Construction method of annular building

By using finite element software and three-dimensional scanning technology in ring building construction, the deformation of steel structures and concrete structures is monitored in real time and the construction plan is dynamically adjusted, the construction progress and quality problems are solved to ensure safety.

CN120401658APending Publication Date: 2025-08-01SHANGHAI MECHANIZED CONSTR GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510505899.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-04-22
Publication Date
2025-08-01

AI Technical Summary

Technical Problem

In the prior art, during the construction process of steel structures, concrete structures and curtain wall structures, the actual situation deviates from the simulation results, resulting in slow construction progress, poor quality, and may even cause safety accidents.

Method used

The main model is established using finite element software, and the deformation of the steel structure and concrete structure are monitored through three-dimensional scanning, and the construction plan is adjusted in a timely manner to ensure that the theoretical deformation of each structure is consistent with the actual deformation, and the construction plan of the curtain wall structure is dynamically adjusted.

Benefits of technology

Through real-time monitoring and adjustment of construction plans, we can reduce construction errors, ensure progress and quality, avoid safety accidents, and improve construction efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120401658A_ABST
    Figure CN120401658A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of building construction, and discloses a construction method of an annular building, which comprises the following steps: firstly, determining the construction sequence and construction requirements of a steel structure, a concrete structure and a curtain wall structure, then establishing a main model, analyzing and calculating, setting a construction scheme according to a calculation structure, and constructing each structure in sequence, after construction of each structure is completed, whether the deformation quantity of the structure is consistent with the theoretical deformation quantity or not is compared, if yes, construction continues according to the current construction scheme, and if not, the deformation quantity of the structure is substituted into the main model, analysis and calculation are conducted again, and construction continues after the construction scheme is adjusted. According to the construction method of the annular building, the constructed structure is monitored in real time in the whole construction process, so that the construction scheme can be adjusted in time according to the actual situation, the construction progress and the working efficiency are guaranteed, the construction quality is prevented from being affected, and safety accidents are avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of building construction, and particularly to a construction method for a circular building. Background Art

[0002] In building engineering, in order to improve the overall performance and functionality of a building, the building is usually designed as a steel-concrete structure building, that is, a steel structure and a concrete structure are combined to form a composite stress system, which improves the overall bearing capacity, reduces the amount of materials used, and a curtain wall is installed on the steel-concrete structure to improve the aesthetics of the building.

[0003] In the prior art, when constructing a steel structure, a concrete structure, and a curtain wall structure, the construction process is usually simulated in advance, and each part is constructed in sequence according to the simulation results. After the construction is completed, the overall deformation of the building is monitored. However, there are usually deviations between the actual construction conditions of each part and the simulation results. If the construction plan is not adjusted in time and the construction is still carried out according to the simulation results, on the one hand, it will hinder the construction of subsequent structures, affect the construction progress, and reduce the construction efficiency. On the other hand, it may affect the construction quality, and in severe cases, it may even cause safety accidents. Summary of the Invention

[0004] The purpose of the present invention is to provide a construction method for a circular building, which can adjust the construction plan in time, ensure the construction progress and work efficiency, prevent the construction quality from being affected, and avoid causing safety accidents.

[0005] To achieve the above object, the present invention adopts the following technical solutions:

[0006] Provide a construction method for a circular building. The circular building includes a steel structure, a concrete structure, and a curtain wall structure. The construction method of the circular building includes:

[0007] S1. Determine the construction sequence and construction requirements of the steel structure, the concrete structure, and the curtain wall structure;

[0008] S2. Use finite element software to establish a main model. The main model includes a steel structure model part, a concrete structure model part, and a curtain wall structure model part. Analyze and calculate the main model to obtain the theoretical deformation amount of the steel structure model part, the theoretical deformation amount of the concrete structure model part, and the theoretical deformation amount of the curtain wall structure model part, and set the construction plans of the steel structure, the concrete structure, and the curtain wall structure accordingly;

[0009] S3. Construct the steel structure according to the existing construction plan;

[0010] S4. After the construction of the steel structure is completed, use a scanning device to perform three-dimensional scanning on the steel structure and record the position of the steel structure, and thereby calculate the deformation amount of the steel structure;

[0011] S5. Determine whether the deformation of the steel structure is consistent with the theoretical deformation of the steel structure model part. If not, execute S6 and S7; if so, directly execute S7.

