Substation-level one-key sequence control method and system based on combined interval thinking
Through the one-click sequence control method of substation based on combined interval thinking, the complex problem of multi-interval operation of substations is solved, efficient station-level one-click sequence control is achieved, and the automation level and operation and maintenance efficiency of substations are improved.
Patent Information
- Application Number
- CN202510563558.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-04-30
- Publication Date
- 2025-08-05
AI Technical Summary
The existing one-click sequence control technology of substations handles equipment operations at multiple intervals, making it difficult for operation and maintenance personnel to operate, especially in the switching of large-scale operation modes of 110kV substations.
Using a method based on combination interval thinking, the substation is divided into virtual combination intervals according to voltage levels, the sequence interval is defined and the association relationship is established, the operation mode and switching strategy are defined according to the operation procedures, the sequence operation ticket is configured, and the power is checked without interruption through the operation ticket verification tool, and the one-click sequence operation is finally realized.
It reduces the work burden of operation and maintenance personnel, improves the automation level of the substation, simplifies the shutdown operation process, and reduces the probability of misoperation.
Smart Images

Figure CN120433436A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of intelligent substations, and in particular to a substation-level one-button sequential control method and system based on combined interval thinking. Background Art
[0002] Substations are a vital component of the power system, converting high-voltage grid electricity into low-voltage power for power users. Substation one-touch sequential control technology uses advanced automation equipment and intelligent systems to enable remote monitoring, control, and operation of substation equipment. The basic principle is to transmit status information of various substation devices to a monitoring center through information transmission and data processing, and then remotely control and operate the equipment through the central system.
[0003] However, in the actual one-button sequential control process, in addition to the conventional single-bay decommissioning and recommissioning operations, the switching operation requirements of the daily operation and maintenance work of substations mainly based on 110kV are mainly concentrated on the large-scale operation mode switching at the station level. One operation task often involves the operation of equipment in multiple bays, which increases the operation difficulty for the operation and maintenance personnel. Summary of the Invention
[0004] The purpose of the present invention is to solve at least one technical problem in the background technology and to provide a substation-level one-button sequential control method and system based on combined interval thinking.
[0005] To achieve the above objectives, the present invention provides a substation-level one-button sequential control method based on combined interval thinking, comprising:
[0006] Define virtual combined bays according to substation voltage level type;
[0007] Define the corresponding sequence control interval according to the virtual combination interval and establish an association relationship with the virtual combination interval;
[0008] Define all interval operation modes of virtual combined intervals according to the operator's regulations;
[0009] Define the sequential control operation ticket according to the operator's regulations for the switching strategy requirements of all interval operation modes of the virtual combined interval;
[0010] Configure the sequential control operation ticket according to the operator's switching operation ticket text file;
[0011] The sequential control operation ticket is verified without power outage using the operation ticket verification tool and is set to the verified status;
[0012] Select the virtual combination interval, source operation mode, and target operation mode, match the corresponding sequence control operation ticket, and perform the sequence control execution operation after the rehearsal is successful.
[0013] According to one aspect of the present invention, the virtual combined interval is defined according to the substation voltage level type as follows:
[0014] The substation is defined as multiple virtual combined bays according to voltage levels, and corresponding virtual combined bay objects are created in the database.
[0015] According to one aspect of the present invention, a corresponding sequence interval is defined according to a virtual combination interval, and an association relationship is established with the virtual combination interval as follows:
[0016] Create a corresponding sequence interval object in the sequence configuration tool based on the virtual combined interval, and associate the corresponding virtual combined interval with the primary interval property of the sequence interval.
[0017] According to one aspect of the present invention, the operation modes of all intervals defined as virtual combined intervals according to the operator's regulations are as follows:
[0018] Create the corresponding bay status object in the database according to the substation operation regulations, then create the bay operation mode of all virtual combined bays in the sequence control configuration tool, and establish an association relationship with the corresponding sequence control bay, and each bay operation mode only matches one bay status object.
[0019] According to one aspect of the present invention, the switching strategy for all interval operation modes of the virtual combined interval according to the operator's regulations requires defining the sequential control operation ticket as follows:
[0020] Create a sequence control operation ticket object in the sequence control configuration tool according to the switching strategy of the interval operation mode of each virtual combination interval, and describe its sequence control direction.
[0021] According to one aspect of the present invention, configuring the sequential control operation ticket according to the transporter switching operation ticket text file includes:
[0022] In the sequence control configuration tool, associate the source and target operation modes of the sequence control operation ticket;
[0023] In the sequence control configuration tool, associate the instantaneous conditions, operation conditions and blocking signals of the sequence control operation ticket;
[0024] All steps to create a sequence control operation ticket in the sequence control configuration tool.
