A Dynamic Wireless Power Supply and Vehicle Speed ​​Joint Optimization Method and System Based on Vehicle-Network Cooperation

By using a vehicle-grid collaborative dynamic wireless power supply and vehicle speed joint optimization method, the vehicle speed and charging power are adjusted in real time, solving the problems of microgrid overload and charging target failure caused by uncontrollable vehicle speed in dynamic wireless power supply of electric vehicles, and achieving efficient energy utilization and system reliability.

CN123104435APending Publication Date: 2026-11-17HEBEI UNIV OF TECH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611464878.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-20
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

In existing dynamic wireless power supply technologies for electric vehicles, the instantaneous high-power load impact caused by the uncontrollable vehicle speed leads to microgrid overload, failure to achieve charging targets, and low energy utilization efficiency. Furthermore, existing systems lack the ability to actively intervene in the vehicle's motion status.

Method used

By establishing a dynamic wireless power supply and vehicle speed joint optimization method for vehicle-network collaboration, and using model predictive control algorithms, the vehicle speed and coil charging power are actively adjusted in real time. This establishes a combination of vehicle longitudinal dynamic characteristics and macroscopic power scheduling of the roadside microgrid, achieving two-way information interaction closed-loop control.

Benefits of technology

It effectively reduces instantaneous power peaks, improves energy utilization and control robustness, reduces infrastructure investment and operation and maintenance costs, and ensures the completion rate of charging tasks and the reliability of the system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123104435A_ABST
    Figure CN123104435A_ABST
Patent Text Reader

Abstract

This application relates to the field of dynamic wireless power supply and vehicle-grid cooperative control for electric vehicles. It provides a method and system for joint optimization of dynamic wireless power supply and vehicle speed based on vehicle-grid cooperation, including: acquiring vehicle position, speed, state of charge (SOC), target SOC, dynamic parameters, remaining safety capacity of the microgrid, and comprehensive time delay; constructing a cross-domain predictive model using coil transmit power and suggested cruising speed as joint decision variables; and employing model predictive control to solve for the power and speed sequences under constraints of microgrid capacity, road speed limit, vehicle speed change rate, coil output, and battery receive power; issuing the first control cycle command to the roadside inverter and vehicle actuators respectively, and performing position feedforward compensation based on the comprehensive time delay; and updating the model based on measured load, position, vehicle speed, and SOC. This scheme reduces instantaneous power peaks and improves energy utilization and control robustness through coordinated regulation of power receiving time, traction energy consumption, and microgrid load.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application belongs to the field of dynamic wireless power supply and vehicle-to-grid cooperative control technology for electric vehicles, and particularly relates to a method and system for dynamic wireless power supply and vehicle speed joint optimization based on vehicle-to-grid cooperation. Background Technology

[0002] In the current field of dynamic wireless power supply technology for electric vehicles on highways, existing microgrid energy management and charging scheduling strategies generally adopt a unidirectional, passive power allocation mode. When formulating charging plans, existing roadside control units only calculate the expected dwell time of vehicles on the receiving coil based on their current fixed speed, and then statically or heuristically allocate power in a single electrical dimension. In this control mode, traffic flow status and vehicle speed are treated as exogenous and uncontrollable predetermined parameters. This is because existing technologies, at their underlying architecture, sever the intrinsic connection between the traffic physical domain and the roadside electrical domain, failing to establish a two-way collaborative information loop between vehicles and the network. This results in a lack of proactive intervention capability for vehicle motion status, forcing the system to mechanically and passively adapt to real-time changes in traffic flow, leading to a series of insurmountable technical bottlenecks and application pain points.

