Bulk cargo wharf operation and maintenance situation awareness method and system

By constructing a health status analysis model and a remaining life probability distribution prediction model, the problem of abnormal equipment failure in traditional equipment monitoring methods has been solved, enabling accurate assessment of equipment health and remaining life, and improving the operation and maintenance efficiency and production continuity of bulk cargo terminals.

CN121389823AActive Publication Date: 2026-01-23CCCC FIRST HARBOR ENGINEERING CO LTD +2

Patent Information

Application Number
CN202511958712.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-12-24
Publication Date
2026-01-23
Estimated Expiration
2045-12-24

AI Technical Summary

Technical Problem

Traditional online equipment monitoring methods cannot assess the health of equipment based on its own wear and tear, leading to abnormal equipment failures and affecting the operational efficiency and production continuity of bulk cargo terminals.

Method used

By constructing a health status analysis model, a remaining life probability distribution prediction model, and a situational awareness model, the system uses equipment influencing factors to predict the equipment health index and remaining life, generates equipment alarm signals, assists in management plans, and rationally plans equipment maintenance time.

Benefits of technology

This has improved equipment utilization and on-site production efficiency, increased cargo turnover and efficiency at bulk cargo terminals, and ensured the perception and management of equipment health status and operational status.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN121389823A_ABST
    Figure CN121389823A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of bulk cargo wharf operation and maintenance situation awareness, and relates to a bulk cargo wharf operation and maintenance situation awareness method and system. The residual life of the equipment is calculated through the residual life probability distribution of the equipment predicted by the constructed residual life probability distribution prediction model, and the failure rate of the equipment is predicted through the constructed situation awareness model according to the health degree index of the equipment and the residual life of the equipment, so that equipment alarm signals of different grades are obtained. An auxiliary management scheme is generated and executed according to the equipment alarm signal, the equipment user maintenance time is reasonably planned, and the equipment utilization rate and the field production efficiency are improved. Health state monitoring and operation and maintenance situation awareness of the bulk cargo wharf are achieved, the equipment utilization rate and the field production efficiency are improved, and the turnover rate and turnover efficiency of wharf cargos are improved.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application belongs to the technical field of bulk cargo terminal operation and maintenance management, and relates to a bulk cargo terminal operation and maintenance situation awareness method and system. BACKGROUND

[0002] With the continuous expansion of modern bulk cargo terminals, the continuous improvement of informatization level, and the continuous increase of operation and maintenance business, the operation safety, operation and maintenance efficiency, and production continuity of bulk cargo terminal equipment have become an important issue. The common operation mode of bulk cargo terminals is linear, and the operation process mainly focuses on loading and unloading equipment (for example: car dumper, stacker, loader, ship transfer machine, etc.) and conveying equipment (for example: belt conveyor, etc.). The traditional on-line monitoring method of equipment can only evaluate the health degree according to the monitoring state of the equipment at that time, and cannot evaluate the health degree according to the self-wear of the equipment, resulting in unexpected equipment failure, inability to coordinate the generation and operation work, and reduction of the efficiency of the port area. At the same time, when the operation personnel selects the operation process line, the health degree of the process cannot be considered, and only the preset process can be started fixedly, which will cause the whole production line to be unable to proceed when a fault occurs at a key node, greatly affecting the operation efficiency. SUMMARY

[0003] The present application provides a bulk cargo terminal operation and maintenance situation awareness method and system to solve the above problems such as low operation efficiency in the prior art. The device influence factor of different devices in a set time period is obtained, the health state analysis model is constructed, the device health degree index is predicted, the residual life probability distribution prediction model is constructed, the probability distribution of the device residual life is predicted, the risk failure time is determined according to the probability distribution of the device residual life, the device residual life is calculated according to the risk failure time and the current time, the device failure rate is predicted according to the device health degree index and the device residual life through the constructed situation awareness model, and then the device alarm signal of different levels is obtained. According to the device alarm signal, an auxiliary management scheme is generated and executed, the device maintenance time is reasonably planned, the device utilization rate and the on-site production efficiency are improved, and the turnover rate and turnover efficiency of the bulk cargo terminal goods are improved.

[0004] In a first aspect, the present application provides a bulk cargo terminal operation and maintenance situation awareness method, comprising: Data acquisition step: acquiring device influence factors of different devices in a set time period, wherein the device influence factors include device environment parameters and device state parameters; Health degree prediction step: evaluating the device health degree index according to the device influence factors of the set time period through the pre-constructed health state analysis model to obtain the device health degree index at different time; Remaining life prediction steps: Based on the equipment impact factors within a set time period, predict the probability distribution of the remaining life of the equipment using a pre-built remaining life probability distribution prediction model; determine the risk failure time based on the probability distribution of the remaining life of the equipment; and calculate the remaining life of the equipment based on the risk failure time and the current time. Situation prediction steps: Based on the equipment health index and remaining equipment lifespan, predict the equipment failure rate using a pre-built situation awareness model; Assessment steps: Generate different levels of equipment alarm signals based on the equipment failure rate; Equipment management steps: Generate an auxiliary management plan based on the equipment alarm signal, and control the execution of the auxiliary management plan to assist in the management of the equipment.

[0005] In some embodiments, the method for constructing the health status analysis model is as follows: The historical device impact factors and historical device health indices of different devices are obtained to form a dataset, and the dataset is divided into a training set and a validation set; Based on a regression model, a health status analysis model is constructed using equipment influencing factors as input and equipment health index as output; the health status analysis model is expressed as follows:

[0006] In the formula, This indicates the equipment health index. This indicates the equipment's health index before it leaves the factory. Let n be the standardized value of the impact factor index for the nth device. The weight of the influence factor for the nth device; The health status analysis model was trained and validated using training and validation sets.

[0007] In some embodiments, when training a health status analysis model, a weight region is trained using a training set, and statistical methods are used to update the weights of the health status analysis model.

[0008] In some embodiments, the method for constructing the remaining lifetime probability distribution prediction model is as follows: A dataset is formed by obtaining the historical equipment impact factors and the probability distribution of the remaining lifespan of different equipment, and the dataset is divided into a training set and a validation set. Based on the Long Short-Term Memory (LSTM) network, a remaining lifetime probability distribution prediction model is constructed using the equipment impact factor as input and the equipment remaining lifetime probability distribution as output; the remaining lifetime probability distribution prediction model is expressed as:

[0009] In the formula, Let be the risk prediction function based on the risk failure time t, representing the covariate... the instantaneous failure risk; is a baseline risk function, representing the natural aging trend of the equipment; is a covariate coefficient, representing the first the impact weight of the equipment impact factor on the failure risk; is the first the covariate of the equipment impact factor; is the number of equipment impact factors; Train and verify the remaining life probability distribution prediction model through the training set and the verification set.