[0025] According to one aspect of the present invention, the operation ticket verification tool displays the contents of the sequential control operation ticket in a visual manner for verifying the face of the sequential control operation ticket; the contents of the sequential control operation ticket include operation task information, operation item information, operation condition information, and locking signal information;
[0026] The operation ticket verification tool is configured with an interval scheduling number confirmation function before the sequential control operation ticket is verified;
[0027] The operation ticket verification tool visually verifies the operation conditions, locking signals and target status of the operating equipment of the sequential control operation ticket;
[0028] Sequential control operation tickets that have not been successfully verified by the operation ticket verification tool are not allowed to be called for execution;
[0029] The operation ticket verification tool supports the start of a simulation verification process, and assists in verifying the operation object, operation item sequence, pre-execution conditions, confirmation conditions, and error prevention rules of the sequential control operation ticket by simulating the execution process of the sequential control operation ticket.
[0030] Furthermore, to achieve the above-mentioned purpose, the present invention also provides a substation-level one-button sequential control system based on combined interval thinking, comprising:
[0031] Virtual combination bay definition module, defines virtual combination bay according to substation voltage level type;
[0032] The interval association module defines the corresponding sequence control interval according to the virtual combination interval and establishes an association relationship with the virtual combination interval;
[0033] The operation mode definition module defines all interval operation modes of the virtual combined interval according to the operator's regulations;
[0034] The sequential control operation ticket definition module defines the sequential control operation ticket according to the operator's regulations for the switching strategy requirements of all interval operation modes of the virtual combined interval;
[0035] Sequential control operation ticket configuration module, configures sequential control operation tickets according to the operation ticket text file switched by the transporter;
[0036] Sequential control operation ticket verification module: Sequential control operation tickets are verified without power outages using the operation ticket verification tool and are set to the verified status;
[0037] In the sequence control execution module, select the virtual combination interval, source operation mode, and target operation mode, match the corresponding sequence control operation ticket, and perform the sequence control execution operation after the rehearsal is successful.
[0038] Furthermore, to achieve the above-mentioned purpose, the present invention also provides an electronic device, comprising a processor, a memory, and a computer program stored in the memory and runnable on the processor. When the computer program is executed by the processor, the substation-level one-button sequential control method based on combined interval thinking as described above is implemented.
[0039] Furthermore, to achieve the above-mentioned purpose, the present invention also provides a computer-readable storage medium, on which a computer program is stored. When the computer program is executed by a processor, the substation-level one-button sequential control method based on combined interval thinking as described above is implemented.
[0040] The present invention utilizes a "virtual station-level bay" concept to divide the entire station into virtual sequential control bays with different voltage levels. These bays define their operating modes and then pre-set one-click sequential control operation tickets for switching from one operating mode to another based on these virtual sequential control bays. This not only reduces the workload for operators and maintenance personnel but also allows for single-click switching operations, improving the substation's automation level.
[0041] The present invention proposes a substation-level one-button sequential control method based on combined interval thinking to realize the one-button sequential control operation function of "operation switching" of the substation, providing an effective technical means for the substation switching operation, improving the efficiency of on-site operation and maintenance, reducing the complexity of the substation switching operation, and greatly improving the automation level of the substation. BRIEF DESCRIPTION OF THE DRAWINGS
[0042] Figure 1 A flowchart schematically illustrates a substation-level one-button sequential control method based on combined bay thinking according to an embodiment of the present invention;
[0043] Figure 2 Schematically showing a flow chart of the substation-level 110kV virtual combined bay one-key sequential control configuration based on the combined bay concept of Example 1;
[0044] Figure 3 The flowchart of the substation-level 10kV virtual combined bay one-key sequential control configuration based on the combined bay concept of Example 2 is schematically shown. DETAILED DESCRIPTION
[0045] The present invention will now be discussed with reference to exemplary embodiments. It should be understood that the embodiments discussed are only for enabling those skilled in the art to better understand and implement the present invention, rather than implying any limitation on the scope of the present invention.
[0046] As used herein, the term "including" and variations thereof are to be interpreted as open-ended terms meaning "including, but not limited to." The term "based on" is to be interpreted as "based, at least in part, on." The terms "one embodiment" and "an embodiment" are to be interpreted as "at least one embodiment."
[0047] Figure 1 The flowchart of the substation level one-key sequential control method based on combined interval thinking according to one embodiment of the present invention is schematically shown. Figure 1 As shown, in this embodiment, the substation-level one-button sequential control method based on the combined interval thinking includes:
[0048] Define virtual combined bays according to substation voltage level type;
[0049] Define the corresponding sequence control interval according to the virtual combination interval and establish an association relationship with the virtual combination interval;
[0050] Define all interval operation modes of virtual combined intervals according to the operator's regulations;
[0051] Define the sequential control operation ticket according to the operator's regulations for the switching strategy requirements of all interval operation modes of the virtual combined interval;
[0052] Configure the sequential control operation ticket according to the operator's switching operation ticket text file;
[0053] The sequential control operation ticket is verified without power outage using the operation ticket verification tool and is set to the verified status;
[0054] Select the virtual combination interval, source operation mode, and target operation mode, match the corresponding sequence control operation ticket, and perform the sequence control execution operation after the rehearsal is successful.
