Precast beam plate sliding erection method and device
Through the prefabricated beam and slab sliding installation device, stable lateral movement of beam and slabs is achieved using equipment such as transverse rails and jacks, which solves the problem of construction site restrictions, improves construction efficiency and reduces costs, and reduces environmental damage.
Patent Information
- Application Number
- CN202510762889.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-06-09
- Publication Date
- 2025-07-22
AI Technical Summary
The existing technology lacks prefabricated beam slab erection methods that deal with small construction sites, such as steep terrain at the junction of bridges and tunnels, the impact of the tunnel entrance and tunnel clearance and width, resulting in the bridge erecting machine being unable to complete the beam lifting and beam mounting operations of side beams.
Prefabricated beam slab sliding erecting devices are adopted, including transverse tracks, transverse slides, reaction seats, limit plates and support and chain systems. The beam slabs are arranged horizontally through the tunnel opening, and the oil roof and jack are used to achieve stable displacement and fixation of the beam slabs.
The impact of restriction of the entrance site is reduced, construction efficiency is significantly improved, construction costs are reduced, and ecological damage to the environment is reduced.
Smart Images

Figure CN120350618A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of the erection construction of bridge engineering beam slabs, and particularly relates to a method and device for sliding erection of precast beam slabs. Background Art
[0002] In the current method, there are few construction methods for the erection of beam slabs at the openings of highway bridge tunnels. The common and frequently used construction methods are as follows: installing slides and trolleys on the abutment and capping beam, and using a bridge erection machine to cooperate in the erection of beam slabs; or directly using an engineering crane for the erection of beam slabs.
[0003] However, in the existing technology methods, due to the large volume and heavy weight of precast beam slabs, with a general weight of over 100 tons, the stability and safety during the sliding process need to be improved.
[0004] The main problem faced by the method of using an engineering crane for erection is that it has high requirements for the construction site. When the construction site has steep mountain cliff sections or terrain restrictions, it is directly impossible to use an engineering crane to cooperate to complete the construction.
[0005] Obviously, in the existing technology, there is a lack of a method for erecting precast beam slabs to cope with small construction sites, such as the steep terrain restrictions at the connection of bridges and tunnels, and the influence restrictions of the open cut and tunnel clearance and width at the tunnel entrance. This makes it impossible for the bridge erection machine to directly complete the beam lifting and erection operations of the side beams, and the on-site terrain conditions also cannot meet the requirements for crane beam erection.
[0006] Obviously, for the above technical problems, there is an urgent need to propose a solution to cope with the beam slab erection method. Summary of the Invention
[0007] The present invention aims to solve the technical problem in the existing technology that there is a lack of a method for erecting precast beam slabs to cope with small construction sites, such as the steep terrain restrictions at the connection of bridges and tunnels, and the influence restrictions of the open cut and tunnel clearance and width at the tunnel entrance, and provides a method and device for sliding erection of precast beam slabs.
[0008] To solve the above technical problems, the technical solution of the present invention is specifically as follows:
[0009] Firstly: A method for erecting a device for sliding erection of precast beam slabs, including the following steps:
[0010] Step S101, during the construction of the abutment 1, after embedding steel bars at the middle block 2a position of the adjacent side beam 2, temporarily not pouring concrete, and using a transverse sliding beam erection device 100.
[0011] Step S102, install and fix a transverse movement track 10 at 25 - 35 cm inside the abutment 1, and one end of the transverse movement track 10 is close to the middle block 2a.
