate an excavation body model, and the excavation body model is a three-dimensional model; based on the grouting model and the excavation body model, generate a grouting blind area model.
[0026] In a third aspect, an embodiment of the present application provides an electronic device, which includes a processor, a memory and an interface; the memory is used to store instructions; the interface is used to communicate with other devices; the processor is used to execute the instructions stored in the memory so that the electronic device executes the method described in the first aspect.
[0027] In a fourth aspect, an embodiment of the present application provides a readable storage medium, which includes computer instructions. When the computer instructions are executed on a computer, the computer executes the method described in the first aspect.
[0028] In summary, one or more technical solutions provided in the embodiments of the present application have at least the following technical effects or advantages: 1. By generating multiple cylindrical models according to the coordinates of the grouting holes in the tunnel section, and then performing Boolean union on the multiple cylindrical models, a grouting model of the tunnel section is generated, so that the grouting effect of the tunnel section can be visualized, which improves the accuracy of analyzing the mountain conditions after grouting. Since manual investigation is not allowed, the safety of the staff is improved.
[0029] 2. A cross-sectional contour model is established through the two-dimensional coordinates of the tunnel section, and an excavation model is generated in combination with the preset excavation length of the tunnel section. The grouting blind area model is obtained by performing Boolean difference between the grouting model and the excavation model, so that the mountain after grouting can be visualized and the areas that have not been grouted can be intuitively analyzed, thereby improving the efficiency and accuracy of grouting.
[0030] 3. Since the grouting model volume, excavation model volume and grouting blind area volume are obtained respectively, a more cost-effective grouting model can be obtained according to the ratio of the three model volumes, which improves the grouting efficiency and accuracy. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 It is a flow chart of a method for generating a tunnel section grouting model provided in an embodiment of the present application.
[0032] Figure 2A-2C It is a structural block diagram of a method for generating a tunnel section grouting model provided in an embodiment of the present application.
[0033] Figure 3 It is a structural diagram of a grouting model of a tunnel section provided in an embodiment of the present application.
[0034] Figure 4 It is a flow chart of a method for generating a tunnel section grouting blind area model provided in an embodiment of the present application. Figure 5 It is a structural diagram of the excavation body model provided in an embodiment of the present application.
[0035] Figure 6 It is a structural diagram of the grouting blind area model provided in an embodiment of the present application.
[0036] Figure 7 It is a schematic diagram of a device for generating a grouting blind area model provided in an embodiment of the present application.
[0037] Figure 8 It is a schematic diagram of the structure of an electronic device disclosed in an embodiment of the present application. DETAILED DESCRIPTION
[0038] In order to enable technicians in this field to better understand the technical solutions in this specification, the technical solutions in the embodiments of this specification will be clearly and completely described below in conjunction with the drawings in the embodiments of this specification. Obviously, the described embodiments are only part of the embodiments of this application, not all of the embodiments.
[0039] In the description of the embodiments of the present application, words such as "for example" or "for example" are used to indicate examples, illustrations or explanations. Any embodiment or design described as "for example" or "for example" in the embodiments of the present application should not be interpreted as being more preferred or more advantageous than other embodiments or designs. Specifically, the use of words such as "for example" or "for example" is intended to present related concepts in a specific way.
[0040] In the description of the embodiments of the present application, the term "plurality" means two or more. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance or implicitly indicating the indicated technical features. Thus, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. The terms "include", "comprise", "have" and their variations all mean "including but not limited to", unless otherwise specifically emphasized.
[0041] The method for generating a tunnel section grouting model provided in the embodiment of the present application generates multiple cylindrical models using the three-dimensional coordinates of the grouting holes of the tunnel section, and generates a grouting model of the tunnel section based on the multiple cylindrical models. The grouting effect on the tunnel rupture surface can be intuitively seen through the grouting model. Compared with the prior art, there is no need to monitor the grouting mountain on site through a seismograph or an electromagnetic instrument, thereby improving the accuracy and efficiency of analyzing the grouting effect.
