A method for installing a secondary reducer for a high-precision converter tilting mechanism to prevent offset
By combining the sliding support assembly and the synchronous jacking alignment assembly, the problems of large alignment offset, poor coaxiality, uneven jacking force, and cumbersome leveling during the installation of the converter secondary reducer were solved, achieving a high-precision, safe, and efficient installation effect.
Patent Information
- Application Number
- CN202611138251.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-07-29
- Publication Date
- 2026-11-10
AI Technical Summary
The existing converter secondary reducer installation process suffers from problems such as large alignment misalignment, difficulty in ensuring coaxiality, uneven jacking force, cumbersome leveling, and low construction efficiency, resulting in short equipment lifespan and unstable operation.
By employing sliding support components and synchronous jacking alignment components, combined with graded adjustment pads and rigid tension limiting components, the secondary reducer achieves full-range anti-lateral deviation, synchronous jacking, and precise graded elevation adjustment, adapting to different trunnion spacings and improving alignment and coaxial accuracy.
This significantly improves the alignment accuracy of the secondary reducer, shortens the installation period, protects the equipment body from damage, reduces construction costs and safety risks, and improves construction efficiency.
Smart Images

Figure CN123063572A_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the technical field of steelmaking converter equipment installation, specifically relating to a method for installing a secondary reducer of a high-precision converter tilting mechanism to prevent deviation. Background Technology
[0002] The converter tilting mechanism in the steelmaking workshop is the core heavy-duty equipment that drives the converter body to complete the entire process of iron charging, feeding, steel tapping, slag dumping, and resetting. It mainly consists of three major components: a primary reducer, a secondary reducer, and a torsion bar. The equipment operates under heavy loads and large impact loads. Therefore, the coaxial alignment accuracy of the secondary reducer with the trunnion of the support ring and the transmission side bearing seat directly determines the service life and operational stability of the tilting mechanism.
[0003] The existing installation and construction process of secondary reducers for converters has the following technical defects: 1. Large misalignment and difficulty in ensuring coaxiality: Traditional construction uses hand-operated hoists and simple jacking tools to move reducers. There is no lateral limiting or synchronous jacking structure during the moving process. The reducer is prone to horizontal and vertical misalignment. The coaxiality of the trunnion flange and the reducer input shaft exceeds the tolerance. Later, vibration, tooth surface wear due to uneven load, and oil leakage failure will occur during operation. 2. Uneven jacking force can easily damage equipment: Without a synchronous hydraulic jacking structure, unilateral force can easily cause deformation of the reducer housing and local crushing of the bearing trunnion end face, resulting in extremely high repair costs for heavy-duty equipment. 3. The elevation and level adjustment are complicated: the elevation of the reducer base is only temporarily supported by scattered thin steel plates, and there is no standardized slide structure for the graded leveling. It requires repeated lifting and adjustment, resulting in a long construction period and high hoisting safety risks. 4. Poor tooling versatility and large amount of on-site modification work: Conventional top push tooling does not have an adjustable tie beam structure to adapt to different trunnion spacings. Different furnace types require separate tooling processing, resulting in material waste and long processing cycles. 5. Limited operating space and low bolt alignment efficiency: The gap between the reducer and the trunnion end face cannot be precisely controlled, the operating space for disassembling and assembling flange connection bolts is insufficient, and manual alignment is time-consuming.
[0004] In summary, existing construction tools and installation processes cannot meet the requirements for high-precision, anti-deviation, synchronous force, and high-efficiency and safe secondary reducer installation. There is an urgent need for an integrated alignment device and standardized construction method that integrates slide leveling, synchronous jacking with double jacks, and rigid tie beam limiting to prevent deviation. Summary of the Invention
[0005] The purpose of this invention is to provide a high-precision installation method for the secondary reducer of a converter tilting mechanism that prevents offset. Addressing the technical pain points of existing converter secondary reducers, such as large installation offset, poor coaxiality, uneven jacking force, cumbersome leveling, and low construction efficiency, this method prevents lateral offset throughout the reducer's movement, ensures uniform force during synchronous jacking with dual jacks, provides precise and adjustable elevation levels, and allows for tooling to accommodate different trunnion spacings. This significantly improves alignment and coaxiality accuracy, shortens the installation period, and protects the heavy-duty equipment from construction damage.
