Plasma Cutting Equipment and Process for Building Steel
By using a movable and liftable fume collection device and a negative pressure suction system in plasma cutting equipment, the problem of fume overflow during the cutting of large-size steel plates has been solved, achieving efficient and stable dust removal, simplifying the operation process and reducing energy consumption.
Patent Information
- Application Number
- CN202611536275.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-30
- Publication Date
- 2026-11-17
AI Technical Summary
When cutting large-sized building steel plates, existing plasma cutting equipment suffers from the inability of traditional partitions to rise and fall stably and quickly, resulting in cumbersome operation, high energy consumption, and poor dust removal, making it difficult to meet the cutting needs of large-sized steel materials.
The system employs a horizontally movable and vertically adjustable flue gas collection device, combined with a negative pressure suction device. Through the matching design of the ventilation window and the flue gas collection hood, a relatively closed flue gas collection chamber is formed, enabling targeted and directional extraction of smoke and dust, and preventing the spillage of smoke and dust.
It effectively reduces the spillover of smoke and dust into the environment, improves the working environment of the cutting station, has a compact and convenient overall structure, can be moved to any cutting position, ensures efficient and stable negative pressure suction, and reduces dust removal energy consumption.
Smart Images

Figure CN123103138A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of plasma cutting technology, and in particular to plasma cutting equipment and processes for building steel. Background Technology
[0002] Plasma cutting is an important processing method for cutting thick steel plates in the field of building steel structures. It relies on a high-temperature plasma arc to melt the steel, and then uses a high-speed plasma gas flow to blow the molten metal away from the workpiece from the kerf. It can efficiently cut building steel plates of different thicknesses. During the cutting process, the plasma jet penetrates the steel plate from top to bottom. Molten metal and metal vapor are carried by the high-speed gas flow through the kerf and rush to the lower side of the plate. After the molten metal reaches the bottom of the plate, it comes into full contact with the air and undergoes violent oxidation, generating a large amount of smoke and dust containing metal oxides and high-temperature slag. Most of the waste gas and particulate matter are released from the bottom of the steel plate to the outside.
[0003] In existing dust removal solutions, a common approach is to install fixed air ducts inside the base of the cutting workbench. For example, patent document CN114603242A discloses a plasma cutting device with a segmented cleaning lathe. By dividing the device into multiple independent compartments and using liftable partitions to open and close the corresponding compartments, negative pressure ventilation is achieved in each compartment, thereby reducing fan energy consumption and collecting and treating the dust generated during cutting.
[0004] Building sheet steel is large in size, and traditional technology makes it difficult to stably and quickly raise and lower the partition baffles with large size spans. The operation is cumbersome, energy-consuming and inefficient. When the cutting position changes continuously, different partition baffles need to be raised and lowered frequently, which is difficult to meet the plasma cutting needs of building sheet steel with large size spans. Summary of the Invention
[0005] To address the aforementioned issues, this invention provides a plasma cutting device and process for building steel. This invention eliminates the need for a dense array of lifting baffles below the plasma cutting device. The overall structure is compact and convenient, and it can be moved to any cutting position to achieve rapid and effective shielding and sealing, ensuring efficient and stable negative pressure suction.
[0006] To solve the above problems, the technical solution adopted by the present invention is as follows:
[0007] The plasma cutting equipment for building steel includes a support base, with a support frame for placing plate-shaped steel on the upper end of the support base. The support frame is a mesh structure with multiple ventilation windows inside. It also includes a plasma cutting head located on the upper end of the support base and a first drive assembly for controlling the movement of the plasma cutting head. A fume collection device with an open top and closed bottom is also provided at the lower end of the support frame. The fume collection device is connected to a negative pressure suction device. The fume collection device includes a fume collection hood with multiple strip-shaped notches through the mesh support frame on its sidewall. The length and width of the horizontal projection surfaces of the multiple ventilation windows are the same. The length and width of the horizontal projection surface of the fume collection hood are multiples of the length and width of the horizontal projection surface of the ventilation windows. A second drive assembly for controlling the horizontal and vertical movement of the fume collection device is also provided below the support frame.