[0010] In some embodiments, in the situation prediction step, the method for predicting the equipment failure rate according to the equipment health index and the equipment remaining life through the pre-constructed situation awareness model is: According to the health index at different times, the mean of the equipment health index and the standard deviation of the equipment health index in a set time period are calculated; The equipment remaining life is normalized to obtain the normalized equipment remaining life; According to the mean of the equipment health index, the standard deviation of the equipment health index and the normalized equipment remaining life, the situation awareness model is used to predict the equipment failure rate.

[0011] In some embodiments, the construction method of the situation awareness model is: Obtain the historical equipment health index, the historical equipment remaining life and the historical equipment failure rate of different equipment; According to the historical equipment health index, the mean of the historical equipment health index and the standard deviation of the historical equipment health index are calculated, and the historical equipment remaining life is normalized to obtain the normalized historical equipment remaining life; The normalized historical equipment remaining life, the mean of the historical equipment health index, the standard deviation of the historical equipment health index and the historical equipment failure rate form a data set, which is divided into a training set and a verification set; Based on the long short-term memory network LSTM, the mean of the equipment health index, the standard deviation of the equipment health index and the normalized equipment remaining life are taken as the input, and the equipment failure rate is taken as the output to construct the situation awareness model; the situation awareness model is represented as:

[0012] In the formula, is the equipment failure rate, is the mean of the equipment health index, is a sensitivity constant, is the standard deviation of the equipment health index, is the normalized equipment remaining life; The situation awareness model is trained and verified through the training set and the verification set.

[0013] In a second aspect, the present application provides a bulk cargo terminal operation situation awareness system for implementing the bulk cargo terminal operation situation awareness method of the first aspect of the present application, comprising: a data acquisition module configured to acquire device influence factors of different devices in a set time period, and historical device influence factors, historical device health indexes, historical device residual life probability distributions, historical device residual lives, and historical failure rates of the different devices; a model generation module configured to generate a health state analysis model according to the historical device influence factors and the historical device health indexes of the different devices, generate a residual life probability distribution prediction model according to the historical device influence factors and the historical device residual life probability distributions of the different devices, and generate a situation awareness model according to the historical device health indexes, the historical device residual lives, and the historical failure rates of the different devices; a prediction module configured to predict device health indexes and probability distributions of device residual lives through the health state analysis model and the residual life probability distribution prediction model respectively according to the device influence factors of the different devices in the set time period, determine a risk failure time according to the probability distributions of the device residual lives, calculate the device residual lives according to the risk failure time and a current time, and predict a device failure rate through the situation awareness model according to the device health indexes and the device residual lives; an evaluation module configured to generate device alarm signals of different levels according to the device failure rate; a device management module configured to generate an auxiliary management scheme according to the device alarm signals, and control the device to be managed by the auxiliary management scheme.

[0014] In some embodiments, the model generation module comprises: a first model generation module configured to generate a health state analysis model according to the historical device influence factors and the historical device health indexes of the different devices; a second model generation module configured to generate a residual life probability distribution prediction model according to the historical device influence factors and the historical device residual life probability distributions of the different devices; a third model generation module configured to generate a situation awareness model according to the historical device health indexes, the historical device residual lives, and the historical failure rates of the different devices.

[0015] In some embodiments, the first model generation module comprises: a first data set generation sub-module configured to form a first data set according to the historical device influence factors and the historical device health indexes of the different devices, and divide the first data set into a first training set and a first verification set; The first model construction submodule is configured to construct a health state analysis model based on a regression model, with the device influence factor as input and the device health index as output. The first model training submodule is configured to train the health state analysis model according to the first training set. The first model verification submodule is configured to verify the performance of the health state analysis model according to the first verification set.

[0016] In some embodiments, the second model generation module comprises: The second data set generation submodule is configured to form a second data set from the historical device influence factors and the historical device remaining life probability distribution of different devices, and divide the second data set into a second training set and a second verification set. The second model construction submodule is configured to construct a remaining life probability distribution prediction model based on a long short-term memory network (LSTM), with the device influence factor as input and the device remaining life probability distribution as output. The second model training submodule is configured to train the remaining life probability distribution prediction model according to the second training set. The second model verification submodule is configured to verify the performance of the remaining life probability distribution prediction model according to the second verification set.

[0017] In some embodiments, the third model generation module comprises: The first calculation submodule is configured to calculate the historical device health index mean and the historical device health index standard deviation according to the historical device health index. The normalization submodule is configured to normalize the historical device remaining life to obtain normalized historical device remaining life. The third data set generation submodule is configured to form a third data set from the normalized historical device remaining life, the historical device health index mean, the historical device health index standard deviation, and the historical device failure rate, and divide the third data set into a third training set and a third verification set. The third model construction submodule is configured to construct a situational awareness model based on a long short-term memory network (LSTM), with the device health index mean, the device health index standard deviation, and the normalized device remaining life as input, and the device failure rate as output. The third model training submodule is configured to train the situational awareness model according to the third training set. The third model verification submodule is configured to verify the performance of the situational awareness model according to the third verification set.

[0018] In some embodiments, the prediction module comprises: The health state prediction submodule is configured to predict the device health index of different devices according to the device influence factor of a set time period through the health state analysis model. a probability distribution prediction submodule configured to predict a probability distribution of the remaining life of the equipment according to the equipment influence factor of a set time period through a remaining life probability distribution prediction model; a second calculation submodule configured to determine a risk failure time according to the probability distribution of the remaining life of the equipment, and calculate the remaining life of the equipment according to the risk failure time and a current time; a situation prediction submodule configured to predict an equipment failure rate according to the equipment health index and the remaining life of the equipment through a situation awareness model.