[0003] This passive adaptive control logic first and foremost threatens the infrastructure construction and safe, stable operation of roadside microgrids, leading to high overall construction and operating costs. Particularly for large commercial vehicles like heavy trucks with high-capacity batteries and high-power traction requirements, the energizing time for the vehicle chassis across a single section of the coil is extremely short when cruising at high speeds on highways. To charge the massive amount of electricity required for long-distance driving within this extremely short window, the roadside microgrid must instantly inject a sharp, instantaneous surge of power into the transmitting coil. This short-term, extremely high load surge, passively triggered by uncontrollable vehicle speed, easily leads to overload of local distribution transformers. The reason for this is that current technology, in order to smooth out these drastic peak-valley fluctuations, can only adopt a compromise solution of increasing hardware redundancy, namely, constructing large-capacity distribution transformers and extremely expensive fixed energy storage battery arrays along the road for passive peak shaving. This not only causes the initial investment in electrified highways to increase exponentially but also brings enormous operating losses and degradation maintenance costs for energy storage batteries.

[0004] Meanwhile, the aforementioned unidirectional passive scheduling mode often leads to vehicles failing to meet their final charging expectations under real-world conditions such as limited microgrid capacity or dense traffic flow, severely weakening the service reliability of the dynamic power supply system. In practical engineering applications, the total output capacity of roadside microgrids and grid-connected inverters has a strict physical upper limit. When multiple high-energy-consuming electric vehicles are simultaneously in the charging zone, causing the theoretical peak power requests of the system to exceed the microgrid's safe capacity limit, existing technologies, in order to ensure that the grid does not collapse, can only be forced to unilaterally adopt a degraded protection strategy that drastically reduces the allocated power or even temporarily interrupts the power supply to some vehicles. The core reason for the serious failure to receive power is that the existing system lacks time-dimensional control measures. While the system implements power current limiting, the vehicle continues to travel at its original high speed and quickly leaves the road segment, and its effective power receiving time window is not compensated or extended in any way. This passive situation of short time and low power directly results in the net charge received by the vehicle's battery being seriously insufficient when the vehicle leaves the power supply zone, completely failing to alleviate range anxiety for long-distance driving.

[0005] Furthermore, existing technologies suffer from severe physical blind spots in energy utilization efficiency, resulting in significant energy waste at the source. This is an inherent flaw of existing one-way scheduling mechanisms. Current control algorithms focus purely on the mathematical allocation of electricity and the optimization of microgrid-side economic efficiency, completely ignoring the nonlinear characteristics of the vehicle's own physical energy consumption. According to vehicle aerodynamics, during high-speed driving, the mechanical traction power required to overcome wind resistance exhibits a nonlinear, exponentially increasing relationship with the cube of the vehicle's speed. In high-speed charging scenarios without intervention from existing technologies, a large amount of precious energy emitted by the microgrid is actually used instantaneously to counteract the vehicle's extremely high air resistance, significantly reducing the effective energy storage ratio of the battery after deducting transient driving energy consumption. This scheduling method, which ignores traffic dynamics, completely misses the enormous energy-saving potential of exponentially reducing instantaneous traction load at the source by fine-tuning vehicle cruising speed. This results in the net energy conversion efficiency of the entire dynamic charging system remaining inefficient for a long time, failing to achieve comprehensive energy efficiency optimization at both the vehicle and grid ends. Summary of the Invention

[0006] In view of this, this application aims to propose a dynamic wireless power supply and vehicle speed joint optimization method and system based on vehicle-grid cooperation, in order to address the problems of high microgrid load peaks, unfulfilled charging targets, and low overall energy conversion efficiency caused by passive adaptation to traffic flow in existing dynamic wireless power supply systems.