[0012] S6. Substitute the deformation of the steel structure into the steel structure model part, and re-analyze and calculate the main model to obtain the theoretical deformation of the new concrete structure model part and the theoretical deformation of the new curtain wall structure model part, and adjust the construction plans of the concrete structure and the curtain wall structure accordingly.

[0013] S7. Construct the concrete structure according to the existing construction plan.

[0014] S8. After the construction of the concrete structure is completed, use the scanning device to perform three-dimensional scanning on the concrete structure and record the position of the concrete structure, thereby calculating the deformation of the concrete structure.

[0015] S9. Determine whether the deformation of the concrete structure is consistent with the theoretical deformation of the new concrete structure model part. If not, execute steps S10 and S11; if so, directly execute S11.

[0016] S10. Substitute the deformation of the concrete structure into the concrete structure model part, re-analyze and calculate the main model, and obtain the theoretical deformation of the new curtain wall structure model part again, and adjust the construction plan of the curtain wall structure accordingly.

[0017] S11. Construct the curtain wall structure according to the existing construction plan.

[0018] Optionally, step S2 specifically includes the following steps:

[0019] S21. Establish the main model using finite element software according to the engineering design. The main model includes a steel structure model part, a concrete structure model part, and a curtain wall structure model part.

[0020] S22. Analyze and calculate the main model in stages according to the construction sequence to obtain the theoretical deformation of the steel structure model part, the theoretical deformation of the concrete structure model part, and the theoretical deformation of the curtain wall structure model part.

[0021] Optionally, step S2 further includes:

[0022] S23. Individually analyze and calculate multiple nodes of the main model.

[0023] S24. Optimize the construction plan according to the calculation results of the nodes.

[0024] Optionally, the steel structure includes a steel structure main body, a first temporary support, and a second temporary support. One end of the first temporary support is connected to the lower surface of the steel structure main body, and the other end is configured to be set on the ground. The second temporary support is disposed on the upper surface of the steel structure main body and is connected to the front end of the steel structure main body. The second temporary support is used to vertically lift the steel structure main body upward.

[0025] Optionally, step S3 specifically includes the following steps:

[0026] S31. Erect the steel structure main body, the first temporary support, and the second temporary support according to the calculation results of the main model;

[0027] S32. Perform a simulation analysis on a part of the steel structure main body in the area with a larger span to obtain the downward deflection of the steel structure main body in the area with a larger span;

[0028] S33. Determine whether the downward deflection of the steel structure main body in the area with a larger span is greater than l0 / 400 (l0 is the span of the steel structure main body). If so, execute S34; if not, execute S4;

[0029] S34. Set the first temporary support and the second temporary support in this area.

[0030] Optionally, step S7 specifically includes the following steps:

[0031] S71. Remove the first temporary support and the second temporary support, and erect permanent supports. The steel structure main body is disposed on the permanent supports;

[0032] S72. Use a scanning device to perform a three-dimensional scan on the steel structure again and record the position of the steel structure, thereby calculating the latest deformation amount of the steel structure;

[0033] S73. Determine whether the latest deformation amount of the steel structure is consistent with the theoretical deformation amount of the latest steel structure model part. If not, execute S74 and S75; if so, directly execute S75;

[0034] S74. Substitute the latest deformation amount of the steel structure into the steel structure model part, and re-analyze and calculate the main model to obtain the theoretical deformation amounts of the latest concrete structure model part and the curtain wall structure model part, and adjust the construction plans of the concrete structure and the curtain wall structure accordingly;

[0035] S75. Construct the concrete structure according to the existing construction plan.

[0036] Optionally, the second temporary support includes a support frame body and a connecting member. The support frame body is arranged on the steel structure main body and extends vertically. One end of the connecting member is connected to the support frame body, and the other end is connected to the front end of the steel structure main body for lifting the steel structure main body upward.

