Ultra-simple water pump inert platform construction method
Through the construction method of water pump inert platform with a combined structure of rebar and concrete, the problems of large weight and high cost in the prior art are solved, and the effect of rapid installation and labor intensity is achieved.
Patent Information
- Application Number
- CN202510817325.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-06-18
- Publication Date
- 2025-08-05
- Estimated Expiration
- 2045-06-18
AI Technical Summary
The existing inert platform of water pumps adopts all-steel welded structure, which leads to high weight, high cost and high workload, making it difficult to achieve rapid installation and reduce labor intensity.
The combined structure of rebar and concrete is adopted, and the rapid construction of the platform is achieved by cutting rebar, laying cross bars and longitudinal bars, welding support seats, and pouring concrete, combined with hydraulic cylinders and auxiliary processing mechanisms.
It reduces the production cost and quality of the inert platform, simplifies the installation process, reduces labor intensity, and ensures the stability and rapid production of the platform.
Smart Images

Figure CN120425925A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of water pump installation auxiliary equipment construction, and in particular to an ultra-simple water pump inert platform construction method. Background Art
[0002] The statements herein merely provide background information related to the present invention and do not necessarily constitute prior art.
[0003] The water pump inert platform is a platform used for water pump installation and subsequent use and maintenance of the water pump. It plays a vital role in ensuring the safe operation of the water pump. The existing inert platform is generally welded with all steel and then installed in the designated position. This makes the entire platform heavy, uses a lot of steel, is costly, and requires multiple welding and bolting to fix it. The overall workload is also large. Summary of the Invention
[0004] The main purpose of the present invention is to provide a construction method for a water pump inert platform.
[0005] To achieve the above object, the technical solution of the present invention is implemented as follows: a super-simple water pump inert platform construction method, comprising the following steps:
[0006] S1: Determine platform specifications and prefabricate templates;
[0007] S2: Cut the rebar and lay it into horizontal bars and vertical bars. Then, assemble multiple horizontal bars and vertical bars into a mesh structure and weld them together. Meanwhile, support seats are welded around the rebar in the mesh structure for support.
[0008] S3: Install formwork around the structure consisting of mesh horizontal and vertical bars, and pour concrete in the space enclosed by the formwork;
[0009] S4: Wait for the concrete to dry and cooperate with the concrete curing.
[0010] Furthermore, adjacent threaded steel bars are welded by oxyacetylene welding.
[0011] Furthermore, a threaded hole is provided on the support seat, and the connection portion between the support seat and the threaded steel bar is located within the concrete enclosure.
[0012] Furthermore, the platform construction method is completed using a construction device.
[0013] Furthermore, the construction device includes a hydraulic cylinder connected to the ground, the moving end of the hydraulic cylinder is connected to a discharging mechanism, the discharging mechanism is used to discharge the threaded steel, and a plurality of auxiliary processing mechanisms are arranged on the outer side of the hydraulic cylinder along its circumferential direction, the auxiliary processing mechanisms are used to perform processing of some processes.
[0014] Furthermore, the auxiliary processing mechanism includes a forming box, in which a forming unit is provided for forming concrete, an adjustment unit is connected to the top of the forming box, and the execution end of the power unit is connected to a hollow supporting platform, and a receiving groove for comprehensive staggering is also provided on the top of the supporting platform, and the receiving groove has the same diameter as the threaded steel bar, and is used to store the corresponding threaded steel bars arranged vertically and horizontally, a plurality of welding grooves are provided on the supporting platform, and welding units for welding are placed in the welding grooves, and crisscrossed air pipes are provided in the supporting platform, and the air pipes are connected to the welding units, and the horizontally arranged air pipes and the longitudinally arranged air pipes are respectively connected to their respective corresponding ventilation pipes, and the ventilation pipes are connected to the external gas tanks, and the adjacent two sides of the supporting platform are connected with a follower plate through a spring hinge, and one side of the follower plate is in contact with the discharging mechanism, and the follower plate intermittently prevents the threaded steel from falling from the discharging mechanism, and the forming box is also connected to a recycling box for collecting materials.