[0042] The method for generating a tunnel cross-section grouting model provided in the embodiment of the present application can be implemented through visual programming software such as Dynamo plug-in and Ue4 plug-in in Revit. In the embodiment of the present application, the implementation of Dynamo plug-in in Revit is taken as an example. Among them, Dynamo is a typical tree-structured visual programming software, and the smallest unit of its code is a node (Node). Different nodes with specific functions are connected as needed to achieve visual programming. The user inputs (Input) data on the left side of the node, performs node function calculations, and then outputs (Output) the results from the right side of the node, which are logically connected in sequence to finally form a complete script. In the embodiment of the present application, the following nodes are used: File FromPath node and Code Block node (code node), Data.ImportExcel node (import data node) and List.RestofItems node (other project node), Point.ByCoordinates node (by coordinate point node), Cone.ByPointsRadius node (by radius node), Soild.ByUnion node (by group node), Element.Curves node (curve node), PolyCurve.ByJoinedCurves node (connecting curve node), List.Firstltem node (prerequisite node), ircle.BycenterPointRadius node (by center radius node), ModelCurve.ByCurve node (by model curve node), Element.Curves node (element curve node), PolyCurve.ByJoinedCurves node (connecting nodes by curves) and Solid.Difference node (making difference node). Revit is designed for building information modeling (BIM) components, providing tools that support architectural design, MEP engineering design and structural engineering, which can help building designers design, build and maintain better quality and more energy-efficient buildings.
[0043] Combine the following Figure 1 , a more detailed description of the method for generating a tunnel section grouting model provided in the embodiment of the present application is given. Please refer to Figure 1 , Figure 1 1 is a flow chart of a method for generating a tunnel section grouting model provided in an embodiment of the present application. The process 100 includes the following steps: Step 101, obtaining the three-dimensional coordinates of multiple grouting holes in the tunnel section, wherein the three-dimensional coordinates of each grouting hole include the three-dimensional coordinates of the grouting hole mouth and the three-dimensional coordinates of the grouting hole bottom, wherein the three-dimensional coordinates of the hole mouth of each grouting hole corresponds to a three-dimensional coordinate of the hole bottom.
[0044] In the embodiment of the present application, the three-dimensional coordinates of multiple grouting holes in the tunnel section are obtained according to the railway tunnel engineering reference map and the tunnel construction method and auxiliary measures, as shown in Table 1. It can be understood that the three-dimensional coordinates of the multiple grouting holes shown in Table 1 are schematic, and in actual application scenarios, more or fewer three-dimensional coordinates of grouting holes may be included.
[0045] Table 1 As can be seen from Table 1, each grouting hole mouth coordinate in multiple grouting holes corresponds to a grouting hole bottom coordinate. Further, please refer to Figure 2, which is a structural block diagram of the method for generating a tunnel section grouting model provided in an embodiment of the present application. In the Dynamo software, firstly, the three-dimensional coordinates of the multiple grouting holes obtained are imported, and the three-dimensional coordinates of the multiple grouting holes obtained are sorted through the File FromPath node and the Code Block node in dynamo, specifically including the three-dimensional coordinates of the imported grouting holes are reorganized and grouped, and then through the Data.ImportExcel and List.Restoftems nodes, the X, Y, and Z coordinates of the bottom coordinates and the hole mouth coordinates of the grouting holes in the group are output respectively.
[0046] Step 102: Generate multiple cylindrical models based on the hole mouth coordinates and hole bottom coordinates of multiple grouting holes.
[0047] In the embodiment of the present application, the cylindrical model refers to the diffusion shape formed by the grouting liquid diffusing in an ideal state after the grouting is completed in a grouting hole, and the diffusion includes lateral diffusion and longitudinal diffusion. Furthermore, multiple cylindrical models are generated through the hole mouth coordinates and hole bottom coordinates of multiple grouting holes, and the multiple cylindrical models can reflect the grouting effect on the tunnel section under an ideal state.
