Engineering project integrated management system and method and storage medium

Through the comprehensive engineering project management system with user terminal-cloud server architecture, the problem of inconvenience in data silos and information sharing in engineering design and construction management is solved, and the whole process is integrated management is realized, the real-time and accuracy of data is improved, and the efficiency and collaboration efficiency of project management are improved.

CN120258712APending Publication Date: 2025-07-04WUHAN FIBERHOME TECHNICAL SERVICES CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510317072.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-03-18
Publication Date
2025-07-04

AI Technical Summary

Technical Problem

The existing engineering design and construction management lack a unified collaboration platform, and the accuracy and real-timeness of data are difficult to ensure. It is difficult to review the use of materials after the project construction is completed, and the project management process is not clear.

Method used

Adopt the user terminal-cloud server architecture to achieve efficient management of project design and construction management throughout the process. User and business identifiers are generated through the cloud server, to create to-do items, and save processing data to the associated storage space, update the to-do status in real time, and the user terminal query and display the to-do processing status.

Benefits of technology

It realizes the integration of the entire process of project design and construction management, improves the efficiency and accuracy of data management, ensures real-time updates and sharing of data, and enhances the flexibility and collaboration efficiency of project management.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120258712A_ABST
    Figure CN120258712A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of engineering management, in particular to an engineering project integrated management system and method and a storage medium, and the system comprises a cloud server side and a user terminal; the cloud server side is used for generating a user identifier according to the user registration information, generating a system identifier according to the registration information of the service processing system, receiving project information uploaded by the user terminal, and executing a project management process, including creating a to-do list according to the service identifier; issuing the service identifier and the to-do list to a service processing system corresponding to the system identifier, storing handling data uploaded by each service processing system to a storage space associated with the service identifier, and updating the processing state of the to-do list in real time; and the user terminal is used for associating one or more service processing systems according to the user identifier, querying the to-do list and displaying the processing state of the to-do list. According to the system, project design and construction management are subjected to whole-process integrated management, user operation is simplified, and efficient management is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of project management, and in particular, to a comprehensive project management system, method, and storage medium. Background Art

[0002] The existing engineering design and construction management lack a unified collaboration platform, and it is difficult to ensure the accuracy and timeliness of data. With the development of technology, the wide application of smartphones and cloud platforms has brought new opportunities to project management. However, most of the current market solutions have problems such as data islands, inconvenient information sharing, and untimely synchronization.

[0003] The general process of engineering design and construction management is as follows:

[0004] 1. The design department uses software such as CAD to draw design drawings;

[0005] 2. The site surveyors conduct on-site surveys based on the design drawings (obtained through manual transfer, network sharing, etc.), estimate the types and quantities of materials (recorded by Excel, paper and pen, etc.), and transmit the survey results back;

[0006] 3. The data entry personnel enter the types and quantities of materials into the material management system;

[0007] 4. The purchasing personnel conduct purchases according to the procurement system;

[0008] 5. The construction personnel apply for materials on the material management system.

[0009] The current project management system has the following problems: Due to the imperfect management system, the data flow and approval between multiple processing systems cannot be well connected. After the project construction is completed, it is difficult to review the material usage situation, and the project management process is not clear. There is a lack of a technical solution in the prior art that can handle the entire process of project design and construction management. Summary of the Invention

[0010] The purpose of the present invention is to provide a comprehensive project management system, method, and storage medium, which adopt a user terminal-cloud server architecture to achieve efficient management of the entire process of project design and construction management.

[0011] To achieve the above purpose, the present invention provides the following technical solutions:

[0012] In the first aspect, a comprehensive project management system is provided, including a cloud server side and a user terminal;

[0013] The cloud server is used to generate a user identifier based on user registration information, manage user permissions based on the user identifier, generate a system identifier according to the registration information of the business processing system, receive project information uploaded by the user terminal, and execute a project management process. The project management process includes creating a to-do item according to a business identifier, sending the business identifier and the to-do item to the business processing system corresponding to the system identifier, and saving the processing data uploaded by each business processing system to a storage space associated with the business identifier, and updating the processing status of the to-do item in real time according to the processing data;

[0014] The user terminal is used to associate one or more business processing systems according to the user identifier, query the to-do item, and display the processing status of the to-do item.

[0015] Further, the user terminal includes a mobile APP, a PC APP, and a web page.