[0015] Furthermore, the welding unit includes a splicing box located in the welding tank, a rectangular ventilation box is arranged in the splicing box, combustion tubes are connected to the four vertical corners of the ventilation box, a detector is connected to the combustion tube, a plurality of sensors are connected to the detector, a diverter pipe is arranged in the ventilation box, one end of the diverter pipe is connected to the corresponding combustion tube, the bottom end of the diverter pipe is connected to a plug-in pipe, one end of the plug-in pipe extends into the gas guide pipe and is communicated with the gas guide pipe.
[0016] Furthermore, the adjustment unit includes a packaging box fixedly connected to the forming box, the top of the packaging box is fixedly connected to a motor, the output end of the motor is transmission-connected to a transmission located in the packaging box, the output end of the transmission is transmission-connected to a transmission shaft, the outer side of the transmission shaft is connected to a moving column through a spline transmission, the moving column is provided with a plurality of M-shaped grooves connected end to end along the circumferential direction, a limiting column fixedly connected to the packaging box is provided in the M-shaped groove, the limiting column limits the moving column to periodically move up and down through the M-shaped groove, the top of the moving column is rotatably connected to a support frame, the top of the support frame is fixedly connected to a pneumatic cylinder, the moving end of the pneumatic cylinder is clamped with a connecting platform, a telescopic rod 2 is provided in the middle of the connecting platform, a telescopic rod 1 arranged along the circumference of the connecting platform is provided on the outer side of the telescopic rod 2, and the moving ends of the telescopic rod 2 and the telescopic rod 1 are both rotationally connected to the bottom of the supporting platform.
[0017] Furthermore, the molding unit includes a vibration box located in the molding box, a plurality of vibration motors are fixedly connected to the vibration box, a guide groove is provided on the vibration box, and a molding mold located in the molding box is slidably provided in the guide groove.
[0018] Furthermore, the discharging mechanism includes an outer frame connected to the moving end of the hydraulic cylinder, a raw material box 1 is arranged in the outer frame, a raw material box 2 is connected in the raw material box 1, a horizontal bar and a vertical bar are respectively placed in the raw material box 1 and the raw material box 2, the bottom of the raw material box 1 and the raw material box 2 are connected to a discharge pipe, an electric telescopic rod is slidably arranged on the discharge pipe, the discharge pipe is hollow, and one end of the discharge pipe is connected to a discharge hole located at the bottom of the outer frame, the discharge hole cooperates with the follower plate, a plurality of vibration motors 2 are also connected in the outer frame, and a controller is placed in the middle of the outer frame.
[0019] The beneficial effects of the present invention are embodied in:
[0020] The present invention abandons the original pure steel structure inert platform and utilizes a combination of steel structure and concrete. This can reduce the overall production cost while ensuring the function of the inert platform, and reduce the quality of the inert platform. While reducing the cost, it is convenient to produce and install the platform. In addition, with the help of corresponding production equipment and manual assistance, platforms of corresponding specifications can be quickly produced with relatively light labor intensity, while ensuring the stability of the quality of the platform. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] In the attached figure:
[0022] Figure 1 This is a three-dimensional structural diagram of the inert platform steel structure;
[0023] Figure 2 It is a three-dimensional structural diagram of the construction device;
[0024] Figure 3 It is a three-dimensional structural diagram of the auxiliary processing mechanism;
[0025] Figure 4 It is a partial three-dimensional structural diagram of the auxiliary processing mechanism;
[0026] Figure 5 It is the main sectional view of the auxiliary processing mechanism;
[0027] Figure 6 It is a partial main sectional view of the auxiliary processing mechanism;
[0028] Figure 7 for Figure 5 A magnified schematic diagram of point A;
[0029] Figure 8 It is the local three-dimensional structure of the welding unit;
[0030] Figure 9 It is a partial three-dimensional structural diagram of the discharging mechanism;
[0031] Figure 10 This is a three-dimensional structural diagram of the feeding pipe.
