Benefits of technology

[0017]本发明的优点在于,挖掘作业舱在压缩空气的配合下,实现水下挖掘区域的无水化,方便了水下化学武器危险品挖掘操作,与常规水上围堰挖掘相比,本发明操作更加方便和灵活;因水下舱可重复利用从而使得挖掘成本更低。

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120589141B_ABST
    Figure CN120589141B_ABST
Patent Text Reader

Abstract

A multi-directional movable underwater excavation cabin is composed of a dangerous goods excavation work ship buoyancy hull, an underwater excavation work cabin, an underwater excavation work cabin lifting device, an underwater excavation work cabin lifting guide structure, a compressed air pipeline, a crane, an underwater camera, an internal pressure monitor, an external water pressure monitor and the like. The underwater dangerous goods excavation work cabin of the present application is installed on a special work ship which can sail and position itself, and the underwater excavation cabin lifting device installed on the ship is used to place the underwater excavation work cabin into water until the bottom of the underwater cabin contacts the river bottom. Compressed air is injected into the underwater cabin through the compressed air system on the ship, and when the pressure of the compressed air is greater than the pressure outside the excavation cabin, the water in the underwater cabin can be pressed out of the excavation cabin, so that the river bottom in the covered area of the excavation cabin is in a water-free state.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of underwater excavation and transfer vessel design and construction, specifically relating to an underwater excavation work cabin that can move in multiple directions. Background Technology

[0002] How to accelerate the excavation process, reduce the excavation costs, and excavate these chemical weapons, which could endanger people's safety at any time, from underwater in the shortest possible time has become a huge challenge. Summary of the Invention

[0003] To address the above problems, this invention provides an underwater excavation work cabin that can move in multiple directions, and the technical solution adopted is as follows: An underwater excavation work cabin that can move in multiple directions has a buoyancy hull located on the water surface, a water-passing moon pool set in the center of the buoyancy hull, the underwater excavation cabin located in the middle of the moon pool, longitudinal guide rails set on the decks on both sides of the moon pool, and longitudinal hydraulic cylinders fixed on the longitudinal guide rails.

[0004] Two transverse guide rails are provided between the two longitudinal guide rails. The transverse guide rails are perpendicular to the longitudinal guide rails and their ends are slidably connected to the longitudinal slide rails. The cylinder body of the longitudinal hydraulic cylinder is fixed on the longitudinal guide rail, and the top of the hydraulic rod of the longitudinal hydraulic cylinder is fixedly connected to the transverse guide rail. A transverse hydraulic cylinder is fixed on the transverse guide rail. The cylinder body of the transverse hydraulic cylinder is fixed on the transverse guide rail, and the top of the hydraulic rod of the transverse hydraulic cylinder is fixedly connected to the movable support on the top of the underwater excavation chamber. The movable support is slidably connected to the transverse guide rail.

[0005] The underwater excavation compartment is divided into two parts: the upper part is the pressure regulating compartment, and the lower part is the excavation operation compartment. The excavation operation compartment has side and top bulkheads, but no bottom plate, resembling an inverted bottomless box.

[0006] Furthermore, the underwater excavation work cabin described above, which can move in multiple directions, is equipped with three vertical support guide columns, a rack is provided along the height direction of the support guide columns, and a matching gear is fixed on the guide frame. The underwater excavation cabin can move up and down through the moon pool through the cooperation of the rack and gear.

[0007] One of the supporting guide columns is a personnel passage column, the bottom of which is connected to the pressure regulating chamber, which is connected to the excavation work chamber; another supporting guide column is a hazardous materials transfer column, the bottom of which is connected to the excavation work chamber; and the last one is a supporting guide column.

[0008] The buoyancy vessel has lifting holes around its hull, and lifting devices are fixed to the lifting holes. Positioning stakes pass through the lifting holes and are movably connected to the buoyancy vessel through the lifting devices.

