Expressway construction safety risk assessment system and method thereof
The system addresses the limitations of static risk assessment methods by using real-time data and neural networks to dynamically adjust construction plans, enhancing risk prediction and safety in highway construction.
Patent Information
- Application Number
- CN202510268226.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-03-07
- Publication Date
- 2025-07-15
AI Technical Summary
Traditional highway construction risk assessment methods lack comprehensive analysis of multi-source data, insufficient evaluation accuracy, cannot be dynamically adjusted, and it is difficult to accurately evaluate safety risks in complex environments.
By installing environmental sensors at the construction site to collect data in real time, using intelligent analysis algorithms to generate risk reports, combining deep neural network models, dynamically adjust construction plans, and optimize resource allocation to reduce risks.
It improves the accuracy and construction safety of construction site risk prediction, reduces safety hazards, and improves construction progress and efficiency.
Smart Images

Figure CN120317656A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical fields of intelligent transportation and construction project safety management, and particularly relates to a highway construction safety risk assessment system and a method thereof. Background Art
[0002] The construction environment of highways is complex and involves various dynamic factors, including meteorological conditions, geological environment, operating status of construction equipment, construction progress, etc. During the construction process, any uncontrollable risk factors may lead to safety accidents, affecting the safety of construction workers, the stability of equipment operation, and the project progress. Traditional construction risk assessment methods usually rely on manual experience or single data monitoring.
[0003] There are the following deficiencies: insufficient assessment accuracy, existing methods lack comprehensive analysis of multi-source data and it is difficult to accurately assess safety risks in complex environments; weak dynamic adjustment ability, most traditional risk assessment methods are based on fixed models or parameters and cannot dynamically adjust the assessment results according to real-time data at the construction site.
[0004] Therefore, we propose a highway construction safety risk assessment system and a method thereof to solve the above problems. Summary of the Invention
[0005] The purpose of this part is to outline some aspects of the embodiments of the present invention and briefly introduce some preferred embodiments. Some simplifications or omissions may be made in this part, as well as in the abstract and title of the present application, to avoid obscuring the purpose of this part, the abstract, and the title, and such simplifications or omissions cannot be used to limit the scope of the present invention.
[0006] In view of the problems existing in the above-mentioned existing highway construction safety risk assessment system and method, the present invention is proposed.
[0007] To solve the above technical problems, the present invention provides the following technical solutions:
[0008] A highway construction safety risk assessment method, the method includes the following steps:
[0009] Step 1: Data collection, installing environmental sensors at the construction site to collect the environmental data of the construction site in real time as the basis for risk assessment;
[0010] Step 2: Formulating an intelligent analysis mechanism for the environmental data of the construction site, predicting and judging the possible risks at the construction site according to the collected environmental data, and generating a risk report;
[0011] Step 3: Construct an optimized construction plan model, using the information in the risk report as the input of the optimized construction plan model. The optimized construction plan model, based on the priorities of construction tasks, the number of construction equipment, and the requirements of the construction period, and combining with the risk data, gives adjustment suggestions again, including: dispatching more personnel, delaying the construction, and adding temporary measures to reduce risks.
[0012] As a preferred embodiment of the method for evaluating highway construction safety risks according to the present invention, wherein: the content included in the risk report includes: normalized environmental data, comprehensive environmental risk value, and the impact of predicted risks on the construction plan; the specific intelligent analysis mechanism includes:
[0013] S201: Normalize the risk factor E i (t), and the processing calculation formula is:
[0014]
[0015] wherein, E i (t) represents the real-time data of the i-th environmental factor, and u i represents the reference value of the environmental factor i, such as common construction standard environmental parameters. The risk factor value after normalization by f i (E i (t)) uses the logarithmic function to smooth the impact of outliers on the whole;
[0016] S202: Combine multiple risk factors to calculate the overall environmental risk value R(t) of the construction site at a certain time t, and the calculation formula is:
[0017]
[0018] wherein, w i represents the weight of the risk factor i, satisfying
[0019] S203: Quantify the impact of risks on the construction plan through the dynamic risk attenuation function.
[0020] As a preferred embodiment of the method for evaluating highway construction safety risks according to the present invention, wherein: the expression of the dynamic risk attenuation function is: e -α·R(t) , where α represents the risk sensitivity adjustment coefficient, and the larger the value, the more significant the impact of the risk on the plan.
