A safe operation method for maintenance and isolation of coal mills in thermal power plants
By implementing comprehensive energy isolation and standardized procedures, safety hazards in the maintenance of coal mills in thermal power plants have been resolved, resulting in improved safety and standardization, and ensuring the safety and traceability of the maintenance process.
Patent Information
- Application Number
- CN202611389651.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-08
- Publication Date
- 2026-11-17
AI Technical Summary
There are safety hazards in the maintenance of coal mills in thermal power plants, including risks such as spontaneous combustion of coal powder, CO poisoning, hot air burns, coal powder explosions, and equipment malfunctions. The existing isolation methods are not standardized or thorough, and lack quantitative standards and closed-loop verification mechanisms.
The system employs comprehensive energy isolation, standardized procedures, physical hardware isolation, quantitative gas detection, and multi-party closed-loop verification. This includes steps such as orderly equipment shutdown, pressure relief and cooling, multi-dimensional electrical isolation, pneumatic gas source isolation, dual physical isolation of hot air pipelines, coal pipeline isolation, auxiliary medium isolation, forced ventilation, quantitative gas detection, and closed-loop verification to ensure safety and compliance.
It completely eliminated safety hazards in maintenance operations, improved the safety and standardization of coal mill maintenance, prevented the risk of poisoning and explosion in confined spaces, and achieved standardization and traceability of operating procedures.
Smart Images

Figure CN123102475A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of safety technology for the maintenance of pulverizing equipment in thermal power plants, specifically to a systematic safety isolation operation method applicable to internal maintenance, cleaning, hot work, and component replacement operations of coal mills. Background Technology
[0002] Coal mills in thermal power plants are core, high-risk equipment in the pulverizing system. Maintenance work presents multiple safety risks, including spontaneous combustion of coal dust, CO poisoning, hot air burns, coal dust explosions, and equipment malfunctions. Currently, routine maintenance isolation methods in the industry are mostly based on experience, resulting in problems such as inconsistent operating sequences, incomplete isolation points, inadequate hardware and software isolation measures, lack of quantifiable testing standards, and a lack of closed-loop verification mechanisms.
[0003] Routine operations rely solely on manual valve closure, power disconnection, and tagging, which poses risks such as internal valve leakage, unreleased residual air pressure and heat, malfunctions of pneumatic mechanisms, missed isolation points, and non-standard gas detection, making them highly susceptible to safety accidents. Existing general operating procedures are common, routine operations, lacking standardized, closed-loop, and implementable complete isolation processes, resulting in poor stability in safety management. Summary of the Invention
[0004] To address the shortcomings of existing coal mill maintenance and isolation procedures, such as non-standardization, incomplete isolation, inadequate risk control, and lack of quantitative judgment standards, this invention provides a safe operation method for coal mill maintenance and isolation in thermal power plants. This method achieves comprehensive energy isolation of the pulverizing system's circuits, air paths, coal paths, gas paths, and media pipelines. Through standardized procedures, physical hardware isolation, quantitative gas detection, and multi-party closed-loop verification, it completely eliminates safety hazards during maintenance operations and improves the safety and standardization of coal mill maintenance.
[0005] To achieve the above and other related objectives, the present invention adopts the following technical solution: A safe operation method for maintenance and isolation of coal mills in thermal power plants, applicable to shutdown maintenance, dust removal, internal inspection, component replacement, and hot work operations of medium-speed coal mills in thermal power plants, characterized by the following steps: S1. Orderly shutdown of equipment: The main motor of the coal mill, the coal feeder, the lubricating oil pump, and the hydraulic oil pump are shut down in sequence. The hot air regulating valve, the sealing air main valve, the hot primary air gate valve, the coal mill inlet coal powder gate valve, and the coal feeder inlet gate valve are closed in sequence to complete the smooth shutdown of the pulverizing system. S2. Pressure relief and cooling treatment: Open the cold air regulating damper and the cold primary air gate, and alternately open the coal powder gate at the coal mill outlet to purge and cool the coal mill area. Once the internal temperature of the coal mill drops below 50°C, the residual heat and pressure will be released. S3. Electrical multi-dimensional isolation: Disconnect the power supply and control circuit power supply of the coal mill, coal feeder, rotary separator, and each electric valve control power supply respectively, and lock and tag each power supply separately; S4. Pneumatic air source isolation: Close the main air source valve of all pneumatic dampers and pneumatic gate valves, disassemble the air source pipeline, vent the residual pressure of the air cylinder, and install thick stainless steel plugs at the pipeline interface for isolation. S5. Double physical isolation of hot air duct: Close the pneumatic gate of the hot air duct and isolate the air source and seal it with a plug. Then use a hand chain hoist to mechanically fix the hot air gate and hot air control valve and lock and tag them. S6. Coal passage isolation: Close the inlet and outlet doors of the coal feeder and lock and tag the outlet door of the coal feeder; S7. Auxiliary medium isolation: Close the fire steam door, sealing damper, lubricating oil valve, and hydraulic oil valve, and lock and tag them respectively; S8. Forced ventilation replacement: Open the manhole doors of the coal mill cylinder and separator, and use natural ventilation in combination with mechanical forced ventilation. The continuous ventilation time shall not be less than 30 minutes. S9. Quantitative Gas Safety Detection: The gas inside the coal mill is tested to control the oxygen concentration to 19.5%~23.5%, the carbon monoxide concentration to ≤25ppm, and the combustible gas concentration to be 20% below the lower explosive limit. All three indicators must meet the standards for environmental compliance. S10. Closed-loop verification and commencement of work: The operation personnel, the work supervisor, and the full-time monitor shall verify the isolation points, blind flange points, and test data. After the closed-loop is confirmed, the corresponding work order shall be issued and the maintenance work shall be carried out. S11. Reverse System Recovery: After maintenance is completed, follow the reverse order of the isolation operation to gradually remove the isolation and restore the system, and complete the equipment reset.