[0009] Furthermore, the aforementioned underwater excavation work cabin, which can move in multiple directions, is equipped with an air compression system and an underwater chemical hazard scanning device. The air compression system is connected to the pressure regulating chamber and the excavation work cabin through compression pipelines.

[0010] Furthermore, the aforementioned underwater excavation work cabin, which can move in multiple directions, is further provided with multiple cross braces between adjacent support guide columns.

[0011] Furthermore, the aforementioned underwater excavation work cabin that can move in multiple directions has hollow interiors for the personnel passage pillars and hazardous materials transfer pillars. The personnel passage pillars are equipped with ladders that extend from the top to the bottom and into the pressure regulating chamber, which is also equipped with ladders.

[0012] Furthermore, in the aforementioned underwater excavation work cabin that can move in multiple directions, a manhole cover is provided between the bottom of the personnel passage pillar and the pressure regulating chamber, and a manhole cover is provided between the pressure regulating chamber and the excavation work cabin.

[0013] Furthermore, in the aforementioned underwater excavation work cabin that can move in multiple directions, the moon pool is rectangular, and the longitudinal guide rail is located on the deck at the short side of the rectangle, with the length of the longitudinal guide rail being greater than the length of the short side of the moon pool.

[0014] Furthermore, the aforementioned underwater excavation work cabin, which can move in multiple directions, is equipped with propulsion and positioning thrusters around its buoyancy hull.

[0015] Furthermore, the aforementioned underwater excavation work cabin that can move in multiple directions has a lifting device consisting of a hydraulic cylinder and a pin. The hydraulic cylinder is installed on the buoyancy hull, and the pin is connected to the pin hole on the positioning pile. By using the extension, retraction, and pushing / pulling of the hydraulic cylinder, the positioning pile is lowered underwater and inserted into the mud at the bottom of the river.

[0016] Furthermore, the aforementioned underwater excavation work cabin, which can move in multiple directions, is also equipped with a generator power system, living quarters, and a control room on its buoyancy hull.

[0017] The advantages of this invention are that, with the assistance of compressed air, the excavation work chamber achieves waterless excavation of the underwater excavation area, which facilitates the excavation of underwater chemical weapons and hazardous materials. Compared with conventional above-water cofferdam excavation, this invention is more convenient and flexible to operate; and because the underwater chamber can be reused, the excavation cost is lower.

[0018] Driven by a mobile device, the excavation work compartment can be moved forward, backward, left, and right within the moon pool area of ​​the excavator, increasing the excavation work area and greatly improving the efficiency of excavation operations after a single positioning. Because the excavation operation is performed under pressure, if hazardous materials leak due to corrosion during the excavation process, the pressure inside the compartment is greater than the internal pressure of the hazardous materials, preventing the hazardous gases from escaping and diffusing from the hazardous material's shell, thus improving safety during the excavation process.

[0019] To prevent the pressure inside the excavation chamber from being too much greater than the pressure outside, which could cause gas to leak out into the water and waste energy, a water pressure monitor is installed outside the excavation chamber to monitor the water pressure at different water depths. Attached Figure Description

