A bypass cable laying system for complex terrain
By using a bypass cable laying system in complex terrain, an executable work list is generated, and the supply of reels, segmented laying, and reel replacement are uniformly constrained. This solves the problem of lack of cable length and location references in complex terrain and improves the safety margin and efficiency of live-line work.
Patent Information
- Application Number
- CN202611480723.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-22
- Publication Date
- 2026-11-10
AI Technical Summary
In complex terrain, the lack of unified length and position benchmarks in existing technologies leads to a lack of constraints in each stage of bypass cable laying operations. The cable length cannot be accurately calculated before entering the site, resulting in insufficient number of reels or excessive excess cable. The reel replacement position and number of round trips cannot be arranged in advance, the closing of the switch lacks constraints, the information of each stage is disconnected, it is difficult to build a temporary power supply circuit according to the predetermined rhythm, and the safety margin of energization is insufficient.
A bypass cable laying operation system for complex terrain is adopted, including a ranging and planning subunit, a cable supply subunit, a cable laying subunit, and a splicing and access subunit. These are connected through a communication link to generate an executable work list, uniformly constraining reel supply, segmented laying, reel replacement and return, and power-on permission. The spatial acquisition module obtains corridor information, the path planning module generates a passable path, calculates the equivalent cable length, and generates a work list. The cable supply subunit supplies reels according to the list, the cable laying subunit lays cables along the path, the splicing and access subunit completes phase verification, and the centralized control module coordinates and controls the movement and reel replacement. Power is only applied when conditions are met.
This system ensures that all components have a unified length and position benchmark, avoiding insufficient number of reels or excessive excess cable. The reel replacement location and number of round trips can be arranged in advance, and the closing permission conditions are clearly defined, which improves the safety margin and work efficiency of live-line work and ensures that temporary power supply circuits are built and decommissioned according to the predetermined schedule.
Smart Images

Figure CN123073590A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of power distribution network bypass operation technology, and more specifically to a bypass cable laying operation system for complex terrain. Background Technology
[0002] During power distribution network maintenance or fault handling, bypass operations are commonly used to avoid prolonged power outages for users. This involves temporarily establishing a bypass power supply circuit between the two lead-out points on both sides of the section to be maintained, transferring the load before proceeding with the original line or equipment work. Once completed, the bypass is removed. A bypass circuit typically consists of a main cable, down-lead cables at both ends, and a bypass load switch. Sites are often located in mountainous areas, fields, and near transformer substations. Lead-out points are scattered, corridors are narrow, and the route includes field ridges, ditches, slopes, and muddy terrain. The passable length and terrain undulations are often difficult to accurately determine before commencing work.
[0003] Current practices typically break down planning, cable preparation, laying, splicing, and switching on into independent processes. The planning side often provides inspection instructions or horizontal distances, which cannot be directly translated into actionable quantities of reels, reel change points, and round trips. The supply side prepares reels based on experience, the laying side lays cables based on on-site intuition, the splicing side operates according to the team's rhythm, and switching on is often treated as an isolated operation. There is a lack of unified length, position, and status benchmarks between these processes; each process is unaware of the progress of the next, and the next cannot constrain the output of the previous process.
[0004] This leads to four types of systemic problems in complex terrain. First, before entering the site, the geometric length of the corridor and the terrain undulations cannot be converted into equivalent cable lengths. The path, number of reels, reel-changing points, and splicing positions cannot be constrained by the same data object, often resulting in insufficient reels for secondary relocation or excessive surplus cable being returned to the reels. Second, supply, laying, and splicing are disconnected in terms of information, with mismatches between the number of prepared reels, the length of laid cables, and the number of cables to be spliced. Third, even if reels can be changed at both ends, the system layer still lacks a unified interface agreement and reel-changing release sequence. The reel-changing position and the number of round trips cannot be pre-arranged, and the risk of movement without locking cannot be eliminated in control. Fourth, the results of splicing and phase verification cannot be used as necessary conditions for closing permission and returned to the control core. This may result in closing before splicing, closing with different phase sequences, or allowing movement and unloading after closing, thus disconnecting the connection.
[0005] Existing technologies possess capabilities for corridor surveying, cable storage and transportation, end-point laying, and live-line splicing. However, these capabilities remain confined to their respective operational interfaces: surveying results stop at the report stage, storage and transportation results stop at delivery, laying results stop at cable landing, and splicing results stop at team confirmation. The problem is not whether equipment is available at any particular stage, but rather that the system lacks a comprehensive operational checklist that integrates surveying, calculation, supply, laying, replacement, splicing, connection, and decommissioning, along with corresponding interface agreements, tension coordination, and closing interlocks. Temporary power supply circuits are difficult to construct and decommission according to a predetermined schedule, resulting in frequent back-and-forth transportation and insufficient live-line safety margins.
[0006] In existing technologies, all-terrain bypass cable automatic laying vehicles already possess multi-reel unwinding, reel replacement, moisture-proof support, and cable laying speed adjustment capabilities; the technical guidelines for bypass operations in power distribution networks and the bypass operation equipment for live-line work stipulate operating according to the work instructions, phase verification before connecting switches, and a permit command system; the power engineering cable design standards provide a calculation method for cable length by multiplying the path length by the terrain correction factor and taking into account the allowance; in the field of cable transmission and traction, there are also speed synchronization and tension limiting methods, and electrical interlocking conventions require that the switch be closed only after the circuit breaker is in place, the status quantity is verified, and the position is locked. The above solutions address some local problems in laying equipment, work procedures, and length estimation, but they still do not converge the equivalent length obtained from corridor surveying, pre-calibrated reel replacement points, overall reel interchange, tension closed loop, and local closing permission into a single rewritable work list. The planning results cannot directly constrain reel backup, reel replacement, and closing, and each link in complex terrain still relies on on-site experience for coordination. Summary of the Invention
[0007] To address the shortcomings of existing technologies, the purpose of this invention is to provide a bypass cable laying operation system for complex terrain. This system converts corridor space information into equivalent cable lengths and generates an executable work list to uniformly constrain reel supply, segmented laying, reel replacement and return, and closing permission. This solves the problems of lack of unified length and position benchmarks, inability to pre-arrange the number of reels and round trips, and lack of constraints on reel replacement and closing in bypass operations in complex terrain.