[0016] Further, the business identifier is a business serial number generated by the cloud server for each business process of the project;

[0017] The to-do item created according to the business identifier includes an execution to-do item and an approval to-do item;

[0018] The execution to-do item includes inputting business data, uploading images or files according to a preset template;

[0019] The approval to-do item includes approving project information, process information, and business data.

[0020] Further, the business processing system includes, but is not limited to, a project management system, a material management system, and a on-site operation quality management system.

[0021] Further, the project management system is used to download basic drawings from the local or the cloud server, obtain project design drawings after project design and collaborative processing. The basic drawings contain geographical information and positioning information, support marking, drawing, measuring, and modifying relevant parameters, create project information according to the project design drawings, and upload the project information to the cloud server;

[0022] And process the project approval to-do item sent by the cloud server, and upload the approval result to the cloud server.

[0023] Further, the material management system is used to process the material management to-do item sent by the cloud server, including inputting or approving subcontractor material requisition, consumption, feeding, and return data, generating material management processing data, and uploading the material management processing data to the cloud server.

[0024] Further, the on-site operation quality management system is used to process the to-do items of on-site operation quality management issued by the cloud server side, including inputting or reviewing on-site survey data, on-site photos, and deviation correction data, generating quality management processing data, and uploading the quality management processing data to the cloud server side.

[0025] In a second aspect, an integrated project management method is provided, which is applied to the cloud server side. The integrated project management method includes:

[0026] Obtain the user registration information of the user terminal and generate a user identifier;

[0027] Obtain the registration information of the business processing system and generate a system identifier;

[0028] Receive the project information uploaded by the user terminal and execute the project management process. The project management process includes creating a to-do item according to the business identifier and issuing the business identifier and the to-do item to the business processing system corresponding to the system identifier;

[0029] Receive the processing data uploaded by each business processing system, save it to the storage space associated with the business identifier, and update the processing status of the to-do item in real time according to the processing data.

[0030] Further, the business identifier is the business serial number generated by the cloud server side for each business process of the project;

[0031] The to-do item created according to the business identifier includes an execution to-do item and a review to-do item;

[0032] The execution to-do item includes inputting business data, taking pictures or uploading files according to a preset template;

[0033] The review to-do item includes reviewing project information, process information, and business data.

[0034] Further, the business processing system includes, but is not limited to, a project management system, a material management system, and an on-site operation quality management system.

[0035] Further, the work process of the project management system is as follows:

[0036] Download the basic drawing from the local or the cloud server side, obtain the project design drawing after project design and collaborative processing. Among them, the basic drawing contains geographical information and positioning information, supports marking, drawing, measuring, and modifying relevant parameters, create project information according to the project design drawing, and upload the project information to the cloud server side;

[0037] Receive the project review to-do items issued by the cloud server, and upload the review results to the cloud server after processing the project review to-do items.

[0038] Further, the workflow of the material management system is as follows:

[0039] Receive the material management to-do items issued by the cloud server;

[0040] Input or review the subcontractor's material requisition, consumption, feeding, and material return data in the material management to-do items to generate material management processing data;

[0041] Upload the material management processing data to the cloud server.

[0042] Further, the workflow of the on-site operation quality management system is as follows:

[0043] Receive the on-site operation quality management to-do items issued by the cloud server;

[0044] Input or review the on-site inspection data, on-site photos, and deviation correction data in the on-site operation quality management to-do items to generate quality management processing data;

[0045] Upload the quality management processing data to the cloud server.

[0046] Based on the same inventive concept, the present invention also provides a computer storage medium, in which computer-executable instructions are stored, and when the computer-executable instructions are executed, the foregoing engineering project comprehensive management method is implemented.

[0047] The technical effects and advantages of the present invention:

[0048] (1) The system conducts full-process integrated management of project design and construction management, improving work efficiency;

[0049] (2) The system adopts a user terminal - cloud server architecture. The cloud server automatically executes the project management process and stores the data uploaded by the user terminal, realizing efficient management and real-time sharing of data;

[0050] (3) The cloud server registers multiple business processing systems according to project management requirements, and issues tasks to each business processing system through user identification and system identification, making the business process and business data traceable, and improving the accuracy and timeliness for the review and recheck processes of each project link.

[0051] Other features and advantages of the present invention will be set forth in the following description, and in part will be obvious from the description, or may be learned by practice of the present invention. The objectives and other advantages of the present invention may be realized and attained by the structure particularly pointed out in the specification, claims as well as the drawings. Description of the Drawings

[0052] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for the description of the embodiments. Obviously, the drawings in the following description are only some embodiments of the present invention. For those of ordinary skill in the art, other drawings can be obtained based on these drawings without creative efforts.