[0048] In a possible implementation, multiple cylindrical models are generated based on the hole mouth coordinates and hole bottom coordinates of multiple grouting holes, including: taking the hole mouths of the multiple grouting holes as the first circle center and based on a preset hole mouth radius, multiple first circles are generated; taking the hole bottoms of the multiple grouting holes as the second circle center and based on a preset hole bottom radius, multiple second circles are generated; each of the multiple first circles corresponds to a second circle; and multiple cylindrical models are generated based on the multiple first circles, the multiple second circles, the three-dimensional coordinates of the hole mouth and the three-dimensional coordinates of the hole bottom.
[0049] In an embodiment of the present application, a first circle is generated according to a preset radius of the hole with the orifice of the grouting hole as the center, and a preset orifice radius and a preset orifice radius of the grouting hole are obtained according to the reference drawing of the railway tunnel project and the tunnel construction method and auxiliary measures, wherein the preset orifice radius should be greater than or equal to 50 mm, and a second circle is generated according to a preset radius with the bottom of the grouting hole as the center, wherein the preset bottom radius should be greater than 45 mm. Since the orifice coordinates of the grouting hole correspond to a hole bottom coordinate, a first circle also corresponds to a second circle; a cylindrical model is generated by combining the first circle, the second circle and the Z coordinate in the three-dimensional coordinates of the hole bottom, that is, the grouting length coordinate.
[0050] Step 103, generating a grouting model of the tunnel section based on the multiple cylindrical models.
[0051] In the examples of this application, please refer to Figure 3 , Figure 3 It is a structural diagram of the grouting model of the tunnel section provided in the embodiment of the present application. In one possible implementation, multiple cylindrical models are Boolean-unionized to generate a grouting model of the tunnel section; the multiple cylindrical models generated in step 102 need to be Boolean-unionized to delete the overlapping parts between the multiple cylindrical models during the grouting process, so as to obtain the grouting model of the tunnel section. For further information, please continue to refer to Figure 3 It can be seen that due to the different coordinates of the orifice and the bottom of the grouting hole, the grouting model is divided into 4 sections, including section A, section B, section C and section D, wherein the length of section A is 12 meters, the length of section B is 18 meters, the length of section C is 24 meters, and the length of section D is 30 meters. In the embodiment of the present application, the grouting model may include n sections, where n is an integer greater than or equal to 1, and the lengths of the multiple sections are not specifically limited.
[0052] In a possible implementation, the volumes of multiple cylindrical models are obtained based on the three-dimensional coordinates of the bottom of multiple grouting holes, the three-dimensional coordinates of the hole mouths, the preset hole mouth radius and the preset hole bottom radius; the volumes of the multiple cylindrical models are Boolean unioned to obtain the volume of the tunnel section grouting model.
[0053] In the embodiments of this application, please continue to refer to Figure 2B In the Dynamo software, the 3D coordinates of the hole mouth in the obtained 3D coordinates of the grouting hole are input into the Point.ByCoordinates node to generate a 3D coordinate set of the hole mouth, and the 3D coordinates of the grouting hole bottom in the obtained 3D coordinates of the grouting hole are input into another Point.ByCoordinates node to generate a 3D coordinate set of the hole bottom, and the two sets of generated 3D coordinate sets are input into the Cone.ByPointsRadi node, and the preset hole mouth radius and preset hole bottom radius are input into the Cone.ByPointsRa di node, and then the volumes of multiple cylindrical models and multiple cylindrical models are obtained, and the volumes of multiple cylindrical models and multiple cylindrical models are input into the Soild.ByUnion node, that is, the volumes of multiple cylindrical models and multiple cylindrical models are Boolean unioned, so as to obtain the grouting model of the tunnel section and the volume of the grouting model; in this embodiment of the application, the preset orifice radius is 50 mm, and the preset hole bottom radius is also 50 mm. According to the three-dimensional coordinates of the grouting hole, the volume of the grouting model can be obtained. In this embodiment of the application, the volume of the grouting model is 6381.45041 cubic meters.