[0019] Compared with the related art, the bulk cargo terminal operation situation awareness method and system provided by the present application predict the probability distribution of the equipment health index and the remaining life of the equipment according to the equipment influence factor of a set time period obtained through the constructed health state analysis model and the remaining life probability distribution prediction model, determine a risk failure time according to the probability distribution of the remaining life of the equipment, calculate the remaining life of the equipment according to the risk failure time and a current time, predict an equipment failure rate according to the equipment health index and the remaining life of the equipment through the constructed situation awareness model, generate equipment alarm signals of different levels according to the equipment failure rate, generate an auxiliary management scheme according to the equipment alarm signals, and control the equipment to be managed by executing the auxiliary management scheme. The present application realizes the perception of the utilization rate, health state and operation situation of the bulk cargo terminal equipment within a certain time (which can be preset according to actual needs), and plans the bulk cargo terminal equipment according to the operation plan, the production plan, the equipment health state and the operation situation, thereby improving the cargo turnover rate and turnover efficiency of the bulk cargo terminal. BRIEF DESCRIPTION OF DRAWINGS

[0020] The accompanying drawings, which are included to provide a further understanding of the present application, form a part of the present application and illustrate the illustrative embodiments of the present application and the explanation of the present application, and do not constitute improper limitations on the present application. In the drawings: Figure 1 a flowchart of the bulk cargo terminal operation situation awareness method according to the embodiment of the present application; Figure 2 a flowchart of the construction method of the health state analysis model according to the embodiment of the present application; Figure 3 a flowchart of the construction method of the remaining life probability distribution prediction model according to the embodiment of the present application; Figure 4 a flowchart of the method of predicting the equipment failure rate according to the equipment health index and the remaining life of the equipment through the pre-constructed situation awareness model according to the embodiment of the present application; Figure 5 a flowchart of the construction method of the situation awareness model according to the embodiment of the present application; Figure 6A structural block diagram of the bulk cargo terminal operation and maintenance situation awareness system according to the embodiment of the present application is shown in the figure. Figure 7 A structural block diagram of the model generation module according to the embodiment of the present application is shown in the figure. Figure 8 A structural block diagram of the first model generation module according to the embodiment of the present application is shown in the figure. Figure 9 A structural block diagram of the second model generation module according to the embodiment of the present application is shown in the figure. Figure 10 A structural block diagram of the third model generation module according to the embodiment of the present application is shown in the figure. Figure 11 A structural block diagram of the prediction module according to the embodiment of the present application is shown in the figure.

[0021] In the figure: 1, data acquisition module, 2, model generation module, 21, first model generation module, 211, first data set generation sub-module, 212, first model construction sub-module, 213, first model training sub-module, 214, first model verification sub-module, 22, second model generation module, 221, second data set generation sub-module, 222, second model construction sub-module, 223, second model training sub-module, 224, second model verification sub-module, 23, third model generation module, 231, first calculation sub-module, 232, normalization sub-module, 233, third data set generation sub-module, 234, third model construction sub-module, 235, third model training sub-module, 236, third model verification sub-module, 3, prediction module, 31, health state prediction sub-module, 32, probability distribution prediction sub-module, 33, second calculation sub-module, 34, situation prediction sub-module, 4, evaluation module, 5, device management module. DETAILED DESCRIPTION

[0022] In order to make the purpose, technical scheme and advantages of the present application more clear, the present application is described and explained below in combination with the figures and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application, and are not used to limit the present application. Based on the embodiments provided by the present application, all other embodiments obtained by those of ordinary skill in the art without creative labor fall within the scope of the present application.

[0023] It is apparent that the drawings in the following description merely show some examples or embodiments of the present application, and the present application can be applied to other similar situations without creative efforts by those skilled in the art based on these drawings. In addition, it can be understood that, although the efforts made in the development process can be complicated and lengthy, some modifications, such as design, manufacture or production, made on the basis of the disclosed technical content of the present application by those skilled in the art related to the disclosed content of the present application are only routine technical means, and should not be understood as insufficient disclosure of the present application.

[0024] In the present application, the term "embodiment" means that the specific features, structures or properties described in connection with the embodiment can be included in at least one embodiment of the present application. The appearance of this phrase in various places in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment to other embodiments. It is explicitly and implicitly understood by those skilled in the art that the described embodiments of the present application can be combined with other embodiments without conflict.

[0025] Unless otherwise defined, technical or scientific terms used in the present application should be understood as their ordinary meanings to those skilled in the art to which the present application belongs. The terms "one", "a", "an", "the" and similar words in the present application do not represent quantity limitation, but can represent singular or plural. The terms "include", "contain", "have" and any variations thereof in the present application are intended to cover non-exclusive inclusion; for example, a process, method, system, product or device including a series of steps or modules (units) is not limited to the listed steps or units, but can also include steps or units not listed, or can also include other steps or units inherent to the process, method, product or device. The terms "connect", "connect", "couple" and similar words in the present application are not limited to physical or mechanical connection, but can include electrical connection, whether direct or indirect. The term "multiple" in the present application means two or more. The association between the associated objects is described by the term "and / or", which means that there can be three relationships, for example, "A and / or B" can mean that A exists alone, A and B exist together, and B exists alone. The character " / " generally represents an "or" relationship between the associated objects. The terms "first", "second", "third" and the like in the present application are merely to distinguish similar objects, and do not represent a specific order for the objects.

[0026] The first aspect of the present application provides a bulk cargo terminal operation and maintenance situation awareness method. Figure 1 is a flowchart of the bulk cargo terminal operation and maintenance situation awareness method of the embodiment of the present application, and the steps of the bulk cargo terminal operation and maintenance situation awareness method include: S1, a data acquisition step: acquiring device influence factors of different devices in a set time period, the device influence factors being multi-dimensional time sequence data reflecting current and historical operating conditions of the devices.

[0027] Specifically, the device influence factors are divided into real-time state parameters (including temperature, vibration, current, voltage, and other high-frequency signals collected by sensors), operating condition parameters (including cumulative operating time, start-stop times, load rate, maintenance records, and other low-frequency operation and maintenance data), and environmental parameters (including temperature and humidity, dust concentration, salt spray level, and other external environmental monitoring values).

[0028] In an embodiment of the present application, the device influence factors include but are not limited to sensor data, device operating parameters, and device environmental parameters. The devices include monitoring devices (such as various sensors including voltage and current sensors, temperature sensors, vibration sensors, ultrasonic sensors, infrared sensors, liquid level sensors, etc.) and production devices (such as car dumpers, stacker-reclaimers, car loaders, ship unloaders, conveyors, etc.). The sensor data includes but is not limited to device temperature, device noise, device voltage, device current, etc. The device operating parameters include but are not limited to device operating time, device carrying capacity, device average start-up time, device start-stop cycle, device maintenance cycle, device maintenance cycle, device wear rate, device operating speed, device factory-set service life, device actual production time, device fault burst rate, etc. The device environmental parameters include but are not limited to weather conditions (such as rain, smog, etc.). The specific settings can be made according to actual needs.