[0053] Figure 1 Schematic diagram of the integrated project management system provided by the first embodiment of the present invention;

[0054] Figure 2 Schematic flowchart of the integrated project management method provided by the second embodiment of the present invention. Detailed Embodiments

[0055] The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, rather than all, of the embodiments of the present invention. All other embodiments obtained by those of ordinary skill in the art based on the embodiments of the present invention without creative efforts fall within the scope of protection of the present invention.

[0056] The first embodiment of the present invention provides an integrated project management system, as Figure 1 shown, the integrated project management system includes a cloud server end and a user terminal.

[0057] The cloud server end is used to generate a user identifier according to the user registration information, manage user permissions based on the user identifier, generate a system identifier according to the registration information of the business processing system, receive project information uploaded by the user terminal, and execute a project management process. The project management process includes creating a to-do item according to a service identifier, sending the service identifier and the to-do item to the business processing system corresponding to the system identifier, and saving the processing data uploaded by each business processing system to a storage space associated with the service identifier, and updating the processing status of the to-do item in real time according to the processing data.

[0058] The cloud server obtains the user registration information through the user terminal interface, generates a user ID as the user identifier based on the user registration information, obtains the registration information of the business processing system through the system terminal interface, and uses the system ID and system service type generated according to the registration information of the business processing system as the system identifier.

[0059] The user terminal is used to associate one or more of the business processing systems according to the user identifier, query the to-do items, and display the processing status of the to-do items.

[0060] According to an embodiment of the present invention, the project designer enters the corresponding business processing system through the user terminal, designs the project and uploads the project information to the cloud server. The cloud server automatically executes the project management process according to the project information, including creating to-do items according to the business identifier, and sending the business identifier and the to-do items to the business processing system corresponding to the system identifier. Other users process the corresponding to-do items after entering the corresponding business processing system based on the user permissions. After the processing is completed, the data is uploaded to the cloud server for storage. The cloud server updates the processing status of the to-do items in real time and displays it on the user terminal.

[0061] The embodiment of the present invention provides an integrated project management system based on a cloud server and a user terminal. External business processing systems are registered on the cloud server and are associated with the user terminal through user identifiers and system identifiers, effectively solving data redundancy, improving data relevance and consistency, and avoiding errors and omissions in the information flow process. By integrating the entire process of project design and construction management, it ensures the real-time update and sharing of data. At the same time, the data synchronization mechanism between the user terminal and the cloud server enhances the flexibility and collaboration of project management, greatly improving the efficiency and quality of project implementation.

[0062] According to a preferred embodiment of the present invention, the user terminal includes a mobile APP, such as mobile phone and tablet APPs, a PC APP, and a web page.

[0063] In this system, several business processing systems are registered on the cloud server according to the project management requirements. The user terminal associates one or more of the business processing systems according to the user ID. Therefore, when the user logs in to the user terminal APP, they enter different business processing systems based on the user permissions to process the to-do items, which is convenient for the user to synchronize and update the project data anytime and anywhere, greatly enhancing the flexibility and convenience of project management.

[0064] According to an embodiment of the present invention, the service identifier is a service serial number generated by the cloud server for each business process of the project. The to-do items created by the cloud server according to the service identifier include execution to-do items and review to-do items. Among them, the execution to-do items include inputting business data, uploading images or files according to a preset template, and the review to-do items include reviewing project information, process information, and business data. Based on user permissions, the user terminal is configured as an execution terminal or a review terminal. The execution terminal is used to process execution to-do items, and the review terminal is used to process review to-do items.

[0065] In an embodiment of the present invention, the cloud server registers several business processing systems according to project management requirements, including but not limited to a project management system, a material management system, and a field operation quality management system. The comprehensive project management system of this project has high scalability, reliability, and security.

[0066] Among them, the project management system is used to download basic drawings from the local or the cloud server, obtain project design drawings after project design and collaborative processing. The basic drawings contain geographic information and positioning information, support marking, drawing, measuring, and modifying relevant parameters, create project information according to the project design drawings, and upload the project information to the cloud server; and process the project review to-do items issued by the cloud server and upload the review results to the cloud server. All project data, design drawings, modification records, etc. are centrally stored and backed up on the cloud server, improving the efficiency and security of project management.