[0021] As a preferred embodiment of the method for evaluating highway construction safety risks according to the present invention, wherein: if R(t) > the first threshold, it is determined that the risk at the construction site is a high risk, and protective measures are added to reduce the risk or the construction is postponed;
[0022] If R(t) < the second threshold, it is determined that the risk at the construction site is low risk, and the existing construction plan is continued;
[0023] If the second threshold ≤ R(t) ≤ the first threshold, it is determined that the risk at the construction site is medium risk, and further monitoring is required and a temporary emergency plan is prepared, and resource investment is increased.
[0024] As a preferred solution of the method for evaluating the safety risk of highway construction described in the present invention, wherein: the construction plan optimization model combines environmental risk and resource utilization rate, and is defined as follows:
[0025]
[0026] Among them, P opt (t) represents the dynamic priority of the construction plan, T1 and T2 represent the construction time intervals, and G represents the constraint of the resource utilization rate on the plan.
[0027] As a preferred solution of the method for evaluating the safety risk of highway construction described in the present invention, wherein: the expression of the constraint G of the resource utilization rate on the plan is:
[0028]
[0029] Among them, U(t) represents the resource utilization rate, and β represents the resource constraint sensitivity. The larger the value, the greater the impact of the resource limit on the construction plan.
[0030] As a preferred solution of the method for evaluating the safety risk of highway construction described in the present invention, wherein: according to the priority P opt (t), the construction plan is reordered, the priority of the urgent tasks is clarified, and the following specific adjustment suggestions are put forward:
[0031] Add temporary measures. If the priority P opt (t) is greater than the set priority threshold and R(t) > the first threshold, the risk is reduced by setting protective measures;
[0032] Delay the construction. If the priority P opt (t) is lower than the set priority threshold and R(t) > the first threshold, the construction is stopped;
[0033] Dispatch more personnel. If the priority P opt (t) is greater than the set priority threshold and the second threshold ≤ R(t) ≤ the first threshold, additional resources can be mobilized to complete the task.
[0034] A risk assessment system applied to the above method for evaluating the safety risk of highway construction, the system includes the following modules:
[0035] A data acquisition module for real-time acquisition of environmental data at the construction site; an intelligent analysis and risk assessment module that uses the acquired environmental data to analyze and evaluate potential risks at the construction site through intelligent algorithms;
[0036] A construction plan optimization module that optimizes the construction plan according to the results of the risk assessment module, the priorities of construction tasks, the availability of construction equipment, personnel allocation, and construction period requirements; a decision execution module that makes construction safety decisions based on the outputs of the intelligent analysis and risk assessment module and the construction plan optimization module, including whether to initiate an early warning, whether to adjust the construction plan, and whether to dispatch additional manpower;
[0037] And an information display and visualization module that displays information such as real-time data, risk assessment results, construction plans, and equipment status to users through charts or graphical interfaces, providing visual decision support.
[0038] The present invention also discloses a computer device, including a memory and a processor, where the memory stores a computer program, and when the processor executes the computer program, the steps of the above-mentioned method for assessing construction safety risks on expressways are implemented.
[0039] A computer-readable storage medium, on which a computer program is stored, characterized in that: when the computer program is executed by a processor, the steps of the above-mentioned method for assessing construction safety risks on expressways are implemented.
[0040] Advantages of the present invention:
[0041] 1. The present invention introduces an intelligent analysis algorithm based on multi-dimensional data fusion. Through real-time acquired environmental data and construction equipment status data, combined with a deep neural network model, it can accurately predict potential risks at the construction site. In this process, the algorithm not only considers the current data input but also makes adaptive adjustments to historical data, improving the accuracy and reliability of the prediction.
[0042] 2. The present invention comprehensively uses a construction plan optimization model to reschedule the construction plan, considering the priorities of construction tasks, the quantity of construction equipment, construction period requirements, and real-time risk data, and intelligently adjusts parameters such as construction progress and resource allocation to ensure that under high-risk conditions, construction operations can be adjusted by dispatching additional personnel, delaying construction, adding temporary measures, etc., minimizing potential safety hazards and accident risks to the greatest extent. Description of the Drawings
[0043] To more clearly illustrate the technical solutions of the embodiments of the present invention, the following will briefly introduce the accompanying drawings required for the description of the embodiments. Obviously, the accompanying drawings in the following description are only some embodiments of the present invention. For those of ordinary skill in the art, without creative efforts, other accompanying drawings can be obtained based on these drawings. Among them:
[0044] Figure 1 It is a schematic diagram of the overall structure of a highway construction safety risk assessment method proposed by the present invention. Specific embodiments
[0045] To make the above objects, features, and advantages of the present invention more obvious and understandable, the following will make a detailed description of the specific embodiments of the present invention in conjunction with the accompanying drawings of the specification.