[0029] S2, a health degree prediction step: evaluating device health degree indexes according to device influence factors in a set time period through a pre-constructed health state analysis model to obtain device health degree indexes at different times.

[0030] Specifically, in an embodiment of the present application, referring to Figure 2 , the construction method of the health state analysis model is: S21, acquiring historical device influence factors and historical device health degree indexes of different devices to form a data set, and dividing the data set into a training set and a validation set.

[0031] Specifically, the historical equipment influence factors include but are not limited to weather conditions (such as rain, haze, etc.), equipment running time, equipment carrying capacity, shutdown start time ratio, carrying cargo type ratio, equipment generated plan life, equipment maintenance cycle, equipment repair cycle, equipment fault burst rate, natural wear and tear, etc. Among them: the equipment running time represents the working time of the equipment since production, the equipment carrying capacity represents the load condition of the equipment in the transportation process, the shutdown start time ratio represents the ratio of idle time and actual working time of the equipment, the carrying cargo type ratio represents the proportion of different types of carrying cargo in the total carrying cargo, the equipment generated plan life represents the expected service life given by the equipment in the design stage, the equipment maintenance cycle represents the time of regular maintenance and repair, the equipment repair cycle represents the use cycle after fault repair, the equipment fault burst rate represents the frequency of past fault events, and the natural wear and tear represents the mechanical wear and tear caused to the equipment in the long-term operation process.

[0032] In the embodiment of the application, the training set and the validation set are divided according to a set proportion. For example, the training set and the validation set are divided according to a proportion of 8:2. It should be noted that the proportion of the training set and the validation set can be set according to actual needs. The fixed proportion segmentation algorithm is used to divide the data set, so as to ensure the fairness of the data set division and avoid the occurrence of features in the training set that are not covered in the validation set.

[0033] S22, based on the regression model, the equipment environment parameters and the equipment state parameters are taken as inputs, and the equipment health degree index is taken as output to construct a health state analysis model.

[0034] The health state analysis model is represented as:

[0035] In the formula, represents the equipment health degree index, represents the equipment factory health index, is the standardized value of the nth equipment influence factor index, is the weight of the nth equipment influence factor.

[0036] S23, the health state analysis model is trained and verified through the training set and the validation set.

[0037] Specifically, in an embodiment of the application, when training the health state analysis model, the weight region is trained through the training set, and the health state analysis model weight is updated by using a statistical method (for example, expert scoring method, regression analysis method and principal component analysis method, etc.).

[0038] It should be noted that in the process of training the health state analysis model through the training set, the health state analysis model learns the features and patterns in the data to optimize the health state analysis model parameters and improve the prediction ability of the health state analysis model on the input data. The use of the training set can effectively avoid data leakage and model overfitting, and ensure that the health state analysis model has good fitting ability in the training stage.

[0039] The trained health state analysis model is verified for performance through the verification set. The role of the verification set is to evaluate the generalization ability of the health state analysis model, that is, the performance of the health state analysis model on unseen data. Through the test of the verification set, the accuracy and other key indicators of the health state analysis model can be accurately determined, so as to determine whether the health state analysis model can meet the actual application requirements.

[0040] In the embodiments of the present application, based on the training and verification mechanism of historical data, through scientific and reasonable data set division, model training and performance verification process, the accuracy and generalization ability of the health state analysis model are effectively improved. In practical application, the health state analysis model can better adapt to the device health state evaluation in different scenarios, and quickly and accurately evaluate the device health index according to real-time input data.

[0041] In some specific implementation manners in the embodiments of the present application, the K-fold cross-validation method is used to train and verify the health state analysis model. Taking the five-fold cross-validation method as an example, the historical device influence factors and historical device health degree indexes of different devices obtained are formed into a data set. In the training and verification, the data set is divided into five subsets, and any one subset is selected as the verification set and the other subsets are selected as the training set. In the training and verification process, the health state analysis model is verified for five rounds, the results of the five rounds of verification are summarized, the average performance indicators of the five rounds are calculated, and the performance indicators of the health state analysis model are obtained.

[0042] In the embodiments of the present application, the health state analysis model is trained and verified by the K-fold cross-validation method, which can fully utilize each sample in the data set, and at the same time avoid the dependence of the health state analysis model on specific data division, so as to more accurately evaluate the generalization ability of the health state analysis model.

[0043] According to the calculated device health degree index , the device health degree level can be divided.

[0044] For example, the health degree level is divided as follows: , which indicates that the health state of the device is good, and the device can continue to operate normally.

[0045] , which indicates that the device is in a sub-healthy state, and regular inspection is recommended.

[0046] , indicating that the device needs attention, suggesting maintenance inspection.

[0047] , indicating that the device has a high risk of failure, suggesting immediate shutdown for comprehensive inspection and repair.

[0048] Traditional equipment health assessment may rely on manual inspection or simple threshold judgment, which is difficult to achieve continuous and accurate quantification. Through the health degree analysis model, on the one hand, the health degree index of the equipment can be updated in real time or periodically according to the continuous data (such as hourly, daily sensor data, etc.) within a set time period, reflecting the changing trend of the equipment state; on the other hand, the complex state of the equipment (such as vibration, temperature, pressure, etc. Multidimensional data) is converted into a single health degree index, making the equipment health status intuitive and visible, facilitating quick understanding and decision-making.

[0049] S3, residual life prediction step: according to the equipment influence factor of the set time period, the residual life probability distribution of the equipment is predicted through the pre-constructed residual life probability distribution prediction model, the risk failure time is determined according to the residual life probability distribution of the equipment, and the residual life of the equipment is calculated according to the risk failure time and the current time.

[0050]

[0051] In the formula, is the residual life of the equipment, is the risk failure time, is the current time.

[0052] Specifically, the method for determining the risk failure time according to the probability distribution of the residual life of the equipment is: selecting the quantile of the probability distribution of the residual life of the equipment at a preset confidence level (such as: 90%) as the risk failure time.

[0053] Specifically, in an embodiment of the application, referring to Figure 3 The construction method of the residual life probability distribution prediction model is: S31, obtaining historical equipment influence factors and historical equipment residual life probability distributions of different equipment to form a data set, and dividing the data set into a training set and a validation set.

[0054] Specifically, the historical equipment influence factors include equipment historical operation data (such as: vibration, temperature, current, voltage, etc.), equipment historical full life cycle operation records (including failure time labels) and equipment environment data (such as: humidity, load, operation mode, etc.).