[0008] During plasma cutting, the sheet steel is first laid flat on the upper surface of the support frame. Then, the fume collection device is moved to a position below the cutting position and lifted to a predetermined height. The upper surface of the fume collection device is controlled to be pressed tightly against the lower surface of the sheet steel at the periphery of the cutting position. At this time, a relatively closed fume collection chamber is formed inside the fume collection device. At the same time as plasma cutting, the negative pressure suction device is activated to continuously and directionally suck and concentrate the fumes generated by plasma cutting, avoiding the overflow of fumes generated during plasma cutting and effectively improving the plasma cutting working environment.
[0009] Preferably, the side wall of the flue gas collection hood is further provided with a first slag discharge port, and the interior of the first slag discharge port is further provided with a shielding structure.
[0010] During the negative pressure dust extraction process, the first slag discharge port is sealed by the shielding structure to ensure that the inside of the flue gas collection hood is in a relatively closed area, thereby improving the effect of negative pressure extraction and preventing flue gas from overflowing. After repeatedly bearing the iron filings or partial fragments that have fallen off the cutting process, the shielding structure is opened to discharge the waste inside the flue gas collection hood to avoid internal blockage and achieve multiple cycles of cutting processing.
[0011] Preferably, the shielding structure includes a screening device, there is a predetermined height between the first slag discharge port and the bottom of the flue gas collection hood for accommodating buffer sand, the screening device includes a screening box with a screening port at the bottom, a second slag discharge port on the side wall of the screening box, and the negative pressure suction device includes a control rod for controlling the lifting and lowering movement of the screening box.
[0012] The first slag discharge port is located on the moving path of the second slag discharge port. During the slag discharge process, the second slag discharge port is controlled to move upward and overlap with the first slag discharge port. At this time, the waste material screened at the bottom of the screening box can be removed. During negative pressure suction, the screening box is controlled to descend, squeeze the buffer sand and pass through the buffer sand. At this time, the side wall of the screening box blocks the first slag discharge port to achieve relative sealing. At the same time, the bottom of the screening box is covered by the buffer sand. At this time, the bottom of the screening box can be protected by the buffer sand to prevent the high-temperature molten material from falling and sticking to the upper surface of the screening box to avoid high-temperature damage.
[0013] Preferably, the bottom of the screening box includes multiple screening sections arranged at intervals, with a screening opening formed between two adjacent screening sections; the screening sections can be selected as strip-shaped or columnar structures.
[0014] Preferably, the negative pressure suction device further includes a first suction component and a second suction component connected to the control air rod, the other side of the second suction component is connected to the interior of the screening box, and the other side of the first suction component is connected to a negative pressure device.
[0015] Preferably, the side wall of the screening section has multiple air jets, and the air jets are connected to a cold source pump mechanism.
[0016] The cooling gas pump mechanism can spray cooling gas through multiple nozzles. The sprayed cooling gas can cool and protect the buffer sand and the bottom of the screening box, and accelerate the solidification of the molten material. On the other hand, it can also form a circulating airflow with the negative pressure suction to achieve a high-efficiency negative pressure suction effect. Preferably, the other side of the second suction component is connected inside the buffer sand, and an interception structure is set at the end of the second suction component to prevent the buffer sand from being sucked in during negative pressure suction. At this time, the buffer sand can act as a filter material.
[0017] Preferably, the control rod includes a control sleeve, a control piston is sealed and slidably mounted inside the control sleeve, a control rod is fixed to the side wall of the control piston, the end of the control rod passes through the flue gas collection hood and is connected to the bottom of the screening box, and a pumping pipe is embedded inside the control rod and communicates with multiple air jets.
[0018] By controlling the piston, the negative pressure suction section and the cold source pump section can be separated, and the two will not affect each other. At the same time, the two can be adjusted simultaneously to adjust the extension and retraction of the control rod, thereby controlling the lifting and lowering movement of the screening box. The screening box can be controlled to vibrate pulses during the rising and falling process to achieve more efficient screening and squeezing descent.
[0019] Preferably, there are two control air rods arranged at intervals, and the first suction assembly includes a first suction end and a second suction end that are respectively connected to the two control air rods.