[0067] The material management system is used to process the material management to-do items issued by the cloud server, generate material management processing data, and upload the material management processing data to the cloud server. The material management to-do items include execution to-do items and review to-do items related to material management. The material management to-do items include inputting or reviewing subcontractor material requisition, consumption, feeding, and return data.

[0068] The field operation quality management system is used to process the field operation quality management to-do items issued by the cloud server, generate quality management processing data, and upload the quality management processing data to the cloud server. The field operation quality management to-do items include execution to-do items and review to-do items related to field operation quality management. The field operation quality management to-do items include downloading the project design drawings to the local and then inputting or reviewing on-site survey data, on-site photos, and deviation correction data. In actual applications, users conduct on-site surveys and track construction progress based on real-time positioning systems such as GPS and Beidou on mobile devices to ensure the accurate matching of construction data with the actual location.

[0069] Exemplarily, an inspection system is also registered on the cloud server side. The inspection system is used to process the inspection to-do items issued by the cloud server side. By obtaining the construction status and construction progress of each process, inspection handling data is generated and uploaded to the cloud server side.

[0070] Furthermore, a delivery operation digital platform, a mobile service post-evaluation tool, an asset management system, a project spare parts management system, etc. can also be registered on the cloud server side. Among them, the delivery operation digital platform is used for the global cryptocurrency FTK business, and the mobile service post-evaluation tool is used for evaluating data filling, analyzing assessment results, and tracking risk issues, etc., which will not be elaborated here one by one.

[0071] According to the embodiments of the present invention, the cloud server side manages user permissions so that users can only view and process the to-do items of the business system on the APP or web side, simplifying the operation and improving work efficiency. After the business processing system uploads the handling data to the cloud server side, the cloud server side stores the handling data in the storage space associated with the business identifier, synchronously updates the item status, and enables other user terminals to view the business process and data change situation in real time. Between the cloud server side and the APP of the embodiments of the present invention, data automatic up and down synchronization is supported. Users do not need to perform additional operations. Through the data synchronization function, project members can maintain collaborative cooperation, timely obtain the latest project progress, and greatly improve the collaboration efficiency and transparency of project implementation.

[0072] Based on the above engineering project comprehensive management system, a second embodiment of the present invention provides an engineering project comprehensive management method, which is applied to the cloud server side, as Figure 2 shown. The engineering project comprehensive management method includes:

[0073] Step S1: Obtain the user registration information of the user terminal and generate a user identifier;

[0074] Step S2: Obtain the registration information of the business processing system and generate a system identifier;

[0075] Step S3: Receive the project information uploaded by the user terminal and execute the project management process. The project management process includes creating a to-do item according to the business identifier and issuing the business identifier and the to-do item to the business processing system corresponding to the system identifier;

[0076] Step S4: Receive the handling data uploaded by each business processing system, save it to the storage space associated with the business identifier, and update the processing status of the to-do item in real time according to the handling data.

[0077] In an embodiment of the present invention, the cloud server obtains user registration information through a user terminal interface, generates a user ID as a user identifier based on the user registration information, manages user permissions based on the user identifier, obtains the registration information of the business processing system through a system terminal interface, and uses the system ID and system service type generated according to the registration information of the business processing system as system identifiers. The business identifier is a business serial number generated by the cloud server for each business process of the project.

[0078] The to-do items created according to the business identifier include execution to-do items and review to-do items. Among them, the execution to-do items include inputting business data, taking pictures, or uploading files according to a preset template, and the review to-do items include reviewing project information, process information, and business data.

[0079] In an embodiment of the present invention, the cloud server registers several business processing systems according to project management requirements, including but not limited to a project management system, a material management system, and a on-site operation quality management system. The user terminal associates one or more of the business processing systems according to the user identifier. The user queries the to-do items of the business processing system through the user terminal, processes the to-do items, uploads the generated processing data to the cloud server for storage, and the cloud server updates the processing status of the to-do items in real time according to the processing data and synchronously displays it on the user terminal. Therefore, the comprehensive project management system has high scalability and realizes efficient management and real-time sharing of data.

[0080] Among them, the work process of the project management system is as follows: download basic drawings from the local or cloud server, obtain project design drawings after project design and collaborative processing. Among them, the basic drawings contain geographical information and positioning information, support marking, drawing, measuring, and modifying relevant parameters, create project information according to the project design drawings, and upload the project information to the cloud server; receive the project review to-do items issued by the cloud server, and upload the review results to the cloud server after processing the project review to-do items. Since all project data, design drawings, modification records, etc. are centrally stored and backed up on the cloud server, the reliability and security of the project management process are improved.