[0055] Furthermore, according to an embodiment of the present invention, the virtual combined interval is defined according to the substation voltage level type as follows:
[0056] The substation is defined as multiple virtual combined bays according to voltage levels (such as 10kV, 110kV, 220kV, etc.), and corresponding virtual combined bay objects are created in the database.
[0057] Furthermore, according to an embodiment of the present invention, a corresponding sequence control interval is defined according to the virtual combination interval, and an association relationship is established with the virtual combination interval as follows:
[0058] Create a corresponding sequence interval object in the sequence configuration tool based on the virtual combined interval, and associate the corresponding virtual combined interval with the primary interval property of the sequence interval.
[0059] Furthermore, according to one embodiment of the present invention, all interval operation modes of the virtual combined interval are defined according to the operator's regulations as follows:
[0060] Create the corresponding interval status object in the database according to the substation operation regulations (i.e., substation operation and maintenance operation specifications and requirements), and then create the interval operation mode of all virtual combined intervals (such as operation side 1, operation side 2, ..., operation side N) in the sequential control configuration tool, and establish an association relationship with the corresponding sequential control interval, and each interval operation mode only matches one of the interval status objects.
[0061] Furthermore, according to an embodiment of the present invention, the switching strategy requirements for all interval operation modes of the virtual combined interval are defined as follows:
[0062] According to the switching strategy of the interval operation mode of each virtual combination interval (such as transport side X→ transport side Y), a sequence control operation ticket object is created in the sequence control configuration tool, and its sequence control direction is described.
[0063] Furthermore, according to an embodiment of the present invention, configuring a sequential control operation ticket according to the transporter switching operation ticket text file includes:
[0064] In the sequence control configuration tool, associate the source and target operation modes of the sequence control operation ticket;
[0065] In the sequence control configuration tool, associate the instantaneous conditions, operation conditions and blocking signals of the sequence control operation ticket;
[0066] All steps to create a sequence control operation ticket in the sequence control configuration tool.
[0067] Furthermore, according to one embodiment of the present invention, the operation ticket verification tool displays the contents of the sequential control operation ticket in a visual manner for verification of the face of the sequential control operation ticket; the contents of the sequential control operation ticket include operation task information (operation ticket name, current status, target status, version information), operation item information, operation condition information, and locking signal information;
[0068] The operation ticket verification tool is configured with the interval scheduling number confirmation function before the sequential control operation ticket is verified;
[0069] The operation ticket verification tool visually verifies the operation conditions, blocking signals, and target status of the operating equipment in the sequential control operation ticket;
[0070] Sequential control operation tickets that have not been successfully verified by the operation ticket verification tool are not allowed to be called for execution;
[0071] The operation ticket verification tool supports the launch of a simulation verification process. By simulating the execution process of a sequential operation ticket, it assists in verifying the operation object, operation item sequence, pre-execution conditions, confirmation conditions, and error prevention rules of the sequential operation ticket.
[0072] Furthermore, according to an embodiment of the present invention, a virtual combination interval, a source operation mode, and a target operation mode are selected, and a corresponding sequence control operation ticket is matched. After a successful preview, the sequence control execution operation is performed as follows:
[0073] After selecting the virtual combination interval, source operation mode, and target operation mode on the one-click sequential control execution interface of the operation ticket verification tool, match the corresponding sequential control operation ticket from the sequential control operation ticket library. After a successful rehearsal, perform the sequential control execution operation, including:
[0074] The one-button sequential control execution interface should support the selection of virtual combination intervals, source operation mode, and target operation mode;
[0075] The one-key sequence control execution interface should support matching the corresponding sequence control operation ticket from the sequence control operation ticket library;
[0076] The one-key sequence control execution interface should support functions such as preview, execution, suspension and termination of sequence control operation tickets;
[0077] Operation tickets that have not been successfully rehearsed are not allowed to be called for execution;
[0078] The one-button sequential control execution interface should support real-time display of the execution status, operating conditions and locking signal status of the current sequential control task and the verification results of the target status.
[0079] The above-mentioned solution utilizes a "virtual station-level bay" concept to divide the entire station into virtual sequential control bays with different voltage levels. These bays define their operating modes and then pre-set one-click sequential control operation tickets for switching from one operating mode to another based on these virtual sequential control bays. This not only reduces the workload of operators and maintenance personnel but also allows for single-click switching operations, improving the substation's automation level.