[0020] Two control rods can be connected more stably to the bottom of the screening box, ensuring its stable lifting and lowering movement. The bottom of the screening box is set to an inclined state, and there can be a certain gap between the screening box and the inner wall of the flue gas collection hood. The two control rods are alternately controlled to vibrate and extend during the lifting and lowering process, which can accelerate the vibration discharge of solidified waste at the top of the screening box.
[0021] Preferably, the first suction assembly further includes a main negative pressure pipe, and a three-way connector is formed between the main negative pressure pipe and the first suction end and the second suction end. An electrically controlled three-way valve is provided in the three-way connector; the valve core of the electrically controlled three-way valve is rotated to alternately or simultaneously control the two control air rods to be in the conducting state.
[0022] The plasma cutting process for building steel, using the aforementioned plasma cutting equipment for building steel, includes the following steps: S1, laying the plate-shaped steel flat on the upper surface of the support frame; S2, driving the fume collection device to move to a position below the cutting position, then lifting the fume collection device to a predetermined height, controlling the upper surface of the fume collection device to be in close contact with the outer perimeter of the cutting position on the lower surface of the plate-shaped steel; S3, simultaneously activating the negative pressure suction device during plasma cutting to continuously and directionally suck and concentrate the fumes generated by plasma cutting.
[0023] The beneficial effects of this invention are as follows:
[0024] Compared with existing technologies, this solution features a second drive component that can move horizontally and lift vertically to drive the fume collection device. During cutting operations, the fume collection hood moves upward and rests against the outer perimeter of the cutting position on the lower surface of the plate steel, forming a relatively closed fume collection chamber below the ventilation window of the support frame. In conjunction with the negative pressure suction device, it can perform targeted suction of the fumes generated by plasma cutting. The fume collection hood has a strip-shaped notch that can pass through the mesh support frame. The fume collection hood and the ventilation window are matched with a multiple projection size to ensure that the fume collection hood can completely cover the different ventilation windows corresponding to the cutting area, greatly reducing the spillage of fumes into the workshop environment, improving the working environment of the cutting station, and overcoming the problems of scattered fumes and poor dust removal in traditional plasma cutting. This device does not require a dense array of lifting baffles under the plasma cutting equipment. The overall structure is compact and convenient, and can be moved to any cutting position to complete a quick and effective shielding and sealing, ensuring the high efficiency and stability of negative pressure suction. Attached Figure Description
[0025] Figure 1 This is a three-dimensional structural diagram of the present invention.
[0026] Figure 2 For the present invention Figure 1 A schematic diagram of the main structure.
[0027] Figure 3For the present invention Figure 2 A schematic diagram of the AA-direction cross-section structure.
[0028] Figure 4 For the present invention Figure 2 Schematic diagram of the BB-direction cross-section structure.
[0029] Figure 5 For the present invention Figure 3 A magnified structural diagram at point C.
[0030] Figure 6 For the present invention Figure 4 A magnified structural diagram at point D.
[0031] Figure 7 This is a three-dimensional structural diagram of the flue gas collection device of the present invention.
[0032] Figure 8 This is a three-dimensional structural diagram of the screening device of the present invention.
[0033] Figure 9 This is a process flow diagram of the present invention.
[0034] In the diagram: 100, support base; 110, support frame; 111, ventilation window; 200, first drive assembly; 210, first transverse electric rail; 220, first longitudinal electric rail; 300, plasma cutting head; 400, second drive assembly; 410, second transverse electric rail; 420, second longitudinal electric rail; 430, lifting assembly; 500, flue gas collection device; 510, flue gas collection hood; 520, strip-shaped notch; 530, first negative pressure suction port; 540, first slag discharge port; 600. Negative pressure suction device; 610, control air rod; 611, control sleeve; 612, control piston; 613, control rod; 620, first suction assembly; 621, main negative pressure pipeline; 622, first suction end; 623, electrically controlled three-way valve; 624, second suction end; 630, second suction assembly; 700, screening device; 710, screening box; 720, second negative pressure suction port; 730, screening section; 731, screening port; 740, second slag discharge port; 800, pump air pipeline. Detailed Implementation
[0035] The present invention will be further described below with reference to the accompanying drawings and embodiments.