[0054] In the embodiment of the present application, a grouting model of the tunnel section is generated according to the above steps. After the actual grouting is completed, the grouting effect can be accurately analyzed through the grouting model. In another embodiment of the present application, the effect after grouting can also be analyzed through the grouting blind area model. Please refer to Figure 4 , Figure 4 400 is a flow chart of a method for generating a tunnel section grouting blind area model provided in an embodiment of the present application. The flow chart 400 includes the following steps: Step 401, based on the two-dimensional coordinates of the tunnel section, establish a cross-sectional contour model of the tunnel, where the cross-sectional contour model is a two-dimensional model.
[0055] In the embodiment of the present application, the tunnel section profile and the two-dimensional coordinates of the profile are first obtained through the railway tunnel engineering reference map and the tunnel construction method and auxiliary measures, and a two-dimensional diagram of the tunnel section is drawn in the CAD software according to the two-dimensional coordinates of the tunnel section. Figure 2A, import the CAD drawing of the tunnel section into the Dynamo software to generate a cross-sectional contour model of the tunnel section, which is a two-dimensional model. Furthermore, the two-dimensional drawing of the tunnel section drawn in CAD is a two-dimensional drawing composed of multiple line segments. After being imported into the Dynamo software, the two-dimensional coordinates of the two-dimensional drawing of the tunnel section are sorted through the Element.Curves node of Dynamo, so that multiple line segments are combined into one line segment, and then the two-dimensional drawing of the tunnel section is converted into a tunnel section model through the PolyCurve.ByJoinedCurves node.
[0056] Step 402: Based on the grouting model, determine the relative position of the cross-section profile model and the grouting model.
[0057] In the embodiment of the present application, since the grouting model is generated according to the coordinates of the grouting holes, and the grouting holes are set based on the tunnel section, it is necessary to determine the relative position of the tunnel section model and the grouting model. Further, among multiple grouting holes, the grouting hole located at the center of the tunnel section is selected as the reference point to determine the relative position of the tunnel section model and the grouting model of the tunnel section. For further information, please continue to refer to Figure 2B In Dynamo software, call the three-dimensional coordinates of the grouting point in the List.Firstltem node, and then select the grouting at the center of the tunnel section according to the circle.BycenterPointRadius node. Set the grouting hole as the reference point through the ModelCurve.ByCurve node, and use this reference point to determine the relative position of the tunnel section model and the grouting model of the tunnel section.
[0058] Step 403: Generate an excavation volume model based on the preset excavation length of the tunnel section and the section contour model. The excavation volume model is a three-dimensional model.
[0059] In the embodiment of the present application, after the grouting liquid cools down, when the grouting effect meets the excavation standard, excavation is performed according to the preset excavation length. To determine whether the grouting effect meets the excavation standard, the embodiment of the present application also needs to establish an excavation body model of the tunnel section. Please refer to Figure 5 , Figure 5 This is the excavation model structure diagram provided by the embodiment of the present application. The excavation model is constructed based on the cross-section contour model generated in the above steps and the preset excavation length of the tunnel section. The preset excavation length is obtained from the railway tunnel engineering reference diagram and the tunnel construction method and auxiliary measures. Specifically, the excavation model is constructed with the cross-section contour model as the bottom surface and the preset excavation length as the height. For further information, please continue to refer to Figure 2B, import the preset excavation length of the tunnel section into Dynamo, and convert the preset excavation length of the tunnel section into three-dimensional coordinates through the Point.ByCoordinates node, such as (0,0,Z), where Z represents the preset excavation length. Through the Line.ByStartPointEndPoint node, the three-dimensional coordinates converted from the preset excavation length are used to generate a baseline. Then, through the Soild.BySweep node, an excavation model is generated based on the excavation contour model of the tunnel and the baseline converted from the preset excavation length. The excavation model visualizes the excavation work of the tunnel and improves the efficiency of tunnel excavation.
[0060] In a possible implementation manner, the volume of the excavation model is obtained based on the two-dimensional coordinates of the tunnel section and a preset excavation length of the tunnel section.