[0037] Optionally, the support frame body includes a portal frame, and the connecting member includes a steel wire rope.

[0038] Optionally, step S11 specifically includes the following steps:

[0039] S111. The curtain wall structure includes a plurality of curtain wall segments. Install the plurality of curtain wall segments in sequence according to the latest calculation results of the main model.

[0040] S112. Each time a curtain wall segment is installed, use the scanning device to perform three-dimensional scanning on the installed curtain wall segment and record the position of the curtain wall segment until all the curtain wall segments are installed.

[0041] S113. Calculate the deformation amount of the curtain wall structure based on the position of the curtain wall segment, and determine whether the deformation amount of the curtain wall structure is consistent with the theoretical deformation amount of the new curtain wall structure model part. If not, execute S114 and S115; if so, directly execute S115.

[0042] S114. Substitute the deformation amount of the curtain wall structure into the curtain wall structure model part, re-analyze and calculate the main model to obtain the theoretical deformation amount of the latest curtain wall structure model part, and adjust the construction plan of the process accordingly.

[0043] S115. Perform the construction of the subsequent process according to the existing construction plan.

[0044] Optionally, the scanning device includes a three-dimensional laser scanner.

[0045] Advantages of the present invention:

[0046] The present invention provides a construction method for a circular building, which includes a steel structure, a concrete structure, and a curtain wall structure. During the construction process of the entire circular building, first, a main model is established for the circular building and simulated and analyzed to obtain the theoretical deformation amounts of each structure. Then, according to the simulation results, the construction of each structure is carried out in sequence. After the construction of each structure is completed, the actual deformation amount of the constructed structure is compared with the theoretical deformation amount of the corresponding structure in the main model. If the two are inconsistent, the actual deformation amount is substituted into the main model for re-analysis and calculation, and the construction plan of the subsequent structure is adjusted in a timely manner according to the calculation results before construction. If the two are consistent, the current existing plan is maintained for continuous construction. By monitoring the constructed structures during the entire construction process and comparing the monitoring results with the simulation results, the construction plan can be adjusted in a timely manner according to the actual situation, reducing construction errors, ensuring the construction progress and work efficiency, preventing the impact on construction quality, and avoiding safety accidents. BRIEF DESCRIPTION OF THE DRAWINGS

[0047] Figure 1 is a flowchart of the construction method for the circular building provided by an embodiment of the present invention;

[0048] Figure 2 is a schematic structural diagram of the steel structure provided by an embodiment of the present invention.

[0049] In the figure:

[0050] 1, steel structure; 11, main body of the steel structure; 12, first temporary support; 13, second temporary support. DETAILED DESCRIPTION OF THE EMBODIMENTS

[0051] The present invention will be further described in detail below with reference to the drawings and embodiments. It can be understood that the specific embodiments described herein are only used to explain the present invention, rather than limiting the present invention. Additionally, it should be noted that for the sake of description, only the parts related to the present invention are shown in the drawings, rather than all the structures.

[0052] In the description of the present invention, unless otherwise clearly defined and limited, the terms "connected", "connected to", and "fixed" shall be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or integrated; it can be a mechanical connection or an electrical connection; it can be directly connected or indirectly connected through an intermediate medium, and it can be the internal communication of two components or the interaction relationship between two components. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0053] In the present invention, unless otherwise clearly specified and defined, the first feature being "on" or "under" the second feature may include direct contact between the first and second features, or may include contact between the first and second features not directly but through additional features therebetween. Moreover, the first feature being "above", "over" and "on top of" the second feature includes the first feature being directly above and obliquely above the second feature, or merely indicating that the horizontal height of the first feature is higher than that of the second feature. The first feature being "under", "beneath" and "underneath" the second feature includes the first feature being directly below and obliquely below the second feature, or merely indicating that the horizontal height of the first feature is less than that of the second feature.

[0054] In the description of this embodiment, the orientation or positional relationships such as "upper", "lower", "left" and "right" are based on the orientation or positional relationships shown in the drawings, and are only for the convenience of description and simplifying the operations, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus should not be construed as a limitation to the present invention. In addition, the terms "first" and "second" are only used for distinction in description and have no special meanings.