[0006] To achieve the above objectives, the present invention provides the following technical solution: A method for installing a secondary reducer in a high-precision converter tilting mechanism to prevent lateral displacement is provided. This method utilizes sliding support components to prevent lateral displacement throughout the entire process of pushing the secondary reducer, and synchronous jacking and alignment components complete the synchronous jacking. The elevation is precisely adjustable in stages, and the tooling is adaptable to different trunnion spacings, improving alignment and coaxial accuracy and protecting the heavy-duty equipment from construction damage. The specific steps include the following: S1. On-site measurement and tooling prefabrication: After the converter body, support ring, and bearing seat are in place, measure the distance between the end face of the drive side of the support ring trunnion and the installation reference of the reducer, and fabricate a rigid tension limit assembly; inspect the weld flaws; and prefabricate graded adjustment shims with a thickness of 10-50mm. S2. Erection of sliding support components: The top surface of the foundation is fully covered with hardwood for leveling, connecting beams and rails are laid, limit clamps are welded to the rails, and the sliding beams are hoisted and clamped to the rails to complete the lateral limit. S3. Coarse adjustment of the elevation of the secondary reducer: The bridge crane lifts the secondary reducer and places it on the slide beam. The shims are added or removed in stages, and the elevation and level of the reducer are coarsely adjusted with the help of a level and dial indicator. S4. Rigid tension limit assembly and fixing: One end of the tension beam is locked to the end face of the support ring trunnion by connecting flange and bolts, and the other end of the tension beam passes through the center hole of the reducer. The end is supported by a pressure-bearing main beam and welded with a limit stop steel plate. S5. Synchronous jacking system debugging: Install two hydraulic jacks symmetrically on the side of the reducer housing, connect them to the synchronous hydraulic pump station, and calibrate the synchronous stroke error of the two jacks under no-load conditions. S6. Synchronous sliding high-precision alignment: Start the synchronous pump station, the double jacks extend synchronously, and rely on the pull beam to constrain the reducer to slide smoothly along the track. Monitor the coaxiality in real time, and push it until the reducer flange and the end face of the support ring trunnion are in contact, leaving a gap for bolt disassembly and assembly. S7. Permanent Connection and Tooling Removal: Tighten the permanent connection bolts between the reducer and the trunnion flange, retract the hydraulic jack, and remove the rigid tension limit assembly and sliding support assembly in sequence, then proceed to the coaxial re-inspection process of the tilting mechanism.
[0007] The sliding support assembly includes hardwood timber, connecting beams, tracks, sliding beams, limiting clamps, and graded adjustment pads. The hardwood timber is laid on the top surface of the transmission side foundation, and the connecting beam is arranged above the timber. Two tracks are fixed to the top surface of the connecting beam. The sliding beam spans both sides of the connecting beam, and the bottom sides of the sliding beam are limited by limiting clamps that engage with the tracks. The limiting clamps are fully welded to the sliding beam and the tracks respectively. The elevation of the sliding track is adjusted using graded adjustment pads.
[0008] The rigid tension limiting assembly includes a tie beam, a connecting flange, a pressure-bearing main beam, and a pressure-bearing steel plate. The tie beam is made of seamless steel pipe, and one end of the tie beam is bolted to the end face of the drive side of the ring trunnion through the connecting flange. The other end of the tie beam passes through the central through hole of the reducer, and two pressure-bearing main beams are erected at the end. Pressure-bearing steel plates and limiting stop steel plates are welded to both sides of the pressure-bearing main beams to form pressure-bearing limiting stops. All connection nodes are welded, and the weld height is not less than the thickness of the corresponding base material plate. The reference dimension of the device is that the distance between the secondary reducer and the end face of the drive side of the ring trunnion is at least 500mm, and the length of the tie beam is adapted according to the measured distance.
[0009] The synchronous jacking and alignment assembly includes two hydraulic jacks, which are vertically symmetrically arranged on both sides of the center vertical line of the secondary reducer housing. The jack pushing end abuts against the end face of the transmission side bearing seat, and the jack base is supported between the pressure-bearing main beam and the secondary reducer. The dual jacks are equipped with a synchronous hydraulic control system.
[0010] In step S5, the no-load stroke synchronization error of the synchronous hydraulic control system of the two hydraulic jacks is ≤0.1mm.
[0011] During the pushing process in step S6, the lateral offset of the reducer is controlled to be ≤0.05mm / m.