[0012] Step S103: Install a transverse sliding plate 20, a limiting plate 30, and a reaction seat 40 on the transverse movement track 10;
[0013] Adjust the position of the reaction seat 40 according to the maximum distance that the bridge erecting machine 1a can move horizontally to ensure that the bridge erecting machine 1a can place the beam slab 3 on the transverse sliding plate 20;
[0014] After the adjustment of the position is completed, fix the reaction seat 40 and the limiting plate 30 by using the pin 40a for fixing, and install a hydraulic jack 50;
[0015] Step S104: Transport the beam slab 3 to the tail of the bridge erecting machine 1a for beam feeding and beam erection operations;
[0016] Step S105: The bridge erecting machine 1a carries the beam slab 3 and moves horizontally, and places both ends of the beam slab 3 on the transverse sliding plate 20 of the transverse sliding beam erection device 100;
[0017] Step S106: Adopt the installation of a support rod 60 and a wire rope hoist 4 for tight connection to fix the beam body of the beam slab 3 to ensure the stability of the beam slab 3 on the transverse sliding beam erection device 100;
[0018] The on-site operators check and confirm the stability of the hydraulic jack 50 and the beam slab 3;
[0019] Step S107: When it is confirmed that the beam slab 3 is stable on the transverse sliding beam erection device 100, use the hydraulic jack 50 to slowly push the beam slab 3 carried by the transverse sliding plate 20 as a whole towards the target side;
[0020] Adjust the positions of the reaction seat 40 and the hydraulic jack 50 towards the target side, and repeat the above operations to gradually slide the side beam of the beam slab 3 to the designed position;
[0021] Step S108: After the side beam of the beam slab 3 reaches the designed position;
[0022] Install on the bottom of the beam slab 3: a first jack 1-1 and a second jack 2-2 with a specification of 100t;
[0023] Through the jacking action of the first jack 1-1 and the second jack 2-2, the beam slab 3 is separated from the transverse sliding plate 20 of the transverse sliding beam erection device 100, and then the whole transverse sliding beam erection device 100 is removed;
[0024] Step S109: Use the first jack 1-1 and the second jack 2-2 to lower the beam;
[0025] After the beam drops, install and arrange round log struts on the outer side of the beam body, move the first jack 1-1 at the bottom plate position to the end cross diaphragm 5, and then remove the second jack 2-2; use the first jack 1-1 to ensure the stability of the side beam.
[0026] Specifically, the transverse movement track 10 is a steel rail 11 of P50 specification;
[0027] The reaction seat 40 includes:
[0028] A seat body 41, which is connected with a seat body rail connection part 42 below, and the seat body rail connection part 42 is rail-connected on the steel rail 11;
[0029] A pin slot 43 is arranged on the side surface of the seat body rail connection part 42, a plurality of pin holes 43 are uniformly arranged on the side surface of the steel rail 11, and the pin 40a can be stuck into the pin slot 43 and penetrate into the pin hole 43;
[0030] The seat body 41 is constructed as a right triangle, and a configuration area 401 is formed between the upper surface of the seat body 41 and the seat body rail connection part 42.
[0031] Specifically, the transverse movement slide plate 20 includes:
[0032] A track connection part 21, which can be rail-connected on the steel rail 11;
[0033] A transverse movement slide plate bearing part 22, which constructs a receiving groove 22a for supporting the beam slab 3; and
[0034] A transverse movement slide plate traction part 24, which is arranged adjacent to the transverse movement slide plate bearing part 22, and the transverse movement slide plate traction part 24 constructs a V-shaped groove 24a.
[0035] Specifically, it further includes a limit plate 30, which is fixedly connected to the steel rail 11 through a pin 40a;
[0036] Among them, on the steel rail 11, the right-angle end of the seat body 41, the V-shaped groove 24a, the receiving groove 22a, and the limit plate 30 are arranged in sequence, and the direction from the seat body 41 to the limit plate 30 is the preset movement direction.
[0037] Specifically, the support rod 60 includes:
[0038] A support rod body 61, the first end of which is a support end for supporting at the included angle between the beam rib and the flange of the beam slab 3;
[0039] The second end of the support rod body 61 is connected with a rolled threaded steel column 62, and a rolled threaded steel adjusting nut 63 is arranged on the rolled threaded steel column 62;
[0040] The second end of the precision rolled threaded steel column 62 is connected within the V-shaped groove 24a.
[0041] Specifically, the transverse movement slide plate traction member 24 has a pushing plate 24b, and the height of the pushing plate 24b is greater than the height of the V-shaped groove 24a;
[0042] A connection hole 24c is formed at the first end of the pushing plate 24b. One end of the wire rope hoist 4 is connected to the flange edge of the beam slab 3 and is tightened against the flange surface and connected within the connection hole 24c.
[0043] Specifically, the oil jack 50 has a pushing end 50a. The oil jack 50 is horizontally arranged and installed within the configuration area 401 such that the pushing end 50a faces the pushing surface of the pushing plate 24b.
[0044] Specifically, it includes: in step S107, after the oil jack is pushed forward by a preset distance, the movement stops;
[0045] The selection range of the preset distance is 10 cm, 15 cm, 20 cm, 25 cm.
[0046] Specifically, in step S102, a support 10a is placed under the bottom of the transverse movement track 10 to ensure the flatness of the track bottom surface;
[0047] Wherein, the support is a wooden board or a steel plate.