[0055] This embodiment provides a construction method for a circular building, as Figure 1 and Figure 2 shown. The construction method for the circular building can timely adjust the construction plan, ensure the construction progress and work efficiency, prevent affecting the construction quality, and avoid causing safety accidents.

[0056] The circular building includes a steel structure 1, a concrete structure and a curtain wall structure. The construction method for the circular building includes the following steps:

[0057] S1. Referring to Figure 1 and Figure 2 shown, determine the construction sequence and construction requirements for the steel structure 1, the concrete structure and the curtain wall structure;

[0058] S2. Referring to Figure 1 shown, use finite element software to establish a main model, the main model including a steel structure 1 model part, a concrete structure model part and a curtain wall structure model part, analyze and calculate the main model to obtain the theoretical deformation amounts of the steel structure 1 model part, the concrete structure model part and the curtain wall structure model part, and accordingly set the construction plans for the steel structure 1, the concrete structure and the curtain wall structure;

[0059] S3. Referring to Figure 1 shown, construct the steel structure 1 according to the existing construction plan;

[0060] S4. Referring to Figure 1As shown, after the construction of the steel structure 1 is completed, use a scanning device to perform three-dimensional scanning on the steel structure 1 and record the position of the steel structure 1, and thus calculate the deformation of the steel structure 1;

[0061] S5. Refer to Figure 1 As shown, determine whether the deformation of the steel structure 1 is consistent with the theoretical deformation of the model part of the steel structure 1. If not, then execute S6 and S7. If so, directly execute S7;

[0062] S6. Refer to Figure 1 As shown, substitute the deformation of the steel structure 1 into the model part of the steel structure 1, and re-analyze and calculate the main model to obtain the theoretical deformation of the new concrete structure model part and the theoretical deformation of the new curtain wall structure model part, and adjust the construction plans of the concrete structure and the curtain wall structure accordingly;

[0063] S7. Refer to Figure 1 As shown, construct the concrete structure according to the existing construction plan;

[0064] S8. Refer to Figure 1 As shown, after the construction of the concrete structure is completed, use a scanning device to perform three-dimensional scanning on the concrete structure and record the position of the concrete structure, and thus calculate the deformation of the concrete structure;

[0065] S9. Refer to Figure 1 As shown, determine whether the deformation of the concrete structure is consistent with the theoretical deformation of the new concrete structure model part. If not, then execute steps S10 and S11. If so, directly execute S11;

[0066] S10. Refer to Figure 1 As shown, substitute the deformation of the concrete structure into the model part of the concrete structure, re-analyze and calculate the main model, and obtain the theoretical deformation of the new curtain wall structure model part again, and adjust the construction plan of the curtain wall structure accordingly;

[0067] S11. Refer to Figure 1 As shown, construct the curtain wall structure according to the existing construction plan.

[0068] When a circular building needs to be constructed, first, the construction staff of the steel structure 1, concrete structure, and curtain wall structure conduct consultations to determine the construction sequence and requirements of the steel structure 1, concrete structure, and curtain wall structure. Use finite element software to establish and analyze the main model, so as to obtain the theoretical deformation of the steel structure 1 model part, the theoretical deformation of the concrete structure model part, and the theoretical deformation of the curtain wall structure model part, that is, obtain the theoretical values of the above three parts. Set the construction plans for the steel structure 1, concrete structure, and curtain wall structure according to the theoretical deformation of the steel structure 1 model part, the theoretical deformation of the concrete structure model part, and the theoretical deformation of the curtain wall structure model part (which is the existing construction plan), and carry out the construction of the steel structure 1 according to this construction plan. After the construction of the steel structure 1 is completed, use scanning equipment to scan the steel structure 1 and record the position information of the steel structure 1, and calculate the deformation of the steel structure 1 based on this (that is, obtain the actual deformation of the steel structure 1 in actual construction).