[0012] In step S7, the flange connection bolts are tightened diagonally in stages to ensure flange sealing and coaxial accuracy.
[0013] Compared with the prior art, the beneficial effects of the present invention are: 1. Full-process anti-deviation, significantly improved alignment accuracy: The dual constraint structure of the slide rail lateral limit clamp + central rigid tie beam restricts the radial and lateral deviation of the reducer during the pushing process, and the coaxiality error is controlled within 0.05mm / m, eliminating the later tooth surface uneven load, vibration and oil leakage failures. 2. Synchronous jacking with two jacks to protect the equipment body: The synchronous hydraulic control system ensures that the jacking force and stroke of the two jacks are completely synchronized, eliminating unilateral stress and avoiding damage to the reducer housing and bearing ring trunnion due to pressure deformation. 3. Precise and adjustable elevation levels simplify the leveling process: Equipped with δ10~50mm graded adjustment pads, there is no need to repeatedly hoist the reducer. Simply adding or removing pads can complete the fine adjustment of elevation and levelness, shortening the leveling construction time by more than 60%. 4. Strong tooling adaptability, reducing modification costs: The tie beam can be modified according to the actual measured trunnion spacing on site, and can be adapted to the installation of secondary reducers of converters of different tonnages and furnace types. The tooling can be reused, reducing the material consumption of single-piece processing. 5. Standardized construction process, safe and controllable operation: Integrated sliding support, rigid limit, and synchronous jacking integrated tooling eliminates the need for high-altitude manual hoist traction, reducing the safety risks of hoisting and high-altitude operations. Flange gap is controllable, bolt disassembly and assembly operation space is sufficient, and manual alignment efficiency is significantly improved. 6. High structural load-bearing strength and good construction safety: The weld height of all welded joints matches the thickness of the base material. The main beam adopts I56a large I-beams and the tie beam adopts thick-walled seamless steel pipes, which can meet the load-bearing requirements of heavy-duty reducer jacking. The tooling has high overall rigidity and no plastic deformation. Attached Figure Description
[0014] Figure 1 This is a schematic diagram of the tooling implementation state of an embodiment of the present invention, showing the positioning state of the sliding support assembly, the synchronous jacking and alignment assembly, the rigid traction and limiting assembly, and the secondary reducer. Figure 2 This is a schematic diagram of the alignment of the secondary reducer in an embodiment of the present invention, with two hydraulic jacks arranged symmetrically vertically. Figure 3 This is a schematic diagram of the rigid tension limiting component structure in an embodiment of the present invention; Figure 4 This is a schematic diagram showing the positioning of the trunnion drive side end face and the secondary reducer in an embodiment of the present invention; In the diagram: 1-Hardwood, 2-Connecting beam, 3-Connecting flange, 4-Railway, 5-Slide beam, 6-Tie beam, 7-Pressure-bearing steel plate, 8-Pressure-bearing main beam, 9-Limit stop steel plate, 10-Limit clamp, 11-Hydraulic jack, 12-Secondary reducer, 13-Transmission side foundation, 14-Support ring, 15-Bearing seat, 16-Converter body, 17-Support ring trunnion. Detailed Implementation
[0015] The technical solution of the present invention will be clearly and completely described below with reference to specific embodiments. Obviously, the described embodiments are some embodiments of the present invention, but not all embodiments.
[0016] To more clearly illustrate the specific embodiments of the present invention or the technical solutions in the prior art, the specific embodiments used in the description of the specific embodiments or the prior art will be briefly introduced below. Obviously, the specific embodiments described below are some embodiments of the present invention. For those skilled in the art, other specific embodiments can be obtained based on these specific embodiments without creative effort.
[0017] See Figure 1-4 This is a schematic diagram of the tooling implementation state of an embodiment of the installation method for a secondary reducer of a high-precision converter tilting mechanism to prevent offset, taking the on-site installation of a 2120t converter secondary reducer as an example. The invention aims to prevent lateral offset of the secondary reducer during the entire pushing process using the sliding support assembly, achieve synchronous pushing with the synchronous jacking and alignment assembly, provide precise and adjustable elevation levels, adapt the tooling to different trunnion spacings, improve alignment and coaxial accuracy, and protect the heavy-duty equipment body from construction damage. Specifically, it includes the following operating steps: S1. On-site measurement and tooling prefabrication: After the converter body 16, support ring 14, and bearing seat 15 are installed in place, the measured distance between the transmission side end face of the support ring trunnion 17 and the installation reference distance of the secondary reducer 12 is 498mm. Rigid tension limit assembly is fabricated. All parts are cut and welded. After welding, the weld strength is inspected by flaw detection. Graded adjustment pads with a thickness of 10-50mm are prefabricated. The graded adjustment pads are prefabricated according to the thickness specifications of 10mm, 20mm, 30mm, 40mm, and 50mm.