[0007] To achieve the above objectives, the technical solution of this application is implemented as follows: Firstly, this application provides a method for joint optimization of dynamic wireless power supply and vehicle speed based on vehicle-to-grid cooperation, including: The system acquires the real-time location, speed, and state of charge of target vehicles entering the dynamic wireless power supply zone, as well as the remaining safe capacity of the roadside microgrid and the overall system-level latency. Using the state of charge and vehicle speed as state variables, and the coil transmission power and suggested cruising speed as joint decision variables, a vehicle-to-grid cross-domain spatiotemporal coupling prediction model is established to simultaneously characterize vehicle traction energy consumption and wireless power replenishment. The vehicle's mechanical traction power is determined based on the suggested cruising speed, and the vehicle's state of charge is predicted based on the coil transmission power, wireless power supply transmission efficiency, and the mechanical traction power. In the prediction time domain, a multi-objective cost function is constructed using microgrid operating costs and peak load penalties, vehicle traffic delay penalties, and terminal charging target mandatory constraint penalties. The weights of each penalty term are adjusted according to the real-time load rate of the microgrid. Under the constraints of microgrid capacity, road vehicle speed and speed change rate, transmitter power and vehicle receiver power, the coil transmitter power sequence and the suggested cruise speed sequence are solved in a rolling manner. Extract the coil transmission power command and suggested cruise speed command of the first control cycle, control the roadside transmitting coil and the vehicle longitudinal speed actuator respectively, and perform feedforward compensation on the effective position of the suggested cruise speed command based on the system-level integrated time delay; The actual load of the microgrid, the actual location of the vehicle, the actual vehicle speed, and the measured state of charge are collected and the prediction model is updated before entering the next control cycle.

[0008] Secondly, based on the same inventive concept, this application also provides a dynamic wireless power supply and vehicle speed joint optimization system based on vehicle-to-grid collaboration, including a state perception module, a cross-domain prediction module, a rolling optimization module, an instruction execution module, and a feedback update module. The state perception module is used to acquire the vehicle state, target departure charge state and vehicle dynamic parameters of the target vehicle, acquire the remaining available safety capacity of the roadside microgrid, and determine the comprehensive time delay from the roadside to the vehicle actuator. The cross-domain prediction module is used to establish a vehicle-to-grid cross-domain prediction model with coil transmission power and suggested cruising speed as joint decision variables. The rolling optimization module is used to solve the coil transmit power sequence and the suggested cruising speed sequence on a rolling basis, under the constraints of microgrid capacity, road traffic and wireless power supply hardware, based on microgrid operating cost and peak load penalty, vehicle traffic delay penalty and terminal charging target mandatory constraint penalty. The instruction execution module is used to send the coil transmission power instruction and the suggested cruise speed instruction of the first control cycle to the roadside electrical execution side and the vehicle traffic execution side respectively, and to perform position feedforward compensation based on the comprehensive time delay; The feedback update module is used to update the vehicle-grid cross-domain prediction model using the actual load of the microgrid, the actual location of the vehicle, the actual vehicle speed, and the latest state of charge.

[0009] Compared with existing technologies, the dynamic wireless power supply and vehicle speed joint optimization method and system based on vehicle-to-grid cooperation described in this application have the following advantages: This application breaks through the limitations of static allocation only in the power dimension. It establishes a two-way information interaction closed loop between vehicles and the network based on the vehicle-to-everything (V2X) communication network, deeply combining the microscopic longitudinal dynamic characteristics of vehicles with the macroscopic power scheduling of roadside microgrids. It adopts the model predictive control (MPC) algorithm to achieve real-time and proactive joint closed-loop control of vehicle speed and coil charging power in the spatiotemporal domain. Through the coordinated regulation of power receiving time, traction energy consumption and microgrid load, it reduces instantaneous power peaks and improves energy utilization and control robustness. Attached Figure Description

[0010] The accompanying drawings, which form part of this application, are used to provide a further understanding of this application. The illustrative embodiments and descriptions of this application are used to explain this application and do not constitute an undue limitation of this application. In the drawings: Figure 1 This is a flowchart of a dynamic wireless power supply and vehicle speed joint optimization method based on vehicle-to-grid cooperation, as described in an embodiment of this application. Figure 2 This is a block diagram illustrating the principle of vehicle-network joint spatiotemporal coupling and closed-loop feedback control based on model predictive control as described in the embodiments of this application. Figure 3 This is a schematic diagram comparing the time series effects of the existing unidirectional passive power allocation method and the active joint optimization method of the present invention as described in the embodiments of this application; Figure 4 This is a block diagram of a dynamic wireless power supply and vehicle speed joint optimization system based on vehicle-to-grid cooperation, as described in an embodiment of this application. Figure 5 This is a schematic diagram of the overall architecture and information and energy interaction relationship of the highway dynamic wireless power supply system for vehicle-to-grid cooperation as described in the embodiments of this application. Detailed Implementation

[0011] To make the objectives, technical solutions, and advantages of this application clearer, the following detailed description is provided in conjunction with specific embodiments and the accompanying drawings.