[0069] Compare the actual deformation of the steel structure 1 with the deformation of the steel structure 1 model part to judge whether they are consistent. If not, substitute the actual deformation of the steel structure 1 into the steel structure 1 model part of the main model, re-analyze and calculate the main model, so as to obtain the new theoretical deformation of the concrete structure model part and the new theoretical deformation of the curtain wall structure model part. Adjust the construction plans of the concrete structure and curtain wall structure according to the latest theoretical deformation of the concrete structure model part and the latest theoretical deformation of the curtain wall structure model part. Then, according to the existing construction plan (that is, the new construction plan after the first adjustment), carry out the construction of the concrete structure; if so, there is no need to adjust the construction plans of the concrete structure and curtain wall structure, and the construction of the concrete structure can be directly carried out. At this time, the existing construction plan is the initial construction plan.

[0070] After the construction of the concrete structure is completed, obtain the deformation of the concrete structure according to the method of obtaining the actual deformation of the steel structure 1 (that is, obtain the actual deformation of the concrete structure). Compare whether the actual deformation of the concrete structure is consistent with the theoretical deformation of the concrete structure model part. If not, according to the treatment method of the steel structure 1, substitute the actual deformation of the concrete structure into the concrete structure model part, calculate and obtain the new theoretical deformation of the curtain wall structure model part, and adjust the construction plan of the curtain wall structure according to the latest theoretical deformation of the curtain wall structure model part. Then, according to the existing construction plan (the new construction plan after the second adjustment), carry out the construction of the curtain wall structure; if so, there is no need to adjust the construction plan after the first adjustment, and the construction of the curtain wall structure can be directly carried out. At this time, the existing construction plan is the construction plan after the first adjustment.

[0071] As can be seen from the above analysis, during the construction process of the entire circular building, first, the circular building is modeled and simulated to obtain the theoretical deformation amounts of each structure. Then, according to the simulation results, the construction of each structure is carried out in sequence. After the construction of each structure is completed, the actual deformation amount of the constructed structure is compared with the theoretical deformation amount. If the two are inconsistent, the actual deformation amount is substituted into the main model for re-analysis and calculation, and the construction plan of the subsequent structure is adjusted in a timely manner according to the calculation results before proceeding with the construction. If the two are consistent, the current existing construction plan is maintained and the construction continues. By monitoring the constructed structures during the entire construction process and comparing the monitoring results with the simulation results, the construction plan can be adjusted in a timely manner according to the actual situation, reducing construction errors, ensuring the construction progress and work efficiency, preventing the impact on construction quality, and avoiding safety accidents.

[0072] Exemplarily, the scanning device includes a three-dimensional laser scanner or a total station, etc.

[0073] Optionally, step S2 specifically includes the following steps:

[0074] S21. Establish a main model using finite element software according to the engineering design. The main model includes a steel structure 1 model part, a concrete structure model part, and a curtain wall structure model part;

[0075] S22. Analyze and calculate the main model in stages according to the construction sequence to obtain the theoretical deformation amounts of the steel structure 1 model part, the concrete structure model part, and the curtain wall structure model part.

[0076] By analyzing and calculating the main model in stages, the theoretical deformation amounts of the steel structure 1 model part, the concrete structure model part, and the curtain wall structure model part can be obtained more accurately, which is conducive to formulating a more perfect construction plan and ensuring the construction quality of the project.

[0077] Optionally, step S2 further includes:

[0078] S23. Analyze and calculate multiple nodes of the main model separately;

[0079] S24. Optimize the construction plan according to the calculation results of the nodes.

[0080] According to the calculation results of multiple nodes, the overall circular building and its individual nodes can be optimized during the construction process, which is conducive to improving the feasibility of the construction plan and ensuring the construction quality of the project.

[0081] It should be noted that usually, the nodes with relatively weak strength of the circular building are analyzed and calculated separately, such as the nodes with large external loads, the nodes with supports, etc.