[0061] In the embodiment of the present application, the excavation body model is calculated according to the two-dimensional coordinates of the cross-sectional profile model and the preset excavation length. For further information, please continue to refer to Figure 2A , generate the excavation model volume according to the Soild.BySweep node in Dynamo software.
[0062] Step 404: Generate a grouting blind area model based on the grouting model and the excavation model.
[0063] In the embodiment of the present application, according to the relative positions of the grouting model and the cross-sectional contour model determined above, since the excavation body model is established based on the cross-sectional contour model, the relative positions of the grouting model and the excavation body model can be determined, and a grouting blind area model can be generated according to the grouting model and the excavation body model. The grouting blind area model refers to the area where the grouting liquid has not diffused in the mountain and the area where the grouting liquid has not been grouted during the grouting process. The grouting blind area model can reflect the effect of grouting and provide a reference for the staff to judge whether grouting is still needed to prevent excessive or insufficient grouting, thereby improving the cost-effectiveness and efficiency of grouting.
[0064] In a possible implementation, a Boolean difference is performed between the excavation model and the grouting model to generate a grouting blind area model.
[0065] In the embodiments of this application, please continue to refer to Figure 2C In Dynamo software, input the excavation model and grouting model into the Solid.Difference node, perform Boolean difference, and obtain the grouting blind area model. Please refer to Figure 6 , Figure 6 It is a structural diagram of the grouting blind area model provided in an embodiment of the present application.
[0066] In a possible implementation, the volume of the grouting blind area model is obtained based on the volume of the excavation model and the volume of the grouting model.
[0067] In the embodiment of the present application, the volume of the grouting blind area model is obtained by performing a Boolean difference between the volumes of the excavation model and the grouting model, that is, the volume of the grouting model is subtracted from the volume of the excavation model. Figure 2C In Dynamo software, the volume of the excavation model is obtained through the Solid.Difference node, which is 177.6677 cubic centimeters. According to the volume of the excavation model, the volume of the grouting model, and the volume of the grouting blind area model, it is judged whether additional grouting is needed in the actual grouting work, and which area needs additional grouting, which improves the efficiency and accuracy of grouting.
[0068] It is understandable that in order to achieve Figure 1 and / or Figure 4 The functions described herein are used to generate the execution subject (e.g., a server) of the method for generating a tunnel section grouting model, which includes hardware and / or software modules corresponding to the execution of each function. In combination with the steps of each example described in the embodiments disclosed herein, the present application can be implemented in the form of hardware or a combination of hardware and computer software. Whether a function is executed in the form of hardware or computer software driving hardware depends on the specific application and design constraints of the technical solution. Those skilled in the art can use different methods to implement the described functions for each specific application in combination with the embodiments, but such implementation should not be considered to be beyond the scope of the present application.
[0069] In this embodiment, the execution subject (e.g., server) of the method for generating a tunnel cross-section grouting model can be divided into functional modules according to the above method example. For example, different functional modules can be divided corresponding to each function, or two or more functions can be integrated into one processing module. The above integrated modules can be implemented in the form of hardware. It should be noted that the division of modules in this embodiment is schematic and is only a logical function division. There may be other division methods in actual implementation.
[0070] In the case of dividing each functional module into corresponding functional modules, Figure 7 A possible schematic diagram of the device 700 for generating a tunnel section grouting model involved in the above embodiment is shown. Figure 7 The corresponding device 700 for generating a tunnel section grouting model may be a software device running on a server, or the device 700 for generating a tunnel section grouting model may be a software and hardware combined device embedded in an execution subject (e.g., a server) of the method for generating a tunnel section grouting model. Figure 7As shown, the device 700 for generating a tunnel section grouting model may include: an acquisition module 701, used to acquire the three-dimensional coordinates of multiple grouting holes in the tunnel section, the three-dimensional coordinates of each grouting hole in the multiple grouting holes include the three-dimensional coordinates of the grouting hole mouth and the three-dimensional coordinates of the grouting hole bottom, wherein the three-dimensional coordinates of the hole mouth of each grouting hole corresponds to a three-dimensional coordinate of the hole bottom; a first generation module 702, based on the hole mouth coordinates and the hole bottom coordinates of the multiple grouting holes, generates a plurality of cylindrical models; a second generation module 703, based on the multiple cylindrical models, generates a grouting model of the tunnel section.