[0081] The work process of the material management system is as follows: receive the material management to-do items issued by the cloud server; input or review subcontractor material requisition, consumption, feeding, and return data in the material management to-do items to generate material management processing data; upload the material management processing data to the cloud server.

[0082] The workflow of the on-site operation quality management system is as follows: receiving the on-site operation quality management to-do items issued by the cloud server; inputting or reviewing on-site survey data, on-site photos, and deviation correction data in the on-site operation quality management to-do items to generate quality management processing data; and uploading the quality management processing data to the cloud server. In practical applications, users conduct on-site surveys and track the construction progress based on real-time positioning systems such as GPS and Beidou on the mobile terminal to ensure the accurate matching of construction data with the actual location.

[0083] According to a preferred embodiment, a patrol inspection system is also registered on the cloud server. The patrol inspection system is used to process the patrol inspection to-do items issued by the cloud server, generate patrol inspection processing data by obtaining the construction status and construction progress of each process, and upload the patrol inspection processing data to the cloud server.

[0084] Furthermore, a delivery operation digital platform, a mobile service post-evaluation tool, an asset management system, a project spare parts management system, etc. can also be registered on the cloud server. Among them, the delivery operation digital platform is used for the global cryptocurrency FTK business, and the mobile service post-evaluation tool is used for evaluating data filling, analyzing assessment results, tracking risk issues, etc., which will not be elaborated here one by one.

[0085] According to the embodiments of the present invention, after the user uploads the processing data to the cloud server through the business processing system, the cloud server stores the processing data in the storage space associated with the business identifier, synchronously updates the item status, so that other user terminals can view the business process and data change situation in real time. Through the data synchronization function of the cloud server, project members can maintain collaborative cooperation, obtain the latest project progress in a timely manner, and greatly improve the collaboration efficiency and transparency of project implementation.

[0086] Based on the same inventive concept, the embodiments of the present invention also provide a computer storage medium, in which computer-executable instructions are stored. When the computer-executable instructions are executed, the foregoing engineering project comprehensive management method is implemented.

[0087] In several embodiments provided in the present application, it should be understood that the disclosed device and method can be implemented in other ways. For example, the device embodiments described above are merely illustrative. For example, the division of the modules is only a logical function division. In actual implementation, there may be other division methods. For example, multiple modules or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the displayed or discussed coupling or direct coupling or communication connection to each other can be through some interfaces. The indirect coupling or communication connection of the device or module can be in an electrical, mechanical or other form.

[0088] The module described as a separation component may or may not be physically separated. The component shown as a module may or may not be a physical module, that is, it may be located in one place or distributed across multiple network modules. Some or all of the modules can be selected according to actual needs to achieve the purpose of the solution of this embodiment. In addition, in each embodiment of the present invention, each functional module can be integrated in a processing module, or each module can exist physically alone, or two or more modules can be integrated in one module. The above-mentioned integrated module can be implemented in the form of hardware or in the form of a software functional module.

[0089] If the integrated module is implemented in the form of a software functional module and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on such an understanding, the technical solution of the present invention, in essence, or the part that contributes to the prior art, or all or part of the technical solution, can be embodied in the form of a software product. This computer software product is stored in a storage medium and includes several instructions for causing a computer device (which can be a personal computer, a server, or a network device, etc.) to execute all or part of the steps of the methods described in each embodiment of the present invention. The foregoing storage medium includes: various media such as USB flash drives, mobile hard disks, read-only memories (ROM, Read-Only Memory), random access memories (RAM, Random Access Memory), magnetic disks, or optical discs that can store program codes.

[0090] It should be noted that for the foregoing method embodiments, for the sake of simple description, they are all expressed as a series of action combinations. However, those skilled in the art should know that the present invention is not limited by the described action sequence, because according to the present invention, some steps can be performed in other sequences or simultaneously. Secondly, those skilled in the art should also know that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily all essential to the present invention.