[0036] See attached document Figure 1 -Appendix Figure 8The plasma cutting equipment for building steel includes a support base 100, a support frame 110 for placing plate-shaped steel on the upper end of the support base 100, the support frame 110 being a mesh with multiple ventilation windows 111 inside, and a plasma cutting head 300 located on the upper end of the support base 100 and a first drive assembly 200 for controlling the movement of the plasma cutting head 300. The first drive assembly 200 controls the plasma cutting head 300 to move to different positions, enabling the cutting of different shapes on the surface of the plate-shaped steel, such as rectangular, circular, or oblong cuts, to meet the needs of subsequent welding and assembly. The first drive assembly 200 includes a first transverse electric rail 210 and a first longitudinal electric rail 220, which work together to control the movement of the plasma cutting head 300 to any position on the plane.
[0037] A flue gas collection device 500 with an open top and closed bottom is also provided at the lower end of the support frame 110. The flue gas collection device 500 is connected to a negative pressure suction device 600. The flue gas collection device 500 can form a relatively closed flue gas collection chamber at the lower end of the plate steel. The flue gas collection chamber can confine the large amount of flue gas generated by plasma cutting to a small area to prevent it from spreading. The negative pressure suction device 600 can continuously suction the flue gas remaining in the flue gas collection chamber to prevent the flue gas from overflowing and improve the surrounding working environment.
[0038] Specifically, the flue gas collection device 500 includes a flue gas collection hood 510, the side wall of which has multiple strip-shaped notches 520 passing through the mesh support frame 110; the length and width of the horizontal projection surfaces of the multiple ventilation windows 111 are the same, the length of the horizontal projection surface of the flue gas collection hood 510 is a multiple of the length of the horizontal projection surface of the ventilation windows 111, and the width of the horizontal projection surface of the flue gas collection hood 510 is a multiple of the width of the horizontal projection surface of the ventilation windows 111; the dimensions of the ventilation windows 111 and the flue gas collection hood 510 are adapted to each other, as shown in the attached figure, the flue gas collection hood 510 can enclose 3×3 ventilation windows 111 at a time, and can enclose 9 ventilation windows 111 at a time, and can also be actually cut to select a larger area or a long strip shape as needed.
[0039] A second drive assembly 400 is also provided below the support frame 110 to control the horizontal and vertical movement of the fume collection device 500. During the plasma cutting process, the plate-shaped steel is first laid flat on the upper surface of the support frame 110. Then, the fume collection device 500 is driven to move to a position below the cutting position and then lifted to a predetermined height. The upper surface of the fume collection device 500 is controlled to abut against the outer periphery of the cutting position on the lower surface of the plate-shaped steel. At this time, a relatively closed fume collection chamber is formed inside the fume collection device 500. At the same time as the plasma cutting, the negative pressure suction device 600 is activated to continuously and directionally suck and concentrate the fumes generated by the plasma cutting, avoiding the overflow of fumes generated during the plasma cutting process and effectively improving the plasma cutting working environment.
[0040] The aforementioned second drive assembly 400 includes a second transverse electric rail 410, a second longitudinal electric rail 420, and a lifting assembly 430. The second transverse electric rail 410, the second longitudinal electric rail 420, and the lifting assembly 430 work together to control the horizontal and vertical movement of the flue gas collection device 500.
[0041] In summary, this solution uses a second drive component 400 that can move horizontally and lift vertically to drive the fume collection device 500. During the cutting operation, the fume collection hood 510 moves upward and abuts against the outer perimeter of the cutting position on the lower surface of the plate steel, forming a relatively closed fume collection chamber below the ventilation window 111 of the support frame 110. Combined with the negative pressure suction device 600, it can perform targeted and directional suction of the fumes generated by plasma cutting. The fume collection hood 510 has a strip-shaped notch 520 that allows passage through the mesh support frame 110. The fume collection hood 510 and the ventilation window 111 of the support frame 110... The air vent 111 is matched with a multiple projection size to ensure that the fume collection hood 510 can completely cover the different ventilation windows 111 corresponding to the cutting area, which greatly reduces the overflow of smoke and dust into the workshop environment, improves the working environment of the cutting station, and overcomes the problems of scattered smoke and dust and poor dust removal effect of traditional plasma cutting. This device does not require a dense array of lifting baffles to be set under the plasma cutting equipment. The overall structure is compact and convenient, and can be moved to any cutting position to complete the quick and effective shielding and sealing, ensuring the high efficiency and stability of negative pressure suction.