[0080] The present invention proposes a substation-level one-button sequential control method based on combined interval thinking to realize the one-button sequential control operation function of "operation switching" of the substation, providing an effective technical means for the substation switching operation, improving the efficiency of on-site operation and maintenance, reducing the complexity of the substation switching operation, and greatly improving the automation level of the substation.
[0081] Furthermore, to achieve the above-mentioned purpose, the present invention also provides a substation-level one-button sequential control system based on combined interval thinking, comprising:
[0082] Virtual combination bay definition module, defines virtual combination bay according to substation voltage level type;
[0083] The interval association module defines the corresponding sequence control interval according to the virtual combination interval and establishes an association relationship with the virtual combination interval;
[0084] The operation mode definition module defines all interval operation modes of the virtual combined interval according to the operator's regulations;
[0085] The sequential control operation ticket definition module defines the sequential control operation ticket according to the operator's regulations for the switching strategy requirements of all interval operation modes of the virtual combined interval;
[0086] Sequential control operation ticket configuration module, configures sequential control operation tickets according to the operation ticket text file switched by the transporter;
[0087] Sequential control operation ticket verification module: Sequential control operation tickets are verified without power outages using the operation ticket verification tool and are set to the verified status;
[0088] In the sequence control execution module, select the virtual combination interval, source operation mode, and target operation mode, match the corresponding sequence control operation ticket, and perform the sequence control execution operation after the rehearsal is successful.
[0089] The above-mentioned substation-level one-button sequential control system based on combined interval thinking according to the present invention can realize the above-mentioned substation-level one-button sequential control method based on combined interval thinking. The specific method steps are as described above and will not be repeated here.
[0090] Furthermore, to achieve the above-mentioned purpose, the present invention also provides an electronic device, including a processor, a memory, and a computer program stored in the memory and runnable on the processor. When the computer program is executed by the processor, the substation-level one-button sequential control method based on the combined interval thinking as described above is implemented.
[0091] Furthermore, to achieve the above-mentioned purpose, the present invention also provides a computer-readable storage medium, on which a computer program is stored. When the computer program is executed by a processor, the substation-level one-button sequential control method based on combined interval thinking as described above is implemented.
[0092] Furthermore, based on the above-mentioned solutions of the present invention, the technical solutions of the present invention are described in detail below in the form of specific embodiments in conjunction with the accompanying drawings.
[0093] Example 1
[0094] This embodiment takes a 220kV substation as an example to provide a substation-level one-key sequential control method based on combined interval thinking. Figure 2 Shown, including:
[0095] Define virtual combined bays according to substation voltage level type;
[0096] Define the corresponding sequence control interval according to the virtual combination interval and establish an association relationship with the virtual combination interval;
[0097] Define all interval operation modes of virtual combined intervals according to the operator's regulations;
[0098] Define the sequential control operation ticket according to the operator's regulations on the switching strategy requirements for the virtual combined interval operation mode;
[0099] Configure the sequential control operation ticket according to the operator switching operation ticket text file provided by the operation and maintenance personnel;
[0100] The sequential control operation ticket is verified without power outage using the "Operation Ticket Verification Tool" and is set to the "Verified" status;
[0101] In the one-key sequence execution interface, select the virtual combination interval, source operation mode, and target operation mode, match the corresponding sequence ticket from the sequence operation ticket library, and execute the operation after a successful rehearsal.
[0102] In this embodiment, defining a virtual combined interval according to the substation voltage level type includes:
[0103] The substation is defined as two virtual combination bays of 110kV and 10kV according to the voltage level, and two virtual combination bays of "110kV transport switching" and "10kV transport switching" are created in the database.
[0104] In this embodiment, defining a corresponding sequential control interval according to the "110kV operation switching" virtual combination interval and establishing an association relationship with the virtual combination interval includes:
[0105] Create a "110kV transport switching sequence control ticket group" sequence control interval object in the sequence control configuration tool based on the "110kV transport switching" virtual combination interval, and associate this virtual combination interval with the "primary interval corresponding to the sequence control interval" attribute;
[0106] In this embodiment, all bay operation modes of the "110kV operator switching" virtual combined bay are defined according to the operator's regulations, including:
[0107] According to the substation operation regulations (i.e., substation operation and maintenance specifications and requirements), two bay status objects, "110kV Mode 1" and "110kV Mode 2", are created in the database;
[0108] In the sequence control configuration tool, create the operating modes of the 110kV virtual combined bay, namely "110kV operation mode 1" and "110kV operation mode 2", and associate the "110kV operator switching sequence control ticket group" sequence control bay.
