Modularized cast-in-place joint construction technology for overlapped assembly type pipe gallery
By employing a multi-layered waterproofing system and precise positioning technology, the connection strength and waterproofing issues of the joints in the composite prefabricated pipe gallery were resolved, resulting in high-quality construction, extended service life of the pipe gallery, and reduced maintenance costs.
Patent Information
- Application Number
- CN202511452599.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-10-12
- Publication Date
- 2025-12-12
AI Technical Summary
The existing construction process for joints in composite prefabricated pipe galleries suffers from problems such as insufficient connection strength, limited waterproofing measures, low construction precision, complex formwork installation, difficulty in guaranteeing concrete pouring quality, and inadequate maintenance measures, which affect the service life and maintenance costs of the pipe galleries.
The design employs a multi-layered and multi-dimensional waterproofing system, including reserved micro-expansion gaps, composite structure waterstop strips, penetrating crystalline waterproof coatings, modular templates, self-compacting waterproof concrete, and high-pressure grouting technology. Combined with an intelligent temperature-controlled curing system and non-destructive testing, it ensures the waterproof performance and connection strength of the joints.
It significantly improves the waterproof performance and connection strength of the joints, enhances construction quality and efficiency, extends the service life of the utility tunnel, and reduces maintenance costs.
Smart Images

Figure CN121110718A_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to the technical field of underground pipe gallery construction, and particularly relates to a modular cast-in-place joint construction process of a composite assembled pipe gallery. BACKGROUND
[0002] With the rapid development of urban infrastructure construction, as an important carrier of urban underground pipelines, the construction technology of comprehensive pipe gallery is constantly innovating. The composite assembled pipe gallery has been widely used in engineering due to its fast construction speed and good quality controllability.
[0003] However, the existing joint construction process of the composite assembled pipe gallery has many problems: the connection strength at the joint is insufficient, and leakage is prone to occur; the waterproof measures are single, and it is difficult to adapt to complex underground environment; the positioning accuracy is not high during construction, affecting the overall structural performance; the formwork installation is complex, and the turnover efficiency is low; the concrete pouring quality is difficult to guarantee; the maintenance measures are imperfect, affecting the joint strength development, etc. These problems not only affect the service life of the pipe gallery, but also increase the later maintenance cost. Among them, the joint leakage is one of the most prominent problems, which can cause serious consequences such as corrosion of internal equipment of the pipe gallery and decrease of structural durability.
[0004] Therefore, a modular cast-in-place joint construction process of a composite assembled pipe gallery is needed, which can significantly improve the waterproof performance and connection strength of the joint through multi-level and multi-dimensional waterproof system design, ensure the construction quality, and improve the construction efficiency. SUMMARY
[0005] In view of the deficiencies of the prior art, the present application provides a modular cast-in-place joint construction process of a composite assembled pipe gallery, which solves the problems raised in the background art.
[0006] Technical scheme: To solve the above technical problems, according to one aspect of the present application, more specifically, a modular cast-in-place joint construction process of a composite assembled pipe gallery, comprising the following steps:
[0007] S1, preparation of prefabricated components: transport the composite bottom plate, top plate, side wall and partition wall prefabricated components of the pipe gallery to the construction site, check the connecting surface and reserved steel bars of each component, and ensure that the quality of the prefabricated components meets the design requirements. Especially check the flatness of the connecting surface of the prefabricated component and the position of the embedded part, to ensure that the waterproof structure can be accurately installed.
[0008] S2, component positioning and installation: accurately align adjacent prefabricated components through a special positioning device, which includes a three-dimensional adjusting mechanism and a laser positioning system, and can realize accurate adjustment in three-dimensional direction, with a positioning accuracy of ±2mm. During positioning, a micro-expansion gap of 1-2mm is intentionally reserved at the joint to provide space for subsequent concrete expansion and waterproof structure, ensuring that the joint position meets the design requirements.
[0009] S3, joint steel bar connection: the reserved steel bars of adjacent components are connected by mechanical connection to form an overall force system. The mechanical connection can adopt straight thread sleeve connection to ensure that the steel bar connection strength is not lower than the base material strength.
[0010] S4, joint interface waterproof pretreatment: after the joint interface is cleaned by high-pressure water jet technology, the joint interface is sequentially pretreated for waterproofing: first, 1.5-2mm thick permeable crystalline waterproofing paint is brushed, and a cross brushing method is used to ensure uniform coverage; then, a water-swelling sealing strip is fixed in the middle of the joint by a pre-embedded clamping groove. The sealing strip has a composite structure, with a rubber sealing core layer in the inner layer and a water-swelling rubber layer with an expansion ratio of ≥250% in the outer layer, forming a composite waterproof base layer.
