Prestressed tension control methods and devices, electronic equipment and computer program products
By using group tensioning and single-strand pre-tightening techniques for the circumferential ducts of the tower, the problem of deflection or elliptic deformation of the tower during tensioning was solved, achieving uniform stress distribution and precise prestress application in the tower.
Patent Information
- Application Number
- CN202611261624.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-19
- Publication Date
- 2026-11-10
AI Technical Summary
Existing tower prestressing tensioning schemes may cause the tower to deflect or elliptical deform during the tensioning process, especially when tensioning is performed clockwise or counterclockwise in sequence, resulting in uneven stress distribution.
By dividing the internal channels on the circumference of the tower into multiple symmetrical tensioning groups, and applying target tension force values to the strands in each symmetrical tensioning group at each tensioning level, the uniformity and symmetry of the tower's stress are ensured by using graded tensioning and single-strand pre-tightening technology.
Effectively control the roundness deformation of the tower, improve the accuracy of prestress application and structural safety of tensioning operation, and ensure the symmetry and uniform stress distribution of the tower during the tensioning process.
Smart Images

Figure CN123067585A_ABST
Abstract
Description
Technical Field
[0001] This disclosure relates to the field of computer technology, and more specifically, to a prestressed tensioning control method, a prestressed tensioning control device, electronic equipment, and computer program products. Background Technology
[0002] Hybrid towers, short for steel-concrete composite tower structures, refer to a hybrid tower structure combining steel and concrete. They offer advantages such as steel conservation, high stability, good corrosion resistance, convenient construction, and high rigidity. Primarily used in specific wind energy resource, geographical environment, and turbine configuration scenarios, their typical structure typically employs a combination of a lower concrete section and an upper steel tower section. Hybrid tower structures usually consist of concrete sections, transition sections, and steel tower sections, connected by prestressed ducts and stranded wires to achieve coordinated stress distribution.
[0003] It should be noted that the information disclosed in the background section above is only used to enhance the understanding of the background of this disclosure, and therefore may include information that does not constitute prior art known to those skilled in the art. Summary of the Invention
[0004] The purpose of this disclosure is to provide a prestressing tensioning control method, a prestressing tensioning control device, an electronic device, a computer-readable storage medium, and a computer program product, thereby at least to some extent overcoming the problem that related tower prestressing tensioning schemes based on clockwise or counterclockwise sequential tensioning may cause the tower to deflect or elliptical deformation during the tensioning process.
[0005] Other features and advantages of this disclosure will become apparent from the following detailed description, or may be learned in part by practice of the invention.
[0006] According to a first aspect of this disclosure, a prestressing tension control method is provided, comprising: determining a plurality of internal channels located on the circumference of a tower; dividing the internal channels into a plurality of symmetrical tensioning groups, each symmetrical tensioning group comprising at least two tensioning channels symmetrically distributed about the central axis of the tower; obtaining a plurality of pre-configured tensioning stages, the tensioning stages being determined based on a specified tension force value within a tension force value range corresponding to the tension force; applying the tension force to the strands in the channels of each symmetrical tensioning group to a target tension force value corresponding to each tensioning stage under each tensioning stage, thereby performing a tension control operation for the strands in the channels; and applying the target tension force value under each tensioning stage to the strands in the channels based on the tension control operation, thereby establishing effective prestress in the tower.
[0007] In one exemplary embodiment of this disclosure, the method further includes: obtaining an initial tension value and a maximum tension value corresponding to the tension force; determining a tension force value range based on the initial tension value and the maximum tension value; determining a plurality of specified tension force values based on the tension force value range; determining a tensioning level corresponding to each specified tension force value; determining the theoretical elongation value of the stranded wire in the duct at each tensioning level; and determining the actual elongation value of the stranded wire in the duct based on the theoretical elongation value.
[0008] In one exemplary embodiment of this disclosure, determining the actual elongation value of the stranded wire based on the theoretical elongation value includes: determining a first tension range and a second tension range corresponding to the tension force; determining a first actual elongation value component based on the theoretical elongation value in response to the tension force being in the first tension range; determining a second actual elongation value component based on the measured elongation value in response to the tension force being in the second tension range; and determining the actual elongation value based on the first actual elongation value component and the second actual elongation value component.
[0009] In one exemplary embodiment of this disclosure, the step of applying the tension force to the strand in the duct of each of the tensioning stages to the target tension force value corresponding to each tensioning stage, in order to perform a tensioning control operation for the strand, includes: determining the current tensioning stage from a plurality of tensioning stages; determining the current symmetrical tensioning stage; applying the current target tension force value corresponding to the current tensioning stage to the strand in the duct of the current symmetrical tensioning stage based on the current tensioning stage; and after the tensioning operation of the current symmetrical tensioning stage is completed, rotating the prestressing tensioning device by a specified angle along the circumference of the tower to perform the tensioning operation on the next symmetrical tensioning stage, until the tensioning operation of all the symmetrical tensioning stages is completed.
[0010] In one exemplary embodiment of this disclosure, applying the current target tension value corresponding to the current tensioning level to the strands in the current symmetrical tensioning group based on the current tensioning level includes: performing a single-strand pre-tensioning step on the strands before grouping the current symmetrical tensioning group; applying a first tension force to a single strand through the single-strand pre-tensioning step, the tension value of the first tension force being determined based on a first proportion of the target tension value; determining the tension force applied to the strands as the target tension value after the single-strand pre-tensioning step; performing an over-tensioning operation on the strands after the tension force of the strands reaches the target tension value, the over-tensioning operation being used to adjust the tension force applied to the strands to a specified multiple of the target tension value; and adjusting the tension force applied to the strands to the target tension value after holding the load at a specified multiple of the target tension value for a predetermined time.
[0011] In one exemplary embodiment of this disclosure, the method further includes: taking the difference between the actual measured elongation value and the theoretical elongation value of the stranded wire as an elongation deviation value based on the tensioning operation applied to the stranded wire; taking the difference between the actual prestress value and the theoretical prestress value of the stranded wire as a prestress difference value; and stopping the tensioning operation in response to the elongation deviation value exceeding an elongation deviation value threshold or the prestress difference value exceeding a prestress difference threshold.
[0012] In one exemplary embodiment of this disclosure, the method further includes: acquiring a pre-established digital twin model of the tower structure and measured data, wherein the measured data includes one or more of the following: duct strand parameters, friction coefficient, and anchor performance; performing a tension simulation operation based on the measured data to obtain a set of tension simulation parameters for the tower and stress distribution under various tension levels, using multiple different parameter combinations; determining recommended tension parameters based on the set of tension simulation parameters, wherein the recommended tension parameters are used to configure the tension force of the duct strands; acquiring actual monitoring data corresponding to the tensioning construction operation of the tower, and transmitting the actual monitoring data back to the digital twin model of the tower structure; and determining tension adjustment parameters based on the simulation results of the actual monitoring data by the digital twin model of the tower structure, wherein the tension adjustment parameters are used to adjust the tension force of the duct strands.
[0013] According to a second aspect of this disclosure, a prestressing tensioning control device is provided, comprising: a symmetry group determination module, configured to determine a plurality of internal channels located on the circumference of a tower, dividing the internal channels into a plurality of symmetrical tensioning groups, each symmetrical tensioning group comprising at least two tensioning channels symmetrically distributed about the central axis of the tower; a tensioning stage determination module, configured to acquire a plurality of pre-configured tensioning stages, the tensioning stages being determined based on a specified tensioning force value within a tensioning force value range corresponding to the tensioning force; a target tensioning value determination module, configured to apply the tensioning force to the strands in the channels of each symmetrical tensioning group to a target tensioning force value corresponding to each tensioning stage under each tensioning stage; a tensioning operation module, configured to perform a tensioning control operation on the strands in the channels based on the target tensioning force value corresponding to each tensioning stage; and a prestressing establishment module, configured to apply the target tensioning force value under each tensioning stage to the strands in the channels based on the tensioning control operation, thereby establishing effective prestress in the tower.