[0071] In a possible implementation, the first generation module is specifically used to: generate multiple first circles with the orifices of multiple grouting holes as the first center and based on a preset orifice radius; generate multiple second circles with the bottoms of multiple grouting holes as the second center and based on a preset bottom radius; each of the multiple first circles corresponds to a second circle; and generate multiple cylindrical models based on the multiple first circles, the multiple second circles, the three-dimensional coordinates of the orifices and the three-dimensional coordinates of the bottoms.
[0072] In a possible implementation, the second generation module is specifically used to perform Boolean union of multiple cylindrical models to generate a grouting model of the tunnel section.
[0073] In a possible implementation, the first generation module also includes: a first generation submodule, which is used to obtain the volume of multiple cylindrical models based on the three-dimensional coordinates of the bottom of multiple grouting holes, the three-dimensional coordinates of the hole mouth, the preset hole mouth radius and the preset hole bottom radius.
[0074] In a possible implementation, the second generation module further includes: a second generation submodule, configured to perform Boolean union of volumes of a plurality of cylindrical models to obtain the volume of the tunnel section grouting model.
[0075] In a possible implementation, the device for generating a tunnel section grouting model also includes a third generation module, which is used to establish a cross-sectional contour model of the tunnel based on the two-dimensional coordinates of the tunnel section, and the cross-sectional contour model is a two-dimensional model; based on the grouting model, determine the relative position of the cross-sectional contour model and the grouting model; based on the preset excavation length of the tunnel section and the cross-sectional contour model, generate an excavation body model, and the excavation body model is a three-dimensional model; based on the grouting model and the excavation body model, generate a grouting blind area model.
[0076] It should be noted that: the device 700 for generating a tunnel cross-section grouting model provided in the above embodiment only uses the division of the above functional modules as an example to implement its functions. In practical applications, the above functions can be assigned to different functional modules as needed, that is, the internal structure of the device can be divided into different functional modules to complete all or part of the functions described above. In addition, the device and method embodiments provided in the above embodiment belong to the same concept, and the specific implementation process is detailed in the method embodiment, which will not be repeated here.
[0077] The present application also discloses an electronic device. Figure 8 , Figure 8 is a schematic diagram of the structure of an electronic device disclosed in an embodiment of the present application. The electronic device may be, for example, a server, and the electronic device is used to execute the following Figure 1 , Figure 4 or Figure 7 The electronic device may include: at least one processor 801 , at least one network interface 804 , a user interface 803 , a memory 805 , and at least one communication bus 802 .
[0078] The communication bus 802 is used to realize the connection and communication between these components.
[0079] The user interface 803 may include a display screen (Display) and a camera (Camera), and the optional user interface 803 may also include a standard wired interface and a wireless interface.
[0080] The network interface 804 may include a standard wired interface or a wireless interface (such as a WI-FI interface) in a possible implementation manner.
[0081] Among them, the processor 801 may include one or more processing cores. The processor 801 uses various interfaces and lines to connect various parts in the entire server, and executes various functions of the server and processes data by running or executing instructions, programs, code sets or instruction sets stored in the memory 805, and calling data stored in the memory 805. In a possible implementation, the processor 801 can be implemented in at least one hardware form of digital signal processing (Digital Signal Processing, DSP), field programmable gate array (Field-Programmable Gate Array, FPGA), and programmable logic array (Programmable Logic Array, PLA). The processor 801 can integrate one or a combination of a central processing unit (Central Processing Unit, CPU), a graphics processing unit (Graphics Processing Unit, GPU) and a modem. Among them, the CPU mainly processes the operating system, user interface and application programs; the GPU is responsible for rendering and drawing the content to be displayed on the display screen; the modem is used to process wireless communications. It can be understood that the above-mentioned modem may not be integrated into the processor 801, and it can be implemented separately through a chip.