[0008] To achieve the above objectives, the present invention is implemented through the following technical solution: A bypass cable laying operation system for complex terrain includes a ranging and planning subunit, a cable supply subunit, a cable laying subunit, and a splicing and access subunit interconnected by a communication link, and the same work list connects the path planning, reel supply, segmented laying, reel replacement and return, and end splicing. The ranging and planning subunit includes a spatial acquisition module, a path planning module, an equivalent length calculation module, and a work list generation module. The spatial acquisition module acquires images or point clouds of the first and second lead-out points on both sides of the line to be inspected, as well as the passable corridor between them, and their synchronized three-dimensional coordinates to form spatial information. The path planning module generates a laying path within the passable corridor that avoids impassable sections based on the spatial information. The equivalent length calculation module calculates the equivalent cable length based on the laying path. The work list generation module determines the number of main cable reels, reel replacement point locations, and round trips based on the equivalent cable length and the nominal length of a single main cable reel, generates the work list, and distributes it to the cable supply subunit and the cable laying subunit. The cable supply subunit is used to store and supply reels carrying the main cable according to the work list, and to adjust the cable release resistance according to the tension command. The cable laying subunit is used to move along the laying path and release the main cable according to the work list; after reaching the reel replacement point or the current reel is empty, it returns to the cable supply subunit and replaces the reel carrying the main cable. Adjacent reels of main cable are connected by an intermediate joint until the main cable path between the first lead-out point and the second lead-out point is completed; after the main cable path is completed, the bypass load switch and the down-lead cable are transported to the first lead-out point and the second lead-out point respectively and the down-lead cable is released. The cable supply subunit and the cable laying subunit use a unified reel interface, allowing the reels carrying the main cable to be interchanged as a whole between the two without having to re-reload the cable on site. The connection subunit is used to connect the down cable to the line to be repaired and complete the phase verification, and send the connection signal and phase verification result to the centralized control module in the cable laying subunit. The centralized control module is configured to: coordinately control movement, cable laying, and reel changing according to the work list; form a tension closed loop with the cable supply subunit, and simultaneously stop movement and cable laying when the tension exceeds the allowable range; issue a closing command only when the bypass load switches located at the first and second lead-out points are both open, connected, have consistent phase sequence, pass phase verification, and the switch status is within the allowable range and the switch is locked in position; after closing, movement, changing the switch position status, and reel winding are prohibited.
[0009] As a further improvement, the spatial acquisition module is acquired by an aerial photogrammetry terminal or a ground mapping terminal, and covers the strip between the first lead-out point and the second lead-out point that may be used as a laying channel; the laying path generated by the path planning module satisfies the following requirements: the channel width has a safety margin for the cable laying sub-unit to pass through, the slope does not exceed its allowable movement capacity, and ditches, water accumulation and sections with insufficient bearing capacity are avoided, and an ordered sequence of track points with plane coordinates, elevation and terrain type labels is output.
[0010] As a further improvement, the equivalent length calculation module divides the laying path into several segments, according to the formula L = Σ(L i ×k i )+L j +L s +L p Calculate the equivalent cable length, where L i Let k be the geometric length of the i-th segment. i L is the terrain correction factor corresponding to the terrain type of this segment. j L is the allowance for the joint. s L is the sag allowance. p For process margin; the terrain types include at least flat land, slopes, field ridges, and muddy land, corresponding to k i The value range is: flat land k i =1.00~1.03, sloping land is classified according to slope and k i =1.05~1.20, k of the field ridge i =1.10~1.18, muddy ground k i =1.12~1.22; The work list generation module will use L and the nominal length L of the single main cable reel. n Comparing the two numbers, rounding up, we get the number of main cable reels N = L / L n The replacement points are marked sequentially along the laying path according to the cumulative equivalent length; the number of round trips is R = N - 1.
[0011] As a further improvement, the work list includes at least the work number, coordinates of the first and second lead-out points, the sequence of track points along the laying path, terrain type and correction coefficient for each segment, equivalent cable length, number of main cable reels, coordinates of the reel replacement point corresponding to each reel, number of round trips, current reel number, allowable tension range, and closing permission conditions. The centralized control module generates movement instructions according to the track point sequence and enters the reel replacement return process when the distance between the current position and the next reel replacement point is less than a set threshold. When the path is changed on site, the distance planning subunit must be written back to recalculate the equivalent cable length and number of reels before generating a new work list.
[0012] As a further improvement, the cable supply subunit includes a reel storage and transportation module and a tension adjustment module; the reel storage and transportation module stores reels carrying the main cable according to the number of main cable reels in the work list, and delivers or retrieves the reels to the cable laying subunit at the reel exchange window; the tension adjustment module receives tension commands issued by the centralized control module, adjusts the cable laying resistance, and keeps the bypass cable tension within the allowable range given in the work list.
[0013] As a further improvement, the cable laying subunit includes a walking control module, a reel winding and unwinding module, a moisture-proof support module, a switch positioning module, and the centralized control module; the walking control module controls movement according to the track point; the reel winding and unwinding module unwinds the main cable or downlead cable at a speed matching the moving speed; the moisture-proof support module unwinds the support medium at a speed matching the cable unwinding speed, so that the support medium is located below the cable; the switch positioning module is used to transport the bypass load switch to the lead-out point and keep it in a locked position.
[0014] As a further improvement, the unified reel interface includes consistent connection specifications and detectable locking status. The locking status is indicated by a microswitch or proximity switch on the alignment structure providing a locking signal. The centralized control module is configured to allow the cable laying subunit to move or start reel winding / unwinding only when the locking signal is valid. Reel changing is permitted in the following order: reaching the reel changing point or emptying the reel, stopping movement and winding / unwinding, returning to the supply side, transferring the entire reel, aligning and locking and confirming the interface, updating the current reel number, and continuing laying. If any step fails, the movement permission remains prohibited.