[0014] In one exemplary embodiment of this disclosure, the prestressed tensioning control device further includes a strand elongation value determination module, configured to: obtain the initial tension value and the maximum tension value corresponding to the tension force; determine a tension force value range based on the initial tension value and the maximum tension value; determine a plurality of specified tension force values based on the tension force value range; determine the tension level corresponding to each specified tension force value; determine the theoretical elongation value of the strand in the duct at each tension level; and determine the actual elongation value of the strand in the duct based on the theoretical elongation value.
[0015] In one exemplary embodiment of this disclosure, the strand elongation value determination module includes an actual elongation value determination unit, configured to: determine a first tension range and a second tension range corresponding to the tension force; in response to the tension force being in the first tension range, determine a first actual elongation value component based on the theoretical elongation value; in response to the tension force being in the second tension range, determine a second actual elongation value component based on the measured elongation value; and determine the actual elongation value based on the first actual elongation value component and the second actual elongation value component.
[0016] In one exemplary embodiment of this disclosure, the tensioning operation module includes a tensioning operation unit, configured to: determine the current tensioning level from a plurality of tensioning levels; determine the current symmetrical tensioning group; apply the current target tensioning force value corresponding to the current tensioning level to the stranded wires in the current symmetrical tensioning group based on the current tensioning level; after the tensioning operation of the current symmetrical tensioning group is completed, rotate the prestressed tensioning device along the circumference of the tower by a specified angle to perform the tensioning operation on the next symmetrical tensioning group, until the tensioning operation of all the symmetrical tensioning groups is completed under each of the tensioning levels.
[0017] In one exemplary embodiment of this disclosure, the tensioning operation unit includes a tensioning operation subunit, configured to: perform a single-strand pre-tensioning step on the duct strands before grouping tensioning of the current symmetrical tensioning group; apply a first tension force to a single duct strand through the single-strand pre-tensioning step, the tension force value of the first tension force being determined based on a first proportion of the target tension force value; after the single-strand pre-tensioning step, determine the tension force applied to the duct strands as the target tension force value; after the tension force of the duct strands reaches the target tension force value, perform an over-tensioning operation on the duct strands, the over-tensioning operation being used to adjust the tension force applied to the duct strands to a specified multiple of the target tension force value; and after holding the load for a predetermined time based on a specified multiple of the target tension force value, adjust the tension force applied to the duct strands to the target tension force value.
[0018] In one exemplary embodiment of this disclosure, the tensioning operation module further includes a tensioning operation control unit, configured to: based on the tensioning operation applied to the duct strand, use the difference between the actual measured elongation value and the theoretical elongation value of the duct strand as an elongation deviation value; use the difference between the actual prestress value and the theoretical prestress value of the duct strand as a prestress difference value; and stop the tensioning operation in response to the elongation deviation value exceeding an elongation deviation value threshold or the prestress difference value exceeding a prestress difference threshold.
[0019] In one exemplary embodiment of this disclosure, the prestressed tensioning control device further includes a tensioning adjustment module, configured to: acquire a pre-established digital twin model of the tower structure and measured data, wherein the measured data includes one or more of the following: duct strand parameters, friction coefficient, and anchor performance; perform a tensioning simulation operation based on the measured data to obtain a set of tensioning simulation parameters for the tower and stress distribution under various tensioning levels, using multiple different parameter combinations; determine recommended tensioning parameters based on the set of tensioning simulation parameters, wherein the recommended tensioning parameters are used to configure the tension force of the duct strands; acquire actual monitoring data corresponding to the tensioning construction operation of the tower, and transmit the actual monitoring data back to the digital twin model of the tower structure; and determine tensioning adjustment parameters based on the simulation results of the digital twin model of the tower structure using the actual monitoring data, wherein the tensioning adjustment parameters are used to adjust the tension force of the duct strands.
[0020] According to a third aspect of this disclosure, an electronic device is provided, comprising: a processor; and a memory storing computer-readable instructions that, when executed by the processor, implement the prestressed tensioning control method according to any one of the preceding claims.
[0021] According to a fourth aspect of this disclosure, a computer-readable storage medium is provided having a computer program stored thereon, which, when executed by a processor, implements the prestressing tension control method according to any one of the preceding claims.
[0022] According to a fifth aspect of this disclosure, a computer program product is provided, comprising a computer program that, when executed by a processor, implements the prestressing tension control method described in any of the preceding claims.
[0023] The technical solution provided in this disclosure may include the following beneficial effects: The prestressing tensioning control method in the exemplary embodiments of this disclosure, on the one hand, by determining a symmetrical tensioning group and performing tensioning operations based on the symmetrical tensioning group, maximizes the symmetry and uniform stress distribution of the tower structure during the tensioning process, and can effectively control the roundness deformation of the tower; on the other hand, by performing tensioning operations through multiple pre-set different tensioning levels, the accuracy of prestressing application and the structural safety during the tensioning operation process are improved.
[0024] It should be understood that the above general description and the following detailed description are exemplary and explanatory only, and are not intended to limit this disclosure. Attached Figure Description
[0025] The accompanying drawings, which are incorporated in and form part of this specification, illustrate embodiments consistent with this disclosure and, together with the description, serve to explain the principles of this disclosure. It is obvious that the drawings described below are merely some embodiments of this disclosure, and those skilled in the art can obtain other drawings based on these drawings without any inventive effort. In the drawings: Figure 1 A flowchart illustrating a prestressed tension control method according to an exemplary embodiment of the present disclosure is shown schematically. Figure 2 A schematic diagram of a tensioning operation using a 36-channel stranded wire as an example, according to an exemplary embodiment of this disclosure, is shown. Figure 3 A flowchart illustrating a tension control operation based on the deviation between prestress deviation value and elongation value according to an exemplary embodiment of this disclosure is shown. Figure 4 A schematic diagram of an installation tensioning device according to an exemplary embodiment of the present disclosure is shown; Figure 5 A block diagram of a prestressed tensioning control device according to an exemplary embodiment of the present disclosure is shown schematically. Figure 6 The schematic diagram illustrates a computer-readable storage medium according to an exemplary embodiment of the present disclosure; Figure 7A block diagram of an electronic device according to an exemplary embodiment of the present disclosure is shown schematically. Detailed Implementation
[0026] Exemplary embodiments will now be described more fully with reference to the accompanying drawings. However, these exemplary embodiments can be implemented in many forms and should not be construed as limited to the embodiments set forth herein; rather, they are provided so that this disclosure will be thorough and complete, and will fully convey the concept of the exemplary embodiments to those skilled in the art. The same reference numerals in the drawings denote the same or similar parts, and therefore repeated descriptions of them will be omitted.
[0027] Furthermore, the described features, structures, or characteristics can be combined in any suitable manner in one or more embodiments. Numerous specific details are provided in the following description to give a thorough understanding of embodiments of this disclosure. However, those skilled in the art will recognize that the technical solutions of this disclosure can be practiced without one or more of the specific details described, or other methods, components, apparatuses, steps, etc., can be employed. In other instances, well-known structures, methods, apparatuses, implementations, materials, or operations are not shown or described in detail to avoid obscuring various aspects of this disclosure.
[0028] The block diagrams shown in the accompanying drawings are merely functional entities and do not necessarily correspond to physically independent entities. That is, these functional entities can be implemented in software, or in one or more software-hardened modules, or in different network and / or processor devices and / or microcontroller devices.