[0018] S2. Sliding support assembly erection: The top surface of the foundation is fully covered with 30 pieces of hard miscellaneous timber 1 for leveling, 10 I10a connecting beams 2 are laid, two 43kg / m steel rails are fixed to the track 4, and 30mm thick limiting clamps 10 are welded to the track 4. The sliding beam 5 is hoisted to the top of the base, and the limiting clamps 10 are engaged with the track 4 to complete the lateral limiting. S3. Coarse adjustment of the elevation of the secondary reducer: The bridge crane hoists the secondary reducer onto the slide beam 5, and adds or removes 10-50mm graded adjustment shims. With the help of a level and dial indicator, the elevation and level of the reducer are coarsely adjusted. 3. Leveling of the reducer: The bridge crane hoists the secondary reducer onto the slide beam 5, and adds or removes adjustment shims to complete the coarse adjustment, ensuring that the input shaft of the secondary reducer 12 and the trunnion 17 are initially coaxial. With the help of a frame level, the longitudinal and transverse levelness of the secondary reducer is ≤0.02mm / m.
[0019] S4. Assembly and fixing of rigid tension limiting component: One end of the tension beam 6, made of Φ325×8 steel pipe, is locked to the end face bolt of the support ring trunnion 17 through the connecting flange 3 with a thickness of 30mm. The other end of the tension beam 6 passes through the center hole of the reducer. Two I56a pressure-bearing main beams 8 are erected at the end and 16mm and 20mm thick pressure-bearing steel plates 7 are welded to form the limiting stop steel plate 9, thus completing the assembly of the rigid tension limiting component. S5. Synchronous jacking system debugging: Install two hydraulic jacks 11 symmetrically on the upper and lower sides of the reducer housing. One end of each hydraulic jack 11 abuts against the end face of the transmission side bearing seat 15, and the other end presses against the limit stop steel plate 9 of the main bearing beam 8. Connect the synchronous hydraulic pump station, debug the synchronous pump station, and slowly jack. During the sliding process, the dial indicator monitors the lateral offset in real time. Push until the flange fits and a 30mm bolt operating gap is reserved. The coaxiality is measured to be 0.04mm / m, which meets the installation accuracy standard. The synchronous stroke error of the two jacks is calibrated under no-load. The no-load stroke synchronization error of the synchronous hydraulic control system of the two hydraulic jacks is ≤0.1mm. The synchronous control system is then calibrated.
[0020] S6. Synchronous sliding high-precision alignment: Start the synchronous pump station, the double jacks extend synchronously, and the secondary reducer is constrained by the pull beam 6 in the opposite direction. The slide beam 5 slides smoothly along the track 4 towards the support ring trunnion 17. During the pushing process, the coaxiality value of the dial indicator is monitored in real time. The lateral offset of the secondary reducer is controlled to be ≤0.05mm / m throughout the process until the flange of the secondary reducer is in contact with the end face of the support ring trunnion 17, and the bolt disassembly and assembly operation gap is reserved. S7. Permanent Connection and Tooling Removal: Tighten the permanent connection bolts between the secondary reducer 12 and the support ring trunnion 17, tighten the flange connection bolts diagonally in stages to ensure flange sealing and coaxial accuracy, retract the hydraulic jack 11, remove the rigid tension limit assembly and sliding support assembly in sequence, and proceed to the coaxial re-inspection process of the tilting mechanism. After re-inspecting the coaxiality of the tilting mechanism, conduct a trial run.
[0021] On-site construction verification showed that by using the device and method of this invention, the alignment time of the reducer was shortened from the traditional 8 hours to 2.5 hours. There was no deviation or equipment off-center stress damage during the entire pushing process. After 6 months of operation, there were no problems with vibration, oil leakage, or abnormal gear wear. The advantages of construction safety, installation accuracy, and economic benefits are significant.