[0032] Description of reference numerals:
[0033] 01. Horizontal bar; 02. Vertical bar; 03. Support base; 11. Hydraulic cylinder; 12. Vibration box; 13. Forming die; 14. Forming box; 15. Recovery box; 17. Support platform; 18. Follower plate; 19. Outer frame; 20. Air guide tube; 21. Telescopic rod 1; 22. Telescopic rod 2; 23. Packaging box; 26. Drive shaft; 27. Connecting platform; 29. Support frame; 30. Limiting column; 31. Moving column 32. Transmission; 33. Motor; 34. Pneumatic cylinder; 35. M-shaped slot; 36. Accommodation slot; 37. Vibration motor 1; 39. Ventilation pipe; 40. Splicing box; 41. Combustion pipe; 42. Plug-in pipe; 44. Ventilation box; 45. Sensor; 46. Detector; 50. Raw material box 1; 51. Raw material box 2; 52. Feeding pipe; 53. Electric telescopic rod; 54. Controller; 55. Vibration motor 2. DETAILED DESCRIPTION
[0034] The present invention will be further described in detail below with reference to the accompanying drawings and embodiments. Obviously, the embodiments described are only some embodiments of the invention, not all embodiments. In the absence of conflict, the embodiments and features in the embodiments of this application can be combined with each other. Based on the embodiments of the invention, all other embodiments obtained by ordinary technicians in this field without making creative efforts are within the scope of protection of the invention.
[0035] Example 1: See Figure 1 ;
[0036] The water pump inert platform includes crisscrossing horizontal bars 01 and vertical bars 02, which are welded to each other. The two ends of some horizontal bars 01 are fixedly connected to support seats 03, which are provided with screw holes. Concrete is also poured on the outside of the horizontal bars 01 and vertical bars 02. By utilizing the welding of steel bars in conjunction with the pouring of concrete, the use of existing steel frames can be avoided, thereby reducing the overall weight and the cost of the entire device.
[0037] Example 2: See Figure 1 ;
[0038] The present invention discloses an ultra-simple water pump inert platform construction method, comprising the following steps:
[0039] S1: Determine platform specifications and prefabricate templates;
[0040] S2: Cut the rebar and lay it into horizontal bars 01 and vertical bars 02. Then assemble multiple horizontal bars 01 and vertical bars 02 into a mesh structure and weld them together. At the same time, weld support seats 03 around the rebar in the mesh structure for support.
[0041] S3: Install formwork around the structure consisting of mesh horizontal bars 01 and vertical bars 02, and pour concrete in the space enclosed by the formwork;
[0042] S4: Wait for the concrete to dry and cooperate with the concrete curing.
[0043] In the second embodiment, adjacent threaded steel bars are welded by oxyacetylene welding, and the stability of the connection between the steel structures is ensured by oxyacetylene welding.
[0044] In the second embodiment, threaded holes are provided on the support base 03, and the connection portion between the support base 03 and the threaded steel bar is located within the concrete enclosure. The threaded holes facilitate connection of the support base 03 with other devices to achieve installation of the inert platform.
[0045] Example 3: Figure 2 As shown, the difference between this embodiment and the first embodiment lies in the difference in the construction device;
[0046] In this embodiment, the platform construction method is completed by using a construction device. The construction device can reduce the labor intensity of workers and facilitate the production of the inert platform.
[0047] In the third embodiment, the construction device includes a hydraulic cylinder 11 connected to the ground, and the movable end of the hydraulic cylinder 11 is connected to a discharging mechanism, which is used to discharge threaded steel bars. A plurality of auxiliary processing mechanisms are provided on the outer side of the hydraulic cylinder 11 along its circumferential direction, and the auxiliary processing mechanisms are used to perform processing of some processes. The discharging mechanism distributes different steel sections to the auxiliary processing mechanism to perform auxiliary work in some processes, thereby reducing the operation of workers.