[0029] According to embodiments of this disclosure, a prestressing tension control method, a prestressing tension control device, a computer-readable storage medium, an electronic device, and a computer program product are proposed.
[0030] The principles and spirit of this disclosure will be explained in detail below with reference to several representative embodiments.
[0031] Hybrid towers are typically annular thin-walled structures that withstand enormous wind loads and bending moments. Prestressing aims to apply uniform circumferential compressive stress to the tower. Improper tensioning sequence can lead to uneven stress distribution within the tower, resulting in localized stress concentrations or even structural deformation. For example, simply tensioning in a clockwise or counterclockwise sequence may cause the tower to deflect or become elliptical during the tensioning process.
[0032] Based on this, in this example embodiment, a prestressing tension control method is first provided. The prestressing tension control method of this disclosure can be implemented by using a prestressing tensioning device in combination with a server, or by using a prestressing tensioning device in combination with a terminal device. The terminal described in this disclosure may include mobile terminals such as mobile phones, tablets, laptops, handheld computers, and personal digital assistants (PDAs), as well as fixed terminals such as desktop computers. Figure 1 A schematic diagram illustrating the flow of a prestressed tension control method according to some embodiments of the present disclosure is shown. Reference Figure 1 The prestressing tension control method may include the following steps: Step S110: Determine multiple internal channels located on the circumference of the tower, and divide the internal channels into multiple symmetrical tensioning groups. Each symmetrical tensioning group contains at least two tensioning channels symmetrically distributed about the central axis of the tower. Step S120: Obtain multiple pre-configured tensioning stages, the tensioning stages are determined based on a specified tensioning value within the tensioning value range corresponding to the tensioning force; Step S130: At each tensioning stage, apply tension force to the strand in the duct of each symmetrical tensioning group to the target tension force value corresponding to each tensioning stage, so as to perform tension control operation for the strand in the duct. Step S140: Based on the tension control operation, the target tension force value at each tension level is applied to the stranded wire in the duct to tension it, so that the tower can establish effective prestress.
[0033] According to the prestressing tensioning control method in this example embodiment, on the one hand, by determining a symmetrical tensioning group and performing tensioning operations based on the symmetrical tensioning group, the symmetry and stress uniformity of the tower structure during the tensioning process are guaranteed to the maximum extent, and the roundness deformation of the tower can be effectively controlled; on the other hand, by performing tensioning operations with multiple different pre-set tensioning levels, the accuracy of prestressing application and the structural safety during the tensioning operation are improved.
[0034] The prestressing tension control method in this example embodiment will be further explained below.
[0035] For step S110, multiple internal channels located on the circumference of the tower are determined, and the internal channels are divided into multiple symmetrical tensioning groups. Each symmetrical tensioning group contains at least two tensioning channels that are symmetrically distributed about the central axis of the tower.
[0036] For the tower, the tower structure is a ring-shaped thin-walled structure. (Reference) Figure 2 , Figure 2A schematic diagram of a tensioning operation using a 36-channel stranded wire as an example, according to an exemplary embodiment of this disclosure, is shown. Figure 2 In the tower section 200, there are multiple internal channels 210 distributed around the circumference. The internal channels refer to the prestressed reserved channels in the tower wall. When the precast concrete tower section is poured, corrugated pipes (such as metal / plastic corrugated pipes) are pre-embedded vertically inside the tower wall. After forming, they form a hollow circular channel that runs vertically and is closed. These reserved pipes are specifically used to run the prestressed strands through the channels.
[0037] After determining the aforementioned internal channels, the multiple internal channels are divided into multiple symmetrical tensioning groups based on the tower's central axis O. A symmetrical tensioning group refers to a tensioning unit consisting of at least two tensioning channels that are centrally symmetrically distributed about the tower's central axis. Its function is to perform symmetrical synchronous tensioning, counteract eccentric forces, and prevent the tower from becoming elliptical. In this embodiment, each symmetrical tensioning group contains at least two tensioning channels symmetrically distributed about the tower's central axis, such as... Figure 2 Tensioning ducts 201 and 202 can form a symmetrical tensioning group. The number of tensioning ducts included in the symmetrical tensioning group can also be 4 or 8, etc., and the number of tensioning ducts included in the symmetrical tensioning group can be set according to specific construction requirements.
[0038] In one exemplary embodiment of this disclosure, the initial tension value and the maximum tension value corresponding to the tension force are obtained, and the tension force value range is determined based on the initial tension value and the maximum tension value; multiple specified tension force values are determined based on the tension force value range, and the tension level corresponding to each specified tension force value is determined; the theoretical elongation value of the stranded wire in the duct is determined for each tension level; and the actual elongation value of the stranded wire in the duct is determined based on the theoretical elongation value.
[0039] Before tensioning, the tensioning design of the duct strands is performed. Tension force can be the external force applied to the duct strands by the jacks at the moment of tensioning; tension force is an external load, measured in kN (kilonewtons). The initial and maximum tension values corresponding to the tension force acting on the duct strands are obtained. The initial tension value is the initial tension force acting on the duct strands, which is usually 0. The maximum tension value is the maximum tension force acting on the duct strands, referring to the tension force corresponding to 100% control stress, and is usually determined by structural design and material limits. Prestress can be the pre-tensioned stress permanently retained inside the duct strands after tensioning and anchoring are completed and the jacks are removed, as well as the pre-compression stress obtained by the tower concrete; it is a permanent internal force within the structure, measured in megapascals (MPa).
[0040] Based on the initial and maximum tension values, the range of tension forces acting on the duct strands can be determined. This range can be defined by using the initial and maximum tension values as the boundary values at both ends. Multiple specified tension values can be determined based on this range; these specified tension values, also known as tension control values, refer to the tension gradually applied to the duct strands during construction. Specified tension values are used to determine multiple different tension levels; for example, they can be 20%, 40%, or 60% of the maximum tension value. The specified tension values can be specifically set according to project requirements.
[0041] After determining several different specified tension values, the theoretical elongation of the corresponding duct strand is calculated based on these specified tension values. This theoretical elongation must be reported to the construction unit before the actual tensioning operation. The duct strand can be made of various materials, such as steel strand, galvanized steel strand, epoxy-coated steel strand, and stainless steel strand. The calculation method for the theoretical elongation of the duct strand at each tension level is shown in Formula 1. (Formula 1) in, It can be the theoretical elongation value of the prestressed duct strand; It can be the tension force of the prestressed strand in the duct at each tensioning level (grade); It can be the length of the prestressed duct strand; It can be the cross-sectional area of the prestressed duct strand; It can be the elastic modulus of prestressed stranded wire.
[0042] After determining the theoretical elongation of the ducted strand, the actual elongation can be further determined based on the theoretical elongation. Before tensioning the ducted strand, ensure that it is threaded through the steering device and placed on the grooved pad. The tension force value of the ducted strand corresponds to the value read from the jack's oil gauge. Based on the tension force values at each tensioning stage, the corresponding theoretical and actual elongation values of the ducted strand can be determined, serving as the operational basis for subsequent tensioning control operations.
[0043] In one exemplary embodiment of this disclosure, determining the actual elongation value of the stranded wire based on the theoretical elongation value includes: determining a first tension range and a second tension range corresponding to the tension force; in response to the tension force being in the first tension range, determining a first actual elongation value component based on the theoretical elongation value; in response to the tension force being in the second tension range, determining a second actual elongation value component based on the measured elongation value; and determining the actual elongation value based on the first actual elongation value component and the second actual elongation value component.