[0109] In this embodiment, according to the operator's regulations for the switching strategy requirements of the "110kV operator switching" virtual combined bay operation mode, the sequential control operation ticket is defined to include:
[0110] According to the switching strategy of the "110kV transport party switching" virtual combined interval operating mode (such as transport party X→ transport party Y), create the sequential control operation ticket objects "110kV transport party switching from 110kV mode 1 to 110kV mode 2" and "110kV transport party switching from 110kV mode 2 to 110kV mode 1" in the sequential control configuration tool. Among them, the sequential control direction of the former is sequential control to the "110kV mode 2" operating mode, and the sequential control direction of the latter is sequential control to the "110kV mode 1" operating mode.
[0111] In this embodiment, the sequential control operation ticket is configured according to the operation switching operation ticket text file provided by the operation and maintenance personnel, including:
[0112] In the sequential control configuration tool, associate the source operating mode "110kV Mode 1" and the target operating mode "110kV Mode 2" of the sequential control operation ticket "110kV transport switching changed from 110kV Mode 1 to 110kV Mode 2". Also associate the source operating mode "110kV Mode 2" and the target operating mode "110kV Mode 1" of the sequential control operation ticket "110kV transport switching changed from 110kV Mode 2 to 110kV Mode 1".
[0113] In the sequential control configuration tool, associate the instantaneous conditions, operating conditions, and blocking signals of the sequential control operation tickets "110kV transport switching changed from 110kV mode 1 to 110kV mode 2" and "110kV transport switching changed from 110kV mode 2 to 110kV mode 1";
[0114] Create all the operation steps of the sequential control operation ticket "110kV transport side switching changed from 110kV mode 1 to 110kV mode 2" and "110kV transport side switching changed from 110kV mode 2 to 110kV mode 1" in the sequential control configuration tool.
[0115] In this embodiment, the sequential control operation ticket is "verified without power outage" by the "operation ticket verification tool" and then set to the "verified" state, including:
[0116] The operation ticket verification tool should visually display the contents of the sequential control operation ticket "110kV operation side switching changed from 110kV mode 1 to 110kV mode 2" and "110kV operation side switching changed from 110kV mode 2 to 110kV mode 1" for verification personnel to verify the ticket;
[0117] Verify the current sequential control operation task information (operation ticket name, current status, target status, version information), operation item information, operation condition information and locking signal information;
[0118] Check the interval dispatch number confirmation function before the sequential control ticket verification to see if it needs to be confirmed and can be configured;
[0119] Check operating conditions, blocking signals, and visual verification of target status of operating equipment;
[0120] Operation tickets that have not been successfully verified by the one-key sequence control verification tool are not allowed to be called for execution;
[0121] The operation ticket verification tool simulates the verification process. The simulation verification interface is based on the existing one-key sequential control interface with expanded functions. By simulating the execution process of the sequential control operation ticket, it assists the verification personnel in verifying the operation object, operation item sequence, pre-execution conditions, confirmation conditions, and error prevention rules of the sequential control operation ticket.
[0122] In this embodiment, after selecting the virtual combination interval, source operation mode, and target operation mode on the one-key sequence control execution interface, the corresponding sequence control ticket is matched from the sequence control operation ticket library. After the preview is successful, the sequence control execution operation is performed, including:
[0123] In the one-key sequential control execution interface, select the corresponding virtual combined bay "110kV transport switching", source operation mode "110kV mode 1" and target operation mode "110kV mode 2" according to the operation task, and then match the corresponding sequential control operation ticket "110kV transport switching from 110kV mode 1 to 110kV mode 2" from the sequential control operation ticket library. Then add a sequential control operation task. In the one-key sequential control interface, select the corresponding virtual combined bay "110kV transport switching", source operation mode "110kV mode 2" and target operation mode "110kV mode 1" according to the operation task, and then match the corresponding sequential control operation ticket "110kV transport switching from 110kV mode 2 to 110kV mode 1" from the sequential control operation ticket library.
[0124] Preview and execute all sequential control operation tickets in sequence on the one-key sequential control execution interface;
[0125] In the one-key sequence execution interface, you can observe the execution status, operating conditions, blocking signal status of the current sequence task, and the verification results of the target status in real time.
[0126] Example 2
[0127] This embodiment takes another substation as an example to provide a substation-level one-key sequential control method based on combined interval thinking, such as Figure 3 Shown, including:
[0128] Define virtual combined bays according to substation voltage level type;
[0129] Define the corresponding sequence control interval according to the virtual combination interval and establish an association relationship with the virtual combination interval;
[0130] Define all interval operation modes of virtual combined intervals according to the operator's regulations;
[0131] Define the sequential control operation ticket according to the operator's regulations on the switching strategy requirements for the virtual combined interval operation mode;
[0132] Configure the sequential control operation ticket according to the operator switching operation ticket text file provided by the operation and maintenance personnel;
[0133] The sequential control operation ticket is verified without power outage using the "Operation Ticket Verification Tool" and is set to the "Verified" status;
[0134] In the one-key sequence execution interface, select the virtual combination interval, source operation mode, and target operation mode, match the corresponding sequence ticket from the sequence operation ticket library, and execute the operation after a successful rehearsal.