[0015] As a further improvement, the centralized control module collects the bypass cable tension through a tension sensor installed at the cable outlet of the cable laying subunit, issues a resistance adjustment command to the cable supply subunit according to the allowable tension range in the work list, and issues a speed command to the cable laying subunit; when the tension exceeds the allowable range and cannot be recovered within a set time, the movement and cable laying are stopped simultaneously; the set time is written into the work list; the centralized control module executes the closing command only when the local interlocking conditions are met, and allows the execution of the opening command and prohibits the execution of the closing command even when remote communication is interrupted.
[0016] As a further improvement, the connection subunit includes a connection execution module and a phase verification module; the connection execution module is used to connect the down-lead cable to the line to be repaired, and send a connection completion signal to the centralized control module after connection is in place; the phase verification module is used to perform phase verification on the down-lead cables at the first lead-out point and the second lead-out point, and determine that the phase verification is qualified when the absolute value of the phase difference between the two ends is less than a set value, and send the phase verification result to the centralized control module.
[0017] As a further improvement, the centralized control module organizes action permissions according to modes, which include at least the transfer mode, laying mode, panel changing mode, positioning mode and live-line monitoring mode; when switching modes, the actions that have been enabled in the previous mode are first blocked, and then the actions allowed in the next mode are enabled.
[0018] The centralized control module is also configured to, upon receiving an exit command, first control the bypass load switch to trip and confirm no voltage, then have the connection subunit disconnect the down-lead cable from the line to be repaired, and then control the cable laying subunit to sequentially retract the down-lead cable, bypass load switch, and main cable.
[0019] Beneficial effects (1) This invention connects the ranging planning subunit, cable supply subunit, cable laying subunit, and splicing access subunit via a communication link, and uses the same work list to connect path planning, reel supply, segmented laying, reel exchange return, and end splicing. As a result, the planning side outputs the path, number of reels, reel exchange points, and number of round trips that can be directly executed by the supply side and the laying side. Each link has a unified length benchmark and position benchmark, which overcomes the shortcomings of existing operations where planning, cable preparation, laying, and splicing are independent of each other and can only be connected by on-site experience.
[0020] (2) In this invention, the spatial acquisition module acquires corridor spatial information, the path planning module generates a passable laying path, and the equivalent length calculation module and the work list generation module continuously export the equivalent cable length and the work list. The survey results are no longer limited to the inspection report, but can be directly converted into the basis for subsequent cable preparation and laying, avoiding the information gap between acquisition and execution.
[0021] (3) In this invention, the equivalent cable length is calculated after the laying path is segmented, and the length is calculated according to N = L / L n Determine the number of main cable reels and mark reel replacement points along the route. The number of reels and the number of round trips can be determined before the cable arrives on site, avoiding insufficient reels, excessive surplus cable, and repeated transportation caused by preparing cables only according to the horizontal distance.
[0022] (4) This invention writes the coordinates of the take-off point, the sequence of track points, the segmented terrain and correction coefficients, the equivalent cable length, the number of main cable reels, the coordinates of the reel replacement point, the number of round trips, the current reel number, the allowable tension range, and the closing permission conditions into the work list; the centralized control module controls the movement according to the track points and switches to the return process when approaching the reel replacement point; when the path is changed on site, the planning side is written back and recalculated. The work list becomes a parsable and write-back data object. After the path is changed, the number of reels and the reel replacement point are updated synchronously, avoiding the quantity misalignment caused by the two ends continuing to work according to different diameters.
[0023] (5) In this invention, the reel storage and transportation module stores, delivers, and retrieves reels carrying the main cable according to the number of reels determined by the work list, and the tension adjustment module adjusts the cable laying resistance according to the instructions of the centralized control module. The reels on the inlet side are consistent with the planning results, and the reel exchange window has clear delivery and retrieval targets; the cable laying resistance is incorporated into the tension benchmark shared with the laying side, and the supply and laying are mechanically coordinated, avoiding cable accumulation or stretching caused by adjusting the resistance based on experience.
[0024] (6) This invention integrates movement control, reel winding and unwinding, moisture-proof support, switch positioning, and centralized control into the same laying execution node, so that the cable laying speed matches the movement speed, and the support medium is synchronously positioned below the cable with the cable, and the switch remains in position and locked at the lead-out point. Segmented laying, moisture-proof support, and switch positioning are completed in the same cycle, avoiding misalignment, incomplete coverage, and uncertain positioning status caused by laying the support and placing the switch separately after laying the cable, and providing a detectable positioning lock input for closing permission.
[0025] (7) This invention stipulates that the supply side and the laying side shall adhere to a unified reel interface, with consistent connection specifications and detectable locking status; movement or reel winding is only permitted after locking is in place; reel replacement shall be permitted in the following order: reaching the replacement point or emptying the reel, stopping movement and reel winding, returning to the supply side, transferring the reel as a whole, aligning and locking and confirming the interface, updating the current reel number and continuing laying. If any step fails to detect, the movement permission remains prohibited. Reels carrying main cables can be interchanged as a whole without rewinding the cables on site. The reel replacement process is detectable and interruptible. The path of moving without locking or transferring without stopping is cut off, reducing the risk of reel misalignment and transfer under load, and keeping the progress of the bill of quantities consistent with the actual on site.
[0026] (8) In this invention, the bypass cable tension is collected by a centralized control module, and the supply-side resistance and the laying-side release speed are adjusted simultaneously according to the preset tension range; when the tension exceeds the allowable range and cannot be recovered within the set time, the movement and cable release are stopped at the same time. The cable release at the entrance and the movement and release in the corridor are in the same tension closed loop, which avoids the breakage or knot caused by the continued operation on one side.
[0027] (9) This invention issues a closing command only when both bypass load switches are fully open, properly connected, have consistent phase sequence, pass phase verification, and the switch status is within the allowable range and the switch is locked in position. After closing, movement, changing the switch's position status, and reel winding are prohibited. Closing is prohibited until phase verification information from both ends is received. Completion of connection does not equate to permission to close; phase sequence confirmation is a necessary input for permission to close, avoiding closing before connection, closing with different phase sequences, and disconnection due to live displacement.