[0020] Figure 1 This is a plan view of the deck of the underwater hazardous materials excavation and transfer vessel of the present invention; Figure 2 This is a side view of the underwater hazardous materials excavation and transfer vessel of the present invention in a floating state; Figure 3 This is a side view of the underwater hazardous materials excavation and transfer vessel of the present invention after the floating positioning pile is inserted into the mud and the excavation chamber is lowered to the bottom of the water. Figure 4 This is a schematic diagram showing the underwater excavation compartment of the present invention arranged at different positions within the moon pool area of ​​the hull; Figure 5 This is a schematic diagram of the underwater excavation cabin moving device arrangement of the present invention; Figure 6 This is a top-down view of the excavation work cabin; Figure 7 This is a top-down view of the pressure regulating chamber; Figure 8 This is a typical elevation view of the underwater excavation compartment of the present invention; Figure 9 This is a schematic diagram of a typical process for underwater excavation of hazardous materials according to the present invention; Among them, 1. Dangerous goods dredging vessel; 2. Underwater dredging compartment; 2-1. Dredging compartment; 2-2. Pressure regulating compartment; 2-3. Personnel access pillar; 2-4. Dangerous goods transport pillar; 2-5. Support pillar; 2-6. Horizontal bracing structure; 2-7. Rack and pinion; 2-8. Internal personnel ladder of pillar; 2-9. External personnel ladder of pillar; 2-10. Ladder to the dredging compartment; 2-11. Manhole cover to the dredging compartment; 2-12. Manhole cover to the pressure regulating compartment; 2-13. Manhole leading from the pressure regulating compartment to the dangerous goods transport channel pillar. Manhole cover, 2-14, Manhole cover for the column leading from the excavation work compartment to the hazardous materials transport channel, 2-15, Inner manhole cover for the column of the hazardous materials transport channel, 2-16, Outer manhole cover for the column of the hazardous materials transport channel, 2-17, Outer manhole cover for the column of the personnel passage, 2-18, Airtight operating handhole, 3, Gear, 4, Transverse guide rail, 5, Compressed air pipeline, 6, Crane, 7, Underwater camera, 8, Water pressure monitor, 9, Air pressure monitor, 10, Positioning stake, 11, Thruster, 12, Longitudinal guide rail, 4-4, Longitudinal hydraulic cylinder, 4-6, Transverse hydraulic cylinder. Detailed Implementation

[0021] The invention will be further described with reference to the accompanying drawings.

[0022] A multi-directionally movable underwater excavation work cabin, such as Figures 1-9 As shown, there is a buoyancy hull on the water surface, with a water-passing moon pool at the center of the buoyancy hull. The underwater excavation compartment is located in the middle of the moon pool, and longitudinal guide rails are installed on the decks on both sides of the moon pool. Longitudinal hydraulic cylinders are fixed on the longitudinal guide rails.

[0023] Two transverse guide rails are provided between the two longitudinal guide rails. The transverse guide rails are perpendicular to the longitudinal guide rails. The two ends of the transverse guide rails are slidably connected to the longitudinal slide rails. The cylinder body of the longitudinal hydraulic cylinder is fixed on the longitudinal guide rail, and the top of the hydraulic rod of the longitudinal hydraulic cylinder is fixedly connected to the transverse guide rail. A transverse hydraulic cylinder is fixed on the transverse guide rail. The cylinder body of the transverse hydraulic cylinder is fixed on the transverse guide rail, and the top of the hydraulic rod of the transverse hydraulic cylinder is fixedly connected to the movable support on the top of the underwater excavation chamber. The movable support is slidably connected to the transverse guide rail. The underwater excavation compartment is divided into two parts: the upper part is the pressure regulating compartment, and the lower part is the excavation operation compartment. The excavation operation compartment has side and top bulkheads, but no bottom plate, resembling an inverted bottomless box.

[0024] The underwater excavation compartment 2 and related facilities installed on it were hoisted and installed as a whole between the moon pool and the guide frame 4 of the excavation compartment.

[0025] Adjust the hydraulic cylinder and auxiliary system of the excavation work cabin lifting device to ensure a good fit between the hydraulic cylinder of the lifting device and the pin hole on the lifting guide plate structure on the underwater excavation cabin, so as to enable the underwater work cabin 2 to be lowered into the water from the moon pool area or retrieved from the water into the moon pool area of ​​the hull.

[0026] Connect and debug the compressed air pipeline 5 to the compressed air system of the excavator to ensure that the compressed air system can deliver compressed air to the excavation work chamber 2-1 and the pressure regulating chamber 2-2 through the compressed air pipeline 5.

[0027] After completing the above installation and commissioning work, the underwater hazardous materials excavation and transfer vessel can then proceed to relevant waters to conduct underwater hazardous materials detection work as needed, such as... Figure 2 As shown, the underwater hazardous materials excavation and transfer vessel floats on the water surface and can navigate freely on the water by propulsion and positioning thrusters.