[0006] Preferably, in step S3, electrical isolation is divided into three categories: power supply isolation, auxiliary machine control circuit isolation, and electric valve power supply isolation. All isolation lock keys are kept in a unified manner by a designated person.
[0007] Preferably, in step S5, the key to the lock fitted after the hand chain hoist is mechanically fixed is managed separately by the on-site maintenance personnel.
[0008] Preferably, in step S9, a portable gas detector is used to sample and test multiple points inside the coal mill. If the gas indicators do not meet the standards, the ventilation time is extended and the test is repeated.
[0009] Preferably, in step S10, all isolation information, testing data, and ticket information are uniformly registered in the work log for full traceability.
[0010] Preferably, during step S2, the negative pressure in the boiler furnace is maintained stably throughout the entire process.
[0011] Compared with the prior art, the beneficial effects of the present invention are as follows: (1) Multi-dimensional energy isolation, thorough isolation: covering all related systems including electrical system, pneumatic air source, hot air pipeline, raw coal channel, lubricating oil / hydraulic oil system, fire steam, and sealing air. Multiple hard isolation methods such as power-off tagging, pipeline blocking plates, and valve mechanical fixation are adopted to solve the problems of valve internal leakage, pneumatic mechanism malfunction, and residual air pressure and heat leakage.
[0012] (2) Standardized operation process and unified specifications: fixed operation steps and operation sequence are set to replace traditional experience-based operation, avoid safety hazards caused by human error and disordered sequence, and are applicable to all types of maintenance operations of medium-speed coal mills in various thermal power plants.
[0013] (3) Quantify safety indicators and make objective judgments: Clearly define the detection thresholds for three gases: oxygen, carbon monoxide, and combustible gas. Abandon human sensory judgment and use instrument-quantified data as the basis for work access, effectively preventing the risk of poisoning and explosion in confined spaces.
[0014] (4) The ventilation duration is strictly regulated and harmful gases are fully replaced: the forced ventilation duration is required to be no less than 30 minutes to ensure that the accumulated powder, flue gas and toxic gases inside the coal mill are completely replaced, thereby reducing safety risks from the source.
[0015] (5) Multi-party closed-loop review and strict control: All isolation measures and test data are jointly reviewed by the operators, the person in charge of the work and the full-time guardian. The work permit, confined space permit and hot work permit are managed in a hierarchical manner to form a multi-level safety control defense line.
[0016] (6) Reverse recovery and traceability of records, with full control: After maintenance, the protection is strictly removed in the reverse order of isolation, and it is forbidden to unlock in advance; all operation, testing and verification information is uniformly registered in the ledger to achieve full traceability of the operation, which facilitates safety supervision and accident tracing.
[0017] Other additional advantages and benefits of this application will be set forth in part in the description which follows, and in part will be obvious from the description, or may be learned by practice of this application. Attached Figure Description
[0018] The accompanying drawings are provided to further illustrate the invention and form part of the specification. They are used in conjunction with embodiments of the invention to explain the invention and do not constitute a limitation thereof. In the drawings: Figure 1 This is a schematic diagram of the overall structure of the coal mill internal maintenance, cleaning, hot work, and component replacement system according to an embodiment of this application.