[0028] (10) In this invention, the centralized control module organizes the action permissions according to modes such as transfer, laying, panel replacement, positioning, and live-line monitoring. When switching modes, the actions that are enabled in the previous mode are blocked first, and then the actions allowed in the next mode are enabled. In the live-line monitoring mode, only monitoring of operation information and execution of circuit breaker tripping are allowed. Mutually exclusive actions will not be superimposed at the same time. Even if a movement, descent, or retraction request is mistakenly issued during the live-line phase, it will not be executed, thus improving the safety margin of live-line operations.
[0029] (11) This invention allows the execution of tripping commands and prohibits the execution of closing commands even when remote communication is interrupted. Closing permission is completed locally and does not depend on unstable remote links. The bypass circuit can still safely exit when communication is downgraded, avoiding accidental closing when the status is incomplete.
[0030] (12) Upon receiving the exit command, this invention first controls the bypass load switch to open and confirms no voltage, then disconnects the down-lead cable from the line to be repaired, and then sequentially retracts the down-lead cable, bypass load switch, and main cable; from closing the switch until opening to confirm no voltage, movement, changing the switch's position, and rewinding the reel are prohibited. The exit sequence is the reverse of the closing sequence, avoiding live disconnection or cable rewinding, and ensuring that the construction and dismantling of the temporary power supply circuit are subject to the same interlock constraint.
[0031] (13) This invention fixes the site entry planning, reel supply, segmented laying, reel replacement and return, switch positioning and connection, closing permission and exit and recovery as sequential operation steps, so that the above module relationships and interlocking conditions have a repeatable time sequence. There is no need for temporary negotiation to connect each link on site, the operation cycle can be arranged in advance, the progress can be written back, and key actions can be prohibited, thereby shortening the bypass operation cycle in complex terrain and improving the safety margin of live work. Attached Figure Description
[0032] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the accompanying drawings used in the embodiments will be briefly described below.
[0033] Figure 1 This is a schematic diagram of the unit composition and work arrangement.
[0034] Figure 2This is a schematic diagram of the components of the distance measurement planning subunit.
[0035] Figure 3 This diagram illustrates the supply and overall interchangeability of reels.
[0036] Figure 4 This is a schematic diagram of unit communication and control interlocking.
[0037] In the diagram: 1. Distance planning subunit; 11. Spatial acquisition module; 12. Path planning module; 13. Equivalent length calculation module; 14. Work list generation module; 2. Cable supply subunit; 21. Reel storage and transportation module; 22. Tension adjustment module; 3. Cable laying subunit; 31. Walking control module; 32. Reel winding and unwinding module; 33. Moisture-proof support module; 34. Switch positioning module; 35. Centralized control module; 4. Connection and access subunit; 41. Connection execution module; 42. Phase verification module; 5. Work list; 6. Reel interface; 15. First lead-out point; 16. Second lead-out point. Detailed Implementation
[0038] The present invention will be further described below with reference to the accompanying drawings. The described embodiments are only some embodiments of the present invention and are not intended to limit the present invention.
[0039] In this invention, complex terrain refers to an operational environment where there are field ridges, ditches, slopes, muddy ground, or narrow passages between the two lead-out points, and the cables stored at the entrance side cannot be continuously placed in one go, requiring segmented supply and reel replacement. The equivalent cable length is the converted length used to determine the number of spare cable reels after taking into account terrain corrections, joint allowances, sag allowances, and process margins on the path geometry. The work list is structured data generated by the planning side and distributed to the supply and laying sides to unify constraints on the path, number of reels, reel replacement points, and number of round trips. Complete interchange refers to the transfer of the reel carrying the main cable as a complete logistics unit between the supply and laying sides without re-laying the cable on site.
[0040] Example 1 refer to Figures 1 to 4 A bypass cable laying system for complex terrain includes a ranging and planning subunit 1, a cable supply subunit 2, a cable laying subunit 3, and a splicing and access subunit 4 interconnected by a communication link, and the same work list 5 connects the path planning, reel supply, segmented laying, reel replacement and return, and end splicing. The ranging planning subunit 1 is used to collect spatial information of the first lead-out point 15 and the second lead-out point 16 on both sides of the line to be inspected, as well as the passable corridor between them. Based on the spatial information, it generates the laying path and the equivalent cable length, and determines the number of main cable reels, the reel replacement point location and the number of round trips based on the equivalent cable length and the nominal length of a single main cable reel. It generates the work list 5 and sends it to the cable supply subunit 2 and the cable laying subunit 3. The cable supply subunit 2 is used to store and supply reels carrying the main cable according to the work list 5, and to adjust the cable release resistance according to the tension command. The cable laying subunit 3 is used to move along the laying path and release the main cable according to the work list 5; after reaching the reel replacement point or the current reel is empty, it returns to the cable supply subunit 2 and replaces the reel carrying the main cable. The two adjacent reels of main cable are connected by an intermediate joint until the main cable path between the first lead-out point 15 and the second lead-out point 16 is completed; after the main cable path is completed, the bypass load switch and the down-lead cable are transported to the first lead-out point 15 and the second lead-out point 16 respectively and the down-lead cable is released. The cable supply subunit 2 and the cable laying subunit 3 use a unified reel interface 6, so that the reels carrying the main cable can be interchanged as a whole between the two without having to re-reload the cable on site. The connection subunit 4 is used to connect the down cable to the line to be repaired and complete the phase verification, and send the phase verification result to the centralized control module 35 in the cable laying subunit 3. The centralized control module 35 is configured to: coordinately control movement, cable laying, and reel changing according to the work list 5; form a tension closed loop with the cable supply subunit 2, and simultaneously stop movement and cable laying when the tension exceeds the allowable range; issue a closing command only when the bypass load switches located at the first lead-out point 15 and the second lead-out point 16 are both open, connected, have consistent phase sequence, pass phase verification, and the switch status is within the allowable range and the switch is locked in position; after closing, movement, changing the switch position status, and reel winding are prohibited.