[0042] After plasma cutting is completed in this area, the control flue gas collection hood 510 is lowered as a whole and moved towards the next cutting area to achieve continuous cutting of other areas and negative pressure suction of flue gas. This meets the requirements for continuous cutting of sheet steel while minimizing the spread of flue gas from the bottom and improving the surrounding working environment.
[0043] Furthermore, a first slag discharge port 540 is provided on the side wall of the flue gas collection hood 510. The first slag discharge port 540 is also provided with a shielding structure inside. During the process of negative pressure suction of dust, the shielding structure controls the closure of the first slag discharge port 540 to ensure that the inside of the flue gas collection hood 510 is in a relatively closed area, so as to improve the effect of negative pressure suction and prevent flue gas from overflowing. After repeatedly bearing the iron filings or partial fragments cut off, the shielding structure is opened to discharge the waste inside the flue gas collection hood 510 to avoid internal blockage and realize multiple cycle cutting processes.
[0044] A first slag discharge port 540 with a shielding structure is set on the side wall of the flue gas collection hood 510. During the negative pressure suction operation, the shielding structure closes the first slag discharge port 540 to ensure the sealing of the internal chamber of the flue gas collection hood 510, prevent air leakage from the slag discharge port from causing negative pressure attenuation, and ensure the efficiency of flue gas suction. When a lot of cutting iron filings and fragments of waste accumulate inside the flue gas collection hood 510, the shielding structure can be opened to discharge the internal waste, preventing the waste from accumulating and clogging the chamber and flow channel. The equipment does not need to be frequently stopped for disassembly and cleaning, and multiple continuous cyclic cutting operations can be achieved, improving the continuity of the whole machine operation.
[0045] Specifically, the shielding structure includes a screening device 700, with a predetermined height between the first slag discharge port 540 and the bottom of the flue gas collection hood 510 for accommodating buffer sand. The screening device 700 includes a screening box 710 with a screening port 731 formed at the bottom, and a second slag discharge port 740 opened on the side wall of the screening box 710. The negative pressure suction device 600 includes a control air rod 610 for controlling the lifting and moving of the screening box 710.
[0046] The first slag discharge port 540 is located on the moving path of the second slag discharge port 740. During the slag discharge process, the second slag discharge port 740 is controlled to move upward and overlap with the first slag discharge port 540. At this time, the waste material screened at the bottom of the screening box 710 can be removed. During negative pressure suction, the screening box 710 is controlled to descend, squeeze the buffer sand and pass through the buffer sand. At this time, the side wall of the screening box 710 blocks the first slag discharge port 540 to achieve relative sealing. At the same time, the bottom of the screening box 710 is covered by the buffer sand. At this time, the bottom of the screening box 710 can be protected by the buffer sand to prevent the high-temperature molten material from falling and sticking to the upper surface of the screening box 710 to avoid high-temperature damage.
[0047] The side wall of the screening device 700 is used as a shielding structure for the first slag discharge port 540. The bottom of the flue gas collection hood 510 and the first slag discharge port 540 are reserved to hold buffer sand. Under negative pressure suction, the control rod 610 drives the screening box 710 to descend and squeeze and bury the buffer sand. The side wall of the screening box 710 seals the first slag discharge port 540 to ensure the chamber is sealed. At the same time, the buffer sand covers the bottom of the screening box 710 to prevent the high-temperature molten cutting slag from directly contacting the screening box 710 and avoid the high-temperature molten material from sticking, burning and damaging the screening box 710. During the slag discharge, the screening box 710 is raised so that the second slag discharge port 740 overlaps with the first slag discharge port 540, so that the waste slag screened in the screening box 710 can be discharged outward. One structure realizes multiple functions of slag discharge port sealing, high temperature protection and waste slag screening and discharge at the same time, simplifying the number of parts of the whole machine.
[0048] Specifically, the bottom of the screening box 710 includes a plurality of screening sections 730 arranged at intervals, and a screening port 731 is formed between two adjacent screening sections 730; the screening section 730 can be selected as a strip-shaped or columnar structure.