[0082] Optionally, such asFigure 1 As shown in the figure. The steel structure 1 includes a main body of the steel structure 1, a first temporary support 12 and a second temporary support 13. One end of the first temporary support 12 is connected to the lower surface of the main body of the steel structure 1, and the other end is configured to be set on the ground. The second temporary support 13 is arranged on the upper surface of the main body of the steel structure 1 and is connected to the front end of the main body of the steel structure 1. The second temporary support 13 is used to lift the main body of the steel structure 1 vertically upward. By arranging the first temporary support 12 below the main body of the steel structure 1, the main body of the steel structure 1 can be supported, thereby raising the vertical height of the main body of the steel structure 1, facilitating the splicing construction of the main body of the steel structure 1. At the same time, by arranging the second temporary support 13, the front end of the main body of the steel structure 1 can be lifted, so that the main body of the steel structure 1 maintains a slightly lifted posture, which can increase the longitudinal stability of the main body of the steel structure 1, thereby reducing the risk of overturning and ensuring the construction safety.

[0083] Optionally, the second temporary support 13 includes a support frame body and a connecting member. The support frame body is arranged on the main body of the steel structure 1 and extends vertically. One end of the connecting member is connected to the support frame body, and the other end is connected to the front end of the main body of the steel structure 1, and is used to lift the main body of the steel structure 1 upward. By arranging the support frame body and the connecting member, the connecting member lifts the main body of the steel structure 1 upward, thereby reducing the structural deformation of the main body of the steel structure 1 caused by the cantilever effect, ensuring the overall stability of the structure. At the same time, the connecting member transfers part of the load borne by the main body of the steel structure 1 to the support frame body, which can optimize the force distribution of the structure.

[0084] Exemplarily, the support frame body includes a portal frame, and the connecting member includes a steel wire rope.

[0085] Optionally, step S3 specifically includes the following steps:

[0086] S31. Erect the main body of the steel structure 1, the first temporary support 12 and the second temporary support 13 according to the calculation results of the main model;

[0087] S32. Conduct a simulation analysis on part of the main body of the steel structure 1 in the area with a larger span to obtain the downward deflection of the main body of the steel structure 1 in the area with a larger span;

[0088] S33. Judge whether the downward deflection of the main body of the steel structure 1 in the area with a larger span is greater than l0 / 400 (l0 is the span of the main body of the steel structure 1). If so, execute S34; if not, execute S4;

[0089] S34. Set the first temporary support 12 and the second temporary support 13 in this area.

[0090] By simulating and analyzing part of the main body of the steel structure 1 in a relatively large-span area, the downward deflection of the main body of the steel structure 1 in this area can be obtained, so as to judge whether a temporary support structure needs to be set for the main body of the steel structure 1 in this area, thereby preventing the main body of the steel structure 1 in the large-span area from buckling and deforming, enhancing the overall stability of the main body of the steel structure 1, and ensuring the safety and construction quality of the construction.

[0091] Optionally, step S7 specifically includes the following steps:

[0092] S71. Remove the first temporary support 12 and the second temporary support 13, and erect a permanent support, and the main body of the steel structure 1 is arranged on the permanent support;

[0093] S72. Use a scanning device to perform a three-dimensional scan on the steel structure 1 again and record the position of the steel structure 1, so as to calculate the latest deformation amount of the steel structure 1;

[0094] S73. Judge whether the latest deformation amount of the steel structure 1 is consistent with the theoretical deformation amount of the latest steel structure 1 model part. If not, execute S74 and S75. If so, directly execute S75;

[0095] S74. Substitute the latest deformation amount of the steel structure 1 into the steel structure 1 model part, and re-analyze and calculate the main model to obtain the deformation amounts of the latest concrete structure model part and the curtain wall structure model part, and adjust the construction plans of the concrete structure and the curtain wall structure accordingly;

[0096] S75. Construct the concrete structure according to the existing construction plan.

[0097] After removing the first temporary support 12 and the second temporary support 13, erect a permanent support and arrange the main body of the steel structure 1 on the permanent support, which can provide better support for the main body of the steel structure 1 to prevent it from overturning and shifting. Moreover, after removing the first temporary support 12 and the second temporary support 13, calculate the actual deformation amount of the steel structure 1 again, and compare the actual deformation amount with the theoretical deformation amount of the new steel structure 1 model part, so as to update the construction plans of the subsequent structures in a timely manner, enhance the feasibility and adaptability of the construction plans, and ensure the construction quality of the project.