[0048] On the other hand, a precast beam slab sliding erection device is proposed, including:
[0049] A transverse movement slide plate 20, whose trajectory is on the transverse movement track 10 and is used to carry the beam slab 3;
[0050] A limiting plate 30, which is fixedly connected to the transverse movement track 10 and is used to limit the maximum movement distance of the transverse movement slide plate 20; and
[0051] A support and chain system, which is used to provide partial support for the carried beam slab 3 and use a wire rope hoist 4 to tighten the beam slab 3, so that an oil jack 50 of a reaction force pushing system uses the position fixed on the transverse movement track 10 by the reaction force seat 40 as a support point to push the transverse movement slide plate 20 to move a movement distance.
[0052] The present invention has the following beneficial effects:
[0053] In the first aspect, this technical solution can directly dispense with the cooperation of engineering cranes. By horizontally erecting beam slabs at the tunnel entrance, the influence of limited site at the entrance is reduced, the influence on the construction site for implementing this technical solution is greatly reduced, and the construction efficiency can be significantly improved. This method causes less damage to the ecological environment and has advantages in environmental protection, and can also greatly improve the erection efficiency of beam slabs.
[0054] In the second aspect, compared with the traditional beam erection construction method, the construction cost of this technical solution can be reduced, and the problem of erecting side beams when the tail of the bridge erection machine is restricted by the site and cannot be horizontally displaced is overcome, ultimately reducing the erection cost of each beam. BRIEF DESCRIPTION OF THE DRAWINGS
[0055] The present invention will be further described in detail below with reference to the drawings and specific embodiments.
[0056] Figure 1 It is a schematic flow diagram of the method of the present invention;
[0057] Figure 2 It is a schematic diagram of the horizontal sliding beam erection device of the present invention;
[0058] Figure 3 It is a schematic diagram of the implementation mode of the horizontal sliding plate of the present invention;
[0059] Figure 4 It is a schematic diagram of the implementation mode of the bridge erection machine and the beam slab;
[0060] Figure 5 It is a schematic diagram of the configuration of the second jack of the present invention;
[0061] Figure 6 It is a schematic diagram of the configuration of the first jack of the present invention.
[0062] The reference numerals in the drawings are represented as:
[0063] Abutment 1, side beam 2, middle block 2a, horizontal sliding beam erection device 100;
[0064] Horizontal movement track 10, middle block 2a;
[0065] Horizontal sliding plate 20, limit plate 30, reaction seat 40;
[0066] Bridge erection machine 1a, beam slab 3;
[0067] Pin 40a, oil jack 50;
[0068] Support rod 60, wire rope hoist 4;
[0069] End cross diaphragm 5, first jack 1-1, second jack 2-2;
[0070] Rail 11;
[0071] Seat body 41, seat body rail connection part 42, pin slot 44, pin hole 43, configuration area 401;
[0072] Track connection part 21, connection part pin slot 23;
[0073] Transverse sliding plate bearing part 22, accommodation groove 22a, transverse sliding plate traction component 24, V-shaped groove 24a;
[0074] Support rod body 61, precision rolled threaded steel column 62, precision rolled threaded steel adjusting nut 63;
[0075] Pushing plate 24b, connection hole 24c;
[0076] Pushing end 50a, support 10a. Specific implementation manner
[0077] The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention. It should be noted that for the convenience of description in this application, the "left side" in the current view is taken as the "first end", the "right side" as the "second end", the "upper side" as the "first end", and the "lower side" as the "second end". The purpose of such description is to clearly express the technical solution and should not be construed as an improper limitation of the technical solution of this application.
[0078] The present invention aims to solve the technical problem of the lack of a method for erecting precast beam slabs in the prior art that can cope with small construction sites, such as the limitations caused by the steep terrain at the junction of bridges and tunnels, the influence of the open cut at the tunnel entrance and the tunnel clearance and width. A method and device for sliding erection of precast beam slabs are provided.