[0055] In the embodiments of the present application, the training set and the validation set are divided according to a set proportion. For example, the training set and the validation set are divided according to a proportion of 9:1. It should be noted that the proportion of the training set and the validation set can be set according to actual needs. The fixed proportion segmentation algorithm is used to divide the data set, so as to ensure the fairness of the data set division and avoid the occurrence of features in the training set that are not covered in the validation set.

[0056] In S32, a remaining useful life probability distribution prediction model is constructed based on a long short-term memory network (LSTM), with the device influence factor as the input and the device remaining useful life probability distribution as the output.

[0057] The device remaining useful life probability distribution prediction model based on the LSTM outputs the probability distribution (such as a normal distribution, a Weibull distribution, or an interval distribution obtained through quantile regression) of the device remaining useful life by inputting the device influence factor (such as sensor data, operating parameters, environmental variables, etc.), which has a more comprehensive uncertainty expression capability compared with traditional point prediction models.

[0058] It should be noted that, on the one hand, when the traditional LSTM model predicts the remaining useful life, it usually outputs a single-point estimate (such as a remaining useful life of 10 days), which cannot reflect the confidence of the prediction result (such as a 90% probability within 8-12 days). However, the probability distribution prediction model can explicitly quantify the uncertainty by outputting the probability density function (PDF) or cumulative distribution function (CDF) of the remaining useful life. For example, if the prediction result is that the remaining useful life follows a normal distribution with a mean of 10 and a standard deviation of 2, it can be inferred that there is a 68% probability that the device will fail within 8-12 days and a 95% probability that the device will fail within 6-14 days.

[0059] On the other hand, the degradation process of a device is often influenced by multiple factors (such as load fluctuations, environmental corrosion, component aging, etc.), and there is significant nonlinearity and randomness. The traditional LSTM model can effectively capture long-term temporal dependencies through its gating mechanism (forget gate, input gate, and output gate), and the probability distribution output further adapts to the randomness of the degradation process. For example, when predicting the remaining useful life of a bearing, the model can learn the temporal changes of influence factors such as vibration signals and temperature, and output the Weibull distribution of the remaining useful life (Weibull distribution is often used to describe the "bathtub curve" characteristics of device life), which is more consistent with the actual degradation law than single-point prediction.

[0060] The historical device influence factors and the historical actual device remaining useful life of the key part roller and the liner plate of the conveyor system are collected, the historical device influence factors are formed into corresponding data sets, and the remaining useful life is predicted through the traditional LSTM model and the remaining useful life probability distribution model described in the present application according to the roller data set and the liner plate data set. The prediction results are shown in Table 1.

[0061] Table 1

[0062] Experiments show that, compared with the point prediction of the traditional LSTM model, the remaining life probability distribution model of the application reduces the MAE by 38% on multiple device data sets (such as the roller data set and the liner data set), and the accuracy is improved more significantly especially in the "late stage" when the device is close to failure.

[0063] Specifically, in an embodiment of the application, the remaining life probability distribution prediction model is represented as:

[0064] In the formula, is a risk prediction function according to the risk failure time t, which represents the instantaneous failure risk of the device under the covariate ; is a baseline risk function, which represents the natural aging trend of the device; is a covariate coefficient, which represents the influence weight of the device influence factor on the failure risk; is the device influence factor; is the number of device influence factors.

[0065] S33, training and verifying the remaining life probability distribution prediction model through the training set and the verification set.

[0066] In the embodiments of the application, based on the training and verification mechanism of historical data, through a scientific and reasonable data set division, model training and performance verification process, the accuracy and generalization ability of the remaining life probability distribution prediction model are effectively improved. In practical applications, the remaining life probability distribution prediction model can better adapt to the device remaining life probability distribution prediction in different scenarios, and quickly and accurately evaluate the remaining life probability distribution according to real-time input data.

[0067] In the embodiments of the application, by learning the time sequence degradation mode of the device state parameters, the remaining life probability distribution prediction model is trained, so as to quantify the time distribution of the device from failure.

[0068] In some specific implementation manners in the embodiments of the application, K-fold cross-validation is used to evaluate the performance of the model, so that each sample participates in training and verification, effectively reducing the evaluation bias, avoiding the dependence of the remaining life probability distribution prediction model on specific data division, and thus more accurately evaluating the generalization ability of the remaining life probability distribution prediction model.

[0069] S4, situation prediction step: predicting the device failure rate through the pre-constructed situation awareness model according to the device health index and the device remaining life.

[0070] In the embodiments of the present application, based on the equipment health index and the equipment remaining life, the precise quantification and forward prediction of the failure risk are realized by predicting the equipment failure rate through the situational awareness model, and the pain points of the traditional failure rate prediction, such as relying on experience, ignoring dynamic state, and poor timeliness, are solved.

[0071] Specifically, in the first embodiment of the application, referring to Figure 4 , the method for predicting the equipment failure rate according to the equipment health index and the equipment remaining life through the pre-constructed situational awareness model is as follows: S411, calculating the mean value and the standard deviation of the equipment health index in a set time period according to the health index at different time points.

[0072] For example, taking the current time point as the end point, the equipment health index sequence in a preset time window (such as 7 days) is backtracked, and the mean value and the standard deviation of the sequence are calculated to represent the stability of the equipment health state.

[0073] S412, normalizing the equipment remaining life to obtain the normalized equipment remaining life.

[0074] Specifically, the equipment remaining life is normalized by using the maximum design life related to the equipment type, so as to ensure the scale consistency between different equipment.

[0075] S413, predicting the equipment failure rate according to the mean value of the equipment health index, the standard deviation of the equipment health index, and the normalized equipment remaining life through the situational awareness model.

[0076] Specifically, in the first embodiment of the application, referring to Figure 5 , the construction method of the situational awareness model is as follows: S421, obtaining the historical equipment health index, the historical equipment remaining life, and the historical equipment failure rate of different equipment.

[0077] S422, calculating the mean value and the standard deviation of the historical equipment health index according to the historical equipment health index, and normalizing the historical equipment remaining life to obtain the normalized historical equipment remaining life; S423, forming a data set by using the normalized historical equipment remaining life, the mean value of the historical equipment health index, the standard deviation of the historical equipment health index, and the historical equipment failure rate, and dividing the data set into a training set and a validation set.