[0098] Optionally, step S11 specifically includes the following steps:

[0099] S111. The curtain wall structure includes multiple curtain wall sub-parts, and install multiple curtain wall sub-parts in sequence according to the latest calculation results of the main model;

[0100] S112. Use a scanning device to perform a three-dimensional scan on the installed curtain wall sub-parts every time a curtain wall sub-part is installed, and record the position of the curtain wall sub-part until all the curtain wall sub-parts are installed;

[0101] S113. Calculate the deformation amount of the curtain wall structure based on the position of the curtain wall branch, and determine whether the deformation amount of the curtain wall structure is consistent with the theoretical deformation amount of the new curtain wall structure model part. If not, execute S114 and S115; if so, directly execute S115;

[0102] S114. Substitute the deformation amount of the curtain wall structure into the curtain wall structure model part, re-analyze and calculate the main model to obtain the deformation amount of the latest curtain wall structure model part, and adjust the construction plan of the process accordingly;

[0103] S115. Perform the construction of subsequent processes according to the existing construction plan.

[0104] Obviously, the above embodiments of the present invention are merely examples for clearly illustrating the present invention, rather than limiting the implementation manners of the present invention. For those of ordinary skill in the art, various obvious changes, re-adjustments and substitutions can be made without departing from the protection scope of the present invention. It is not necessary and impossible to enumerate all the implementation manners here. Any modifications, equivalent substitutions and improvements made within the spirit and principle of the present invention shall be included in the protection scope of the claims of the present invention.

Claims

1. A construction method for a circular building, the circular building comprising a steel structure (1), a concrete structure and a curtain wall structure, characterized in that, The construction method of the circular building includes: S1. Determine the construction sequence and construction requirements of the steel structure (1), the concrete structure, and the curtain wall structure; S2. Use finite element software to establish a main model, which includes a steel structure model part, a concrete structure model part, and a curtain wall structure model part. Analyze and calculate the main model to obtain the theoretical deformation amount of the steel structure model part, the theoretical deformation amount of the concrete structure model part, and the theoretical deformation amount of the curtain wall structure model part, and accordingly set the construction plans for the steel structure (1), the concrete structure, and the curtain wall structure; S3. Construct the steel structure (1) according to the existing construction plan; S4. After the construction of the steel structure (1) is completed, use a scanning device to perform three-dimensional scanning on the steel structure (1) and record the position of the steel structure (1), thereby calculating the deformation amount of the steel structure (1); S5. Judge whether the deformation amount of the steel structure (1) is consistent with the theoretical deformation amount of the steel structure model part. If not, execute S6 and S7; if so, directly execute S7; S6. Substitute the deformation amount of the steel structure (1) into the steel structure model part, and re-analyze and calculate the main model to obtain the new theoretical deformation amount of the concrete structure model part and the new theoretical deformation amount of the curtain wall structure model part, and accordingly adjust the construction plans for the concrete structure and the curtain wall structure; S7. Construct the concrete structure according to the existing construction plan; S8. After the construction of the concrete structure is completed, use the scanning device to perform three-dimensional scanning on the concrete structure and record the position of the concrete structure, thereby calculating the deformation amount of the concrete structure; S9. Judge whether the deformation amount of the concrete structure is consistent with the new theoretical deformation amount of the concrete structure model part. If not, execute steps S10 and S11; if so, directly execute S11; S10. Substitute the deformation amount of the concrete structure into the concrete structure model part, re-analyze and calculate the main model, and obtain the new theoretical deformation amount of the curtain wall structure model part again, and accordingly adjust the construction plan for the curtain wall structure; S11. Construct the curtain wall structure according to the existing construction plan.

2. The construction method of the circular building according to claim 1, wherein The specific steps of step S2 include the following steps: S21. Use finite element software to establish the main model according to the engineering design. The main model includes a steel structure model part, a concrete structure model part, and a curtain wall structure model part; S22. Analyze and calculate the main model in stages according to the construction sequence to obtain the theoretical deformation amount of the steel structure model part, the theoretical deformation amount of the concrete structure model part, and the theoretical deformation amount of the curtain wall structure model part.