[0041] Reference Figure 1-2 The four sub-units—distance planning sub-unit 1, cable supply sub-unit 2, cable laying sub-unit 3, and connection sub-unit 4—can be located at the survey site, corridor entrance, inside the corridor, and near the tower, respectively, but they form a closed loop in terms of information.
[0042] The ranging planning subunit 1, located on the planning layer, completes the collection of corridor spatial information and the generation of work list 5 before the start of large-scale operations. The cable supply subunit 2, located on the supply layer, stores reels and bypass load switches according to the list, delivers or retrieves reels at the reel-changing window, and adjusts the cable laying resistance according to instructions. The cable laying subunit 3, located on the execution layer, lays cables according to the flight path, returns according to the reel-changing point, transports switches, and releases the downlead cable. The connection and access subunit 4, located on the access layer, completes the connection and phase verification of the downlead cable to the line under maintenance. The centralized control module 35 is the interlocking decision point during operation: work list 5 flows downwards from the planning side, phase verification results flow upwards from the access layer, tension is in a closed loop between the centralized control module 35 and the tension adjustment module 22, and closing permission is only issued after all local conditions are met.
[0043] The above layering describes functional coupling, not limitations on installation location or carrier shape. The planning layer outputs no longer inspection instructions, but rather track data, number of reels, reel change points, and tension ranges that can be analyzed by the execution layer; the phase verification results from the access layer must be returned to the closing permission for closing to cease being an isolated action. Communication can utilize a private wireless network, a public network module, or a field self-organizing network. Regardless of the link used, closing permission must be granted locally within the centralized control module 35; remote commands cannot bypass the local interlock.
[0044] Example 2 Reference Figure 2 and Figure 3 The ranging planning subunit 1 includes a spatial acquisition module 11, a path planning module 12, an equivalent length calculation module 13, and a work list generation module 14. The spatial acquisition module 11 acquires corridor images or point clouds, along with synchronized three-dimensional coordinates. Acquisition can be performed by an aerial photogrammetry terminal or a ground-based surveying terminal; this invention does not limit the acquisition carrier. Before operation, a first lead-out point 15 and a second lead-out point 16 are marked on the planning side, and the strip between the first lead-out point 15 and the second lead-out point 16 that may be used as a laying passage is covered. When multiple candidate passages exist, they can be acquired separately and then compared by the path planning module 12.
[0045] The path planning module 12 constructs a passable passage based on spatial information. Planning principles include at least: the passage width must meet the safety margin required for the passage of subunit 3; the slope must not exceed its allowable mobility; obviously impassable ditches, waterlogged areas, and sections with insufficient load-bearing capacity must be avoided; and locations with minimal width and elevation difference between the two banks must be selected as reserved points for crossing. The output is an ordered sequence of track points, each with plane coordinates, elevation, and terrain type labels.
[0046] The equivalent length calculation module 13 divides the path into several segments. These segments can be divided according to terrain type change points, or they can be divided by a fixed step size and then assigned a type. The equivalent cable length is calculated using the following formula: L=Σ(Li ×k i )+L j +L s +L p In the formula, L i The geometric length of the i-th segment is the sum of the spatial distances between adjacent waypoints; k i L is the terrain correction factor; j L represents the joint allowance. s L is the sag allowance. p This refers to the process margin.
[0047] The terrain correction factor is used to account for additional costs such as detours, undulations, and deceleration during cable laying in the reserve cable calculation. An example of an implementable grading system is: flat terrain k. i =1.00~1.03; Sloping land is graded according to slope: less than 8° is 1.05~1.08, 8°~15° is 1.08~1.15, and greater but still passable is 1.15~1.20; Field ridge k i =1.10~1.18; k for muddy or paddy field surface i =1.12~1.22. The above values are empirical ranges for ease of implementation. In engineering, they can be measured in the calibration section and then written into the planning side. This invention does not limit a certain fixed decimal to a unique value.
[0048] Connector allowance L j The allowance is calculated as the product of the planned number of joints and the reserved length on one side, which is typically 2 to 5 meters on one side. Sag allowance L s Calculated as 1% to 3% of the path geometry length. Process margin L p Calculate 3% to 8% of the sum of the aforementioned items, and use it for cutting losses, inconvenient to empty the innermost layer on the plate, and temporary diversion.
[0049] The work list generation module 14 will compare L with the nominal length L of the single-reel main cable. n Comparing the two numbers, rounding up, we get the number of main cable reels N = L / L n The cumulative equivalent length along the path from the starting point is calculated, and each time an L is reached... n Set a disk swap point, where the last disk can be less than L. n The number of round trips for single-machine operation is R = N - 1; if a return to the supply side is required after each empty run, the number of times the machine changes hands is counted. Work list 5 must include at least: Job number, coordinates and elevations of first and second leader points 15 and 16, track point sequence, terrain type of each segment, and k i Equivalent length L, nominal length L nThe list includes the number of reels (N), coordinates of each reel replacement point, number of round trips, current reel number, allowable tension range, and closing permit conditions. This list is distributed to Supply Subunit 2 and Laying Subunit 3, and progress is updated during execution. Once confirmed, the list serves as a constraint for subsequent movement, cable laying, and reel replacement; any temporary on-site route changes must be recalculated and updated to the planning side to avoid inconsistencies in backup cables at both ends due to verbal changes.
[0050] Example 3 Reference Figure 4 The cable supply subunit 2 includes a reel storage and transportation module 21 and a tension adjustment module 22. The reel storage and transportation module 21 stores reels containing the main cable according to the number N in the inventory list, and delivers full reels to the laying side and retrieves empty reels at the reel exchange window. The tension adjustment module 22 adjusts the cable laying resistance according to the instructions of the centralized control module 35. The supply subunit 2 is typically deployed at the entrance node closest to the corridor and convenient for centralized storage; the present invention does not limit its carrier form.