[0044] When determining the actual elongation value of the channel strand based on the theoretical elongation value, it can be done in conjunction with the tension force applied to the channel strand. The tension force range can be different ranges determined based on the specific value of the tension force acting on the channel strand. The first tension force range and the second tension force range can represent the range corresponding to different tension force values; for example, the first tension force range can be the numerical range when the tension force is stretched from 0 to 20% of the maximum tension value; the second tension force range can be the numerical range when the tension force is stretched from 20% to 100% of the maximum tension value. The first tension force range and the second tension force range can also be set according to specific needs, and this disclosure does not impose any special limitations on them.
[0045] After determining the different tension ranges corresponding to the tension force, the actual elongation value of the duct strand can be determined based on the different tension ranges and the actual elongation component of the duct strand. The actual elongation value of the duct strand can be calculated according to the following formula 2: L = 20% theoretical elongation + 20% to 100% actual elongation (Formula 2) Where L can be the actual elongation of the stranded wire in the duct. Formula 2 is a segmented calculation formula. The first part of the formula represents the actual elongation of the stranded wire in the duct when the tension is in the first tension range (0→20%), which is the first actual elongation component. The second part of the formula represents the actual elongation of the stranded wire in the duct when the tension is in the second tension range (20%→100%), which is the second actual elongation component.
[0046] Formula 2 indicates that for the actual elongation of the duct strand, in the 0→20% stage, the theoretical elongation value (i.e., the calculated value) is used. In the initial tensioning stage (usually 0→20%F design), the duct strand is not fully taut and exhibits nonlinear factors such as slack, bending, anchor gaps, and duct friction. At this time, the measured elongation includes a large amount of inelastic deformation and cannot truly reflect the elastic modulus of the duct strand. Therefore, for the elongation in the 0→20% stage, the theoretical formula is used directly for calculation: 20% calculated elongation (i.e., theoretical elongation value) = (0.2F design·Lp) / (Ap·Ep)), to eliminate inelastic interference.
[0047] In the 20%→100% stage, actual measurements are used. Once the tension exceeds 20%, the stranded wire in the duct is in an elastic working state, and the inelastic deformation is basically complete. At this time, the measured elongation (ΔL20%-100% measured) can truly reflect the elastic elongation of the stranded wire. Therefore, the total actual elongation = theoretical calculation value from 0→20% + actual measurement value from 20%→100%. Through the above calculation formula, the actual elongation value of the stranded wire in different tension ranges can be determined. Using the first and second tension ranges to calculate the actual elongation value of the stranded wire is to eliminate the inelastic deformation and system gaps of the stranded wire in the initial tensioning stage, thereby obtaining true and reliable elastic elongation data.
[0048] In one exemplary embodiment of this disclosure, at each tensioning stage, tension force is applied to the strands in the ducts of each symmetrical tensioning group to the target tension force value corresponding to each tensioning stage, in order to perform tensioning control operations for the strands in the ducts, including: determining the current tensioning stage from a plurality of tensioning stages; determining the current symmetrical tensioning group, and applying the current target tension force value corresponding to the current tensioning stage to the strands in the ducts of the current symmetrical tensioning group based on the current tensioning stage; after the tensioning operation of the current symmetrical tensioning group is completed, rotating the prestressed tensioning device by a specified angle along the circumference of the tower to perform tensioning operation on the next symmetrical tensioning group, until the tensioning operation of all symmetrical tensioning groups is completed at each tensioning stage.
[0049] In this embodiment, a graded tensioning method is used to tension the stranded wire in the duct. Before tensioning, the target tension value corresponding to each tensioning stage can be determined. The tensioning stage can be a set of stages matching different numerical ranges of the tension applied to the stranded wire. The target tension value can be the tension applied to the stranded wire at multiple different tensioning stages. For example, in actual tensioning, the tensioning stages can be determined as 0%-20%-60%-105%-100% of the maximum tension value, i.e., 5 different tensioning stages, each corresponding to a different target tension value. For example, the target tension value corresponding to the third tensioning stage is 60% of the maximum tension value.
[0050] Based on the multiple tensioning stages provided above, for each tensioning stage, the following operations are performed sequentially: Under the current tensioning stage, apply tension force to the strands in each symmetrical tensioning group to the target tension force value corresponding to that stage; after completing the tensioning of one symmetrical tensioning group, rotate the prestressing tensioning equipment along the circumference of the tower by a preset specified angle to perform the tensioning operation on the next symmetrical tensioning group; under each tensioning stage, after all symmetrical tensioning groups of the current tensioning stage are tensioned, proceed to the next stage. Repeat the above steps until the tensioning operation of all symmetrical tensioning groups under all tensioning stages is completed.
[0051] The number of tensioning stages and the target tension value corresponding to each tensioning stage can be configured according to specific needs. For example, in actual construction, the stress loading requirements and ease of operation shall prevail. This disclosure does not impose any special restrictions on the number of tensioning stages or the specific value of the target tension value under each tensioning stage.
[0052] Example 1: Taking four symmetrical tensioning groups as an example, each group contains four tensioning holes symmetrically distributed at 90° intervals about the central axis of the tower; the preset angle is 45°, so that the tensioning points of adjacent symmetrical tensioning groups are staggered by 45° on the circumference, forming a star-shaped distribution. For example, four jacks are respectively placed at the four symmetrical tensioning holes of the first group. After completing the tensioning of this group, the four jacks are rotated counterclockwise by 45° and placed at the four symmetrical tensioning holes of the second group, and so on, until the tensioning of all symmetrical groups is completed.
[0053] Example 2: Figure 2 Taking the 36-bundle stranded wire as an example, the 36-bundle stranded wire is usually evenly distributed on the circumference of the tower, that is, the included angle between two adjacent bundles is 10°. At the same level, all the "cross-shaped" four-point groups are tensioned sequentially. After each group is tensioned, the four jacks are rotated as a whole by 10° (one hole interval) to align with the next group of four points, and tensioning continues. This rotation is repeated 9 times (starting from 0° and rotating to 80°), resulting in 9 groups of four points, each group with 4 holes, exactly covering all 36 holes (9×4=36). After completing all 9 groups of tensioning at the current level, the process is repeated at the next level. Specific operating steps (taking the 20% level as an example) include: Step 1: Initial Positioning (Group 1, Four Points). Establish a coordinate system with the tower's central axis O as the origin. Align the four jacks with 0° (hole 1, first quadrant, number ①), 90° (hole 10, second quadrant, number ①), 180° (hole 19, third quadrant, number ①), and 270° (hole 28, fourth quadrant, number ①). Apply tension to the steel strands in these four holes to 20% of the design value (paired or synchronous symmetrical tensioning is acceptable, but the resultant force must pass through the center of the circle). After tensioning, lock this stage (do not anchor, only maintain tension).
[0054] Step 2: Rotate 10° and tension the second set of four points. Rotate the four jacks counterclockwise by 10° as a whole, aligning them with 10° (hole 2, the hole numbered ② in the first quadrant), 100° (hole 11, the hole numbered ② in the second quadrant), 190° (hole 20, the hole numbered ② in the third quadrant), and 280° (hole 29, the hole numbered ② in the fourth quadrant). Apply tension to the steel strands in these four holes to 20% of the design value. After tensioning, hold the tensioned strands in place.
[0055] Step 3: Continue rotating 10° and tension the third set of four points. Rotate to 20° (hole 3, the hole numbered ③ in the first quadrant), 110° (hole 12, the hole numbered ③ in the second quadrant), 200° (hole 21, the hole numbered ③ in the third quadrant), and 290° (hole 30, the hole numbered ③ in the fourth quadrant), and tension to 20%.
[0056] Step 4: Repeat the rotation until the 9th set is completed. At this point, tension has been applied to all 36 holes at the 20% level.