[0046] In the following description, many specific details are set forth to fully understand the present invention. However, the present invention can also be implemented in other ways different from those described herein. Those skilled in the art can make similar extensions without departing from the connotation of the present invention. Therefore, the present invention is not limited by the specific embodiments disclosed below.
[0047] Secondly, the so-called "one embodiment" or "embodiment" herein refers to a specific feature, structure, or characteristic that can be included in at least one implementation manner of the present invention. The phrase "in one embodiment" appearing in different places in this specification does not necessarily refer to the same embodiment, nor is it a separate or alternative embodiment that excludes other embodiments.
[0048] Refer to Figure 1 , which is an embodiment of the present invention, providing a highway construction safety risk assessment method. This method includes the following steps:
[0049] Step 1: Data collection. Install environmental sensors at the construction site to collect environmental data of the construction site in real time as the basis for risk assessment. Through the real-time nature of the collected data, the changes in the construction environment can be obtained in real time, and the risks can be quickly evaluated.
[0050] Step 2: Develop an intelligent analysis mechanism for the environmental data of the construction site. Based on the collected environmental data, use intelligent analysis algorithms to predict and judge the possible risks at the construction site and generate a risk report.
[0051] Specifically, the content included in the risk report includes: normalized environmental data, comprehensive environmental risk values, and the impact of predicted risks on the construction plan; the specific intelligent analysis mechanism includes:
[0052] S201: Normalize the risk factor E i (t), and the processing calculation formula is:
[0053]
[0054] Among them, E i (t) represents the real-time data of the i-th environmental factor, and u i represents the reference value of environmental factor i, such as the environmental parameters of common construction standards. Through f i (E i (t)), the normalized risk factor value is obtained, and the logarithmic function is used to smooth the impact of outliers on the whole;
[0055] S202: Combine multiple risk factors to calculate the overall environmental risk value R(t) of the construction site at a certain time t. The comprehensive risk value is calculated by weighted summation, and the calculation formula is:
[0056]
[0057] Among them, w i represents the weight of risk factor i, satisfying N represents that the priority of the construction plan is a positive number, and the higher the value, the more urgent it is.
[0058] S203: Quantify the impact of risk on the construction plan through a dynamic risk attenuation function. The expression of the dynamic risk attenuation function is: e -αR ( t ), where α represents the risk sensitivity adjustment coefficient, and the larger the value, the more significant the impact of risk on the plan.
[0059] If R(t) > the first threshold, it is determined that the risk at the construction site is a high risk, and protective measures are increased to reduce the risk or the construction is postponed; if R(t) < the second threshold, it is determined that the risk at the construction site is a low risk, and the existing construction plan is continued; if the second threshold ≤ R(t) ≤ the first threshold, it is determined that the risk at the construction site is a medium risk, and further monitoring is required and a temporary emergency plan is prepared, and resource investment is increased.
[0060] Through dynamic adjustment, the construction plan can be adjusted at any time according to risk data to ensure construction safety.
[0061] Step 3: Build an optimized construction plan model. Use the information in the risk report as the input of the optimized construction plan model. The optimized construction plan model gives adjustment suggestions again according to the priority of the construction tasks, the number of construction equipment, and the requirements of the construction period, combined with risk data, including: adding manpower, delaying construction, and increasing temporary measures to reduce risk.
[0062] Specifically, the optimized construction plan model combines environmental risk and resource utilization rate, and is defined as follows:
[0063]
[0064] Among them, P opt (t) represents the dynamic priority of the construction plan, T1 and T2 represent the construction time intervals, and G represents the constraint of resource utilization rate on the plan.
[0065] The priority of the construction plan is a positive number. The higher it is, the more urgent it is. The construction in the safety area is arranged first to reduce the construction period delay caused by accidental interruption.
[0066] The expression of the constraint G of the resource utilization rate on the plan is:
[0067]
[0068] Among them, U(t) represents the resource utilization rate, and β represents the resource constraint sensitivity. The larger the value, the greater the impact of the resource limit on the construction plan.
[0069] Reorder the construction plan according to the calculation result of the priority P opt (t), clarify the priority of the urgent tasks, and put forward the following specific adjustment suggestions:
[0070] Add temporary measures. If the priority P opt (t) is greater than the set priority threshold and R(t) > the first threshold, reduce the risk by setting protective measures;
[0071] Delay the construction. If the priority P opt (t) is lower than the set priority threshold and R(t) > the first threshold, stop the construction;
[0072] Dispatch more personnel. If the priority P opt (t) is greater than the set priority threshold and the second threshold ≤ R(t) ≤ the first threshold, mobilize additional resources to complete the task.