[0091] In the above embodiments, the descriptions of each embodiment have their own emphases. For the parts not detailed in a certain embodiment, reference can be made to the relevant descriptions of other embodiments. Finally, it should be noted that the above are only the preferred embodiments of the present invention and are not used to limit the present invention. Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments, or perform equivalent replacements for some of the technical features. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. An integrated project management system, characterized in that, The comprehensive project management system includes a cloud server and user terminals; The cloud server is used to generate a user identifier based on user registration information, manage user permissions based on the user identifier, generate a system identifier based on the registration information of the business processing system, receive project information uploaded by the user terminal, and execute a project management process. The project management process includes creating a to-do item according to a business identifier, sending the business identifier and the to-do item to the business processing system corresponding to the system identifier, and saving the processing data uploaded by each business processing system to a storage space associated with the business identifier, and updating the processing status of the to-do item in real time according to the processing data; The user terminal is used to associate one or more business processing systems according to the user identifier, query the to-do item, and display the processing status of the to-do item.

2. The integrated project management system according to claim 1, characterized in that The user terminal includes a mobile APP, a PC APP, and a web page.

3. The integrated project management system according to claim 1, wherein, The business identifier is a business serial number generated by the cloud server for each business process of the project; The to-do item created according to the business identifier includes an execution to-do item and an approval to-do item; The execution to-do item includes inputting business data, uploading images or files according to a preset template; The approval to-do item includes approving project information, process information, and business data.

4. The integrated project management system according to claim 3, characterized in that, The business processing system includes, but is not limited to, a project management system, a material management system, and a on-site operation quality management system.

5. The integrated project management system according to claim 4, wherein The project management system is used to download basic drawings from the local or the cloud server, obtain project design drawings after project design and collaborative processing. The basic drawings contain geographic information and positioning information, support marking, drawing, measuring, and modifying relevant parameters, create project information according to the project design drawings, and upload the project information to the cloud server; And process the project approval to-do item sent by the cloud server and upload the approval result to the cloud server.

6. The integrated project management system according to claim 4, wherein The material management system is used to process the material management to-do item sent by the cloud server, including inputting or approving subcontractor material requisition, consumption, feeding, and material return data, generating material management processing data, and uploading the material management processing data to the cloud server.

7. The integrated project management system according to claim 4, wherein The on-site operation quality management system is used to process the on-site operation quality management to-do item sent by the cloud server, including inputting or approving on-site survey data, on-site photos, and deviation correction data, generating quality management processing data, and uploading the quality management processing data to the cloud server.

8. An integrated project management method, which is applied to a cloud server, is characterized in that, The comprehensive project management method includes: Obtain the user registration information of the user terminal and generate a user identifier; Obtain the registration information of the business processing system and generate a system identifier; Receive the project information uploaded by the user terminal and execute a project management process. The project management process includes creating a to-do item according to a business identifier, and sending the business identifier and the to-do item to the business processing system corresponding to the system identifier; Receive the processing data uploaded by each business processing system, save it to the storage space associated with the business identifier, and update the processing status of the to-do items in real time according to the processing data.

9. The integrated project management method according to claim 8, characterized in that, The business identifier is the business serial number generated by the cloud server for each business process of the project; The to-do items created according to the business identifier include execution to-do items and review to-do items; The execution to-do items include inputting business data, taking pictures or uploading files according to a preset template; The review to-do items include reviewing project information, process information, and business data.

10. The comprehensive project management method according to claim 9, characterized in that, The business processing system includes, but is not limited to, a project management system, a material management system, and a on-site operation quality management system.

11. The comprehensive project management method according to claim 10, characterized in that, The work process of the project management system is as follows: Download basic drawings from the local or cloud server, obtain project design drawings after project design and collaborative processing. Among them, the basic drawings contain geographical information and positioning information, support marking, drawing, measuring, and modifying relevant parameters. Create project information according to the project design drawings and upload the project information to the cloud server; Receive the project review to-do items issued by the cloud server, upload the review results to the cloud server after processing the project review to-do items.

12. The integrated project management method according to claim 10, wherein The work process of the material management system is as follows: Receive the material management to-do items issued by the cloud server; Input or review subcontractor material requisition, consumption, feeding, and return material data in the material management to-do items to generate material management processing data; Upload the material management processing data to the cloud server.

13. The comprehensive project management method according to claim 10, characterized in that The work process of the on-site operation quality management system is as follows: Receive the on-site operation quality management to-do items issued by the cloud server; Input or review on-site survey data, on-site photos, and deviation correction data in the on-site operation quality management to-do items to generate quality management processing data; Upload the quality management processing data to the cloud server.

14. A computer-readable storage medium, characterized in that, The computer-readable storage medium stores computer-executable instructions, and when the computer-executable instructions are executed, the comprehensive project management method described in any one of claims 8-13 is implemented.