[0057] Step 5: Proceed to the next level. Increase the target tension value to 60%, and repeat steps 1-4 above (starting again from the four points of group 1, rotating and tensioning all 9 groups in sequence). After completion, proceed to level 105%, and repeat the above process (holding the load for 2 minutes).
[0058] Finally, at the 100% level, the above process is repeated, and anchoring and locking are performed after the final tensioning. This disclosure, through graded symmetrical tensioning operations, maximizes the symmetry and stress uniformity of the tower structure during tensioning, effectively controlling the roundness deformation of the tower.
[0059] In one exemplary embodiment of this disclosure, applying a current target tension value corresponding to the current tensioning level to the strands in the current symmetrical tensioning group based on the current tensioning level includes: performing a single-strand pre-tensioning step on the strands before grouping the current symmetrical tensioning group; applying a first tension force to a single strand through the single-strand pre-tensioning step, the tension value of the first tension force being determined based on a first proportion of the target tension value; determining the tension force applied to the strands as the target tension value after the single-strand pre-tensioning step; performing an over-tensioning operation on the strands after the tension force of the strands reaches the target tension value, the over-tensioning operation being used to adjust the tension force applied to the strands to a specified multiple of the target tension value; and adjusting the tension force applied to the strands to the target tension value after holding the load for a predetermined time based on a specified multiple of the target tension value.
[0060] In actual construction, during the threading and installation of the individual strands within the same bundle, inconsistencies in slackness, curvature, and slight differences in the path length through the ducts are inevitable. Furthermore, the exposed lengths of the strands may vary. If the entire bundle is tensioned directly without pre-tensioning, in the initial stage of tensioning, the slacker strands need to be stretched to the same length as the tighter strands before they begin to bear actual stress. This will result in inconsistent starting points for stress on each strand, leading to uneven stress distribution within the bundle after tensioning.
[0061] When performing tensioning operations, the tensioning of prestressed strands in prestressed ducts should adopt the form of "single strand pretensioning, whole bundle tensioning". At the same time, it is recommended that the pretensioning force be 20% of the calculated tension force. Tensioning should be carried out in stages to ensure uniform stress distribution (taking tensioning stages of 0%-20%-60%-105%-100% as an example, all bundles should be tensioned at the current stage before moving to the next stage).
[0062] Single strand pretensioning stage: Before formal bundle tensioning, a small, uniform tension force (e.g., 20% of the maximum tension value) is applied individually to each strand within the bundle to initially taut each strand. Bundle tensioning stage: After single strand pretensioning, the entire bundle of strands is simultaneously tensioned in stages until the final tension required by the design, i.e., the target tension value, is reached. After the tension of the strands in the duct reaches the target tension value, an over-tensioning operation is performed. During the over-tensioning operation, the tension applied to the strands in the duct is adjusted to a specified multiple of the target tension value, such as 105% of the target tension value, and held for a predetermined time, such as 2 minutes.
[0063] When performing over-tensioning, the tension applied to the strand in the duct is adjusted to the target tension value, such as from 105% to 100% of the target tension value. The tensioning sequence can be 0→1.05f. pyk (Hold the load for two minutes) → f pyk ; where f pyk This can be the target tension value. The core of this operation lies in: using individual strand pre-tensioning to eliminate initial differences, creating a uniform stress starting point for subsequent whole-bundle tensioning, thereby ensuring the uniformity of stress on each strand during whole-bundle tensioning. Based on this, the initial relaxation differences among the strands within the bundle can be eliminated, creating a uniform stress starting point for whole-bundle tensioning.
[0064] Conventional overall tensioning methods have an inherent drawback: due to factors such as differences in anchor wedge installation and friction differences between individual strands and the duct wall, the stress on each strand naturally becomes uneven during overall tensioning, and this unevenness becomes more severe with the number of strands in the bundle. Single-strand pretensioning, by applying the same initial tension to each strand individually, forcibly straightens the relaxed state of each strand within the bundle, ensuring that each strand is in a essentially identical initial stress state before entering the overall tensioning stage. This solves the problem of strand straightness and achieves uniform stress distribution across the strands within the bundle. Single-strand pretensioning, combined with overall tensioning, can also reduce prestress loss, improve the effective prestress retention rate, and enhance the effectiveness and accuracy of anchorage quality testing.
[0065] In one exemplary embodiment of this disclosure, based on the tensioning operation applied to the duct strand, the difference between the actual measured elongation value and the theoretical elongation value of the duct strand is taken as the elongation deviation value; the difference between the actual prestress value and the theoretical prestress value of the duct strand is taken as the prestress difference value; and the tensioning operation is stopped in response to the elongation deviation value exceeding the elongation deviation value threshold or the prestress difference value exceeding the prestress difference threshold.
[0066] During the tensioning process, the verification results of the tension elongation value can comprehensively reflect whether the tension force is sufficient, whether the duct friction loss is excessive, and whether there are any abnormalities in the duct strands. Therefore, during the tensioning process, the actual elongation value of the duct strands is measured, and the actual measured elongation value is compared with the calculated theoretical elongation value. The difference between the two is taken as the elongation deviation value. At the same time, the actual prestress value of the duct strands is determined, and the actual prestress value is compared with the theoretical prestress value. The difference between the two is taken as the prestress difference value.
[0067] refer to Figure 3 , Figure 3 A flowchart illustrating a tension control operation based on the deviation between prestress and elongation values according to an exemplary embodiment of this disclosure is shown. In step S301, a tensioning operation is performed. In step S302, the actual prestress value and the theoretical prestress value are obtained. In step S303, it is determined whether the prestress difference is less than or equal to a prestress difference threshold. If yes, in step S304, the determination result is confirmed as a qualified prestress value. If not, in step S305, the tensioning operation is stopped.
[0068] In step S306, the actual measured elongation value and the actual calculated elongation value are obtained. In step S307, it is determined whether the difference in elongation values is less than or equal to the elongation value difference threshold. If not, the tensioning operation is stopped in step S308. If yes, the result of the elongation value being qualified is combined with the result of the qualification judgment in step S309. In step S310, the result of qualified tensioning is obtained. The judgment process of prestress deviation value and elongation value deviation in the above judgment process can be carried out simultaneously, and this disclosure does not make any special limitations on this.
[0069] The calculated elongation deviation and prestress difference values are compared with pre-set thresholds. For example, during tensioning, the deviation between the actual elongation value (i.e., the actual measured elongation value) and the theoretically calculated elongation value should be within the elongation deviation threshold (e.g., ±6%). The relative deviation between the prestress value and the design-specified inspection value should be within the prestress difference threshold (e.g., ±5%). If these values are exceeded, tensioning should be stopped immediately, the cause investigated, and appropriate measures taken before resuming operations.
[0070] Furthermore, after the prestressed strands in the ducts are tensioned, a specified period (e.g., 12 hours) should be observed for any slippage. Excess exposed length should then be trimmed, and a protective cover should be installed on the outside of the anchorage. Slippage refers to the unexpected axial sliding of the steel strand within the anchorage wedges after tensioning and jack unloading, resulting in prestress loss. Slippage can be caused by insufficient wedge hardness, oil or rust on the steel strand surface, incomplete wedge tightening, or uneven relaxation of the prestressing tendons. Observing for the specified time after tensioning allows the anchorage system to undergo initial stress adjustment and potential creep under load. Hidden wedge clamping insufficiency usually manifests within hours after unloading (slow or sudden slippage of the steel strand). Timely detection of slippage allows for measures such as additional tensioning, wedge replacement, or complete strand replacement to prevent prestress failure after the structure has entered service.