[0135] In this embodiment, defining a virtual combined interval according to the substation voltage level type includes:
[0136] The substation is defined as two virtual combination bays of 110kV and 10kV according to the voltage level, and two virtual combination bays of "110kV transport switching" and "10kV transport switching" are created in the database.
[0137] In this embodiment, defining a corresponding sequential control interval according to the "10kV operation switching" virtual combination interval and establishing an association relationship with the virtual combination interval includes:
[0138] Create a "10kV transport switching sequence control ticket group" sequence control interval object in the sequence control configuration tool based on the "10kV transport switching" virtual combination interval, and associate the virtual combination interval with the "primary interval corresponding to the sequence control interval" attribute;
[0139] In this embodiment, all bay operation modes of the "110kV operator switching" virtual combined bay are defined according to the operator's regulations, including:
[0140] According to the substation operation regulations (i.e., substation operation and maintenance specifications and requirements), three national grid interval status objects, "10kV Mode 1", "10kV Mode 2" and "10kV Mode 3", are created in the database;
[0141] In the sequence control configuration tool, create the operating modes of the 110kV virtual combined bay, namely "10kV operation mode 1", "10kV operation mode 2" and "10kV operation mode 3", and associate the "10kV operator switching sequence control ticket group" sequence control bay.
[0142] In this embodiment, according to the operator's regulations for the switching strategy requirements of the "10kV operator switching" virtual combined bay operation mode, the sequential control operation ticket is defined to include:
[0143] According to the switching strategy of the "10kV operator switching" virtual combined interval operating mode (such as operator X→operator Y), create sequential control operation ticket objects "10kV operator switching from 10kV mode 1 to 10kV mode 2", "10kV operator switching from 10kV mode 2 to 10kV mode 3", and "10kV operator switching from 10kV mode 3 to 10kV mode 1" in the sequential control configuration tool. Among them, the sequential control directions of the sequential control operation tickets are sequential control to the "10kV mode 2" operating mode, sequential control to the "10kV mode 3" operating mode, and sequential control to the "10kV mode 1" operating mode.
[0144] In this embodiment, configuring the sequential control operation ticket according to the operation switching operation ticket text file provided by the operation and maintenance personnel includes:
[0145] In the sequential control configuration tool, associate the source operating mode "10kV Mode 1" and the target operating mode "10kV Mode 2" of the sequential control operation ticket "10kV transport switching changed from 10kV Mode 1 to 10kV Mode 2", associate the source operating mode "10kV Mode 2" and the target operating mode "10kV Mode 3" of the sequential control operation ticket "10kV transport switching changed from 10kV Mode 2 to 10kV Mode 3", and associate the source operating mode "10kV Mode 3" and the target operating mode "10kV Mode 1" of the sequential control operation ticket "10kV transport switching changed from 10kV Mode 3 to 10kV Mode 1";
[0146] In the sequential control configuration tool, associate the instantaneous conditions, operating conditions, and blocking signals of the sequential control operation tickets "10kV transport switching changed from 10kV mode 1 to 10kV mode 2", "10kV transport switching changed from 10kV mode 2 to 10kV mode 3", and "10kV transport switching changed from 10kV mode 3 to 10kV mode 1";
[0147] In the sequential control configuration tool, create all the operation steps of the sequential control operation ticket "10kV transport side switching changed from 10kV mode 1 to 10kV mode 2", "10kV transport side switching changed from 10kV mode 2 to 10kV mode 3" and "10kV transport side switching changed from 10kV mode 3 to 10kV mode 1".
[0148] In this embodiment, the sequential control operation ticket is "verified without power outage" by the "operation ticket verification tool" and is set to the "verified" state, including:
[0149] The operation ticket verification tool should visually display the contents of the sequential control operation ticket, such as "10kV operation side switching changed from 10kV mode 1 to 10kV mode 2", "10kV operation side switching changed from 10kV mode 2 to 10kV mode 3", and "10kV operation side switching changed from 10kV mode 3 to 10kV mode 1", for verification personnel to verify the ticket surface;
[0150] Verify the current sequential control operation task information (operation ticket name, current status, target status, version information), operation item information, operation condition information and locking signal information;
[0151] Check the interval dispatch number confirmation function before the sequential control ticket verification to see if it needs to be confirmed and can be configured;
[0152] Check operating conditions, blocking signals, and visual verification of target status of operating equipment;
[0153] Operation tickets that have not been successfully verified by the one-key sequence control verification tool are not allowed to be called for execution;
[0154] The operation ticket verification tool simulates the verification process. The simulation verification interface is based on the existing one-key sequential control interface with expanded functions. By simulating the execution process of the sequential control operation ticket, it assists the verification personnel in verifying the operation object, operation item sequence, pre-execution conditions, confirmation conditions, and error prevention rules of the sequential control operation ticket.