[0049] The bottom of the screening box 710 is composed of multiple sets of spaced strip or columnar screening sections 730, with screening openings 731 formed between the screening sections 730. The waste residue generated from cutting falls onto the screening box 710. Smaller waste residue can fall into the buffer sand area below through the screening openings 731, while larger cutting fragments are intercepted and retained inside the screening box 710, achieving waste residue classification and screening. Fine waste residue falls into the buffer sand, reducing the direct impact and damage from large fragments, facilitating the later centralized discharge of large pieces of waste residue, and reducing the frequency of slag discharge.
[0050] Specifically, the negative pressure suction device 600 also includes a first suction component 620 and a second suction component 630 connected to the control air rod 610. The other side of the second suction component 630 is connected to the interior of the screening box 710, and the other side of the first suction component 620 is connected to a negative pressure device.
[0051] The negative pressure suction device 600 is equipped with a first suction component 620 and a second suction component 630. The first suction component 620 is connected to a negative pressure device, and the control air rod 610 is connected to the first suction component 620. The second suction component 630 is connected to the inside of the screening box 710. The flue gas in the screening box 710 passes through the second suction component 630, the control air rod 610 and the first suction component 620 in sequence and is finally extracted and collected.
[0052] Furthermore, multiple air jets are provided on the side wall of the screening section 730, and the air jets are connected to a cold source pump mechanism. The cold source pump mechanism can spray cooling gas through the multiple air jets. The sprayed cooling gas can cool and protect the buffer sand and the bottom of the screening box 710, and accelerate the solidification of the molten material. On the other hand, it can also form a circulating airflow with the negative pressure suction to form a highly efficient negative pressure suction effect. Preferably, the other side of the second suction component 630 is connected inside the buffer sand, and an interception structure is provided at the end of the second suction component 630 to prevent the buffer sand from being sucked in during negative pressure suction. At this time, the buffer sand can act as a filter material.
[0053] A first negative pressure suction port 530 is opened on the side wall of the flue gas collection hood 510, and a second negative pressure suction port 720 is opened on the side wall of the screening box 710. After the screening box 710 is lowered, the second negative pressure suction port 720 and the first negative pressure suction port 530 overlap, realizing the overlap of the flue gas negative pressure suction window.
[0054] The side wall of the screening section 730 is equipped with air jets, and the external cold source pump mechanism sprays out cooling gas. On the one hand, it forces the bottom of the screening box 710 and the buffer sand to accelerate the rapid solidification of the molten cutting slag and reduce the probability of high-temperature molten slag adhesion. On the other hand, the air jet cooling airflow and the negative pressure suction form a convection circulation, which enhances the dust entrainment suction effect. The second suction component 630 is connected to the inside of the buffer sand and is equipped with an interception structure. The buffer sand acts as a filter medium, which can block iron filings and waste from entering the suction pipeline, prevent pipeline wear and blockage, and protect the downstream negative pressure equipment.
[0055] Specifically, the control rod 610 includes a control sleeve 611, inside which a control piston 612 is sealed and slides. A control rod 613 is fixed to the side wall of the control piston 612. The end of the control rod 613 passes through the flue gas collection hood 510 and is connected to the bottom of the screening box 710. A pumping pipe 800 is embedded inside the control rod 613 and communicates with multiple air jets. The control piston 612 can separate the negative pressure suction part and the cold source pumping part, so that the two will not affect each other. At the same time, the two can be adjusted simultaneously to adjust the extension and retraction of the control rod 610, thereby controlling the lifting and lowering movement of the screening box 710. The screening box 710 can be controlled to vibrate pulses during the rising and falling process to achieve more efficient screening and squeezing descent.
[0056] The control rod 610 adopts a piston-sleeve structure consisting of a control sleeve 611, a control piston 612, and a control rod 613. The control piston 612 separates the inner cavity of the sleeve, achieving mutual isolation between the negative pressure suction air path and the cold source pump air path, preventing cross-contamination between the two media. The control rod 613 integrates a pump air pipe 800 to supply air to the jet nozzle, resulting in a high degree of structural integration. The screening box 710 can be raised and lowered through air path adjustment, and pulse vibration can also be achieved by controlling the airflow pulse impact. The pulse vibration of the screening box 710 is beneficial for the shaking and screening of waste residue, making it easier for waste residue to pass through the screening port 731 and improving screening efficiency.