[0012] It should be noted that, unless otherwise defined, the technical or scientific terms used in the embodiments of this application should have the ordinary meaning understood by one of ordinary skill in the art to which this application pertains. The terms "first," "second," and similar terms used in the embodiments of this application do not indicate any order, quantity, or importance, but are merely used to distinguish different components. Terms such as "comprising" or "including" mean that the element or object preceding the word encompasses the elements or objects listed after the word and their equivalents, without excluding other elements or objects. Terms such as "connected" or "linked" are not limited to physical or mechanical connections, but can include electrical connections, whether direct or indirect. Terms such as "upper," "lower," "left," and "right" are only used to indicate relative positional relationships; when the absolute position of the described object changes, the relative positional relationship may also change accordingly.

[0013] Please see Figure 1 As shown, this embodiment provides a dynamic wireless power supply and vehicle speed joint optimization method based on vehicle-to-grid cooperation, using discrete time steps. To control the cycle, the following steps are executed sequentially: Step S10: Obtain the real-time location, speed, state of charge, and target state of charge of the target vehicle entering the dynamic wireless power supply section, and obtain the remaining safe capacity of the roadside microgrid and the system-level comprehensive latency.

[0014] Specifically, in this embodiment, this step mainly performs real-time perception and synchronization of multi-source state information. When the target vehicle approaches the dynamic wireless power supply preparation area, the roadside edge computing server establishes a wireless connection with the vehicle's OBU through the RSU, and collects and synchronizes cross-domain state data in real time: ① Vehicle-side operating parameters: including the vehicle's current precise position coordinates and initial entry speed. The current state of charge of the vehicle's battery as reported by the BMS. The driver sets a target to leave the state of charge. Vehicle curb weight Windward area drag coefficient and rolling resistance coefficient .

[0015] ② Microgrid-side boundary parameters: Obtain the upper limit of the remaining available safe capacity of the roadside microgrid distribution transformers within the current control cycle. And real-time time-of-use electricity price data.

[0016] ③ Cross-domain communication and execution latency parameters: The system calibrates in real time and obtains the estimated system-level comprehensive latency between the edge computing system (MEC) and the vehicle chassis actuators. (This parameter includes V2X air interface transmission latency, edge computing command parsing latency, and vehicle chassis mechanical response hysteresis.)

[0017] This embodiment addresses the specific implementation mechanism for comprehensive latency: System-level overall latency is determined by dynamic network communication latency. Compared with static chassis mechanical lag The system consists of two superimposed parts, and performs real-time calibration and updates within the control cycle according to the following sub-steps: Step S101: Dynamic network latency calculation based on high-precision time synchronization.

[0018] The edge computing server (MEC) and the on-board unit (OBU) maintain microsecond-level clock synchronization using the IEEE 1588 Precision Time Protocol (PTP). At the start of each control cycle, the MEC sends a data transmission carrying an absolute timestamp. The heartbeat detection packet is received and parsed by the OBU, which immediately generates a data entry packet carrying the receiving timestamp. The edge computing server uses the response packet to calculate the dynamic total network latency for one-way air interface transmission and command parsing. .

[0019] Step S102: Static mechanical hysteresis matching based on cloud-based digital twin library.

[0020] Because the mechanical and physical response speeds of the chassis brake-by-wire and drive systems of intelligent electric vehicles of different brands and tonnages vary greatly, the edge computing server queries a pre-stored local or cloud-based vehicle chassis response calibration database (Look-Up Table) based on the unique vehicle identification number (VehicleID) and vehicle curb weight (m) reported by the OBU during connection establishment to obtain the specific vehicle model's response speed at the current vehicle speed. Inherent mechanical response hysteresis calibration value under mapping .

[0021] Step S103: Digital filtering and updating of the overall time delay.