[0048] Example 4: Figure 2-Figure 8 As shown, the difference between this embodiment and the second embodiment lies in the difference in the auxiliary processing mechanism;
[0049] In this embodiment, the auxiliary processing mechanism includes a forming box 14, a forming unit is provided in the forming box 14, which is used for forming concrete, an adjustment unit is connected to the top of the forming box 14, and the execution end of the power unit is connected to the hollow supporting platform 17. The top of the supporting platform 17 is also provided with a accommodating groove 36 for comprehensive staggering. The longitudinal and transverse accommodating grooves 36 are not in the same plane. The accommodating grooves 36 are the same as the diameter of the threaded steel bars, and are used to store the corresponding longitudinal and transverse threaded steel bars to ensure the entry of each corresponding threaded steel bar. A plurality of welding grooves are provided on the supporting platform 17, and welding units for welding are placed in the welding grooves. The supporting platform 17 is provided with crisscrossing air guide pipes 20, which are connected to the welding units, and the transversely arranged air guide pipes 20 are connected to the welding units. The tube 20 and the longitudinally arranged air guide pipe 20 are respectively connected to their respective corresponding ventilation pipes 39, and the ventilation pipe 39 is connected to the external gas tank, where the gas tank is acetylene gas and oxygen, and then enters the longitudinal and transverse air guide pipes 20 respectively through two support frames 29, and then the gas is transmitted to ensure subsequent welding. The adjacent two sides of the support platform 17 are connected with a follower plate 18 through a spring hinge, and one side of the follower plate 18 is in contact with the discharging mechanism. The follower plate 18 intermittently prevents the threaded steel from falling from the discharging mechanism. The forming box 14 is also connected to a recovery box 15 for collecting materials. Through the spring hinge, the follower plate 18 is always in contact with the discharging mechanism, and cooperates with the discharging mechanism to carry out feeding and unloading. The recovery box 15 receives excess or missed threaded steel.
[0050] In the fourth embodiment, the welding unit includes a splicing box 40 located in the welding groove, a rectangular ventilation box 44 is provided in the splicing box 40, the four vertical corners of the ventilation box 44 are connected to the combustion tube 41, the combustion tube 41 is connected to a detector 46, the detector 46 is connected to a plurality of sensors 45, a diverter tube is provided in the ventilation box 44, one end of the diverter tube is connected to the corresponding combustion tube 41, the bottom end of the diverter tube is connected to a plug-in tube 42, one end of the plug-in tube 42 extends into the gas guide tube 20 and is connected to the gas guide tube 20, the external acetylene gas passes through the ventilation box 44 and is diverted into the combustion tube 41, and then is ignited by electric shock, and the contact point of the two threaded steel bars is sprayed with fire and melted at high temperature. The sensor 45 detects the acetylene gas content in the splicing box 40 for safety monitoring.