[0057] Furthermore, two control air rods 610 are arranged at intervals. The first suction assembly 620 includes a first suction end 622 and a second suction end 624, which are respectively connected to the two control air rods 610. The two control air rods 610 can be more stably connected to the bottom of the screening box 710 to ensure its stable lifting and lowering movement. The bottom of the screening box 710 is set in an inclined state. At the same time, there can be a certain gap between the screening box 710 and the inner wall of the flue gas collection hood 510. By alternately controlling the two control air rods 610 to vibrate and extend during the lifting and lowering process, the vibration discharge of solidified waste at the top of the screening box 710 can be accelerated.
[0058] The top of the control rod 610 and the bottom of the screening box 710 can be connected by a flexible sealed joint to ensure that the screening box 710 and the control rod 610 can move synchronously and also vibrate pulses.
[0059] Two sets of spaced-apart control rods 610 jointly support the bottom of the screening box 710, ensuring balanced lifting force and smoother operation. The bottom of the screening box 710 has an inclined structure, which helps the waste residue to converge to one side. A gap is reserved between the screening box 710 and the inner wall of the flue gas collection hood 510. The two sets of control rods 610 are alternately driven to vibrate and extend, causing the screening box 710 to swing back and forth slightly. This vibration causes the solidified waste residue on the box to fall off, accelerating the discharge of waste residue and reducing the accumulation and blockage of waste residue.
[0060] Specifically, the first suction assembly 620 also includes a main negative pressure pipe 621, and a three-way connector is formed between the main negative pressure pipe 621 and the first suction end 622 and the second suction end 624. An electrically controlled three-way valve 623 is provided in the three-way connector. By controlling the valve core of the electrically controlled three-way valve 623 to rotate, the two control rods 610 can be alternately or simultaneously controlled to be in the conducting state.
[0061] The first suction assembly 620 is equipped with a total negative pressure pipeline 621, which is connected to the first suction end 622 and the second suction end 624 of the two control air rods 610 through a three-way connector. The three-way connector is equipped with an electrically controlled three-way valve 623. By switching the valve core of the electrically controlled three-way valve 623, single-path conduction or simultaneous conduction of both paths can be realized, flexibly switching the negative pressure working state of the two sets of control air rods, adapting to different working conditions such as static, unilateral vibration, and synchronous lifting of the screening box 710, and the negative pressure supply following the action mode is flexibly adjustable.
[0062] The invention will be further explained below with reference to specific plasma cutting processes.
[0063] See attached document Figure 9 The plasma cutting process for building steel, using the plasma cutting equipment for building steel according to any one of claims 1-9, includes the following steps:
[0064] S1. Lay the plate-shaped steel flat on the upper surface of the support frame 110; ensure that the plate-shaped steel is in a relatively flat state on the upper surface of the support frame 110.
[0065] S2. After the flue gas collection device 500 is moved to a position below the cutting position, the flue gas collection device 500 is lifted to a predetermined height, and the upper surface of the flue gas collection device 500 is brought into contact with the outer periphery of the cutting position on the lower surface of the plate-shaped material; at this time, a relatively closed flue gas collection chamber is formed inside the flue gas collection device 500.
[0066] S3. Simultaneously with plasma cutting, the negative pressure suction device 600 is activated to continuously and directionally draw and concentrate the fumes generated during plasma cutting, preventing a large amount of fumes from escaping outwards from the bottom during the cutting process.
[0067] Using the aforementioned equipment for plasma cutting of building steel, after the sheet metal is loaded and positioned, the fume collection device is first moved below the cutting position and then raised to press against the lower surface of the sheet metal to establish a locally sealed collection chamber. The negative pressure suction is activated simultaneously with the cutting. The process is simple, and the fume collection chamber is aligned synchronously with the cutting point, ensuring that dust is extracted in a sealed manner wherever cutting is performed. This avoids large-scale dust removal across the entire workstation, resulting in lower dust removal energy consumption, higher fume collection efficiency, and effectively reducing the outward diffusion of plasma cutting fumes. This improves the workshop working environment and is suitable for batch cutting production of building steel sheets.
[0068] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.