[0071] Cutting off excess exposed length is to avoid interference with the subsequent installation of the protective cover. After tensioning, the steel strands will extend a certain length from the outside of the anchorage. Excessive exposed length will hinder the fit and sealing of the protective cover, so it must be cut to a suitable length first; this also eliminates the risk of additional bending moment and fatigue. Installing a protective cover outside the anchorage provides long-term corrosion protection, ensures the durability of prestressed steel, prevents stress corrosion cracking caused by rust at the ends of the steel strands, and enables traceable structural inspection. After the prestressed steel strands are tensioned, a 12-hour pause is taken to observe for slippage, excess length is cut off, and the protective cover is installed. The core objectives can be summarized as: confirming the stability of the prestressed locking state, eliminating potential safety hazards later, and achieving long-term durability of the anchoring system.
[0072] In one exemplary embodiment of this disclosure, a pre-established digital twin model of the tower structure and measured data are acquired. The measured data includes one or more of the following: duct strand parameters, friction coefficient, and anchor performance. Based on the measured data, a tensioning simulation operation is performed to obtain a set of tensioning simulation parameters for the tower and stress distribution under various tensioning levels, using multiple different parameter combinations. Recommended tensioning parameters are determined based on the set of tensioning simulation parameters and are used to configure the tension force of the duct strands. Actual monitoring data corresponding to the tower's tensioning construction operation is acquired and transmitted back to the tower structure digital twin model. Based on the simulation results of the actual monitoring data, the tower structure digital twin model determines tension adjustment parameters, which are used to adjust the tension force of the duct strands.
[0073] Based on a pre-established digital twin model of the tower structure, the operation of adaptively adjusting the tensioning parameters during actual construction can be carried out through the following steps: Step 1: Preliminary Data Acquisition and Digital Twin Modeling. This step may include acquiring the geometric and material parameters of the tower structure. Using 3D laser scanning or Building Information Modeling (BIM) models, the actual geometric dimensions of the concrete tower to be constructed are obtained, including but not limited to tower height, radii of various sections, wall thickness, location of doorways / openings, and coordinates of the centerline of pre-embedded ducts. Material parameters may include, but are not limited to, measured cubic compressive strength, elastic modulus, Poisson's ratio, density, shrinkage and creep curves of concrete; measured diameter, nominal cross-sectional area, elastic modulus, ultimate tensile strength, relaxation rate, and other parameters of the duct strands; and the duct friction coefficient. Performance parameters of anchorages and jacks can also be acquired. For example, the anchorage efficiency coefficient and anchorage retraction of anchorage clips; and the hydraulic pressure gauge and tension calibration curves, piston friction loss coefficient, etc., of jacks. The data obtained through data acquisition is used as the measured data.
[0074] After data acquisition, a finite element digital twin model is established. The prestressed duct strands are simulated using embedded elements or the cooling / initial strain method, and contact friction is defined to simulate duct friction. The tensioning process is simulated using multiple load steps, with each load step corresponding to a single tension force and a set of symmetrical points. Boundary conditions can be consolidation at the bottom of the tower and freedom at the top (or according to actual constraints). Model verification can be performed using known scaled-down tests or past engineering data to benchmark the model and ensure that the error is within acceptable limits.
[0075] Before formal tensioning, a finite element digital twin model of the tower structure is established, and measured data such as duct strand parameters, friction coefficient, and anchor performance are input. Tensioning simulation is then performed based on the boundary conditions and measured data. By simulating the effects of different grading schemes, rotation angle sequences, and over-tension values on tower deformation and stress distribution, a set of tensioning simulation parameters is determined. Then, based on this set, the optimal recommended tensioning parameters are automatically determined, so that the tension force acting on the duct strands can be determined subsequently.
[0076] During formal construction, actual monitoring data corresponding to the tensioning operations of the tower is acquired and transmitted back to the digital twin model in real time. The digital twin model of the tower structure then performs continuous corrections based on the simulation results of the actual monitoring data, providing real-time adjustment suggestions and outputting tensioning adjustment parameters. These parameters are then used to adjust the tension of the strands in the ducts. These operational steps upgrade the tensioning process from experience-driven to simulation-prediction-driven, significantly reducing trial-and-error costs, and are particularly suitable for the initial construction of new models or ultra-large mixed-type towers.
[0077] refer to Figure 4 , Figure 4A schematic diagram of an installation tensioning device according to an exemplary embodiment of this disclosure is shown. (Reference) Figure 4 During construction, the limiting plate is inserted through the lower part of the steel strand and tightly fitted with the flat anchor. Four jack sleeves are inserted sequentially through the ends of the steel strands, raising the tops of the jacks to the limiting plate and ensuring tight fit. Tensioning is performed symmetrically at four points. The steel strands in the four holes are tensioned symmetrically in sequence. After tensioning the steel strands in each hole is completed, the four tensioning points are rotated 45 degrees counterclockwise to begin tensioning the steel strands in that hole. This completes the star-shaped tensioning. Similarly, the remaining steel strands in the holes are tensioned in the same sequence.
[0078] In summary, the prestressed tensioning control method disclosed herein identifies multiple internal ducts located on the circumference of the tower, divides these ducts into multiple symmetrical tensioning groups, each containing at least two tensioning ducts symmetrically distributed about the central axis of the tower; obtains multiple pre-configured tensioning stages, determined based on specified tension force values within a specified tension force range corresponding to the tension force; at each tensioning stage, applies tension force to the strands in the ducts of each symmetrical tensioning group to the target tension force value corresponding to each tensioning stage, thereby performing tensioning control operations for the strands; based on the tensioning control operations, applies the target tension force values for each tensioning stage to the strands in the ducts to tension them, thereby establishing effective prestress in the tower. On the one hand, by determining a symmetrical tensioning group and performing tensioning operations based on this group, the symmetry and stress uniformity of the tower structure during tensioning are maximized, effectively controlling the roundness deformation of the tower. On the other hand, by performing tensioning operations with multiple pre-set different tensioning stages, the accuracy of prestress application and the structural safety during tensioning operations are improved. Furthermore, through a dual verification logic of elongation deviation and prestress difference, it can be ensured that the designed tension force has been accurately and uniformly applied to the strands in the ducts, and that the stress state of the strands is normal. Finally, by establishing a digital twin model, the tensioning process can be upgraded from experience-driven to simulation-prediction-driven, significantly reducing trial-and-error costs.
[0079] It should be noted that although the steps of the method in this invention are described in a specific order in the accompanying drawings, this does not require or imply that the steps must be performed in that specific order, or that all the steps shown must be performed to achieve the desired result. Additional or alternative steps may be omitted, multiple steps may be combined into one step, and / or one step may be broken down into multiple steps.
[0080] Furthermore, in this example embodiment, a prestressing tension control device is also provided. (Reference) Figure 5The prestressing tension control device 500 may include: a symmetry group determination module 510, a tensioning stage determination module 520, a tensioning operation module 530, and a prestress establishment module 540.
[0081] Specifically, the symmetry group determination module 510 is used to determine multiple internal channels located on the circumference of the tower, dividing the internal channels into multiple symmetrical tensioning groups, each symmetrical tensioning group containing at least two tensioning channels symmetrically distributed about the central axis of the tower; the tensioning stage determination module 520 is used to obtain multiple pre-configured tensioning stages, the tensioning stages being determined based on a specified tensioning force value within a specified tensioning force value range corresponding to the tensioning force; the tensioning operation module 530 is used to apply tensioning force to the strands in the channels of each symmetrical tensioning group to the target tensioning force value corresponding to each tensioning stage under each tensioning stage, in order to perform tensioning control operations for the strands in the channels; the prestress establishment module 540 is used to apply the target tensioning force value under each tensioning stage to the strands in the channels based on the tensioning control operations, so that the tower establishes effective prestress.