[0051] In the fourth embodiment, the adjustment unit includes a packaging box 23 fixedly connected to the forming box 14, the top of the packaging box 23 is fixedly connected to a motor 33, the output end of the motor 33 is transmission-connected to a transmission 32 located in the packaging box 23, the output end of the transmission 32 is transmission-connected to a transmission shaft 26, the outer side of the transmission shaft 26 is connected to a moving column 31 through a spline transmission, the moving column 31 is provided with a plurality of M-shaped grooves 35 connected end to end along the circumferential direction, the M-shaped groove 35 is provided with a limiting column 30 fixedly connected to the packaging box 23, the limiting column 30 limits the moving column 31 to periodically move up and down through the M-shaped groove 35, the top of the moving column 31 is rotatably connected to a support frame 29, the top of the support frame 29 is fixedly connected to a pneumatic cylinder 34, the moving end of the pneumatic cylinder 34 is clamped with a connecting platform 27, and a telescopic rod 22 is provided in the middle of the connecting platform 27. 2. A telescopic rod 1 21 is provided on the outer side of the telescopic rod 22 and is arranged along the circumference of the connecting platform 27. The movable ends of the telescopic rod 22 and the telescopic rod 1 21 are both rotatably connected to the bottom of the supporting platform 17. During the preliminary work, multiple telescopic rods 1 21 and telescopic rod 2 22 can be adjusted to limit the height and inclination of the supporting platform 17. During the work, the vibration of the vibration motor 1 37 below is transmitted, so that the supporting platform 17 vibrates synchronously, which facilitates the falling of the threaded steel. At the same time, the motor 33 works and then transmits it through the transmission 32 to drive the transmission shaft 26 and the moving column 31 to rotate. At this time, the cooperation of the limiting column 30 and the M-shaped groove 35 is limited, so that the moving column 31 performs periodic up and down movement, thereby driving the supporting platform 17 and the follower plate 18 to perform periodic up and down movement to carry out the unloading of the threaded steel.
[0052] In the fourth embodiment, the molding unit includes a vibration box 12 located in a molding box 14, a plurality of vibration motors 37 are fixedly connected in the vibration box 12, a guide groove is provided on the vibration box 12, a molding mold 13 located in the molding box 14 is slidably provided in the guide groove, the vibration motor 37 generates vibration, a spliced grid is installed in the molding mold 13, and concrete is poured at the same time and waits for solidification, and the molding mold 13 can be conveniently moved in the molding box 14 through the guide groove to facilitate discharge.
[0053] Example 5: Figure 2-Figure 9 As shown, the difference between this embodiment and the third embodiment lies in the different discharging mechanisms;
[0054] In this embodiment, the discharging mechanism includes an outer frame 19 connected to the moving end of the hydraulic cylinder 11, a raw material box 1 50 is provided in the outer frame 19, a raw material box 2 51 is sleeved in the raw material box 1 50, a horizontal bar 01 and a vertical bar 02 are placed in the raw material box 1 50 and the raw material box 2 51 respectively, the bottom of the raw material box 1 50 and the raw material box 2 51 are connected to a discharge pipe 52, a plurality of electric telescopic rods 53 are slidably provided on the discharge pipe 52, the cross section of the discharge pipe 52 is an inclined F-shaped structure, the electric telescopic rod 53 is located at the position of the pipeline connected to the raw material box 1 50 and the raw material box 2 51, and the moving end part of the electric telescopic rod 53 is located in the discharge pipe 52, the discharge pipe 52 is hollow, and one end of the discharge pipe 52 is connected to the discharge hole located at the bottom of the outer frame 19, and the discharge hole is connected to the follower plate 18 cooperate with each other, and multiple vibration motors 55 are also connected to the outer frame 19. A controller 54 is placed in the middle of the outer frame 19. Corresponding horizontal bars 01 and vertical bars 02 are placed in the raw material box 2 51 and the raw material box 1 50 respectively. Then, under the vibration of the vibration motor 2 55 and the action of its own gravity, the raw material is diverted to the discharge hole through the discharge pipe 52, and finally enters the receiving groove 36 on the supporting platform 17 under the action of gravity to realize unloading. After the installation of the horizontal bar 01 is completed, the supporting platform 17 is manually rotated so that the supporting platform 17 rotates 90 degrees, that is, the unloading of the vertical bar 02 is carried out. The discharge of the raw material box 1 50 or the raw material box 2 51 can be realized through the control of the electric telescopic rod 53. During the up and down movement of the follower plate 18, the discharge hole is intermittently sealed and released to realize intermittent discharge.
[0055] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.