[0028] When dangerous materials are found underwater or in the mud, the propulsion and positioning thrusters of the dredging and transfer vessel must be switched from navigation mode to positioning mode. The dredging and transfer vessel is positioned with the center of the dredging compartment 2 as the vessel positioning center and the location of the discovered dangerous materials as the reference center. The propulsion and positioning thrusters are used to slowly align the vessel positioning center with the reference center of the dangerous materials.

[0029] Start the positioning pile lifting device on the excavation and transfer vessel, and slowly lower the positioning pile into the water until the positioning pile is fully inserted into the underwater mud bed and the excavation vessel 1 is fixed on the water surface, ensuring that the vessel's movement will not be affected by waves during the excavation process.

[0030] The gears of the underwater excavation compartment are activated, and the compartment is slowly lowered into the water by the lifting device. The descent is temporarily stopped when the compartment is about to be lowered to the concrete surface.

[0031] By checking the water pressure at this location using the water pressure monitoring instrument 8 installed outside the excavation compartment, the air compressor and compressed air system on the excavation transfer vessel are started. The compressed air generated by the air compressor is transported to the lower excavation working compartment of the excavation compartment 2 through the compressed air pipeline 5. As the compressed air pressure increases, when the compressed air pressure is greater than the water pressure at this location, the water in the excavation compartment will be forced out of the excavation compartment from the bottom of the excavation compartment by the compressed air.

[0032] Reactivate the lifting device of the underwater excavation compartment 2, and slowly lower the underwater excavation compartment 2 to the underwater mud surface. Continue to lower the underwater excavation compartment 2 until the bottom of the side panel of the lower excavation work compartment of the underwater excavation compartment 2 is inserted into the mud. At this point, the lowering of the underwater excavation compartment 2 can be stopped.

[0033] During the lowering of the underwater excavation chamber 2 and throughout the entire excavation operation, the air compressor and compressed air system continuously pressurize and maintain the pressure inside the excavation chamber, ensuring that the excavation work chamber 2-1 remains water-free.

[0034] The camera 7 installed inside the underwater excavation chamber checks whether the bottom excavation work chamber of the underwater excavation chamber 2 is dry. If so, the excavation workers put on the appropriate equipment according to the previous excavation work and go down to the outside of the pressure regulating chamber through the manhole cover 2-17 on the top of the personnel passage pillar 2-3 of the excavation chamber and along the personnel ladder 2-8 installed inside the passage pillar.

[0035] Open the manhole cover 2-12 on the outside of the pressure regulating chamber, and the excavation operator can enter the pressure regulating chamber 2-2 to undergo high-pressure acclimatization before excavation.

[0036] Before acclimatizing in the pressure regulating chamber 2-2, the gas pressure inside the chamber is checked using the internal gas pressure monitor 9 installed at the bottom of the excavation work chamber 2-1. The operator then adjusts and acclimatizes to the pressure based on this value.

[0037] Once the excavation workers have completed pressure acclimatization and are ready to enter the excavation work chamber 2-1 to carry out excavation work, they will again check whether the environment inside the excavation work chamber meets the conditions for entering the chamber for work by using the camera 7 and the gas pressure monitor 9 installed inside the excavation work chamber 2-1.

[0038] If the conditions are met, the excavation workers can open the manhole cover 2-11 of the excavation work chamber 2-1 inside the pressure regulating chamber 2-2, and enter and descend to the work area through the manhole along the ladder 2-10 to excavate hazardous materials.

[0039] Once the hazardous materials are excavated and conditions are met for external transfer, first check whether the manhole cover 2-15 inside the hazardous materials transport channel pillar 2-4 is closed.

[0040] If the manhole cover 2-15 inside the hazardous materials transport channel pillar is closed, the manhole cover 2-14 leading from the excavation work compartment 2-1 to the hazardous materials transport channel pillar can be opened.