[0078] S424, constructing a situational awareness model based on a long short-term memory network (LSTM), taking the mean value of the equipment health index, the standard deviation of the equipment health index, and the normalized equipment remaining life as the input, and taking the equipment failure rate as the output; the situational awareness model is represented as:

[0079] wherein, is the equipment failure rate; is the equipment health index mean value; is the sensitivity constant, which is set by expert experience; is the equipment health index standard deviation; is the normalized equipment remaining life.

[0080] For example, the equipment health index mean value is the equipment health index mean value in the past 30 days, and the equipment health index standard deviation is the equipment health index standard deviation in the past 30 days, and the equipment health index mean value is taken as .

[0081] S425, training and verifying the situational awareness model through the training set and the verification set.

[0082] In the embodiments of the present application, based on the training and verification mechanism of historical data, through a scientific and reasonable data set division, model training and performance verification process, the accuracy and generalization ability of the situational awareness model are effectively improved. In practical application, the situational awareness model can better adapt to the equipment failure rate prediction in different scenarios, and quickly and accurately evaluate the equipment failure rate according to real-time input data.

[0083] In some specific implementation manners in the embodiments of the present application, the K-fold cross-validation method is used to train and verify the situational awareness model. Through the K-fold cross-validation method, the situational awareness model is trained and verified, each sample in the data set can be fully utilized, and at the same time the dependence of the situational awareness model on specific data division is avoided, so that the generalization ability of the situational awareness model can be more accurately evaluated.

[0084] S5, evaluation step: generating different levels of equipment alarm signals according to the equipment failure rate.

[0085] In the embodiments of the present application, based on the equipment failure rate, multi-level alarms are divided (such as: first-level alarm ≤5% (low risk), 5%<second-level alarm ≤15% (medium risk), 15%<third-level alarm ≤30% (high risk), fourth-level alarm >30% (extremely high risk)), different levels correspond to different alarm methods (such as first-level only system record, second-level pop-up reminder, third-level sound and light alarm, fourth-level emergency shutdown notification). The alarm level is dynamically updated with the failure rate (such as when the equipment failure rate increases from 8% to 18%, the second-level alarm is automatically upgraded to the third-level alarm), avoiding the alarm lag caused by the static threshold, and at the same time filtering low-risk alarms through grading, reducing the invalid response of operation and maintenance personnel.

[0086] S6, equipment management step: generating an auxiliary management scheme according to the equipment alarm signal, and controlling to execute the auxiliary management scheme to assist in managing the equipment.

[0087] The application realizes rapid decision-making through the linkage of alarm levels and preconfigured auxiliary management schemes. Different alarm levels are preset with standardized auxiliary management schemes (for example, the second alarm corresponds to "increasing the inspection frequency to once every 2 hours + real-time monitoring of key parameters"; the third alarm corresponds to "arranging maintenance within 48 hours + allocating spare parts"; and the fourth alarm corresponds to "emergency shutdown for maintenance + starting standby equipment"). When an alarm is triggered, the scheme is automatically pushed to the operation and maintenance management system, and the core execution points (such as maintenance priority, required spare part model, and operation process) are marked, without the need for manual additional research and judgment. The response time is shortened from the traditional several hours to minutes, and the fault handling efficiency is significantly improved.

[0088] It should be noted that the steps shown in the above process or the flowchart of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and although a logical order is shown in the flowchart, in some cases, the steps shown or described can be executed in an order different from that here.

[0089] The bulk cargo terminal operation and maintenance situation perception method of the embodiment of the application predicts the instantaneous health state and residual life of the equipment, predicts the equipment failure rate based on the health state and residual life, and realizes accurate early warning, rapid response and effective control of equipment risks through hierarchical alarm driven by the equipment failure rate, linkage of alarm and management scheme, and closed-loop control of the execution process, so as to finally achieve the core goal of "reducing failure loss, improving operation and maintenance efficiency, and ensuring production safety", and provide core support for fine management of the whole life cycle of the equipment.

[0090] The second aspect embodiment of the application provides a bulk cargo terminal operation and maintenance situation perception system for realizing the bulk cargo terminal operation and maintenance situation perception method of the first aspect embodiment of the application. Figure 6 The structure block diagram of the bulk cargo terminal operation and maintenance situation perception system of the embodiment of the application is shown in Figure 6 As shown in the figure, the bulk cargo terminal operation and maintenance situation perception system comprises: A data acquisition module 1 is configured to acquire device influence factors of different devices in a set time period, and historical device influence factors, historical device health indexes, historical device residual life probability distributions, historical device residual life, and historical failure rates of different devices. A model generation module 2 is configured to generate a health state analysis model according to the historical device influence factors and the historical device health indexes of different devices, generate a residual life probability distribution prediction model according to the historical device influence factors and the historical device residual life probability distributions of different devices, and generate a situation perception model according to the historical device health indexes, the historical device residual life, and the historical failure rates of different devices. The prediction module 3 is configured to predict the equipment health index and the probability distribution of the equipment residual life of different equipment according to the equipment influence factor of the set time period through the health state analysis model and the residual life probability distribution prediction model respectively, determine the risk failure time according to the probability distribution of the equipment residual life, calculate the equipment residual life according to the risk failure time and the current time, and predict the equipment failure rate through the situation awareness model according to the equipment health index and the equipment residual life. The evaluation module 4 is configured to generate equipment alarm signals of different levels according to the equipment failure rate. The equipment management module 5 is configured to generate an auxiliary management scheme according to the equipment alarm signal, and control the equipment to be managed by the auxiliary management scheme.

[0091] In some embodiments, referring to Figure 7 , the model generation module 2 comprises: The first model generation module 21 is configured to generate the health state analysis model according to the historical equipment influence factor and the historical equipment health index of different equipment. The second model generation module 22 is configured to generate the residual life probability distribution prediction model according to the historical equipment influence factor and the historical equipment residual life probability distribution of different equipment. The third model generation module 23 is configured to generate the situation awareness model according to the historical equipment health index, the historical equipment residual life and the historical failure rate of different equipment.

[0092] In some embodiments of the present application, referring to Figure 8 , the first model generation module 21 comprises: The first data set generation sub-module 211 is configured to form a first data set according to the historical equipment influence factor and the historical equipment health index of different equipment, and divide the first data set into a first training set and a first verification set. The first model construction sub-module 212 is configured to construct the health state analysis model based on a regression model, taking the equipment influence factor as the input and the equipment health index as the output. The first model training sub-module 213 is configured to train the health state analysis model according to the first training set. The first model verification sub-module 214 is configured to verify the performance of the health state analysis model according to the first verification set.