[0056] It should be noted that if the embodiments of the invention involve directional indications (such as up and down), the directional indications are only used to explain the relative position relationship, movement status, etc. between the components under a certain specific posture (as shown in the accompanying drawings). If the specific posture changes, the directional indication will also change accordingly.
[0057] In addition, the meaning of "and / or" appearing in the full text includes three parallel schemes. Taking "A and / or B" as an example, it includes scheme A, scheme B, or schemes in which A and B are satisfied at the same time. In addition, if there are descriptions involving "first", "second", etc. in the embodiments of the invention, the descriptions of "first", "second", etc. are only used for descriptive purposes and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one such feature. In addition, "multiple" refers to more than two. In addition, the technical solutions between the various embodiments can be combined with each other, but they must be based on the ability of ordinary technicians in this field to implement them. When the combination of technical solutions is mutually contradictory or cannot be implemented, it should be deemed that such a combination of technical solutions does not exist and is not within the scope of protection required by the invention.
Claims
1. A super simple water pump inert platform construction method, characterized in that: The following steps are involved: S1: Determine platform specifications and prefabricate templates; S2: cutting the threaded steel bars and laying them into horizontal bars (01) and vertical bars (02), assembling multiple horizontal bars (01) and vertical bars (02) into a mesh structure and welding them, and welding support seats (03) for support around the threaded steel bars of the mesh structure; S3: Install formwork around the structure consisting of the mesh cross bars (01) and longitudinal bars (02), and pour concrete in the space enclosed by the formwork; S4: Wait for the concrete to dry and cooperate with the concrete curing.
2. The method for constructing an ultra-simple water pump inert platform according to claim 1, characterized in that: Adjacent threaded steel bars are welded by oxygen welding.
3. The method for constructing an ultra-simple water pump inert platform according to claim 1, characterized in that: The support seat (03) is provided with a threaded hole, and the connection portion between the support seat (03) and the threaded steel bar is located within the concrete enclosure.
4. A super-simple water pump inert platform construction method according to any one of claims 1-4, characterized in that: The platform construction method is completed by using a construction device.
5. The method for constructing an ultra-simple water pump inert platform according to claim 4, characterized in that: The construction device comprises a hydraulic cylinder (11) connected to the ground, a discharging mechanism is connected to the movable end of the hydraulic cylinder (11), and the discharging mechanism is used to discharge threaded steel bars. A plurality of auxiliary processing mechanisms are provided on the outer side of the hydraulic cylinder (11) along its circumferential direction, and the auxiliary processing mechanisms are used to perform processing of part of the process.
6. The method for constructing an ultra-simple water pump inert platform according to claim 5, characterized in that: The auxiliary processing mechanism includes a forming box (14), wherein a forming unit is provided in the forming box (14) for forming concrete, an adjustment unit is connected to the top of the forming box (14), and an execution end of the adjustment unit is connected to a hollow supporting platform (17), and the top of the supporting platform (17) is also provided with crisscross distributed receiving grooves (36), the receiving grooves (36) having the same diameter as the threaded steel bars, and used for storing the corresponding threaded steel bars arranged in the vertical and horizontal directions, a plurality of welding grooves are provided on the supporting platform (17), and welding units for welding are placed in the welding grooves, and the supporting platform (17) is provided with a plurality of welding grooves. ) is provided with crisscrossing air guide pipes (20), the air guide pipes (20) are connected to the welding unit, the transverse air guide pipes (20) and the longitudinal air guide pipes (20) are respectively connected to their corresponding ventilation pipes (39), the ventilation pipes (39) are connected to the external gas tank, the adjacent two sides of the support platform (17) are connected to the follower plate (18) through the spring hinge, one side of the follower plate (18) is in contact with the discharge mechanism, and the follower plate (18) intermittently prevents the threaded steel from falling from the discharge mechanism, and the forming box (14) is also connected to the recovery box (15) for collecting materials.