[0041] The excavated hazardous materials are placed in the hazardous materials transport channel, and then the manhole cover 2-14 of the column leading from the excavation work compartment to the hazardous materials transport channel is closed.

[0042] Inside the excavation work compartment, the manhole cover 2-15 in the hazardous materials transport passage is opened through the airtight operating manhole 2-18.

[0043] Climb to the top of the hazardous materials transport column 2-4 via the external personnel ladder 2-9 and open the external manhole cover 2-16 of the hazardous materials transport channel column.

[0044] A crane is installed on the deck at the top of the dangerous goods transport channel. External operators slowly lower the hook of crane 6 into the dangerous goods transport channel. When the hook is about to reach the dangerous goods placement position, the lowering of the hook is stopped.

[0045] Hook the hazardous material onto the hook of the crane 6 through the airtight manhole 2-18 and confirm the safety of the suspension.

[0046] Then, crane 6 is restarted to slowly lift the hazardous materials from the hazardous materials transport channel to the open deck of the excavator, where personnel on deck collect, store, or dispose of the hazardous materials.

[0047] Finally, inside the excavation work compartment, the manhole cover 2-15 inside the hazardous materials transport channel pillar is closed through the airtight operating manhole 2-18.

[0048] This completed the excavation and transfer of underwater hazardous materials.

[0049] After completing their excavation work, the workers in the excavation work compartment 2-1 need to open the manhole cover 2-11 for entering the excavation work compartment via ladder 2-10 before returning to the open deck.

[0050] Then enter the pressure regulating chamber 2-2. After entering the pressure regulating chamber, first close the manhole cover 2-11 for entering the excavation work chamber.

[0051] Pressure is regulated within the pressure regulating chamber by gradually reducing the pressure from high pressure to normal ambient pressure.

[0052] Once it is confirmed that the operator has fully adapted to the normal environmental pressure, the operator can open the manhole cover 2-12 leading to the personnel passage pillar in the pressure regulating chamber, and through the manhole cover to reach the internal personnel ladder 2-8. Then, the operator can go up the ladder to the top of the personnel passage pillar, open the manhole cover 2-17 at the top of the personnel passage pillar, and return to the open deck through the manhole.

[0053] Once the excavation operators return to the open deck, they can activate the vessel's lifting mechanism to raise the excavation work compartment from underwater into the vessel's moon pool.

[0054] This completed the excavation and removal of the underwater hazardous materials at that location.

[0055] Depending on the underwater hazardous materials buried at the excavation site, if there are still hazardous materials buried in other locations within the moon pool coverage area of ​​the excavation vessel that need to be dealt with, the underwater excavation work cabin 2 can be moved from one excavation location to another excavation location within the moon pool coverage area by activating the horizontal or vertical hydraulic cylinders and moving the horizontal and vertical guide rails.

[0056] Before horizontal movement, the underwater excavation work compartment 2 is first raised to a certain height from underwater using a lifting device, ensuring that the bottom of the excavation work compartment 2 is completely detached from the muddy surface at the bottom of the water. This prevents the underwater mud layer from affecting the horizontal movement of the excavation work compartment.

[0057] After completing the above work, the underwater excavation work compartment 2 can be moved from one working position to another within the water-passing pool of the excavator via the transverse guide rails on the longitudinal guide rails. The movement method is as follows: Figure 4 As shown.

[0058] Once the underwater excavation work compartment 2 is horizontally moved to another excavation work location, and it is determined that the work status is suitable for the next step of the operation, the relevant excavation and transfer work can be carried out in accordance with the aforementioned excavation work method.

[0059] Once all hazardous materials buried within the water-filled moon pool area covered by the excavation vessel have been excavated and cleared, the vessel can then carry the excavation work cabin and sail on the water again to detect any hazardous materials underwater. If hazardous materials are found, the vessel can repeat the excavation operation to complete the underwater hazardous materials excavation work.