[0019] Explanation of reference numerals for major components: 1. Main motor of coal mill; 2. Coal feeder; 3. Lubricating oil pump; 4. Hydraulic oil pump; 5. Hot air regulating damper; 6. Sealed air main damper; 7. Hot primary air gate; 8. Coal mill inlet pulverized coal gate; 9. Coal feeder inlet gate; 10. Cold air regulating damper; 11. Cold primary air gate; 12. Outlet pulverized coal gate. Detailed Implementation
[0020] The specific embodiments of the present invention will be further described below with reference to the accompanying drawings. The following specific examples illustrate the embodiments of the present invention, and those skilled in the art can easily understand other advantages and effects of the present invention from the content disclosed in this specification. The present invention can also be implemented or applied through other different specific embodiments, and the details in this specification can also be modified or changed based on different viewpoints and applications without departing from the spirit of the present invention. It should be noted that, unless otherwise specified, the following embodiments and features in the embodiments can be combined with each other. Example
[0021] This invention provides a method for safe and isolated maintenance operations of coal mills in thermal power plants, specifically comprising the following eleven steps: S1. Orderly shutdown of equipment. The main motor 1 of the coal mill, the coal feeder 2, the lubricating oil pump 3, and the hydraulic oil pump 4 are shut down sequentially and smoothly. The hot air regulating damper 5, the corresponding coal mill sealing air main damper 6, the hot primary air gate 7, the coal mill inlet pulverized coal gate 8, and the coal feeder 2 inlet gate are gradually closed to complete the smooth shutdown of the pulverizing system. The system load change rate is controlled throughout the process to prevent airflow and pulverized coal disturbances in the pulverizing system.
[0022] S2. Pressure Relief and Cooling Treatment. Open the cold air regulating damper 10 and the cold primary air baffle 11 of the coal mill, and alternately open multiple sets of coal powder outlet baffle 12 of the coal mill; maintain the normal negative pressure in the boiler furnace, and cool and purge the entire area from the coal mill stone coal chamber to the burner to completely release the residual air pressure and high-temperature waste heat inside the system; monitor the internal temperature of the coal mill in real time, and when the temperature drops below 50℃, determine that the waste heat and residual pressure in the isolation area are cleared, and proceed to the next process.
[0023] S3. Comprehensive Electrical Isolation. Employing a layered power-off and independent locking / tagout system, electrical isolation is achieved across three types of circuits: (1) Power supply isolation: disconnect the main power supply of the coal mill, the main power supply of the coal feeder 2, and the main power supply of the rotary separator respectively, and lock each power supply independently and hang a warning sign prohibiting the switch; (2) Auxiliary control power supply isolation: disconnect the control power supply of the main motor 1 of the coal mill, the control circuit power supply of the hydraulic oil pump 4, the main power supply of the coal mill separator control cabinet, and the control power supply of the coal feeder 2, and lock and tag them separately; (3) Power supply isolation for electric valves: disconnect the control power supply of cold primary air gate 11, hot primary air gate 7, coal mill outlet gate, fire steam electric door, and sealing air main door 6 respectively, and lock and tag them independently; All isolation lock keys must be kept in a designated place and must not be lent out without permission.
[0024] S4. Pneumatic air source isolation. Close the main pneumatic air source valve corresponding to all pneumatic dampers and pneumatic slide gates of the coal mill; disconnect the air source connection pipelines of each pneumatic component and thoroughly purge the residual air pressure inside the cylinder; install a 3mm thick stainless steel plug at the pipeline disconnection point for physical isolation, forming a permanent and obvious disconnection point to completely prevent residual pressure from causing malfunction of dampers and slide gates.
[0025] S5. Double physical isolation for hot air ducts. Double physical isolation is installed on the high-temperature hot air ducts to prevent hot air from entering the work area: (1) First isolation: Close the pneumatic gate valve of the hot air pipeline, close the corresponding main air source valve, disassemble the air source pipeline and exhaust cylinder residual pressure, and install a 3mm thick stainless steel plug at the pipeline interface to seal it; (2) Secondary mechanical locking: The hot air gate and the hot air regulating gate 5 are mechanically locked and fixed by hand chain hoists. Locks are installed on the hand chain hoists and warning signs are hung. The lock keys are managed by the on-site maintenance personnel to prevent the operators from accidentally opening the valves.
[0026] S6. Coal passage isolation. Close the inlet and outlet gates of coal feeder 2, install locks on the outlet gate of coal feeder 2 and hang warning signs to block the upper raw coal falling passage, so as to avoid the risk of raw coal sliding into the coal mill due to misoperation, causing dust accumulation and burying people.
