Construction method for long-distance box culvert with shallow covering soil penetrating through railway yard
By dividing long-distance box culverts into jacking sections and cast-in-place sections, and using temporary beam structures to suspend railway lines, construction was achieved without interrupting railway operations under shallow overburden conditions. This solved the problem of integrating urban roads and railway stations and provided a new construction method.
Patent Information
- Application Number
- CN202510867420.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-06-26
- Publication Date
- 2025-10-17
AI Technical Summary
Existing technologies, when crossing existing railway stations, face limitations in rotation construction due to high-rise buildings. The required thickness of the soil cover for tunnel boring machines results in long road lines with poor landscape integration, and the length of the underpass section and the elevation of the existing road surface are difficult to connect smoothly.
The long-distance box culvert passing under the railway station is divided into a jacking section, a cast-in-place section, and a jacking section. A temporary beam structure is used to jack the railway line. The precast box culvert is jacked in from both sides and then connected by cast-in-place, so as to achieve construction without interrupting railway operation.
This method enables urban roads to smoothly cross railway stations under shallow soil cover conditions, providing a construction method that does not interrupt railway operations. It solves the problem of integrating urban roads with railway stations and has high practicality and promotion value.