[0093] In some embodiments of the present application, referring to Figure 9 , the second model generation module 22 comprises: The second data set generation sub-module 221 is configured to form a second data set according to the historical equipment influence factor and the historical equipment residual life probability distribution of different equipment, and divide the second data set into a second training set and a second verification set. The second model construction submodule 222 is configured to construct a residual life probability distribution prediction model based on a long short-term memory network (LSTM), with the device influence factor as input and the device residual life probability distribution as output. The second model training submodule 223 is configured to train the residual life probability distribution prediction model according to the second training set. The second model verification submodule 224 is configured to verify the performance of the residual life probability distribution prediction model according to the second verification set.

[0094] In some embodiments, referring to Figure 10 , the third model generation module 23 comprises: The first calculation submodule 231 is configured to calculate a historical device health index mean and a historical device health index standard deviation according to the historical device health index. The normalization submodule 232 is configured to normalize the historical device residual life to obtain normalized historical device residual life. The third data set generation submodule 233 is configured to form a third data set by combining the normalized historical device residual life, the historical device health index mean, the historical device health index standard deviation, and the historical device failure rate, and divide the third data set into a third training set and a third verification set. The third model construction submodule 234 is configured to construct a situational awareness model based on a long short-term memory network (LSTM), with the device health index mean, the device health index standard deviation, and the normalized device residual life as input and the device failure rate as output. The third model training submodule 235 is configured to train the situational awareness model according to the third training set. The third model verification submodule 236 is configured to verify the performance of the situational awareness model according to the third verification set.

[0095] In some embodiments of the present application, referring to Figure 11 , the prediction module 3 comprises: The health state prediction submodule 31 is configured to predict the device health index of different devices according to the device influence factor of a set time period through a health state analysis model. The probability distribution prediction submodule 32 is configured to predict the probability distribution of the device residual life according to the device influence factor of a set time period through a residual life probability distribution prediction model. The second calculation submodule 33 is configured to determine the risk failure time according to the probability distribution of the device residual life, and calculate the device residual life according to the risk failure time and the current time. The situational prediction submodule 34 is configured to predict the device failure rate according to the device health index and the device residual life through a situational awareness model.

[0096] The bulk cargo wharf operation situation perception system of the embodiment of the present application can predict the instantaneous health state and residual life of the equipment, predict the equipment failure rate based on the health state and residual life, and realize accurate early warning, rapid response and effective control of the equipment risk through hierarchical alarm driven by the equipment failure rate, linkage of alarm and management scheme, and closed-loop control of the execution process, so as to finally achieve the core goal of "reducing failure loss, improving operation efficiency and ensuring production safety", and provide core support for fine management of the whole life cycle of the equipment.

[0097] The following will compare the bulk cargo wharf operation situation perception method and system of the present application (hereinafter referred to as the present application) with the prior art through specific embodiments to verify the effectiveness of the present application.

[0098] Embodiment: The historical influence factors, historical health degree index, historical residual life and historical failure rate of the main vulnerable parts of the bulk cargo wharf conveyor are used, the historical influence factors are taken as the data set of the roller, and the failure rate analysis of the tripper is carried out on the data set by the present application and the prior art. The analysis result is shown in Table 2.

[0099] Table 2

[0100] As can be seen from Table 2, compared with the prediction of the traditional method, the prediction error of the failure rate on the roller data set is obviously reduced, for example, the MAE is reduced by 18.3%, and the RMSE is reduced by 18.2%, which can effectively identify the equipment failure rate, realize accurate early warning, rapid response and effective control of the equipment risk through hierarchical alarm driven by the equipment failure rate, linkage of alarm and management scheme, and closed-loop control of the execution process.

[0101] The technical features of the above-described embodiments can be combined in any manner, and to make the description concise, not all possible combinations of the technical features in the above-described embodiments are described, however, as long as the combinations of the technical features do not exist contradictory, they should be considered as the scope of the present application.

[0102] The above-described embodiments only express several embodiments of the present application, and the description is more specific and detailed, but it should not be understood as a limitation on the scope of the patent. It should be pointed out that for ordinary skilled in the art, without departing from the concept of the present application, some modifications and improvements can be made, which are all within the scope of the present application. Therefore, the protection scope of the present application patent should be subject to the appended claims.

Claims

1. A bulk cargo terminal operation and maintenance situation awareness method, characterized in that, The method comprises the following steps: a data acquisition step of acquiring device influence factors of different devices in a set time period; a health degree prediction step of evaluating a device health degree index according to the device influence factors in the set time period through a pre-constructed health state analysis model to obtain device health degree indexes at different times; a residual life prediction step of predicting a probability distribution of a device residual life according to the device influence factors in the set time period through a pre-constructed residual life probability distribution prediction model, determining a risk failure time according to the probability distribution of the device residual life, and calculating the device residual life according to the risk failure time and a current time; a situation prediction step of predicting a device failure rate according to the device health degree index and the device residual life through a pre-constructed situation awareness model; an evaluation step of generating device alarm signals of different levels according to the device failure rate; a device management step of generating an auxiliary management scheme according to the device alarm signals and controlling the device to be managed by executing the auxiliary management scheme.

2. The bulk cargo terminal operation and maintenance situation awareness method of claim 1, wherein, The health state analysis model is constructed by: acquiring historical device influence factors and historical device health degree indexes of different devices to form a data set, and dividing the data set into a training set and a verification set; based on a regression model, constructing a health state analysis model with the device influence factors as input and the device health degree index as output; the health state analysis model is represented as: In the formula, an equipment health index, an equipment factory health index, is the nth equipment influence factor index normalized value, is the nth equipment influence factor weight; training and verifying the health state analysis model through the training set and the verification set.

3. The bulk cargo terminal operation and maintenance situation awareness method of claim 2, wherein, When training the health state analysis model, the training set is used to train the weight area, and a statistical method is used to update the weight of the health state analysis model.

4. The bulk cargo terminal operation and maintenance situation awareness method of claim 1, wherein, The residual life probability distribution prediction model is constructed by: acquiring historical device influence factors and historical device residual life probability distributions of different devices to form a data set, and dividing the data set into a training set and a verification set; based on a long short-term memory network (LSTM), constructing a residual life probability distribution prediction model with the device influence factors as input and the device residual life probability distribution as output; the residual life probability distribution prediction model is represented as: wherein, is a risk prediction function according to the risk failure time t, representing the instantaneous failure risk of the equipment at the covariates ; is a baseline risk function, representing the natural aging trend of the equipment; is a covariate coefficient, representing the influence weight of the equipment influence factor on the failure risk; is the covariate of the equipment influence factor; is the number of equipment influence factors; training and verifying the residual life probability distribution prediction model through the training set and the verification set.