[0022] In this embodiment, the sliding support assembly includes a hardened timber 1, a connecting beam 2, a track 4, a sliding beam 5, a limiting clamp 10, and a graded adjustment pad. The hardened timber 1 is laid on the top surface of the transmission side foundation 13. Two I10a specification connecting beams 2 are arranged above the timber, and two 43kg / m steel rails 4 are fixed to the top surface of the connecting beams 2. The sliding beam 5 spans across both sides of the connecting beam 2. The bottom sides of the sliding beam 5 are engaged and limited with the track 4 by the limiting clamps 10 made of 30mm thick steel plates. The limiting clamps 10 are fully welded to the sliding beam 5 and the track 4 respectively. A graded adjustment pad with a thickness of 10-50mm is laid between the sliding beam 5 and the secondary reducer base to achieve graded fine adjustment of the reducer's elevation and level. All structural components of the tooling are made of Q235-B carbon structural steel. The supporting parts include 30 pieces of 300mm×250mm×3000mm hardwood logs, 10 I10a connecting beams, 1 30mm thick connecting flange, 2 43kg / m rails, 2 sliding beams, 1 Φ325×8 tie beam, 4 16mm thick steel plates, 2 I56a main beams, and 2 20mm thick steel plates.
[0023] The synchronous jacking and alignment assembly includes two hydraulic jacks 11, which are vertically and symmetrically arranged on both sides of the center vertical line of the secondary reducer housing. The jack pushing end abuts against the end face of the transmission side bearing seat 15, and the jack base is supported between the pressure-bearing main beam 8 and the secondary reducer 12. The dual jacks are equipped with a synchronous hydraulic control system to ensure that the jacking stroke and jacking force are completely synchronized, and to avoid the reducer being subjected to force deviation on one side and the housing being deformed.
[0024] The rigid tension limiting assembly includes a tension beam 6, a connecting flange 3, a pressure-bearing main beam 8, and a pressure-bearing steel plate 7. The tension beam 6 is made of seamless steel pipe. One end of the tension beam 6 is bolted to the transmission side end face of the support ring trunnion 17 via the connecting flange 3. The other end of the tension beam 6 passes through the central through hole of the reducer. Two I56a I-beams are erected at the end as the pressure-bearing main beam 8. 16mm and 20mm thickened pressure-bearing steel plates 7 are welded to both sides of the pressure-bearing main beam 8 to form a limiting stop steel plate 9. When the hydraulic jack 11 pushes, the tension beam 6 provides a reverse rigid tension constraint, restricting the reducer from radial and lateral displacement throughout the entire process, ensuring the coaxiality of the support ring trunnion 17 and the input shaft of the secondary reducer 12. All connection nodes are welded, and the weld height is not less than the corresponding base plate thickness. The reference dimension of the device is that the distance between the transmission side end face of the secondary reducer and the support ring trunnion 17 is at least 500mm. The length of the tension beam 6 is adapted according to the measured distance. The distance between the secondary reducer and the drive side end face of the trunnion 17 is 500mm. If there is a deviation in the distance measured on site, the modification can be completed by simply cutting and lengthening or shortening the Φ325×8 tie beam 6. No other parts need to be modified. The length of the tie beam 6 is adapted to different converter types according to the actual distance measured on site.
[0025] In this embodiment, all connection nodes of the tooling structure in the sliding support assembly and the rigid tension limiting assembly are fully penetrated welded, with the weld height not less than the corresponding base plate thickness, ensuring the overall load-bearing strength of the tooling. All components are uniformly made of Q235-B carbon structural steel.
[0026] Although embodiments of the invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the appended claims and their equivalents.