Claims

1. A multi-directionally movable underwater excavation work container, characterized in that, It has a buoyancy hull on the water surface, a water-passing moon pool in the center of the buoyancy hull, an underwater excavation compartment in the middle of the moon pool, and longitudinal guide rails on the decks on both sides of the moon pool, with longitudinal hydraulic cylinders fixed on the longitudinal guide rails. Two transverse guide rails are provided between the two longitudinal guide rails. The transverse guide rails are perpendicular to the longitudinal guide rails. The two ends of the transverse guide rails are slidably connected to the longitudinal slide rails. The cylinder body of the longitudinal hydraulic cylinder is fixed on the longitudinal guide rail, and the top of the hydraulic rod of the longitudinal hydraulic cylinder is fixedly connected to the transverse guide rail. A transverse hydraulic cylinder is fixed on the transverse guide rail. The cylinder body of the transverse hydraulic cylinder is fixed on the transverse guide rail, and the top of the hydraulic rod of the transverse hydraulic cylinder is fixedly connected to the movable support on the top of the underwater excavation chamber. The movable support is slidably connected to the transverse guide rail. The underwater excavation compartment is divided into two parts: the upper part is the pressure regulating compartment and the lower part is the excavation operation compartment. The excavation operation compartment has side and top bulkheads but no bottom plate, resembling an inverted bottomless box. The underwater excavation compartment is equipped with three vertical support guide columns, and racks are installed along the height of the support guide columns. The underwater excavation compartment can move up and down through the moon pool. One of the supporting guide columns is a personnel passage column, the bottom of which is connected to the pressure regulating chamber, which in turn is connected to the excavation work chamber; another supporting guide column is a hazardous materials transfer column, the bottom of which is connected to the excavation work chamber; and the last one is a supporting guide column. The buoyancy vessel is equipped with lifting holes around its hull, and lifting devices are fixed to the lifting holes. Positioning stakes pass through the lifting holes and are movably connected to the buoyancy vessel through the lifting devices. The buoyancy hull is equipped with an air compression system and an underwater chemical hazard scanning device. The air compression system is connected to the pressure regulating chamber and the excavation work chamber through compression pipelines. The personnel passage pillars and hazardous materials transfer pillars are hollow inside. The personnel passage pillars are equipped with ladders that extend from the top to the bottom and into the pressure regulating chamber, which is also equipped with ladders.

2. The underwater excavation work cabin capable of moving in multiple directions according to claim 1, characterized in that, A manhole cover is installed between the bottom of the personnel passage pillar and the pressure regulating chamber, and a manhole cover is installed between the pressure regulating chamber and the excavation work chamber.

3. The underwater excavation work cabin capable of moving in multiple directions according to claim 1, characterized in that, The moon pool is rectangular, and the longitudinal guide rail is located on the deck at the short side of the rectangle. The length of the longitudinal guide rail is greater than the length of the short side of the moon pool.

4. The underwater excavation work cabin capable of moving in multiple directions according to claim 1, characterized in that, The buoyancy vessel is equipped with propulsion and positioning thrusters around its hull.

5. The underwater excavation work container capable of moving in multiple directions according to claim 1, characterized in that, Multiple cross braces are installed between adjacent support guide columns.

6. The underwater excavation work cabin capable of moving in multiple directions according to claim 1, characterized in that, The lifting device consists of a hydraulic cylinder and a pin. The hydraulic cylinder is installed on the buoyancy hull, and the pin is connected to the pin hole on the positioning pile. By using the extension, retraction and pushing / pulling of the hydraulic cylinder, the positioning pile is lowered into the water and inserted into the mud at the bottom of the river.

7. The underwater excavation work container capable of moving in multiple directions according to claim 1, characterized in that, The buoyancy hull is also equipped with a generator power system, living quarters, and a control room.

Citation Information

Patent Citations

  • Simple dredger for gravels in flowing water and method for dredging gravels

    CN102874384A

  • Multifunctional dredge boat

    CN104912144A