[0051] The cable laying subunit 3 includes a travel control module 31, a reel winding / unwinding module 32, a moisture-proof support module 33, a switch positioning module 34, and a centralized control module 35. The travel control module 31 controls movement according to the track points and stops when an impassable obstacle is detected and the distance is less than a set value. The reel winding / unwinding module 32 releases the main cable or downlead cable at a speed matching the travel speed, and can also wind / unwind independently upon instruction. The moisture-proof support module 33 releases the support medium at a speed matching the cable release speed, ensuring the support medium is below the cable to prevent direct contact between the cable and the wet surface; if the speed deviation exceeds a threshold, the release speed of the support medium is corrected. The switch positioning module 34 transports the bypass load switch to the lead-out point and maintains its locked position.
[0052] The walking control module 31 can implement positioning methods such as satellite positioning or a combination of satellite positioning and inertial navigation, and moves by tracking waypoints; the safety margin of the channel width is, for example, the maximum width of the laying sub-unit plus not less than 0.3m, and the allowable slope is, for example, not exceeding 15°. It stops when an impassable obstacle is detected and the distance is less than a set value, for example, 2m to 5m.
[0053] Reel interface 6 is a standardized reel interface agreed upon by the supply side and the laying side. It has two essential components: consistent connection specifications to allow the reel carrying the main cable to be transferred as a complete unit; and detectable locking status to enable the control unit to determine whether the reel has been reliably connected.
[0054] One feasible locking detection method is as follows: Alignment pins are installed at the docking seats of the reel frame and the laying subunit 3. Once aligned, a microswitch or proximity switch provides a locking signal. The centralized control module 35 only allows movement or initiation of cable reeling / unloading when the locking signal is valid. Therefore, a reel of cable prepared at the inlet side can enter the laying process without on-site cable rewinding, and the empty reel can be returned to the supply side as a complete unit.
[0055] Disk swapping is a control process under list constraints. Central control module 35 grants permissions in the following order; if any step fails, the move permission remains prohibited.
[0056] T1 indicates that the current position has reached a reel change point in the list, or the remaining length of the current reel is less than the set threshold.
[0057] T2, once the tension is within the allowable range, stop moving and stop retraction.
[0058] T3, return to the supply side along the laid path or the planned return path; cable laying is prohibited during the return process, and temporary fixation should be made to the ends of the laid cables if necessary.
[0059] T4, after the lock is released, returns the empty reel as a complete unit to the supply side, and transfers the next reel containing the main cable to the laying side as a whole.
[0060] T5, after alignment and locking, the centralized control module 35 confirms that the locking signal is valid.
[0061] T6, update the current reel number and next reel replacement point, continue laying along the track until the main cable path between the first exit point 15 and the second exit point 16 is completed. Completion means that the main cables of each reel have been electrically connected at the predetermined positions via intermediate joints, and that down-leading cables can be connected at both ends; it does not mean the switch is closed. Adjacent reels of main cables are connected using prefabricated insulated intermediate joints or quick-connect couplings. After connection, the circuit is measured for continuity, and then the current reel number is updated.
[0062] The tension closed-loop system places the supply side and the laying side on the same mechanical reference. The centralized control module 35 collects the bypass cable tension via a tension sensor located at the cable outlet of the cable laying subunit 3. If the tension is below the lower limit, it indicates cable accumulation or slower release than expected; therefore, the release speed is increased or the supply-side resistance is reduced, and the movement speed is decreased if necessary. If the tension is above the upper limit, it indicates the cable is stretched or obstructed; therefore, the release speed is reduced or the resistance is increased, and movement is stopped if necessary. If the tension exceeds the allowable range and cannot be pulled back within a set time, both movement and cable laying are stopped simultaneously. The allowable tension range and set time are written as fields into the work list 5, allowing the tension reference for a single operation to be determined during the planning phase. One feasible value is: the allowable tension range is written according to the cable specification, for example, 200N to 800N; the set time is for example, 3s to 8s. The above values are intended to enable those skilled in the art to implement the operation and are not limited to the only possible values.
[0063] The centralized control module 35 organizes action permissions according to modes, which include at least the following modes: transfer mode, laying mode, reel-changing mode, positioning mode, and live-line monitoring mode. In transfer mode, only low-speed movement is allowed; the switch remains out of position, and the reel remains locked. In laying mode, movement, cable laying, and medium support are released synchronously, while descent actions unrelated to positioning are disabled. In reel-changing mode, only unlocking, transfer, and locking related to the reel-changing sequence are allowed; moving while changing reels is prohibited. In positioning mode, switch positioning and locking are enabled, and long-distance movement is restricted. Live-line monitoring mode is entered after closing the circuit breaker and only allows monitoring and tripping. When switching modes, actions enabled in the previous mode are first blocked, and then actions allowed in the next mode are enabled.
[0064] After the main cable path is completed, the installation process begins. Laying subunit 3 transports the bypass load switch and downlead cable to the first lead-out point 15, while the switch installation module 34 remains locked; then the second lead-out point 16 is processed. If there is only one laying execution node, the execution is carried out in the order of first lead-out point 15 followed by second lead-out point 16, with the transport cycle time reserved in the list.
[0065] Reference Figure 4 The connection subunit 4 includes a connection execution module 41 and a phase verification module 42. The connection execution module 41 connects the down-lead cable to the corresponding phase of the line to be repaired. After connection, it sends a connection signal to the centralized control module 35 via a limit switch, image verification, or confirmation button. The phase verification module 42 verifies the phases at the first lead-out point 15 and the second lead-out point 16, confirming that the phase sequence is consistent with the original line, and sends the result to the centralized control module 35. One feasible phase verification method is to use a dual-end phase comparator. When the absolute value of the phase difference between the two ends is less than a set value, the phase verification is considered qualified. An example of the set value is 15°. Before receiving information that both ends are connected in place and the phase verification is qualified, closing the circuit is prohibited. The specific work carrier for connection can be replaced, but the coupling between connection in place and qualified phase verification before closing the circuit cannot be omitted.
[0066] A closing permission requires a set of conditions to be true simultaneously: both bypass load switches at both ends must be open; both ends must be properly connected; the phase sequence at both ends must be consistent; the phase verification at both ends must be qualified; the switch status variables must be within the allowable range; and the switch must be locked in position. The switch status variables must include at least the open / close position, energy storage status, and locked-in status, and their allowable ranges are written into work list 5 as closing permission conditions. Closing is only issued after all conditions are met. Immediately after closing, the system enters live-line monitoring mode, prohibiting movement, changing the switch's position status, and reel winding. If remote communication is interrupted, the centralized control module 35 enters a degraded state, still allowing opening but prohibiting closing, ensuring the bypass circuit is always in a safe exit state.