[0027] S7. Auxiliary Media Isolation. Close the coal mill's fire-fighting steam valve, sealing damper, lubricating oil system valve, and hydraulic oil system valve in sequence. Lock and tag each valve to cut off the supply of auxiliary media such as steam, sealing air, lubricating oil, and hydraulic oil.
[0028] S8. Forced ventilation replacement. Fully open the manhole doors of the coal mill cylinder and the separator, and adopt a combination of natural ventilation and mechanical forced ventilation. The continuous ventilation time shall not be less than 30 minutes to fully replace the residual coal dust, toxic and harmful gases and flue gas inside the equipment.
[0029] S9. Quantitative Gas Safety Testing. Using a portable professional gas detector, collect gas samples from multiple points inside the coal mill for testing. The operational access standards are: oxygen concentration controlled between 19.5% and 23.5%, carbon monoxide concentration ≤25 ppm, and combustible gas concentration below 20% of the lower explosive limit. Only when all three indicators meet the standards can the working environment be deemed qualified. If any indicator exceeds the standard, extend the ventilation time and retest until all indicators are qualified.
[0030] S10. Closed-Loop Verification and Commencement. The operation personnel, the work supervisor, and the dedicated monitor must be present to verify all isolation points, lockout points, blind flange installation points, and gas detection data item by item. After all three parties confirm the accuracy and complete the closed-loop signature confirmation, a work permit, confined space work permit, or hot work permit must be processed according to the type of work. Only after all procedures are complete can personnel be organized to enter the site to carry out maintenance work. All verified data and permit information must be entered into the safety operation log.
[0031] S11. Reverse System Recovery. After all maintenance work is completed and personnel and tools have left the equipment, the system recovery shall be carried out in the exact opposite order to the isolation operation: remove warning signs, remove locks, remove pipeline blind flanges, release valve mechanical fixation, restore pneumatic air supply, restore all electrical power supplies, and gradually open all valves to smoothly restore the equipment to standby or operating conditions; unlocking any isolation or protective measures in advance is strictly prohibited throughout the process.
[0032] Based on the above scheme, it is implemented according to the systems engineering logic of "energy gradient release to environmental state reconstruction". This involves utilizing the high-temperature thermal energy (≥200℃) within the hot air duct, the residual gas pressure energy within the system, the chemical energy released from the volatilization of pulverized coal (explosion risk), and the automatic closing / opening of dampers due to gravitational potential energy. Conventional practices often only focus on power cutoff and the closure of a single valve, neglecting the timing of energy release and the reliability and redundancy of isolation measures.
[0033] After a routine shutdown, directly opening the cold air damper causes the cold air to easily follow a "short-circuit flow line," creating a thermal dead zone at the bottom of the pulverizer shell and on the leeward side of the separator baffle plate. This solution employs alternating opening of the pulverizer outlet coal powder inlet gate 12 in conjunction with cold air purging. When a single outlet gate is open, the pressure gradient of the internal flow field of the pulverizer undergoes a directional shift; during alternating opening, the airflow direction forms an unsteady turbulent boundary layer within the shell. This dynamic purging not only achieves cooling but, more importantly, utilizes the micro-deformation of the metal due to thermal stress generated by alternating hot and cold temperatures to cause the clumps of coal powder adhering to the shell wall and stationary ring to develop "crack textures" and peel off on their own. Compared to conventional purging, this method significantly improves the effective removal rate of residual coal powder inside the pulverizer.
[0034] This solution first disassembles the air source pipeline and installs a thick stainless steel blocking plate, which physically isolates the "fluid static pressure energy." Secondly, for the hot air slide door and regulating door, a hand-operated hoist is used for mechanical fixing. This utilizes the pre-tightening force constraint from rigid body mechanics to forcibly counteract negative pressure fluctuations within the air duct and the valve's own weight settling. This solution, through mechanical locking and reverse thrust, unexpectedly achieves pre-intervention for door hinge jamming or incomplete closing caused by thermal expansion and contraction of the hot air duct. The fixing tension of the hand-operated hoist forces the door panel to always be at the end of its fully closed stroke, compensating for stroke deviations in the pneumatic actuator caused by aging seals.
[0035] This plan requires that all three indicators—oxygen (19.5%~23.5%), carbon monoxide (≤25ppm), and combustible gas (<20% of the lower explosive limit)—meet the standards. Meeting the oxygen standard only ensures personnel breathing safety, but a high-oxygen environment can promote combustion. CO concentration is a specific marker of the smoldering latency period (even when the temperature drops below 50℃, oxidation reactions continue deep within the coal seam); combustible gas concentration reflects the continuous desorption rate of volatiles. A "negative feedback verification" of environmental stability is constructed. That is, only when CO is consistently maintained at an extremely low level can it be proven that the internal oxidation reaction has been completely suppressed, and only then does meeting the oxygen concentration standard have safety significance. This "dynamic equilibrium safety window" effect means that even if the oxygen level is qualified, if CO is high, it indicates that heat is still being released internally. If ventilation is prematurely implemented at this time, the added oxygen will accelerate the conversion of smoldering into open flame. This triple-combined judgment method eliminates the blind spot of the "latency period" from the root of combustion science, ensuring that the working environment achieves a thermodynamic and chemical steady state.