[0079] The content of the present invention is actually based on the practical application of the WYTJ-04 section project of the Xinjiang Urumqi-Yecheng Highway Package PPP project undertaken by the applicant. The actual construction content reduces the influence of limited site at the tunnel entrance, effectively improves the beam slab erection efficiency, and reduces the beam erection cost. At the same time, this method has less damage to the ecological environment. The situation of the project actually undertaken by the present invention is that the terrain at the junction of bridges and tunnels is steep. Due to the influence of the open cut at the tunnel entrance and the tunnel clearance and width, the gantry crane cannot directly complete the beam lifting and erection operations for the side beams, and the on-site terrain conditions also cannot meet the requirements for crane beam erection;
[0080] To this end, the technical solution of the present invention is based on the construction method of erecting beam slabs by a bridge girder erecting machine. On this basis, a transverse sliding beam erecting device 100 is adopted to achieve the smooth erection of precast beam slabs 3 under limited topographic and in-cave site conditions. The transverse sliding beam erecting device 100 includes:
[0081] A transverse movement track 10, a transverse sliding plate 20, a limit plate 30, a reaction seat 40, a fixing pin 40a for use, a wire rope hoist 4, and a support rod 60. Specifically:
[0082] The transverse sliding plate 20 has a track on the transverse movement track 10 and is used to carry the beam slab 3;
[0083] The limit plate 30 is fixedly connected to the transverse movement track 10 and is used to limit the maximum movement distance of the transverse sliding plate 20; and
[0084] A support and chain system is used to provide partial support for the carried beam slab 3 and use the wire rope hoist 4 to tighten the beam slab 3, so that a hydraulic jack 50 of a reaction force pushing system uses the position of the reaction seat 40 fixed on the transverse movement track 10 as a support point to push the transverse sliding plate 20 to move a certain action distance.
[0085] In a specific embodiment, please refer to Figure 1 、 2 As shown, the main features of the method part are:
[0086] (1) The transverse sliding plate 20 and the reaction seat 40 are formed by welding steel plates and are placed on the pre-erected transverse movement track 10. The lower part of the transverse movement track 10 uses templates and steel plates as its support, and it is necessary to ensure flatness;
[0087] (2) The support and chain system belongs to a temporary support system and is used for beam slab transverse movement operations after installation;
[0088] Before transverse movement, it is necessary to first reinforce and support the beam slab with the wire rope hoist 4 and the support rod 60 to ensure the stability of the beam body;
[0089] The bottom of the hydraulic jack 50 is abutted against the reaction seat 40, and the top of the hydraulic jack 50 abuts against the pulley to exert force to push the pulley forward. Since the displacement of the beam movement is relatively long, the hydraulic jack 50 cannot reach the designated position at one time. It is necessary to move the reaction seat 40 towards the beam slab and fix it after each jacking, and then the hydraulic jack 50 abuts against it and pushes forward. Repeat the cycle until the beam slab reaches the designated position; since jacks are used to move the beam at both ends of the beam along the sliding tracks, it is necessary to ensure that the propulsion error of the jacks at both ends is less than 10 cm.
[0090] (3) After the precast beam and slab are horizontally moved to the designated position, they are supported by two 100t jacks at the bottom of the beam and slab, and the side wings can also be supported by jacks. After ensuring that the beam body is horizontally moved in place, the fixed chain hoist and steel pipe support are removed, the slide rail jack is depressurized, and the beam and slab are installed. The specific detailed method is to provide an erection method for a precast beam and slab sliding erection device, including the following steps:
[0091] Step S101, during the construction of the abutment 1, after embedding steel bars at the middle block 2a position of the adjacent side beam 2, the concrete is not poured temporarily, and a horizontal sliding beam erection device 100 is adopted;
[0092] Step S102, at 25 - 35 cm inside the abutment 1, a horizontal movement track 10 is installed and fixed, and one end of the horizontal movement track 10 is close to the middle block 2a;
[0093] Step S103, install a horizontal movement slide plate 20, a limit plate 30, and a reaction seat 40 on the horizontal movement track 10;
[0094] Adjust the position of the reaction seat 40 according to the maximum distance that the bridge erection machine 1a can move horizontally to ensure that the bridge erection machine 1a can place the beam and slab 3 on the horizontal movement slide plate 20;
[0095] After the position adjustment is completed, fix the reaction seat 40 and the limit plate 30 by using the fixing method of the pin 40a, and install an oil jack 50;
[0096] Step S104, transport the beam and slab 3 to the tail of the bridge erection machine 1a for beam feeding and beam erection operations;
[0097] Step S105, the bridge erection machine 1a carries the beam and slab 3 horizontally and places the two ends of the beam and slab 3 on the horizontal movement slide plate 20 of the horizontal sliding beam erection device 100;
[0098] Step S106, use the installation of the support rod 60 and the wire rope hoist 4 chain tightening connection method to fix the beam body of the beam and slab 3 to ensure the stability of the beam and slab 3 on the horizontal sliding beam erection device 100;
[0099] The on-site operators check and confirm the stability of the oil jack 50 and the beam and slab 3;
[0100] Step S107, when it is confirmed that the beam and slab 3 are stable on the horizontal sliding beam erection device 100, use the oil jack 50 to slowly push the beam and slab 3 carried by the horizontal movement slide plate 20 as a whole towards the target side;
[0101] Adjust the positions of the reaction seat 40 and the oil jack 50 towards the target side, repeat the above operations, and gradually slide the side beam of the beam and slab 3 to the designed position;
[0102] Step S108, after the side beam of the beam and slab 3 reaches the designed position;
[0103] Install at the bottom of the beam-slab 3: the first jack 1-1 and the second jack 2-2 with a specification of 100t.