[0067] The site planning space acquisition module 11 covers sections 15 and 16 and the corridor. The planning side generates paths and equivalent lengths, resulting in, for example, an equivalent length of 820 meters, 300 meters per panel, 3 panels required, two panel changing points, and 2 round trips. This forms the work list 5 and issues it out. The supply subunit 2 prepares materials according to 3 panels of main cable and switches at both ends.
[0068] Initial connection. The laying subunit 3 connects to the first panel on the supply side via interface specification 6, and enters laying mode after locking in place.
[0069] Segmented laying and reel replacement. The cable is laid along the flight path, with the supporting medium synchronously positioned below the cable. Tension resistance and release speed are adjusted using a closed-loop system. Upon approaching the reel replacement point, a prompt to return is issued. The reel replacement is completed following steps T1 to T6, and the progress is updated until the main cable is fully laid.
[0070] Positioning, connection, and closing. The switch and downlead cable are positioned and locked at 15 and 16 respectively. Connection and phase verification are completed in subunit 4. After the centralized control module 35 checks the permitting conditions, the switch is closed, and live monitoring begins. The original line is de-energized and grounded before maintenance is carried out. During the monitoring period, movement, lowering, and retraction are prohibited.
[0071] Exit Recycling. Upon receiving the exit command, first control the switches at both ends to open and confirm no pressure; disconnect the connection in sub-unit 4; in sub-unit 3, first retrieve the down-lead cable and switch, then retrieve the main cable in sections in the reverse order of laying, returning the empty reel to the supply side until the cable is removed from the corridor. Before confirming no pressure by opening the switches, the prohibitions for live-line duty remain in effect.
[0072] When the corridor is long and empty runs to and from a single node are unacceptable, two laying execution nodes adhering to the same interface specification can be used, with the responsibility section and joint meeting point divided by the same work list 5. The closing permission is still issued by the centralized control module 35, acting as the master station, after summarizing the status of both ends. At the meeting point, the two main cable sections are also connected using prefabricated insulated intermediate joints or quick-connect joints, and the centralized control module 35, acting as the master station, confirms continuity before proceeding to the placement process.
[0073] When it is inconvenient to transfer reels in one go between the entrance and the corridor, a transition handover can be added, but the interface specifications and locking detection remain unchanged. The terrain type in the equivalent length can be divided into categories in addition to flat land, slope, field ridge, and muddy land. As long as each type has a corresponding correction coefficient and is clearly indicated in the list, it will not deviate from the concept of using the equivalent length to drive the number of reels and the reel change point.
[0074] The above embodiments demonstrate that this invention does not simply list the four capabilities of surveying, cable preparation, laying, and splicing side by side. Instead, it uses a work list to transform the planned length and location into constraints that supply and execution must adhere to; it uses a unified interface specification to connect supply and laying into a single, interchangeable material flow; it uses a tension closed loop to connect cable laying resistance and movement release into a single adjustment process; and it uses a closing permission to connect phase verification, switch status, and positioning lock into a single safety decision. With these four couplings coexisting, bypass cable laying in complex terrain can be transformed from multi-stage on-site coordination based on experience into the continuous and controllable construction and withdrawal of temporary power supply circuits according to a predetermined rhythm.
[0075] The above description is merely a preferred embodiment of the present invention and is not intended to limit the present invention. All modifications, equivalent substitutions, and improvements made within the spirit and principles of the present invention should be included within the scope of protection of the present invention.
Claims
1. A bypass cable laying system for complex terrain, characterized in that, It includes a ranging planning subunit (1), a cable supply subunit (2), a cable laying subunit (3), and a splicing access subunit (4) that are interconnected by a communication link, and the same work list (5) connects the path planning, reel supply, segmented laying, reel replacement and end splicing. The ranging planning subunit (1) includes a spatial acquisition module (11), a path planning module (12), an equivalent length calculation module (13), and a work list generation module (14). The spatial acquisition module (11) acquires images or point clouds of the first lead-out point (15), the second lead-out point (16), and the passable corridor between the two sides of the line to be inspected, as well as the three-dimensional coordinates synchronized therewith, to form spatial information. The path planning module (12) generates a laying path in the passable corridor that avoids the inaccessible section based on the spatial information. The equivalent length calculation module (13) calculates the equivalent cable length based on the laying path. The work list generation module (14) determines the number of main cable reels, the location of the reel replacement point, and the number of round trips based on the equivalent cable length and the nominal length of a single reel of main cable, generates the work list (5), and sends it to the cable supply subunit (2) and the cable laying subunit (3). The cable supply subunit (2) is used to store and supply reels carrying the main cable according to the work list (5), and to adjust the cable release resistance according to the tension command; The cable laying subunit (3) is used to lay out the main cable while moving along the laying path according to the work list (5); Upon reaching the reel replacement point or after the current reel is emptied, return to the cable supply subunit (2) and replace the reel carrying the main cable. Adjacent reels of main cable are connected via intermediate joints until the main cable path between the first lead-out point (15) and the second lead-out point (16) is completed. After the main cable path is completed, transport the bypass load switch and the down-lead cable to the first lead-out point (15) and the second lead-out point (16) respectively and release the down-lead cable. The cable supply subunit (2) and the cable laying subunit (3) comply with the same reel interface (6), so that the reels carrying the main cable can be interchanged as a whole between the two without having to re-reload the cable on site. The connection subunit (4) is used to connect the down cable to the line to be repaired and complete the phase verification, and send the connection signal and phase verification result to the centralized control module (35) in the cable laying subunit (3). The centralized control module (35) is configured to: coordinately control movement, cable laying and reel changing according to the work list (5); form a tension closed loop with the cable supply subunit (2); stop movement and cable laying simultaneously when the tension exceeds the allowable range; issue a closing command only when the bypass load switches at the first lead-out point (15) and the second lead-out point (16) are both in the open position, hooked in place, phase sequence consistent, phase verification qualified, switch status quantity within the allowable range and switch in position locked; after closing, movement is prohibited, changing the switch in position is prohibited and reel winding is prohibited.