3. The construction method of the circular building according to claim 2, characterized in that, Step S2 also includes: S23. Analyze and calculate multiple nodes of the main model separately; S24. Optimize the construction plan according to the calculation results of the nodes.

4. The construction method of the circular building according to claim 1, characterized in that, The steel structure (1) includes a steel structure main body (11), a first temporary support (12) and a second temporary support (13). One end of the first temporary support (12) is connected to the lower surface of the steel structure main body (11), and the other end is configured to be set on the ground. The second temporary support (13) is arranged on the upper surface of the steel structure main body (11) and is connected to the front end of the steel structure main body (11). The second temporary support (13) is used to lift the steel structure main body (11) vertically upward.

5. The construction method of the circular building according to claim 4, characterized in that, The specific steps of step S3 include the following steps: S31. Erect the steel structure main body (11), the first temporary support (12) and the second temporary support (13) according to the calculation results of the main model; S32. Conduct a simulation analysis on part of the steel structure main body (11) in the area with a larger span to obtain the downward deflection of the steel structure main body (11) in the area with a larger span; S33. Judge whether the downward deflection of the steel structure main body (11) in the area with a larger span is greater than l0 / 400 (l0 is the span of the steel structure main body (11)). If so, execute S34; if not, execute S4; S34. Set the first temporary support (12) and the second temporary support (13) in this area.

6. The construction method of the circular building according to claim 5, characterized in that, The specific steps of step S7 include the following steps: S71. Remove the first temporary support (12) and the second temporary support (13), and erect permanent supports. The steel structure main body (11) is arranged on the permanent supports; S72. Use a scanning device to conduct a three-dimensional scan on the steel structure (1) again and record the position of the steel structure (1), thereby calculating the latest deformation amount of the steel structure (1); S73. Judge whether the deformation amount of the latest steel structure (1) is consistent with the theoretical deformation amount of the latest steel structure model part. If not, execute S74 and S75; if so, directly execute S75; S74. Substitute the deformation amount of the latest steel structure (1) into the steel structure model part, and re-analyze and calculate the main model to obtain the theoretical deformation amounts of the latest concrete structure model part and the curtain wall structure model part, and adjust the construction plans of the concrete structure and the curtain wall structure accordingly; S75. Construct the concrete structure according to the existing construction plan.

7. The construction method of the circular building according to claim 4, characterized in that The second temporary support (13) includes a support frame body and a connecting member. The support frame body is arranged on the steel structure main body (11) and extends vertically. One end of the connecting member is connected to the support frame body, and the other end is connected to the front end of the steel structure main body (11) for lifting the steel structure main body (11) upward.

8. The construction method of the circular building according to claim 7, characterized in that, The support frame body includes a portal frame, and the connecting member includes a steel wire rope.

9. The construction method of the circular building according to any one of claims 1-8, characterized in that, The specific steps of step S11 include the following steps: S111. The curtain wall structure includes a plurality of curtain wall branches. Install the plurality of curtain wall branches in sequence according to the latest calculation results of the main model; S112. For each installed curtain wall section, use the scanning device to perform three-dimensional scanning on the installed curtain wall section and record the position of the curtain wall section until all curtain wall sections are installed; S113. Calculate the deformation amount of the curtain wall structure based on the position of the curtain wall section, and determine whether the deformation amount of the curtain wall structure is consistent with the theoretical deformation amount of the new curtain wall structure model section. If not, execute S114 and S115. If so, directly execute S115; S114. Substitute the deformation amount of the curtain wall structure into the curtain wall structure model section, re-analyze and calculate the main model to obtain the theoretical deformation amount of the latest curtain wall structure model section, and adjust the construction plan of the process accordingly; S115. Perform the construction of the subsequent process according to the existing construction plan.

10. The construction method of the circular building according to any one of claims 1-8, characterized in that, The scanning device includes a three-dimensional laser scanner.