[0104] Through the lifting actions of the first jack 1-1 and the second jack 2-2, the beam-slab 3 is disengaged from the transverse sliding plate 20 of the transverse sliding beam erection device 100, and then the transverse sliding beam erection device 100 is removed as a whole.
[0105] Step S109, use the first jack 1-1 and the second jack 2-2 to lower the beam.
[0106] After lowering the beam, install and arrange round log diagonal braces on the outside of the beam body, move the first jack 1-1 at the bottom plate position to the end cross diaphragm 5, and then remove the second jack 2-2; use the first jack 1-1 to ensure the stability of the side beam.
[0107] On the first hand, this technical solution can directly abandon the cooperation of engineering cranes, erect the beam-slab horizontally through the tunnel entrance, reduce the influence caused by the limited site at the entrance, greatly reduce the influence on the construction site for implementing this technical solution, and can significantly improve the construction efficiency. This method has less damage to the ecological environment and also has advantages in environmental protection, and can also greatly improve the erection efficiency of the beam-slab.
[0108] On the second hand, compared with the traditional beam erection construction method, the construction cost of this technical solution can be reduced, and the problem of erecting the side beam when the tail of the bridge erecting machine is restricted by the site and cannot be horizontally moved is overcome, and finally the erection cost of each beam is reduced.
[0109] In a specific embodiment, please refer to Figure 2 As shown: the transverse movement track 10 is a steel rail 11 with a P50 specification.
[0110] The reaction support 40 includes:
[0111] A seat body 41, which is connected with a seat body rail connection part 42 below, and the seat body rail connection part 42 is rail-connected to the steel rail 11.
[0112] A pin slot 44 is arranged on the side of the seat body rail connection part 42, and a plurality of pin holes 43 are evenly arranged on the side of the steel rail 11. The pin 40a can be stuck into the pin slot 44 and penetrate into the pin hole 43.
[0113] The seat body 41 is constructed as a right triangle, and a configuration area 401 is formed on the upper surface of the seat body 41 and the seat body rail connection part 42.
[0114] In a specific embodiment, please refer to Figures 1 - 6 As shown:
[0115] The transverse sliding plate 20 includes:
[0116] The track connection part 21, which can be track-connected to the steel rail 11;
[0117] The transverse movement slide plate bearing part 22, which constructs a receiving groove 22a for supporting the beam slab 3; and
[0118] The transverse movement slide plate traction component 24, which is arranged adjacent to the transverse movement slide plate bearing part 22, and the transverse movement slide plate traction component 24 constructs a V-shaped groove 24a.
[0119] In a specific embodiment, please refer to Figures 1 - 6 as shown:
[0120] It further includes a limit plate 30, which is fixedly connected to the steel rail 11 through a pin 40a;
[0121] Wherein, on the steel rail 11, the right-angle end of the seat body 41, the V-shaped groove 24a, the receiving groove 22a, and the limit plate 30 are arranged in sequence, and the direction from the seat body 41 to the limit plate 30 is the preset movement direction.
[0122] In a specific embodiment, please refer to Figure 2 as shown, the support rod 60 includes:
[0123] The support rod body 61, whose first end is the support end for supporting at the included angle between the beam rib and the flange of the beam slab 3;
[0124] The second end of the support rod body 61 is connected to a precision rolled threaded steel column 62, and a precision rolled threaded steel adjusting nut 63 is arranged on the precision rolled threaded steel column 62;
[0125] The second end of the precision rolled threaded steel column 62 is connected in the V-shaped groove 24a.