[0073] To verify the effectiveness of the present invention, a detailed embodiment is given below, including experimental data and data tables, to verify the effect of the invention scheme in practical applications.
[0074] A certain expressway is under construction, and there are various environmental factor interferences such as wind speed, rainfall, and temperature in the construction area. To improve the construction safety, the present invention scheme is adopted to conduct real-time environmental monitoring, intelligent analysis, and optimize the construction plan for the construction site.
[0075] By collecting the environmental data of the construction site and using the construction safety risk assessment method in the present invention, evaluate the effect of this method in reducing construction accidents and improving construction efficiency.
[0076] Table 1 shows part of the environmental data collected within five days and the risk assessment results generated by intelligent analysis
[0077]
[0078] According to the experimental data, Table 2 is a comparison table of safety and efficiency before and after optimization.
[0079] Time Number of accidents before optimization Number of accidents after optimization Project progress (before optimization) Project progress (after optimization) Day 1 3 1 60% 75% Day 2 4 2 62% 78% Day 3 2 1 65% 80% Day 4 3 1 58% 74% Day 5 3 0 59% 76%
[0080] Combined with the experimental data, it shows that after the construction plan is optimized, the number of accidents at the construction site has decreased significantly. Through the intelligent analysis mechanism, potential high-risk environments can be predicted and prevented, thereby reducing safety accidents caused by environmental factors, and the project progress has also been significantly improved. Through the comprehensive assessment of environmental risks, the construction plan is adjusted, and resources are reasonably allocated, resulting in a project progress improvement of approximately 10% - 15%. Through the implementation of the optimization plan, the construction safety and work efficiency at the construction site have been improved, verifying the effectiveness and practicality of the proposed solution of the present invention in practical applications.
[0081] An evaluation system applied to the above-mentioned method for evaluating safety risks in highway construction, the system includes the following modules:
[0082] A data collection module for collecting environmental data at the construction site in real time; an intelligent analysis and risk assessment module that uses the collected environmental data to analyze and evaluate potential risks at the construction site through intelligent algorithms. A construction plan optimization module that optimizes the construction plan according to the results of the risk assessment module, the priority of construction tasks, the availability of construction equipment, personnel allocation, and construction period requirements; a decision execution module that makes construction safety decisions based on the outputs of the intelligent analysis and risk assessment module and the construction plan optimization module, including whether to initiate a warning, whether to adjust the construction plan, and whether to dispatch additional personnel. And an information display and visualization module that displays information such as real-time data, risk assessment results, construction plans, and equipment status to users through charts or graphical interfaces, providing visual decision support.
[0083] This embodiment also provides a computer device applicable to the situation of a method for evaluating safety risks in highway construction, including: a memory and a processor; the memory is used to store computer-executable instructions, and the processor is used to execute the computer-executable instructions to implement a method for evaluating safety risks in highway construction as proposed in the above embodiment.
[0084] The computer device may be a terminal, which includes a processor, a memory, a communication interface, a display screen, and an input device connected via a system bus. Among them, the processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system and a computer program. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The communication interface of the computer device is used to communicate with an external terminal in a wired or wireless manner, and the wireless manner can be achieved through WIFI, a carrier network, NFC (Near Field Communication), or other technologies. The display screen of the computer device can be a liquid crystal display screen or an electronic ink display screen, and the input device of the computer device can be a touch layer covering the display screen, or buttons, a trackball, or a touchpad provided on the outer shell of the computer device, or an external keyboard, touchpad, or mouse, etc.
[0085] This embodiment also provides a storage medium, on which a computer program is stored. When the program is executed by a processor, it implements the method for evaluating the safety risks of highway construction proposed in the above embodiment; the storage medium can be implemented by any type of volatile or non-volatile storage device or a combination thereof, such as Static Random Access Memory (SRAM for short), Electrically Erasable Programmable Read-Only Memory (EEPROM for short), Erasable Programmable Read-Only Memory (EPROM for short), Programmable Read-Only Memory (PROM for short), Read-Only Memory (ROM for short), magnetic memory, flash memory, a magnetic disk, or an optical disc.
[0086] It should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention and not to limit them. Although the present invention has been described in detail with reference to the preferred embodiments, those of ordinary skill in the art should understand that the technical solutions of the present invention can be modified or equivalently replaced without departing from the spirit and scope of the technical solutions of the present invention, and they should all be covered by the scope of the claims of the present invention.
