Synchronous installation method for irregular structure curtain wall
By using staggered construction and the construction of temporary operating platforms, combined with multi-suspension systems and BIM technology, the problem of simultaneous installation of multiple work sections in curtain wall construction was solved, achieving efficient and safe curtain wall construction and promoting the intelligent development of curtain wall engineering.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- CHINA MCC5 GROUP CORP LTD
- Filing Date
- 2026-06-10
- Publication Date
- 2026-07-17
AI Technical Summary
Existing curtain wall construction technology cannot achieve simultaneous construction of multiple work sections, resulting in excessively long construction cycles and significant idle work. It is constrained by the spatial sequence of the splicing process, the single-channel bottleneck of vertical transportation, and safety regulations for cross-operations.
By constructing the project in staggered sections, setting up temporary operating platforms and multiple suspended platform systems, and adopting BIM dynamic zoning, electronic tag scheduling, and drone inspection, independent and synchronous installation of multiple work sections can be achieved.
It significantly improves construction efficiency, shortens the construction period by more than 30%, enhances construction safety and structural stability, improves installation accuracy and quality, and promotes the digitalization and intelligentization of curtain wall construction.