[0126] In a specific embodiment, please refer to Figures 1 - 6 as shown:
[0127] The transverse movement slide plate traction component 24 has a push plate 24b, and the height of the push plate 24b is greater than the height of the V-shaped groove 24a;
[0128] The first end of the push plate 24b forms a connection hole 24c, and one end of the wire rope hoist 4 is connected to the edge of the flange of the beam slab 3 and is tightened against the flange surface and connected in the connection hole 24c.
[0129] In a specific embodiment, please refer to Figures 1 - 6 as shown:
[0130] The oil jack 50 has a push end 50a, and the oil jack 50 is horizontally arranged and installed in the configuration area 401 so that the push end 50a faces the push surface of the push plate 24b.
[0131] In a specific embodiment, please refer toFigure 1 , 2 As shown in 2 , in step S107, when the oil jack is pushed forward by a preset distance, the movement is stopped;
[0132] The selection range of the preset distance is 10 cm, 15 cm, 20 cm, 25 cm, and the embodiment parameter in the actual project application is 20 cm.
[0133] In a specific embodiment, please refer to Figure 1 , 5 , as shown in 5 and 6, in step S102, a support 10a is placed under the bottom of the transverse movement track 10 to ensure that the bottom surface of the track is flat; wherein, the support is a wooden board or a steel plate.
[0134] Obviously, the above embodiments are merely examples for clear illustration and are not limitations on the implementation manners. For those of ordinary skill in the art, other different forms of changes or variations can be made based on the above description. It is not necessary and impossible to list all the implementation manners here. And the obvious changes or variations derived therefrom are still within the protection scope of the present invention.
Claims
1. Erection method of a precast beam and slab sliding erection device, characterized in that, It includes the following steps: In step S101, during the construction of the abutment (1), after embedding steel bars at the position of the middle retaining block (2a) of the adjacent side beams (2), the concrete is not poured temporarily, and a transverse sliding beam erection device (100) is adopted; In step S102, at a position 25 - 35 cm inside the abutment (1), a transverse movement track (10) is installed and fixed, and one end of the transverse movement track (10) is close to the middle retaining block (2a); In step S103, a transverse movement slide plate (20), a limit plate (30), and a reaction seat (40) are installed on the transverse movement track (10); Adjust the adjustment position of the reaction seat (40) according to the maximum distance that the bridge erection machine (1a) can move horizontally to ensure that the bridge erection machine (1a) can place the beam slab (3) on the transverse movement slide plate (20); After the adjustment position is adjusted, the reaction seat (40) and the limit plate (30) are fixed by using the fixing method of the pin (40a), and an oil jack (50) is installed; In step S104, the beam slab (3) is transported to the tail of the bridge erection machine (1a) for beam feeding and beam erection operations; In step S105, the bridge erection machine (1a) carries the beam slab (3) and moves horizontally, and places both ends of the beam slab (3) on the transverse movement slide plate (20) of the transverse sliding beam erection device (100); In step S106, the beam body of the beam slab (3) is fixed by adopting the connection method of installing the support rod (60) and the wire rope hoist (4) to ensure the stability of the beam slab (3) on the transverse sliding beam erection device (100); The on-site operators check and confirm the stability of the oil jack (50) and the beam slab (3); In step S107, when it is confirmed that the beam slab (3) is stable on the transverse sliding beam erection device (100), the oil jack (50) is used to slowly push the beam slab (3) carried by the transverse movement slide plate (20) as a whole towards the target side; Adjust the positions of the reaction seat (40) and the oil jack (50) towards the target side, repeat the above operations, and gradually slide the side beam of the beam slab (3) to the designed position; In step S108, after the side beam of the beam slab (3) reaches the designed position; Install: a first jack (1 - 1) and a second jack (2 - 2) with a specification of 100t at the bottom of the beam slab (3); Through the jacking action of the first jack (1 - 1) and the second jack (2 - 2), the beam slab (3) is separated from the transverse movement slide plate (20) of the transverse sliding beam erection device (100), and then the transverse sliding beam erection device (100) is removed as a whole; In step S109, the first jack (1 - 1) and the second jack (2 - 2) are used for beam lowering; After beam lowering, round log diagonal braces are installed and arranged on the outer side of the beam body, the first jack (1 - 1) at the bottom plate position is moved to the end transverse diaphragm (5), and then the second jack (2 - 2) is removed; the first jack (1 - 1) is used to ensure the stability of the side beam.