[0082] Among them, the memory 805 may include a random access memory (Random Access Memory, RAM) and may also include a read-only memory (Read-Only Memory). In one possible implementation, the memory 805 includes a non-transitory computer-readable storage medium. The memory 805 can be used to store instructions, programs, codes, code sets or instruction sets. The memory 805 may include a program storage area and a data storage area, wherein the program storage area may store instructions for implementing an operating system, instructions for at least one function (such as a touch function, a sound playback function, an image playback function, etc.), instructions for implementing the above-mentioned various method embodiments, etc.; the data storage area may store data involved in the above-mentioned various method embodiments, etc. In a possible implementation, the memory 805 may also be at least one storage device located away from the aforementioned processor 801. Refer to Figure 8 , the memory 805 as a computer storage medium may include an operating system, a network communication module, a user interface module and an application program of a data processing method.
[0083] exist Figure 8In the electronic device shown, the user interface 803 is mainly used to provide an input interface for the user and obtain the data input by the user; and the processor 801 can be used to call an application program storing a data processing method in the memory 805, and when executed by one or more processors 801, the electronic device executes one or more of the methods described in the above embodiments. It should be noted that for the aforementioned method embodiments, for the sake of simple description, they are all expressed as a series of action combinations, but those skilled in the art should be aware that the present application is not limited by the described order of actions, because according to the present application, certain steps can be performed in other orders or simultaneously. Secondly, those skilled in the art should also be aware that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily required for the present application.
[0084] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.
[0085] In the several implementation modes provided in this application, it should be understood that the disclosed devices can be implemented in other ways. For example, the device embodiments described above are only schematic, such as the division of unit modules, which is only a logical function division. There may be other division methods in actual implementation, such as multiple unit modules or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some service interfaces, and the indirect coupling or communication connection of devices or units can be electrical or other forms.
[0086] The unit modules described as separate components may or may not be physically separated, and the components displayed as unit modules may or may not be physical unit modules, that is, they may be located in one place or distributed on multiple network unit modules. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0087] In addition, each functional unit module in each embodiment of the present application can be integrated into a processing unit, or each unit module can exist physically separately, or two or more unit modules can be integrated into one unit. The above-mentioned integrated unit module can be implemented in the form of hardware or in the form of software functional unit.
[0088] If the integrated unit module is implemented in the form of a software functional unit module and sold or used as an independent product, it can be stored in a computer-readable memory. Based on this understanding, the technical solution of the present application, or the part that contributes to the prior art, or all or part of the technical solution can be embodied in the form of a software product, which is stored in a memory and includes several instructions for a computer device (which can be a personal computer, server or network device, etc.) to perform all or part of the steps of the various embodiments of the present application. The aforementioned memory includes: various media that can store program codes, such as USB flash drives, mobile hard drives, magnetic disks or optical disks.
[0089] The above is only an exemplary embodiment of the present disclosure and cannot be used to limit the scope of the present disclosure. That is, any equivalent changes and modifications made according to the teachings of the present disclosure are still within the scope of the present disclosure. After considering the disclosure of the specification and the truth of practice, those skilled in the art will easily think of other embodiments of the present disclosure.
[0090] This application is intended to cover any modifications, uses or adaptations of the present disclosure, which follow the general principles of the present disclosure and include common knowledge or customary technical means in the technical field not recorded in the present disclosure.
Claims
1. A method for generating a tunnel section grouting model, characterized in that: include: Acquire the three-dimensional coordinates of multiple grouting holes in the tunnel section, wherein the three-dimensional coordinates of each grouting hole in the multiple grouting holes include the three-dimensional coordinates of the grouting hole mouth and the three-dimensional coordinates of the grouting hole bottom, wherein the three-dimensional coordinates of the hole mouth of each grouting hole correspond to a three-dimensional coordinate of the hole bottom; Based on the hole mouth coordinates and hole bottom coordinates of the plurality of grouting holes, a plurality of cylindrical models are generated; Based on the multiple cylindrical models, a grouting model of the tunnel section is generated.