Claims
1. A method for installing a secondary reducer of a high-precision converter tilting mechanism to prevent offset, characterized in that, The secondary reducer, with the aid of sliding support components, prevents lateral deviation during the entire pushing process. Synchronous jacking and alignment components complete the synchronous jacking, with precise and adjustable elevation levels. The tooling is adaptable to different trunnion spacings, improving alignment and coaxial accuracy and protecting the heavy-duty equipment from construction damage. The specific operating steps include the following: S1. On-site measurement and tooling prefabrication: After the converter body, support ring, and bearing seat are in place, measure the distance between the end face of the drive side of the support ring trunnion and the installation reference of the reducer, and fabricate a rigid tension limit assembly; inspect the weld flaws; and prefabricate graded adjustment shims with a thickness of 10-50mm. S2. Erection of sliding support components: The top surface of the foundation is fully covered with hardwood for leveling, connecting beams and rails are laid, rail limit clamps are welded, and the sliding beam is hoisted and clamped to the rail to complete the lateral limit. S3. Coarse adjustment of the elevation of the secondary reducer: The bridge crane lifts the secondary reducer and places it on the slide beam. The shims are added or removed in stages, and the elevation and level of the reducer are coarsely adjusted with the help of a level and dial indicator. S4. Rigid tension limit assembly and fixing: One end of the tension beam is locked to the end face of the support ring trunnion by connecting flange and bolts, and the other end of the tension beam passes through the center hole of the reducer. The end is supported by a pressure-bearing main beam and welded with a limit stop steel plate. S5. Synchronous jacking system debugging: Install two hydraulic jacks symmetrically on the side of the reducer housing, connect them to the synchronous hydraulic pump station, and calibrate the synchronous stroke error of the two jacks under no-load conditions. S6. Synchronous sliding high-precision alignment: Start the synchronous pump station, the double jacks extend synchronously, and rely on the pull beam to constrain the reducer to slide smoothly along the track. Monitor the coaxiality in real time, and push it until the reducer flange and the end face of the support ring trunnion are in contact, leaving a gap for bolt disassembly and assembly. S7. Permanent Connection and Tooling Removal: Tighten the permanent connection bolts between the reducer and the trunnion flange, retract the hydraulic jack, and remove the rigid tension limit assembly and sliding support assembly in sequence, then proceed to the coaxial re-inspection process of the tilting mechanism.
2. The method for installing a secondary reducer of a high-precision converter tilting mechanism to prevent offset according to claim 1, characterized in that, The sliding support assembly includes hardwood (1), connecting beam (2), track (4), slide beam (5), limiting clamp (10), and graded adjustment pads; the hardwood is laid on the top surface of the transmission side foundation, the connecting beam is arranged above the wood, and two tracks are fixed to the top surface of the connecting beam (2); the slide beam (5) spans across both sides of the connecting beam (2), and the bottom sides of the slide beam (5) are engaged with the track (4) by the limiting clamp (10), and the limiting clamp (10) is fully welded to the slide beam (5) and the track (4) respectively; the slide elevation is adjusted by graded adjustment pads.
3. The method for installing a secondary reducer of a high-precision converter tilting mechanism to prevent offset, as described in claim 2, is characterized in that... The rigid tension limiting assembly includes a tie beam (6), a connecting flange (3), a pressure-bearing main beam (8), and a pressure-bearing steel plate (7). The tie beam is made of seamless steel pipe. One end of the tie beam is bolted to the end face of the trunnion drive side through the connecting flange. The other end of the tie beam passes through the central through hole of the reducer. Two pressure-bearing main beams are erected at the end. Pressure-bearing steel plates (7) and limiting stop steel plates (9) are welded to both sides of the pressure-bearing main beams to form pressure-bearing limiting stop seats. All connection nodes are welded. The weld height is not less than the thickness of the corresponding base material plate. The reference dimension of the device is that the distance between the secondary reducer and the end face of the trunnion drive side is at least 500mm. The length of the tie beam is adapted according to the measured distance.
4. The method for installing the secondary reducer of the anti-deviation high-precision converter tilting mechanism according to claim 3, characterized in that, The synchronous jacking and alignment assembly includes two hydraulic jacks, which are vertically and symmetrically arranged on both sides of the center vertical line of the secondary reducer housing. The jack jacks push against the end face of the transmission side bearing seat, and the jack base is supported between the pressure-bearing main beam (8) and the secondary reducer. The dual jacks are equipped with a synchronous hydraulic control system.
5. The installation method of the secondary reducer for the anti-deviation high-precision converter tilting mechanism according to claim 1, characterized in that: In step S5, the no-load stroke synchronization error of the synchronous hydraulic control system of the two hydraulic jacks is ≤0.1mm.
6. The method for installing a secondary reducer of a high-precision converter tilting mechanism to prevent offset according to claim 1, characterized in that, During the pushing process in step S6, the lateral offset of the reducer is controlled to be ≤0.05mm / m.
7. The method for installing a secondary reducer of a high-precision converter tilting mechanism to prevent offset according to claim 1, characterized in that, In step S7, the flange connection bolts are tightened diagonally in stages to ensure flange sealing and coaxial accuracy.