2. The erection method of the precast beam and slab sliding erection device according to claim 1, characterized in that The transverse movement track (10) is a rail (11) of P50 specification; The reaction seat (40) includes: The seat body (41) is connected with a seat body rail connection part (42) below it, and the seat body rail connection part (42) is rail-connected to the steel rail (11). A pin slot (44) is arranged on the side surface of the seat body rail connection part (42), and a plurality of pin holes (43) are evenly arranged on the side surface of the steel rail (11). The pin (40a) can be stuck into the pin slot (44) and penetrate into the pin hole (43). The seat body (41) is configured as a right triangle, and an arrangement area (401) is formed on the upper surface of the seat body (41) and the seat body rail connection part (42).
3. The erection method of the precast beam and slab sliding erection device according to claim 2, characterized in that The transverse movement slide plate (20) includes: A track connection part (21) which can be rail-connected to the steel rail (11). A transverse movement slide plate bearing part (22) which constructs a receiving groove (22a) for supporting the beam slab (3); and A transverse movement slide plate traction component (24) which is arranged adjacent to the transverse movement slide plate bearing part (22), and the transverse movement slide plate traction component (24) constructs a V-shaped groove (24a).
4. The erection method of the precast beam and slab sliding erection device according to claim 3, characterized in that A limiting plate (30) is further included, which is fixedly connected to the steel rail (11) through a pin (40a). Wherein, on the steel rail (11), the right-angle end of the seat body (41), the V-shaped groove (24a), the receiving groove (22a), and the limiting plate (30) are arranged in sequence, and the direction from the seat body (41) to the limiting plate (30) is the preset movement direction.
5. The erection method of the precast beam and slab sliding erection device according to claim 4, characterized in that, The support rod (60) includes: A support rod body (61) whose first end is a support end for supporting at the included angle between the beam rib and the flange of the beam slab (3). The second end of the support rod body (61) is connected with a precision rolled threaded steel column (62), and a precision rolled threaded steel adjusting nut (63) is arranged on the precision rolled threaded steel column (62). The second end of the precision rolled threaded steel column (62) is connected in the V-shaped groove (24a).
6. The erection method of the precast beam and slab sliding erection device according to claim 5, characterized in that, The transverse movement slide plate traction component (24) has a push plate (24b), and the height of the push plate (24b) is greater than the height of the V-shaped groove (24a). A connection hole (24c) is formed at the first end of the push plate (24b), and one end of the wire rope hoist (4) is connected to the edge of the flange of the beam slab (3) and is tightened against the flange surface and connected in the connection hole (24c).
7. The erection method of the precast beam and slab sliding erection device according to claim 6, characterized in that, The oil jack (50) has a push end (50a), and the oil jack (50) is horizontally arranged and installed in the arrangement area (401) so that the push end (50a) faces the push surface of the push plate (24b).
8. The erection method of the precast beam and slab slipping erection device according to claim 7, characterized in that Including: In step S107, when the oil jack is pushed forward by a preset distance, stop moving. The selection range of the preset distance is 10 cm, 15 cm, 20 cm, 25 cm.
9. The erection method of the precast beam and slab sliding erection device according to claim 6, characterized in that, In step S102, a support (10a) is placed under the bottom of the transverse movement track (10) to ensure the flatness of the track bottom surface. Wherein, the support is a wooden board or a steel plate.
10. A precast beam-slab sliding erection device, characterized in that, Including: A transverse movement slide plate (20) whose track is on the transverse movement track (10) and is used for carrying the beam slab (3). The limit plate (30) is fixedly connected to the transverse movement track (10) and is used to limit the maximum movement distance of the transverse movement slide plate (20); and The support and chain system is used to provide partial support for the beam slab (3) carried thereon and to tighten the beam slab (3) by using a wire rope hoist (4), so that the oil jack (50) of a reaction force pushing system uses the position where the reaction force seat (40) is fixed on the transverse movement track (10) as a support point to push the transverse movement slide plate (20) to move an action distance.
Citation Information
Patent Citations
Girder erection construction method suitable for special space and auxiliary girder moving equipment
CN109440653A
Construction method for connecting bridge with T beam
CN110886233A
Method for erecting first-span T beam at tunnel exit
CN113322819A
Tunnel portal girder erection construction method
CN117587722A
Precast beam transverse moving device
CN213328694U