5. The bulk cargo terminal operation and maintenance situation awareness method according to claim 1, wherein, In the situation prediction step, the device failure rate is predicted according to the device health degree index and the device residual life through a pre-constructed situation awareness model by: calculating the mean and standard deviation of the device health degree index in the set time period according to the health degree index at different times; normalizing the device residual life to obtain normalized device residual life; predicting the device failure rate through the situation awareness model according to the mean of the device health degree index, the standard deviation of the device health degree index, and the normalized device residual life.

6. The bulk cargo terminal operation and maintenance situation awareness method of claim 5, wherein, The situation awareness model is constructed by: acquiring historical device health degree indexes, historical device residual life, and historical device failure rates; calculating the mean and standard deviation of the historical device health degree index according to the historical device health degree index, and normalizing the historical device residual life to obtain normalized historical device residual life; The normalized historical equipment residual life and the historical equipment health index mean, the historical equipment health index standard deviation, and the historical equipment failure rate form a data set, and are divided into a training set and a validation set; Based on the long short-term memory network LSTM, a situational awareness model is constructed with the equipment health index mean, the equipment health index standard deviation, and the normalized equipment residual life as input and the equipment failure rate as output. The situational awareness model is represented as: In the formula, is the device failure rate, is the mean of the device health index, is the sensitivity constant, is the standard deviation of the device health index, is the normalized device remaining life; The situational awareness model is trained and verified through the training set and the validation set.

7. A bulk cargo terminal operation and maintenance situation awareness system for implementing the bulk cargo terminal operation and maintenance situation awareness method according to any one of claims 1 to 6, characterized in that, It comprises: A data acquisition module for acquiring device influence factors of different devices in a set time period, and historical device influence factors, historical equipment health indexes, historical equipment residual life probability distributions, historical equipment residual life, and historical failure rates of different devices; A model generation module for generating a health state analysis model according to historical device influence factors and historical equipment health indexes of different devices, generating a residual life probability distribution prediction model according to historical device influence factors and historical equipment residual life probability distributions of different devices, and generating a situational awareness model according to historical equipment health indexes, historical equipment residual life, and historical failure rates of different devices; A prediction module for predicting equipment health indexes and probability distributions of equipment residual life through the health state analysis model and the residual life probability distribution prediction model respectively according to device influence factors of different devices in a set time period; determining a risk failure time according to the probability distribution of equipment residual life, calculating equipment residual life according to the risk failure time and the current time, and predicting equipment failure rates through the situational awareness model according to equipment health indexes and equipment residual life; An evaluation module for generating device alarm signals of different levels according to equipment failure rates; A device management module configured to generate an auxiliary management scheme according to the device alarm signal, and control the auxiliary management device to execute the auxiliary management scheme.

8. The bulk cargo terminal operation and maintenance situation awareness system of claim 7, wherein, The model generation module comprises: A first model generation module for generating a health state analysis model according to historical device influence factors and historical equipment health indexes of different devices; A second model generation module for generating a residual life probability distribution prediction model according to historical device influence factors and historical equipment residual life probability distributions of different devices; A third model generation module for generating a situational awareness model according to historical equipment health indexes, historical equipment residual life, and historical failure rates of different devices.

9. The bulk cargo terminal operation and maintenance situation awareness system of claim 8, wherein, The first model generation module comprises: A first data set generation submodule for forming a first data set according to historical device influence factors and historical equipment health indexes of different devices, and dividing the first data set into a first training set and a first validation set; A first model construction submodule for constructing a health state analysis model based on a regression model with device influence factors as input and equipment health indexes as output; A first model training submodule for training the health state analysis model according to the first training set; A first model verification submodule for verifying the performance of the health state analysis model according to the first validation set; The second model generation module comprises: The second data set generation submodule is configured to form a second data set from historical device impact factors and historical device residual life probability distributions of different devices, and divide the second data set into a second training set and a second verification set; The second model construction submodule is configured to construct a residual life probability distribution prediction model based on a long short-term memory network (LSTM), take device impact factors as input, and take device residual life probability distributions as output; The second model training submodule is configured to train the residual life probability distribution prediction model according to the second training set; The second model verification submodule is configured to verify the performance of the residual life probability distribution prediction model according to the second verification set; The third model generation module comprises: The first calculation submodule is configured to calculate a historical device health index mean and a historical device health index standard deviation according to historical device health index values; The normalization submodule is configured to normalize historical device residual life to obtain normalized historical device residual life; The third data set generation submodule is configured to form a third data set from the normalized historical device residual life, the historical device health index mean, the historical device health index standard deviation, and historical device failure rates, and divide the third data set into a third training set and a third verification set; The third model construction submodule is configured to construct a situational awareness model based on a long short-term memory network (LSTM), take the device health index mean, the device health index standard deviation, and the normalized device residual life as input, and take device failure rates as output; The third model training submodule is configured to train the situational awareness model according to the third training set; The third model verification submodule is configured to verify the performance of the situational awareness model according to the third verification set.

10. The bulk cargo terminal operation and maintenance situation awareness system of claim 7, wherein, The prediction module comprises: The health state prediction submodule is configured to predict device health index values according to device impact factors of different devices in a set time period by using a health state analysis model; The probability distribution prediction submodule is configured to predict probability distributions of device residual life according to device impact factors in the set time period by using a residual life probability distribution prediction model; The second calculation submodule is configured to determine a risk failure time according to the probability distributions of device residual life, and calculate device residual life according to the risk failure time and a current time; The situation prediction submodule is configured to predict device failure rates according to device health index values and device residual life by using a situational awareness model.

Citation Information

Patent Citations

  • Predictive maintenance system for aerospace equipment

    CN115526375A

  • Power grid historical message processing method and device and power grid monitoring system

    CN118861683A

  • Internet of Things security management and control method and system based on big data

    CN119961576A

  • Production simulation prediction optimization system based on artificial intelligence

    CN120338181A

  • Motor residual life analysis method and system based on support vector machine

    CN120724415A

Cited By

  • Bulk cargo wharf operation and maintenance sensing method and system based on equipment codes and dynamic thresholds

    CN122046313A

  • Bulk cargo terminal operation and maintenance perception method and system based on device coding and dynamic threshold

    CN122046313B