[0011] S5, installation of modular formwork: specially designed modular adjustable formwork is installed, which includes a base frame, a telescopic adjustment mechanism and a sealing assembly, and can adapt to joints of different widths. The formwork is tightly attached to the surface of the prefabricated component to form a sealed pouring space. The inner side of the formwork is provided with a concave-convex pattern structure to enhance the adhesion with the concrete. A water stop ring is provided on the outer side of the formwork to further prevent the occurrence of grout leakage during pouring.
[0012] S6, self-compacting waterproof concrete pouring: self-compacting waterproof concrete is poured into the joint through a special pouring opening. The self-compacting waterproof concrete uses a double-doping technology, which dopes nano calcium carbonate and ultra-fine silica fume, and simultaneously adds a silicone waterproofing agent, so that the concrete has an impermeability grade of ≥P12, an initial expansion degree of not less than 750mm, and a 2h expansion degree loss of not more than 50mm. Low-frequency vibration is used to assist compaction during pouring to ensure that the concrete is filled and saturated. At the same time, a moisture monitoring sensor is pre-embedded during pouring, which can monitor the humidity changes in the joint in real time and timely detect potential leakage risks.
[0013] S7, curing and formwork removal: an intelligent temperature control curing system is used to cure the cast-in-place joint. The system includes a temperature sensor, an automatic spraying device and a thermal insulation layer, which can automatically adjust the curing parameters according to the ambient temperature. When the concrete strength reaches more than 75% of the design strength, the modular formwork is removed.
[0014] S8, joint surface waterproofing reinforcement: cement-based permeable crystalline waterproofing material is brushed on the joint surface, with the brushing range exceeding the joint edge by more than 100mm to form a waterproof reinforcement band. After the surface is dry, high-pressure grouting technology is used to grout the possible micro cracks. The grouting material is modified epoxy resin, the grouting pressure is controlled at 0.3-0.5MPa, and the grouting holes are arranged in a quincunx pattern with a spacing of 300-500mm.
[0015] S9 Joint quality detection: use nondestructive testing technology to detect the quality of cast-in-place joints, including ultrasonic testing and impact echo testing, focusing on the detection of joint internal density; at the same time, water pressure test is used to verify the waterproof performance, the test pressure is 0.2MPa, and the pressure is kept for 30min without leakage to be qualified, to ensure that the design requirements are met.
[0016] The beneficial effects of the modular cast-in-place joint construction process of the overlapped assembly type pipe gallery of the application are:
[0017] (1), the application constructs a three-dimensional waterproof system of "pretreatment + structure self-waterproofing + surface strengthening", which improves the joint waterproof performance from multiple aspects and solves the problem of single waterproof measure in traditional process.
[0018] The pretreatment method of combining the composite structure water-swelling waterstop with the permeable crystalline waterproof coating forms the first waterproof barrier before concrete pouring, effectively blocking groundwater intrusion.
[0019] The surface waterproofing treatment effectively compensates for possible construction defects by expanding the waterproof range and high-pressure grouting technology, forming the third line of defense.
[0020] The introduction of moisture monitoring sensors and water pressure test realizes the whole process monitoring and verification of waterproof performance, ensuring reliable waterproof effect.
[0021] The positioning device and the reserved micro-expansion gap improve the positioning accuracy of the prefabricated component and provide reasonable space for waterproof structure, which is beneficial to improve the overall structural performance and waterproof effect. BRIEF DESCRIPTION OF DRAWINGS
[0022] The application will be further described in detail below in combination with the drawings and specific implementation methods.
[0023] Figure 1 The structural schematic diagram of the application. DETAILED DESCRIPTION
[0024] The application will be further described in detail below in combination with the drawings and specific implementation methods.
[0025] To make the technical scheme of the application clearer, the application will be further described in detail below in combination with the drawings and specific embodiments.
[0026] EMBODIMENT
[0027] REFERENCE Figure 1 A modular cast-in-place joint construction process for an overlapped assembly type pipe gallery, comprising the following steps:
[0028] S1 Preparation of prefabricated components: Transport the factory-prepared composite floor, roof, side wall and partition wall components to the construction site, check the dimensional deviation, appearance quality of the components, and focus on checking the flatness of the connecting surface (deviation ≤ 3 mm) and the position, quantity and length of the reserved steel bars to ensure compliance with the design requirements.