2. The bypass cable laying system for complex terrain according to claim 1, characterized in that: The spatial acquisition module (11) is acquired by an aerial photogrammetry terminal or a ground mapping terminal, and covers the strip between the first lead-out point (15) and the second lead-out point (16) that may be used as a laying channel; the laying path generated by the path planning module (12) satisfies that the channel width has a safety margin for the cable laying subunit (3) to pass through, the slope does not exceed its allowable movement capacity, and avoids ditches, water accumulation and sections with insufficient bearing capacity, and outputs an ordered sequence of track points with plane coordinates, elevation and terrain type labels.
3. A bypass cable laying system for complex terrain according to claim 1, characterized in that: The equivalent length calculation module (13) divides the laying path into several segments, according to the formula L = Σ(L i ×k i )+L j +L s +L p Calculate the equivalent cable length, where L i Let k be the geometric length of the i-th segment. i L is the terrain correction factor corresponding to the terrain type of this segment. j L is the allowance for the joint. s L is the sag allowance. p For process margin; the terrain types include at least flat land, slopes, field ridges, and muddy land, and the corresponding ki values range as follows: flat land k i =1.00~1.03, sloping land is classified according to slope and k i =1.05~1.20, k of the field ridge i =1.10~1.18, muddy ground k i =1.12~1.22; The work list generation module (14) will use L and the nominal length L of the single main cable to form a value. n Comparing the two numbers, rounding up, we get the number of main cable reels N = L / L n The replacement points are marked sequentially along the laying path according to the cumulative equivalent length; the number of round trips is R = N - 1.
4. A bypass cable laying system for complex terrain according to claim 1, characterized in that: The work list (5) includes at least the work number, the coordinates of the first lead-out point (15) and the second lead-out point (16), the sequence of track points of the laying path, the terrain type and correction coefficient of each segment, the equivalent cable length, the number of main cable reels, the coordinates of the reel replacement point corresponding to each reel, the number of round trips, the current reel number, the tension allowable range, and the closing permission conditions; the centralized control module (35) generates a movement command according to the track point sequence, and enters the reel replacement return process when the distance between the current position and the next reel replacement point is less than the set threshold; when the path is changed on site, the distance planning subunit (1) must be written back to recalculate the equivalent cable length and the number of reels before generating a new work list (5).
5. A bypass cable laying system for complex terrain according to claim 1, characterized in that: The cable supply subunit (2) includes a reel storage and transportation module (21) and a tension adjustment module (22). The reel storage and transportation module (21) stores reels containing main cables according to the number of main cable reels in the work list (5), and delivers or retrieves the reels to the cable laying subunit (3) at the reel exchange window. The tension adjustment module (22) receives the tension command issued by the centralized control module (35), adjusts the cable laying resistance, and keeps the bypass cable tension within the allowable range given in the work list (5).
6. A bypass cable laying system for complex terrain according to claim 1, characterized in that: The cable laying subunit (3) includes a walking control module (31), a reel winding and unwinding module (32), a moisture-proof support module (33), a switch positioning module (34), and the centralized control module (35); the walking control module (31) controls the movement according to the track point; the reel winding and unwinding module (32) unwinds the main cable or down cable at a speed matching the moving speed; the moisture-proof support module (33) unwinds the support medium at a speed matching the cable unwinding speed, so that the support medium is located below the cable; the switch positioning module (34) is used to transport the bypass load switch to the lead-out point and keep it in a locked position.
7. A bypass cable laying system for complex terrain according to claim 1, characterized in that: The unified reel interface (6) includes consistent connection specifications and detectable locking status, with the locking status given by a micro switch or proximity switch on the alignment structure; The centralized control module (35) is configured to allow the cable laying subunit (3) to move or start the reel winding and unwinding only when the lock-in signal is valid; The reel change is permitted in the following order: reaching the reel change point or emptying the reel, stopping movement and unloading, returning to the supply side, transferring the entire reel, aligning and locking and confirming the interface, updating the current reel number and continuing to lay the reel. If any step fails, the movement permission remains prohibited.
8. A bypass cable laying system for complex terrain according to claim 1, characterized in that: The centralized control module (35) collects the bypass cable tension through the tension sensor set at the cable outlet of the cable laying subunit (3), issues a resistance adjustment command to the cable supply subunit (2) according to the tension allowable range in the work list (5), and issues a speed command to the cable laying subunit (3). When the tension exceeds the allowable range and cannot be recovered within the set time, both movement and cable laying shall be stopped; the set time shall be written into the work list (5). The centralized control module (35) executes the closing command only when the local interlocking conditions are met, and allows the opening command to be executed and prohibits the closing command to be executed when the remote communication is interrupted.
9. A bypass cable laying system for complex terrain according to claim 1, characterized in that: The connection access subunit (4) includes a connection execution module (41) and a phase module (42). The connection execution module (41) is used to connect the down cable to the line to be repaired, and send a connection signal to the centralized control module (35) after the connection is in place; The phase comparison module (42) is used to compare the phases of the down-leading cables at the first lead-out point (15) and the second lead-out point (16). When the absolute value of the phase difference between the two ends is less than the set value, the phase comparison is deemed qualified, and the phase comparison result is sent to the centralized control module (35).
10. A bypass cable laying system for complex terrain according to claim 1, characterized in that: The centralized control module (35) organizes action permissions according to modes, including at least transfer mode, laying mode, panel changing mode, positioning mode and live-line duty mode; when switching modes, the actions that have been opened in the previous mode are blocked first, and then the actions allowed in the next mode are opened. The centralized control module (35) is also configured to, upon receiving the exit command, first control the bypass load switch to open and confirm that there is no pressure, then the connection subunit (4) removes the connection between the down-lead cable and the line to be repaired, and then controls the cable laying subunit (3) to sequentially retract the down-lead cable, the bypass load switch and the main cable.