[0036] The technical solution of the present invention has been described above with reference to the preferred embodiments shown in the accompanying drawings. The above description is merely a preferred embodiment of the present invention and is not intended to limit the invention. For those skilled in the art, the present invention can have various modifications and variations. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.
Claims
1. A method for safe and isolated maintenance of coal mills in thermal power plants, applicable to shutdown maintenance, dust removal, internal inspection, component replacement, and hot work operations of medium-speed coal mills in thermal power plants, characterized in that... Includes the following steps: S1. Orderly shutdown of equipment: The main motor (1), feeder (2), lubricating oil pump (3), and hydraulic oil pump (4) of the coal mill are shut down in sequence. The hot air regulating valve (5), the sealing air main valve (6), the hot primary air gate (7), the coal mill inlet coal powder gate (8), and the feeder (2) inlet gate are closed in sequence to complete the smooth shutdown of the pulverizing system. S2, Pressure relief and cooling treatment: Open the cold air regulating valve (10) and the cold primary air baffle (11) door, and alternately open the coal powder baffle door (12) at the coal mill outlet to purge and cool the coal mill area. When the internal temperature of the coal mill drops below 50℃, the residual heat and residual pressure are released. S3, Electrical multi-dimensional isolation: Disconnect the power supply and control circuit power supply of the coal mill, coal feeder (2), rotary separator, and each electric valve control power supply respectively, and lock and tag each power supply respectively; S4. Pneumatic air source isolation: Close the main air source valve of all pneumatic dampers and pneumatic gate valves, disassemble the air source pipeline, vent the residual pressure of the air cylinder, and install thick stainless steel plugs at the pipeline interface for isolation. S5. Double physical isolation of hot air pipeline: Close the pneumatic gate of hot air pipeline and isolate the air source and seal the blockage plate. Then use a hand hoist to mechanically fix the hot air gate and hot air regulating door (5) and lock and hang the tag. S6. Coal passage isolation: Close the inlet and outlet doors of the coal feeder (2) and lock and tag the outlet door of the coal feeder (2); S7. Auxiliary medium isolation: Close the fire steam door, sealing damper, lubricating oil valve, and hydraulic oil valve, and lock and tag them respectively; S8. Forced ventilation replacement: Open the manhole doors of the coal mill cylinder and separator, and use natural ventilation in combination with mechanical forced ventilation. The continuous ventilation time shall not be less than 30 minutes. S9. Quantitative Gas Safety Detection: The gas inside the coal mill is tested to control the oxygen concentration to 19.5%~23.5%, the carbon monoxide concentration to ≤25ppm, and the combustible gas concentration to be 20% below the lower explosive limit. All three indicators must meet the standards for environmental compliance. S10. Closed-loop verification and commencement of work: The operation personnel, the work supervisor, and the full-time monitor shall verify the isolation points, blind flange points, and test data. After the closed-loop is confirmed, the corresponding work order shall be issued and the maintenance work shall be carried out. S11. Reverse System Recovery: After maintenance is completed, follow the reverse order of the isolation operation to gradually remove the isolation and restore the system, and complete the equipment reset.
2. The method for safe and isolated maintenance of a coal mill in a thermal power plant according to claim 1, characterized in that, In step S3, electrical isolation is divided into three categories: power supply isolation, auxiliary machine control circuit isolation, and electric valve power supply isolation. All isolation lock keys are kept in custody by designated personnel.
3. The method for safe and isolated maintenance of a coal mill in a thermal power plant according to claim 1, characterized in that, In step S5, the key to the lock fitted after the hand chain hoist is mechanically fixed is managed separately by the on-site maintenance personnel.
4. A method for safe and isolated maintenance operations of a coal mill in a thermal power plant according to claim 1, characterized in that, In step S9, a portable gas detector is used to sample and test multiple points inside the coal mill. If the gas indicators do not meet the standards, the ventilation time is extended and the test is repeated.
5. A method for safe and isolated maintenance operations of a coal mill in a thermal power plant according to claim 1, characterized in that, In step S10, all isolation information, testing data, and ticket information are uniformly registered in the work log for full traceability.