Claims
1. A plasma cutting device for building steel, comprising a support base (100), wherein a support frame (110) for placing plate-shaped steel is provided on the upper end of the support base (100), the support frame (110) being a mesh structure with multiple ventilation windows (111) inside, characterized in that: The lower end of the support frame (110) is also provided with a flue gas collection device (500) with an open top and closed bottom, and the flue gas collection device (500) is connected to a negative pressure suction device (600); the flue gas collection device (500) includes a flue gas collection hood (510), and the side wall of the flue gas collection hood (510) has a plurality of strip-shaped notches (520) that pass through the mesh support frame (110). The length and width of the horizontal projection surfaces of the multiple ventilation windows (111) are the same. The length of the horizontal projection surface of the flue gas collection hood (510) is a multiple of the length of the horizontal projection surface of the ventilation window (111), and the width of the horizontal projection surface of the flue gas collection hood (510) is a multiple of the width of the horizontal projection surface of the ventilation window (111). Below the support frame (110) is a second drive assembly (400) for controlling the horizontal and vertical movement of the flue gas collection device (500).
2. The apparatus according to claim 1, wherein The side wall of the flue gas collection hood (510) is also provided with a first slag discharge port (540), and the first slag discharge port (540) is also provided with a shielding structure inside.
3. The plasma cutting equipment for building steel according to claim 2, characterized in that, The shielding structure includes a screening device (700), with a predetermined height between the first slag discharge port (540) and the bottom of the flue gas collection hood (510) for accommodating buffer sand. The screening device (700) includes a screening box (710) with a screening port (731) formed at the bottom. The screening box (710) has a second slag discharge port (740) on its side wall. The negative pressure suction device (600) includes a control rod (610) for controlling the lifting and lowering movement of the screening box (710).
4. The plasma cutting equipment for building steel according to claim 3, characterized in that, The bottom of the screening box (710) includes a plurality of screening sections (730) arranged at intervals, and a screening port (731) is formed between two adjacent screening sections (730).
5. The plasma cutting equipment for building steel according to claim 4, characterized in that, The negative pressure suction device (600) further includes a first suction component (620) and a second suction component (630) connected to the control air rod (610). The other side of the second suction component (630) is connected to the interior of the screening box (710), and the other side of the first suction component (620) is connected to a negative pressure device.
6. The plasma cutting equipment for building steel according to claim 5, characterized in that, The side wall of the screening section (730) has multiple air jets, and the air jets are connected to a cold source pump mechanism.
7. The plasma cutting equipment for building steel according to claim 6, characterized in that, The control rod (610) includes a control sleeve (611), inside which a control piston (612) is sealed and slidable. A control rod (613) is fixed to the side wall of the control piston (612). The end of the control rod (613) passes through the flue gas collection hood (510) and is connected to the bottom of the screening box (710). A pumping pipe (800) is embedded inside the control rod (613) and communicates with multiple air jets.
8. The plasma cutting equipment for building steel according to claim 5, characterized in that, The control air rods (610) are arranged in two spaced intervals. The first suction assembly (620) includes a first suction end (622) and a second suction end (624) which are respectively connected to the two control air rods (610).
9. The plasma cutting equipment for building steel according to claim 8, characterized in that, The first suction assembly (620) further includes a main negative pressure pipe (621), and a three-way connector is formed between the main negative pressure pipe (621) and the first suction end (622) and the second suction end (624), and an electrically controlled three-way valve (623) is provided in the three-way connector.
10. A plasma cutting process for architectural steel, characterized in that, Using the plasma cutting equipment for building steel according to any one of claims 1-9 includes the following steps: S1. Lay the plate-shaped steel flat on the upper surface of the support frame (110); S2. After the flue gas collection device (500) is moved to a position below the cutting position, the flue gas collection device (500) is lifted to a predetermined height, and the upper surface of the flue gas collection device (500) is pressed against the outer periphery of the cutting position on the lower surface of the plate-shaped plate. S3. Simultaneously with plasma cutting, the negative pressure suction device (600) is activated to continuously and directionally suction and concentrate the smoke and dust generated by plasma cutting.
Citation Information
Patent Citations
Plasma cutting device with sectional cleaning lathe
CN114603242A