[0082] In one exemplary embodiment of this disclosure, the prestressed tensioning control device 500 further includes a strand elongation value determination module, used for: acquiring the initial tension value and the maximum tension value corresponding to the tension force; determining the tension force value range based on the initial tension value and the maximum tension value; determining multiple specified tension force values based on the tension force value range; determining the tensioning level corresponding to each specified tension force value; determining the theoretical elongation value of the strand in the duct at each tensioning level; and determining the actual elongation value of the strand in the duct based on the theoretical elongation value.
[0083] In one exemplary embodiment of this disclosure, the strand elongation value determination module includes an actual elongation value determination unit, configured to: determine a first tension range and a second tension range corresponding to the tension force; in response to the tension force being in the first tension range, determine a first actual elongation value component based on the theoretical elongation value; in response to the tension force being in the second tension range, determine a second actual elongation value component based on the measured elongation value; and determine the actual elongation value based on the first actual elongation value component and the second actual elongation value component.
[0084] In one exemplary embodiment of this disclosure, the tensioning operation module includes a tensioning operation unit, configured to: determine the current tensioning level from a plurality of tensioning levels; determine the current symmetrical tensioning group; apply the current target tensioning force value corresponding to the current tensioning level to the strands in the current symmetrical tensioning group based on the current tensioning level; after the tensioning operation of the current symmetrical tensioning group is completed, rotate the prestressed tensioning device along the circumference of the tower by a specified angle to perform tensioning operation on the next symmetrical tensioning group, until the tensioning operation of all symmetrical tensioning groups is completed under each tensioning level.
[0085] In one exemplary embodiment of this disclosure, the tensioning operation unit includes a tensioning operation subunit, configured to: perform a single-strand pre-tensioning step on the duct strands before grouping tensioning of the current symmetrical tensioning group; apply a first tension force to a single duct strand through the single-strand pre-tensioning step, the tension force value of the first tension force being determined based on a first proportion of a target tension force value; after the single-strand pre-tensioning step, determine the tension force applied to the duct strands as a target tension force value; after the tension force of the duct strands reaches the target tension force value, perform an over-tensioning operation on the duct strands, the over-tensioning operation being used to adjust the tension force applied to the duct strands to a specified multiple of the target tension force value; and after holding the load for a predetermined time based on a specified multiple of the target tension force value, adjust the tension force applied to the duct strands to the target tension force value.
[0086] In one exemplary embodiment of this disclosure, the tensioning operation module further includes a tensioning operation control unit, configured to: based on the tensioning operation acting on the duct strand, use the difference between the actual elongation value and the theoretical elongation value of the duct strand as an elongation deviation value; use the difference between the actual prestress value and the theoretical prestress value of the duct strand as a prestress difference value; and stop the tensioning operation in response to the elongation deviation value exceeding the elongation deviation value threshold or the prestress difference value exceeding the prestress difference threshold.
[0087] In one exemplary embodiment of this disclosure, the prestressed tensioning control device further includes a tensioning adjustment module, configured to: acquire a pre-established digital twin model of the tower structure and measured data, the measured data including one or more of the following: duct strand parameters, friction coefficient, and anchor performance; perform tensioning simulation based on the measured data to obtain a set of tensioning simulation parameters for the tower and stress distribution under various tensioning levels, using multiple different parameter combinations; determine recommended tensioning parameters based on the set of tensioning simulation parameters, the recommended tensioning parameters being used to configure the tensioning force of the duct strands; acquire actual monitoring data corresponding to the tensioning construction operation of the tower, and transmit the actual monitoring data back to the digital twin model of the tower structure; and determine tensioning adjustment parameters based on the simulation results of the digital twin model of the tower structure using the actual monitoring data, the tensioning adjustment parameters being used to adjust the tensioning force of the duct strands.
[0088] The specific details of the virtual modules of each prestressed tensioning control device mentioned above have been described in detail in the corresponding prestressed tensioning control methods. For any undisclosed details, please refer to the implementation methods in the method section, and therefore will not be repeated here.
[0089] It should be noted that although several modules or units of the prestressed tensioning control device have been mentioned in the detailed description above, this division is not mandatory. In fact, according to embodiments of this disclosure, the features and functions of two or more modules or units described above can be embodied in one module or unit. Conversely, the features and functions of one module or unit described above can be further divided and embodied by multiple modules or units.
[0090] An exemplary embodiment of this disclosure also provides a computer program product. The computer program product includes a computer program that, when executed by a processor, implements the prestressing tension control method described above.
[0091] In one implementation, the computer program product may be a tangible product containing a computer program, such as a computer-readable storage medium storing the computer program. (See reference...) Figure 6 , Figure 6 The schematic diagram illustrates a computer-readable storage medium 600 according to an exemplary embodiment of the present disclosure. The computer-readable storage medium 600 can be a storage medium based on electrical, magnetic, optical, electromagnetic, infrared, or other signals, including but not limited to: random access memory (RAM), read-only memory (ROM), magnetic tape, floppy disk, flash memory, hard disk drive (HDD), solid-state drive (SSD), etc. Exemplarily, a computer program product can be implemented as a non-volatile storage medium storing a computer program, such as read-only memory, NAND flash memory, etc.
[0092] In one implementation, the computer program product can be an intangible product containing a computer program. For example, the computer program product can be implemented as a virtual digital product, such as an executable file, installation package, or other digital file storing the computer program.
[0093] Computer program code can be written in one or more programming languages. Examples of programming languages include C, Java, and C++. Program code can execute entirely on the user's computing device, partially on the user's computing device, or as a standalone software package. It can also execute partially on the user's computing device and partially on a remote computing device, or entirely on a remote computing device or server. In cases involving remote computing devices, the remote computing device can be connected to the user's computing device via any type of network, such as a local area network (LAN) or a wide area network (WAN), or it can be connected to an external computing device (e.g., via an internet connection provided by a mobile network operator).
[0094] Computer programs can be carried or transmitted via signals such as electricity, magnetism, light, electromagnetic fields, and infrared radiation. Electronic devices can convert the signals carrying computer programs into digital signals, thereby running the computer programs. When a computer program runs on an electronic device, its code is used to cause the electronic device to execute (more specifically, to execute by the processor of the electronic device) the method steps of various exemplary embodiments of this disclosure, such as the prestressed tension control method described above.
[0095] Exemplary embodiments of this disclosure also provide an electronic device, which may include a processor and a memory. The memory stores executable instructions of the processor, such as a computer program. The processor executes the executable instructions to perform the method steps of various exemplary embodiments of this disclosure. Furthermore, the electronic device may also include a display for displaying a graphical user interface.
[0096] The following is for reference. Figure 7 The electronic device is illustrated by way of a general-purpose computing device. It should be understood that... Figure 7 The electronic device 700 shown is merely an example and should not be construed as limiting the functionality and scope of use of the embodiments disclosed herein.
[0097] like Figure 7 As shown, the electronic device 700 may include: a processor 710, a memory 720, a bus 730, an I / O (input / output) interface 740, a network adapter 750, and a display 760.
[0098] The memory 720 may include volatile memory, such as RAM 721 and cache unit 722, and may also include non-volatile memory, such as ROM 723. The memory 720 may also include one or more program modules 724, including but not limited to: an operating system, one or more application programs, other program modules, and program data. Each or some combination of these examples may include an implementation of a network environment. For example, program module 724 may include the modules described above.
[0099] The processor 710 may include one or more processing units, such as an AP (Application Processor), a modem processor, a GPU (Graphics Processing Unit), an ISP (Image Signal Processor), a controller, an encoder, a decoder, a DSP (Digital Signal Processor), a baseband processor, and / or an NPU (Neural-Network Processing Unit).
[0100] The processor 710 can be used to execute executable instructions stored in the memory 720, such as the prestressing tension control method described above.