[0155] In this embodiment, after selecting the virtual combination interval, source operation mode, and target operation mode in the one-key sequence control execution interface, the corresponding sequence control ticket is matched from the sequence control operation ticket library. After the preview is successful, the execution operation includes:
[0156] In the one-key sequential control execution interface, select the corresponding virtual combination interval "10kV operation switching", source operation mode "10kV mode 1" and target operation mode "10kV mode 2" according to the operation task, then match the corresponding sequential control operation ticket "10kV operation switching from 10kV mode 1 to 10kV mode 2" from the sequential control operation ticket library, and then add the sequential control operation task. In the one-key sequential control interface, select the corresponding virtual combination interval "10kV operation switching", source operation mode "10kV mode 2" and target operation mode according to the operation task. Select "10kV Mode 3" and then match the corresponding sequential control operation ticket "10kV operation switching from 10kV Mode 2 to 10kV Mode 3" from the sequential control operation ticket library. Continue to add sequential control operation tasks. In the one-key sequential control interface, select the corresponding virtual combined interval "10kV operation switching", source operation mode "10kV Mode 3" and target operation mode "10kV Mode 1" according to the operation task. Then match the corresponding sequential control operation ticket "10kV operation switching from 10kV Mode 3 to 10kV Mode 1" from the sequential control operation ticket library.
[0157] Preview and execute all sequential control operation tickets in sequence on the one-key sequential control execution interface;
[0158] In the one-key sequence execution interface, you can observe the execution status, operating conditions, blocking signal status of the current sequence task, and the verification results of the target status in real time.
[0159] The substation-level one-button sequential control method based on combined interval thinking provided in this embodiment can improve the automation level and reliability of the substation one-button sequential control, simplify the operation process of cross-interval one-button sequential control by operation and maintenance personnel, and reduce the operation difficulty of one-button sequential control and the probability of erroneous switching operation.
[0160] Those skilled in the art will appreciate that the modules and algorithm steps described in conjunction with the embodiments disclosed herein can be implemented using electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are implemented in hardware or software depends on the specific application and design constraints of the technical solution. Professionals and technicians may use different methods to implement the described functions for each specific application, but such implementation should not be considered beyond the scope of the present invention.
[0161] Those skilled in the art will clearly understand that, for the convenience and brevity of description, the specific working processes of the above-described devices and equipment can refer to the corresponding processes in the aforementioned method implementation methods and will not be repeated here.
[0162] In the embodiments provided in this application, it should be understood that the disclosed devices and methods can be implemented in other ways. For example, the device embodiments described above are merely illustrative. For example, the division of the modules is merely a logical function division. In actual implementation, there may be other division methods, such as multiple modules or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of devices or modules, which can be electrical, mechanical or other forms.
[0163] The modules described as separate components may or may not be physically separate, and the components shown as modules may or may not be physical modules, that is, they may be located in one place or distributed across multiple network modules. Some or all of the modules may be selected according to actual needs to achieve the objectives of the embodiments of the present invention.
[0164] In addition, each functional module in the embodiment of the present invention may be integrated into one processing module, or each module may exist physically separately, or two or more modules may be integrated into one module.
[0165] If the functions are implemented as software modules and sold or used as standalone products, they can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, or the portion that contributes to the prior art, or a portion of the technical solution, can be embodied in the form of a software product. This computer software product is stored in a storage medium and includes instructions for enabling a computer device (which can be a personal computer, server, or network device, etc.) to perform all or part of the steps of the energy-saving signal transmission / reception method according to various embodiments of the present invention. The aforementioned storage medium includes various media capable of storing program code, such as a USB flash drive, a mobile hard drive, ROM, RAM, a magnetic disk, or an optical disk.
[0166] The above description is merely a preferred embodiment of the present application and an illustration of the technical principles employed. Those skilled in the art should understand that the scope of the invention involved in this application is not limited to the technical solutions formed by the specific combination of the above-mentioned technical features, but also encompasses other technical solutions formed by any combination of the above-mentioned technical features or their equivalents without departing from the inventive concept. For example, a technical solution formed by replacing the above-mentioned features with (but not limited to) technical features with similar functions disclosed in this application.
[0167] It should be understood that the size of the serial numbers of each step in the content of the invention and the implementation methods of the present invention does not absolutely mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the implementation methods of the present invention.