[0029] S2 Component positioning and installation: On the completed pipe gallery foundation, set up the base of the special positioning device, hoist the prefabricated components to be installed into position, adjust the position of the components through the three-dimensional adjustment mechanism, and accurately calibrate them using the laser positioning system to ensure that the joint width of adjacent components is uniform, with a deviation of within ± 2 mm, and a micro-expansion gap of 1.5 mm is reserved at the joint.
[0030] S3 Steel bar connection at the joint: Clean the rust and impurities on the surface of the reserved steel bars, connect the reserved steel bars of adjacent components using straight thread sleeves, and tighten them using a torque wrench to ensure that the tightening torque meets the specification requirements (HRB400 grade steel bars use ≥ 360 N·m). After the connection is completed, check the quality of the steel bar connection, and any unqualified components should be returned for reprocessing in a timely manner.
[0031] S4 Joint interface waterproofing pretreatment: Use high-pressure water jet technology to clean the joint interface of the prefabricated components, with a water jet pressure of 25 MPa. The cleaned interface should have a fresh concrete surface without floating slurry, oil stains and other impurities. After cleaning, use compressed air to dry the interface. First, apply a 1.8 mm thick penetrating crystalline waterproofing coating to the joint interface, using the cross-intersection method to apply two coats. Then, fix the water-swelling sealing strip in the middle of the joint through the pre-embedded slot. The cross-sectional size of the sealing strip is 30 mm x 20 mm, with a 20 mm x 10 mm rubber core layer in the inner layer and a 280% expansion ratio water-swelling rubber layer in the outer layer.
[0032] S5 Installation of modular formwork: Select the appropriate modular formwork according to the joint width, adjust the size of the formwork through the telescopic adjustment mechanism to match the joint width. Install the formwork in place and ensure that the formwork tightly adheres to the surface of the prefabricated component without slurry leakage through the sealing components. A rubber sealing ring with a cross-sectional diameter of 10 mm is installed on the outside of the formwork. After installation, check the stability and sealing performance of the formwork.
[0033] S6 Pouring of self-compacting waterproof concrete: The mix proportion of self-compacting waterproof concrete is: cement 380 kg / m 3 , fly ash 80 kg / m 3 , mineral powder 60 kg / m 3 , sand 780 kg / m 3 , stone 820 kg / m 3 , water 175 kg / m 3 , nano calcium carbonate 15 kg / m 310kg / m³ of ultrafine silica fume 3 Organosilicon waterproofing agent 3kg / m 3 Water-reducing agent 8.5 kg / m³ 3 The initial concrete spread is 780mm, and the 2-hour spread is 740mm, with a permeability grade of P12. It is poured in layers through a dedicated pouring port, with each layer not exceeding 300mm in height, and a low-frequency vibrator at 25Hz is used to assist in compaction. During the pouring process, fiber optic moisture sensors are pre-embedded at the joints to monitor humidity changes.
[0034] S7 Curing and Formwork Removal: Cover the outside of the formwork with an insulation layer and install temperature sensors and an automatic sprinkler system. The curing measures are automatically adjusted according to the ambient temperature: spraying every 2 hours when the ambient temperature is above 25℃; spraying every 4 hours when the ambient temperature is between 10-25℃; and taking insulation measures and not spraying when the ambient temperature is below 10℃. The curing time is no less than 14 days. Remove the modular formwork when the concrete strength reaches 80% of the design strength.
[0035] S8 Joint Surface Waterproofing Reinforcement: Apply a cement-based penetrating crystalline waterproofing material to the joint surface, extending 120mm beyond the joint edge to form a waterproof reinforcement zone. The coating thickness is 1.2mm. After the surface dries, use high-pressure grouting technology to treat any micro-cracks. Use modified epoxy resin as the grouting material, control the grouting pressure at 0.4MPa, and arrange the grouting holes in a quincunx pattern with a spacing of 400mm and a hole diameter of 10mm.
[0036] S9 Joint Quality Inspection: An ultrasonic testing machine was used to comprehensively inspect the joints at a frequency of 50-100kHz. Suspicious areas were further verified using impact echo testing. A water pressure test was also conducted simultaneously at 0.2MPa for 30 minutes, with no leakage observed. For any defects found, appropriate repair measures were taken based on their size and location.