[0101] Bus 730 is used to connect different components of electronic device 700 and may include a data bus, an address bus and a control bus.
[0102] Electronic device 700 can communicate with one or more external devices 800 (such as keyboard, mouse, external controller, etc.) through I / O interface 740.
[0103] Electronic device 700 can communicate with one or more networks via network adapter 750. For example, network adapter 750 can provide mobile communication solutions such as 3G / 4G / 5G, or wireless communication solutions such as wireless LAN, Bluetooth, and near-field communication. Network adapter 750 can communicate with other modules of electronic device 700 via bus 730.
[0104] The electronic device 700 can display a graphical user interface via a display 760, such as a simulation modeling interface for controlling the prestressing tension of the tower.
[0105] although Figure 7 As not shown in the diagram, other hardware and / or software modules may also be configured in the electronic device 700, including but not limited to: microcode, device drivers, redundant processors, external disk drive arrays, RAID systems, tape drives, and data backup storage systems.
[0106] As can be seen from the above, the technical solutions disclosed herein can be implemented as methods, apparatus, systems, computer program products, storage media, electronic devices, etc. Those skilled in the art will understand that various aspects of this disclosure can be specifically implemented in the following forms: a completely hardware implementation, a completely software implementation (including firmware, microcode, etc.), or an implementation combining hardware and software aspects, which may be referred to as "circuit," "module," or "system," respectively.
[0107] It should be understood that this disclosure is not limited to the specific methods, steps, or structures described above and shown in the accompanying drawings, and various modifications and changes can be made without departing from its scope. Those skilled in the art will readily conceive of other embodiments based on the specific implementations provided in this disclosure. Therefore, the specific implementations provided in this disclosure are merely exemplary, and the scope and spirit of this disclosure are indicated by the claims, and should cover any variations, uses, or adaptations of this disclosure that follow the general principles of this disclosure and include common knowledge or customary technical means in the art not disclosed in this disclosure.
Claims
1. A method for controlling prestressed tension, characterized in that, include: Multiple internal channels located on the circumference of the tower are identified, and the internal channels are divided into multiple symmetrical tensioning groups. Each symmetrical tensioning group contains at least two tensioning channels that are symmetrically distributed about the central axis of the tower. Obtain multiple pre-configured tensioning stages, wherein the tensioning stages are determined based on a specified tension value within a tension value range corresponding to the tension force; At each of the tensioning stages, the tension force is applied to the strand in the duct of each of the symmetrical tensioning groups to the target tension force value corresponding to each of the tensioning stages, so as to perform tension control operation for the strand in the duct. Based on the tension control operation, the target tension force value at each of the tension levels is applied to the stranded wire in the duct to tension it, so that the tower can establish effective prestress.
2. The method according to claim 1, characterized in that, The method further includes: Obtain the initial tension value and the maximum tension value corresponding to the tension force, and determine the tension force value range based on the initial tension value and the maximum tension value; Based on the specified tension force range, multiple specified tension force values are determined, and the tension level corresponding to each specified tension force value is determined. Determine the theoretical elongation value of the stranded wire in the duct for each of the aforementioned tensioning levels; The actual elongation of the stranded wire in the channel is determined based on the theoretical elongation value.
3. The method according to claim 2, characterized in that, Determining the actual elongation value of the stranded wire based on the theoretical elongation value includes: Determine the first tension range and the second tension range corresponding to the tension force; In response to the tension being within the first tension range, a first actual elongation component is determined based on the theoretical elongation value; In response to the tension force being within the second tension force range, a second actual elongation value component is determined based on the measured elongation value; The actual elongation value is determined based on the first actual elongation value component and the second actual elongation value component.
4. The method according to claim 1, characterized in that, The step of applying the tension force to the strand in the duct of each of the aforementioned tensioning stages to the target tension force value corresponding to each of the aforementioned tensioning stages includes: Determine the current tensioning stage from among the multiple tensioning stages; Determine the current symmetrical tensioning group, and apply the current target tension force value corresponding to the current tensioning stage to the strands in the current symmetrical tensioning group based on the current tensioning stage; After the tensioning operation of the current symmetrical tensioning group is completed, the prestressing tensioning equipment is rotated by a specified angle along the circumference of the tower to perform the tensioning operation on the next symmetrical tensioning group, until the tensioning operation of all the symmetrical tensioning groups is completed at each of the tensioning levels.
5. The method according to claim 4, characterized in that, Applying the current target tension force value corresponding to the current tensioning stage to the strands in the current symmetrical tensioning group based on the current tensioning stage includes: Before performing group tensioning on the current symmetrical tensioning group, a single strand pre-tightening step is performed on the stranded wire in the duct; Through the single-strand pre-tightening step, a first tension force is applied to the single-channel strand, and the tension value of the first tension force is determined based on a first proportion of the target tension value. After the single-strand pre-tightening step, the tension applied to the strand in the channel is determined as the target tension value; After the tension of the duct strand reaches the target tension value, an over-tensioning operation is performed on the duct strand. The over-tensioning operation is used to adjust the tension applied to the duct strand to a specified multiple of the target tension value. After holding the load for a predetermined time at a specified multiple of the target tension value, the tension applied to the stranded wire is adjusted to the target tension value.
6. The method according to claim 5, characterized in that, The method further includes: Based on the tensioning operation applied to the stranded wire, the difference between the actual measured elongation value and the theoretical elongation value of the stranded wire is taken as the elongation deviation value. The difference between the actual prestress value and the theoretical prestress value of the stranded wire in the duct is taken as the prestress difference value; The tensioning operation is stopped in response to the elongation deviation value exceeding the elongation deviation value threshold or the prestress difference value exceeding the prestress difference value threshold.
7. The method according to any one of claims 1-6, characterized in that, The method further includes: Obtain a pre-established digital twin model of the tower structure and measured data, wherein the measured data includes one or more of the following: duct strand parameters, friction coefficient, and anchor performance; Based on the measured data, a tension simulation operation is performed to obtain a set of tension simulation parameters for the tower and stress distribution under each tension level, using multiple different parameter combinations. Recommended tensioning parameters are determined based on the set of tensioning simulation parameters, and the recommended tensioning parameters are used to configure the tension force of the stranded wire in the duct. Obtain the actual monitoring data corresponding to the tensioning construction operation of the tower, and transmit the actual monitoring data back to the digital twin model of the tower structure; Based on the simulation results of the actual monitoring data from the digital twin model of the tower structure, the tension adjustment parameters are determined, and these parameters are used to adjust the tension of the stranded wire in the duct.
8. A prestressed tensioning control device, characterized in that, include: The symmetry group determination module is used to determine multiple internal channels located on the circumference of the tower, and divide the internal channels into multiple symmetrical tensioning groups, each of the symmetrical tensioning groups containing at least two tensioning channels symmetrically distributed about the central axis of the tower. The tensioning stage determination module is used to obtain multiple pre-configured tensioning stages, wherein the tensioning stages are determined based on a specified tension value within the tension value range corresponding to the tension force. The tensioning operation module is used to apply the tensioning force to the target tensioning force value corresponding to each tensioning level to the strand in the duct of each symmetrical tensioning group at each tensioning level, so as to perform tensioning control operation for the strand. The prestressing module is used to apply target tension force values at each of the tensioning levels to the stranded wire in the duct based on the tensioning control operation, so that the tower can establish effective prestress.
9. An electronic device, characterized in that, include: processor; Memory used to store the processor's executable instructions; The processor is configured to execute the instructions to implement the prestressed tension control method as described in any one of claims 1 to 7.
10. A computer program product, comprising a computer program, characterized in that, When the computer program is executed by the processor, it implements the prestressing tension control method according to any one of claims 1 to 7.