Claims
1. A one-button sequential control method for substations based on combined interval thinking is characterized by: include: Define virtual combined bays according to substation voltage level type; Define the corresponding sequence control interval according to the virtual combination interval and establish an association relationship with the virtual combination interval; Define all interval operation modes of virtual combined intervals according to the operator's regulations; Define the sequential control operation ticket according to the operator's regulations for the switching strategy requirements of all interval operation modes of the virtual combined interval; Configure the sequential control operation ticket according to the operator's switching operation ticket text file; The sequential control operation ticket is verified without power outage using the operation ticket verification tool and is set to the verified status; Select the virtual combination interval, source operation mode, and target operation mode, match the corresponding sequence control operation ticket, and perform the sequence control execution operation after the rehearsal is successful.
2. The substation-level one-button sequential control method based on combined interval thinking according to claim 1 is characterized in that: The virtual combined interval is defined according to the substation voltage level type as follows: The substation is defined as multiple virtual combined bays according to voltage levels, and corresponding virtual combined bay objects are created in the database.
3. The substation-level one-button sequential control method based on combined interval thinking according to claim 1 is characterized in that: Define the corresponding sequence control interval according to the virtual combination interval, and establish an association relationship with the virtual combination interval as follows: Create a corresponding sequence interval object in the sequence configuration tool based on the virtual combined interval, and associate the corresponding virtual combined interval with the primary interval property of the sequence interval.
4. The substation-level one-button sequential control method based on combined interval thinking according to claim 1 is characterized in that: All interval operation modes of the virtual combined intervals defined according to the operator's regulations are as follows: Create the corresponding bay status object in the database according to the substation operation regulations, then create the bay operation mode of all virtual combined bays in the sequence control configuration tool, and establish an association relationship with the corresponding sequence control bay, and each bay operation mode only matches one bay status object.
5. The substation-level one-button sequential control method based on combined interval thinking according to claim 1 is characterized in that: The switching strategy for all interval operation modes of the virtual combined interval according to the operator's regulations requires the definition of the sequential control operation ticket as follows: Create a sequence control operation ticket object in the sequence control configuration tool according to the switching strategy of the interval operation mode of each virtual combination interval, and describe its sequence control direction.
6. The substation-level one-button sequential control method based on combined interval thinking according to claim 1 is characterized in that: The configuration of the sequential control operation ticket according to the transport party switching operation ticket text file includes: In the sequence control configuration tool, associate the source and target operation modes of the sequence control operation ticket; In the sequence control configuration tool, associate the instantaneous conditions, operation conditions and blocking signals of the sequence control operation ticket; All steps to create a sequence control operation ticket in the sequence control configuration tool.
7. The substation-level one-button sequential control method based on combined interval thinking according to any one of claims 1 to 6 is characterized in that: The operation ticket verification tool displays the contents of the sequential control operation ticket in a visual manner for verification of the face of the sequential control operation ticket; the contents of the sequential control operation ticket include operation task information, operation item information, operation condition information and locking signal information; The operation ticket verification tool is configured with an interval scheduling number confirmation function before the sequential control operation ticket is verified; The operation ticket verification tool visually verifies the operation conditions, locking signals and target status of the operating equipment of the sequential control operation ticket; Sequential control operation tickets that have not been successfully verified by the operation ticket verification tool are not allowed to be called for execution; The operation ticket verification tool supports the start of a simulation verification process, and assists in verifying the operation object, operation item sequence, pre-execution conditions, confirmation conditions, and error prevention rules of the sequential control operation ticket by simulating the execution process of the sequential control operation ticket.
8. The substation-level one-button sequential control system based on combined interval thinking is characterized by: include: Virtual combination bay definition module, defines virtual combination bay according to substation voltage level type; The interval association module defines the corresponding sequence control interval according to the virtual combination interval and establishes an association relationship with the virtual combination interval; The operation mode definition module defines all interval operation modes of the virtual combined interval according to the operator's regulations; The sequential control operation ticket definition module defines the sequential control operation ticket according to the operator's regulations for the switching strategy requirements of all interval operation modes of the virtual combined interval; Sequential control operation ticket configuration module, configures sequential control operation tickets according to the operation ticket text file switched by the transporter; Sequential control operation ticket verification module: Sequential control operation tickets are verified without power outages using the operation ticket verification tool and are set to the verified status; In the sequence control execution module, select the virtual combination interval, source operation mode, and target operation mode, match the corresponding sequence control operation ticket, and perform the sequence control execution operation after the rehearsal is successful.
9. An electronic device, characterized in that It includes a processor, a memory, and a computer program stored in the memory and capable of running on the processor. When the computer program is executed by the processor, it implements the substation-level one-button sequential control method based on combined interval thinking as described in any one of claims 1 to 7.
10. A computer-readable storage medium, characterized in that The computer-readable storage medium stores a computer program, and when the computer program is executed by the processor, the substation-level one-key sequential control method based on combined interval thinking according to any one of claims 1 to 7 is implemented.