7. The method for constructing an ultra-simple water pump inert platform according to claim 6, characterized in that: The welding unit includes a splicing box (40) located in the welding tank, a rectangular ventilation box (44) is provided in the splicing box (40), four vertical corners of the ventilation box (44) are connected to combustion tubes (41), the combustion tubes (41) are connected to a detector (46), and the detector (46) is connected to a plurality of sensors (45), a shunt pipe is provided in the ventilation box (44), one end of the shunt pipe is connected to the corresponding combustion tube (41), the bottom end of the shunt pipe is connected to a plug-in pipe (42), one end of the plug-in pipe (42) extends into the air guide pipe (20) and is in communication with the air guide pipe (20).
8. The method for constructing an ultra-simple water pump inert platform according to claim 7, characterized in that: The adjustment unit comprises a packaging box (23) fixedly connected to the forming box (14); a motor (33) is fixedly connected to the top of the packaging box (23); an output end of the motor (33) is transmission-connected to a transmission (32) located in the packaging box (23); an output end of the transmission (32) is transmission-connected to a transmission shaft (26); an outer side of the transmission shaft (26) is transmission-connected to a moving column (31) via a spline; the moving column (31) is provided with a plurality of M-shaped grooves (35) connected end to end along a circumferential direction; a limiting column (30) fixedly connected to the packaging box (23) is slidingly provided in the M-shaped groove (35). ), the limiting column (30) limits the moving column (31) to move up and down periodically through the M-shaped groove (35), the top of the moving column (31) is rotatably connected to the support frame (29), the top of the support frame (29) is fixedly connected to the pneumatic cylinder (34), the moving end of the pneumatic cylinder (34) is clamped with the connecting platform (27), the middle of the connecting platform (27) is provided with a telescopic rod 2 (22), the outer side of the telescopic rod 2 (22) is provided with a telescopic rod 1 (21) arranged along the circumference of the connecting platform (27), the moving ends of the telescopic rod 2 (22) and the telescopic rod 1 (21) are both rotatably connected to the bottom of the supporting platform (17).
9. The method for constructing an ultra-simple water pump inert platform according to claim 8, characterized in that: The molding unit comprises a vibration box (12) located in a molding box (14), a plurality of vibration motors (33) are fixedly connected in the vibration box (12), a guide groove is provided on the vibration box (12), and a molding die (13) located in the molding box (14) is slidably provided in the guide groove.
10. The method for constructing an ultra-simple water pump inert platform according to claim 9, characterized in that: The discharging mechanism includes an outer frame (19) connected to the moving end of the hydraulic cylinder (11), a raw material box (50) is arranged in the outer frame (19), a raw material box (51) is sleeved in the raw material box (50), a horizontal bar (01) and a vertical bar (02) are respectively placed in the raw material box (50) and the raw material box (51), the bottoms of the raw material box (50) and the raw material box (51) are connected to a discharge pipe (52), a plurality of electric telescopic rods (53) are slidably arranged on the discharge pipe (52), and the cross section of the discharge pipe (52) is an inclined F-shaped structure. The electric telescopic rod (53) is located at a position of a pipeline connected to the raw material box 1 (50) and the raw material box 2 (51), and the movable end portion of the electric telescopic rod (53) is located in the discharge pipe (52). The discharge pipe (52) is hollow, and one end of the discharge pipe (52) is connected to a discharge hole located at the bottom of the outer frame (19). The discharge hole cooperates with the follower plate (18). A plurality of vibration motors (55) are also connected to the outer frame (19). A controller (54) is placed in the middle of the outer frame (19) for controlling the extension and contraction of the movable end of the electric telescopic rod (53).
Citation Information
Patent Citations
Floating platform mounting structure and method for chemical equipment
CN112682622A
Steel pipe support forming device
CN117506261A
Concrete platform formwork erecting system utilizing steel frame H-shaped steel beam flange formwork erecting
CN216042613U
Grate welding device
KR1020110064186A