[0037] The above construction techniques can effectively improve the construction quality and waterproofing performance of the joints in the composite prefabricated pipe gallery, ensuring that the joints have good stress performance and long-term waterproofing effect, and significantly extending the service life of the pipe gallery.
[0038] The embodiments described above are merely illustrative of several implementations of the present invention, and while the descriptions are specific and detailed, they should not be construed as limiting the scope of the present invention. It should be noted that those skilled in the art can make various modifications and improvements without departing from the concept of the present invention, and these modifications and improvements all fall within the scope of protection of the present invention. Therefore, the scope of protection of this patent should be determined by the appended claims.
Claims
1. A modular cast-in-place joint construction process for composite prefabricated pipe gallery, characterized in that, Includes the following steps: S1. Preparation of prefabricated components: Transport the prefabricated components of the pipe gallery, including the composite bottom slab, top slab, side walls, and central partition wall, to the construction site and check the connection surfaces and reserved reinforcing bars of each component. S2. Component positioning and installation: Adjacent prefabricated components are precisely aligned using a dedicated positioning device to ensure that the joint positions meet the design requirements; S3. Joint reinforcement connection: The reserved reinforcement bars of adjacent components are connected by mechanical connection to form an integral load-bearing system; S4. Waterproofing pretreatment of joint interface: Apply penetrating crystalline waterproof coating and install water-swellable waterstop strip in sequence at the joint interface to form a composite waterproof base layer; S5. Modular formwork installation: Install specially designed modular adjustable formwork, which fits tightly against the surface of the precast component to form a sealed pouring space; S6. Self-compacting waterproof concrete pouring: Self-compacting waterproof concrete is poured into the joint through a special pouring port, while low-frequency vibration is used to assist in compaction. S7. Curing and Formwork Removal: An intelligent temperature-controlled curing system is used to cure the cast-in-place joints. Modular formwork is removed after the design strength is reached. S8. Strengthening of joint surface waterproofing: Apply cement-based penetrating crystalline waterproofing material to the joint surface and use high-pressure grouting technology to grout any micro-cracks that may exist. S9. Joint quality inspection: Non-destructive testing technology is used to inspect the quality of cast-in-place joints to ensure that they meet the design requirements.
2. The modular cast-in-place joint construction process for a composite prefabricated pipe gallery according to claim 1, characterized in that, The dedicated positioning device mentioned in step S2 includes a three-dimensional adjustment mechanism and a laser positioning system, with a positioning accuracy of ±2mm, and a micro-expansion gap of 1-2mm is reserved at the joint.
3. The modular cast-in-place joint construction process for a composite prefabricated pipe gallery according to claim 1, characterized in that, The water-swellable waterstop strip in step S4 adopts a composite structure, with an inner layer of rubber waterstop core and an outer layer of water-swellable rubber with an expansion ratio of ≥250%. The waterstop strip is fixed to the middle of the joint interface through a pre-embedded groove.
4. The modular cast-in-place joint construction process for a composite prefabricated pipe gallery according to claim 1, characterized in that, The self-compacting waterproof concrete in step S6 adopts a dual-admixture technology, incorporating nano-calcium carbonate and ultrafine silica fume, while adding organosilicon waterproofing agent. The concrete has an impermeability grade ≥ P12, an initial expansion of not less than 750mm, and an expansion loss of not more than 50mm after 2 hours.
5. The modular cast-in-place joint construction process for a composite prefabricated pipe gallery according to claim 1, characterized in that, In step S8, the high-pressure grouting uses modified epoxy resin grouting material, the grouting pressure is controlled at 0.3-0.5MPa, and the grouting holes are arranged in a quincunx pattern with a spacing of 300-500mm.
6. The modular cast-in-place joint construction process for a composite prefabricated pipe gallery according to claim 1, characterized in that, In step S4, the thickness of the penetrating crystalline waterproof coating is 1.5-2mm, and it is applied in a cross-coating manner to ensure that the entire joint interface is covered.
7. The modular cast-in-place joint construction process for a composite prefabricated pipe gallery according to claim 1, characterized in that, In step S8, the cement-based penetrating crystalline waterproofing material is applied beyond the edge of the joint by more than 100mm on each side, forming a waterproof reinforcement strip.
8. The modular cast-in-place joint construction process for a composite prefabricated pipe gallery according to claim 1, characterized in that, Step S6 also includes the step of pre-embedding a moisture monitoring sensor, which can monitor the humidity changes at the joint in real time and detect potential leakage risks in a timely manner.