2. The method according to claim 1, characterized in that: The method further comprises: Based on the two-dimensional coordinates of the tunnel section, a cross-sectional profile model of the tunnel is established, wherein the cross-sectional profile model is a two-dimensional model; Based on the grouting model, determining the relative position of the cross-sectional profile model and the grouting model; Based on the preset excavation length of the tunnel section and the section contour model, an excavation volume model is generated, wherein the excavation volume model is a three-dimensional model; A grouting blind area model is generated based on the grouting model and the excavation body model.
3. The method according to claim 2, characterized in that Based on the hole mouth coordinates and hole bottom coordinates of the plurality of grouting holes, the step of generating a plurality of cylindrical models comprises: Taking the openings of the plurality of grouting holes as the first circle center and based on a preset opening radius, generating a plurality of first circles; Taking the bottoms of the plurality of grouting holes as the second circle center and based on a preset hole bottom radius, generating a plurality of second circles; Each of the plurality of first circles corresponds to a second circle; The plurality of cylindrical models are generated based on the plurality of first circles, the plurality of second circles, the three-dimensional coordinates of the hole opening, and the three-dimensional coordinates of the hole bottom.
4. The method according to claim 3, characterized in that Based on the multiple cylindrical models, the step of generating the grouting model of the tunnel section comprises: The multiple cylindrical models are subjected to Boolean union to generate a grouting model of the tunnel section.
5. The method according to claim 4, characterized in that The method further comprises: Obtaining the volumes of the plurality of cylindrical models according to the three-dimensional coordinates of the bottom holes, the three-dimensional coordinates of the hole openings, the preset hole opening radius, and the preset hole bottom radius of the plurality of grouting holes; The volumes of the multiple cylindrical models are Boolean-unionized to obtain the volume of the grouting model of the tunnel section.
6. The method according to claim 2, characterized in that Based on the grouting model and the excavation body model, the step of generating a grouting blind area model comprises: The excavation body model and the grouting model are subjected to Boolean difference to generate the grouting blind area model.
7. The method according to claim 5 or 6, characterized in that: The method further comprises: Obtaining the volume of the excavation model based on the two-dimensional coordinates of the tunnel section and the preset excavation length of the tunnel section; Based on the volume of the excavation model and the volume of the grouting model, the volume of the grouting blind area model is obtained.
8. A system for generating a tunnel fracture surface grouting model, characterized in that: The system comprises: An acquisition module is used to acquire the three-dimensional coordinates of multiple grouting holes in a tunnel section, wherein the three-dimensional coordinates of each grouting hole in the three-dimensional coordinates of the multiple grouting holes include the three-dimensional coordinates of the grouting hole mouth and the three-dimensional coordinates of the grouting hole bottom; wherein the three-dimensional coordinates of the hole mouth of each grouting hole correspond to a three-dimensional coordinate of the hole bottom; A first generating module generates a plurality of cylindrical models based on the hole mouth coordinates and hole bottom coordinates of the plurality of grouting holes; The second generating module generates a grouting model of the tunnel section based on the multiple cylindrical models.
9. An electronic device, characterized in that: including a processor, a memory, a user interface and a network interface; The memory is used to store instructions; The user interface and network interface are used to communicate with other devices; The processor is used to execute instructions stored in the memory so that the electronic device executes the method according to any one of claims 1 to 7.
10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores instructions, and when the instructions are executed, the method steps according to any one of claims 1 to 7 are performed.
Citation Information
Patent Citations
Grouting visualization statistical analysis management platform and use method thereof
CN113373903A
Establishment method of railway tunnel anchor rod refined model
CN115146420A
Simulation test method for directional drilling grouting slurry diffusion
WO2020215469A1