Claims
1. A method for evaluating the safety risks of highway construction, characterized in that, The method includes the following steps: Step 1: Data collection. Install environmental sensors at the construction site to collect the environmental data of the construction site in real time, which serves as the basis for risk assessment; Step 2: Develop an intelligent analysis mechanism for the environmental data of the construction site. According to the collected environmental data, use intelligent analysis algorithms to predict and judge the possible risks at the construction site and generate a risk report; Step 3: Build an optimized construction plan model. Use the information in the risk report as the input of the optimized construction plan model. The optimized construction plan model gives adjustment suggestions again according to the priority of construction tasks, the number of construction equipment, and the requirements of the construction period, in combination with risk data, including: adding more personnel, delaying construction, and increasing temporary measures to reduce risks.
2. The method for evaluating the construction safety risk of an expressway according to claim 1, wherein: The content included in the risk report includes: normalized environmental data, comprehensive environmental risk value, and the impact of predicted risks on the construction plan; The specific intelligent analysis mechanism includes: S201: Normalize the risk factor E i (t), and the processing calculation formula is: Among them, E i (t) represents the real-time data of the i-th environmental factor, and u i represents the reference value of environmental factor i, such as the environmental parameters of common construction standards. Through f i (E i (t)), the normalized risk factor value is used to smooth the impact of outliers on the whole with a logarithmic function; S202: Combine multiple risk factors to calculate the overall environmental risk value R(t) of the construction site at a certain time t. The calculation formula is: S203: Quantify the impact of risks on the construction plan through a dynamic risk attenuation function.
3. The method for evaluating the construction safety risk of an expressway according to claim 2, wherein: The expression of the dynamic risk attenuation function is: e -αR ( t ), where α represents the risk sensitivity adjustment coefficient, and the larger the value, the more significant the impact of the risk on the plan.
4. The method for evaluating construction safety risks of an expressway according to claim 3, characterized in that: If R(t) > the first threshold, it is determined that the risk at the construction site is a high risk, and protective measures are increased to reduce risks or construction is postponed; If R(t) < the second threshold, it is determined that the risk at the construction site is a low risk, and the existing construction plan is continued; If the second threshold ≤ R(t) ≤ the first threshold, it is determined that the risk at the construction site is a medium risk, and further monitoring is required and a temporary emergency plan is prepared, and resource investment is increased.
5. A method for evaluating the safety risks of highway construction according to claim 4, characterized in that: The optimized construction plan model comprehensively considers environmental risks and resource utilization rates, and is defined as follows: Among them, P opt (t) represents the dynamic priority of the construction plan, T1 and T2 represent the construction time intervals, and G represents the constraint of resource utilization rate on the plan.
6. The method for evaluating the construction safety risk of an expressway according to claim 5, characterized in that: The expression of the constraint G of the resource utilization rate on the plan is: Among them, U(t) represents the resource utilization rate, and β represents the resource constraint sensitivity. The larger the value, the greater the impact of resource constraints on the construction plan.
7. A method for evaluating the safety risks of highway construction according to claim 6, characterized in that: According to priority P opt (t) to reorder the construction plan, clarify the priorities of urgent tasks, and put forward specific adjustment suggestions as follows: Add temporary measures if the priority P opt (t) is greater than the set priority threshold and R(t) > the first threshold, and reduce the risk by setting protective measures; Construction delay, if priority P opt (t) is lower than the set priority threshold and R(t) > the first threshold, then stop construction; Dispatch additional personnel if the priority P opt (t) is greater than the set priority threshold, and the second threshold ≤ R(t) ≤ the first threshold, additional resources can be mobilized to complete the task.
8. An evaluation system applied to the highway construction safety risk assessment method according to claim 7, characterized in that: The system includes the following modules: A data collection module for collecting the environmental data of the construction site in real time; An intelligent analysis and risk assessment module that uses the collected environmental data to analyze and evaluate the potential risks at the construction site through intelligent algorithms; An optimized construction plan module that optimizes the construction plan according to the results of the risk assessment module, the priority of construction tasks, the availability of construction equipment, personnel allocation, and construction period requirements; A decision execution module that makes construction safety decisions based on the outputs of the intelligent analysis and risk assessment module and the optimized construction plan module, including whether to initiate an early warning, whether to adjust the construction plan, and whether to dispatch more personnel; And an information display and visualization module that displays information such as real-time data, risk assessment results, construction plans, and equipment status to users through charts or graphical interfaces, providing visual decision support.
9. A computer device, comprising a memory and a processor, the memory storing a computer program, characterized in that: When the processor executes the computer program, it implements the steps of a highway construction safety risk assessment method according to any one of claims 1 to 7.
10. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by the processor, it implements the steps of a highway construction safety risk assessment method according to any one of claims 1 to 7.