[0022] To eliminate random network jitter interference in V2X wireless communication environments, the edge computing server uses an Exponential Moving Average (EMA) filtering algorithm to calculate the final comprehensive latency estimate. Its discrete update iterative formula is as follows: In the formula, For the current number The estimated comprehensive latency for each cycle; This is the smoothed value from the previous period; The set filter update weight coefficient (typically ranging from 0.1 to 0.3) is used to balance the system's sensitivity to network burst delays and its noise smoothness.

[0023] Step S20: Using the state of charge and vehicle speed as state variables, and the coil transmission power and suggested cruising speed as joint decision variables, establish a vehicle-to-grid cross-domain spatiotemporal coupling prediction model that simultaneously characterizes vehicle traction energy consumption and wireless power replenishment. The vehicle's mechanical traction power is determined based on the suggested cruising speed, and the vehicle's state of charge is predicted based on the coil transmission power, wireless power supply transmission efficiency, and mechanical traction power.

[0024] Specifically, in this embodiment, this step mainly involves constructing a vehicle-to-grid cross-domain spatiotemporal coupling dynamic prediction model. In the roadside edge computing server, a discrete state-space prediction model is established that includes both mechanical traction energy consumption and electrical energy transmission replenishment processes. This specifically includes the following: Define the vehicle in the The state variable matrix at each time step is: The joint decision control variable matrix is ​​as follows: .in, The instantaneous electromagnetic emission power allocated by the system to the coil of the corresponding road segment. This refers to the recommended cruising speed issued by the system to the vehicle.

[0025] The mechanical traction power required for a vehicle to overcome air resistance and mechanical friction during operation exhibits a non-linear, exponential relationship with vehicle speed. In the... Within each discrete control cycle, the total mechanical traction power is denoted as: To achieve proactive prediction of future energy consumption in Model Predictive Control (MPC), this embodiment adopts the ideal speed following assumption, which assumes that the vehicle actuators can accurately track the control commands issued by the system, and replaces the actual vehicle speed with the system's recommended cruising speed. The purpose of this replacement is to establish an explicit mapping between expected energy consumption and system decision control variables, thereby allowing the joint optimization algorithm to be fine-tuned. To regulate traction energy consumption. Its discrete dynamic equations are constructed as follows: ; In the formula, Indicates the first Within each control cycle, the expected mechanical traction power of the vehicle is predicted based on the suggested cruise speed issued by the system. Indicates the first Within each control cycle, the system solves for and issues the suggested cruise speed to the vehicle (i.e., the traffic domain control variable of this joint optimization architecture). Indicates the efficiency of the vehicle's powertrain system; Indicates the current air density in the environment; This represents the vehicle's aerodynamic drag coefficient; Indicates the vehicle's effective frontal area; Indicates the vehicle's curb weight; Represents gravitational acceleration; This represents the tire rolling resistance coefficient; This indicates the constant load power of the vehicle's auxiliary electrical system.

[0026] Based on the law of conservation of energy, a discrete dynamic equation for the net charge capacity of the vehicle's power battery is constructed: ; In the formula, To improve the overall transmission efficiency of the dynamic wireless charging system, This refers to the rated total capacity of the vehicle's power battery.

[0027] This application deeply integrates dynamic energy consumption laws, stimulating a dual energy-saving effect and achieving a significant leap in the overall energy conversion efficiency of the system. Addressing the issue that existing control algorithms neglect the nonlinear, exponential relationship between the mechanical traction power required to overcome air resistance and the cube of vehicle speed, leading to a significant amount of grid-transmitted energy being preferentially consumed in the blind spot of resisting high-speed wind resistance, this application embeds a vehicle dynamic energy consumption equation incorporating aerodynamic characteristics into the system's joint scheduling kernel. The system's proactively issued moderate speed reduction command not only provides the vehicle with a longer charging window but also reduces the transient mechanical traction energy consumption required to maintain the vehicle's current cruising state at its source. Under this dual effect, the electromagnetic energy emitted by the roadside coils is no longer largely consumed by the vehicle's massive instantaneous driving load but is instead converted into a higher proportion of net energy storage in the onboard battery. This method breaks through the energy efficiency bottleneck of pure electric dispatching, achieving global comprehensive energy efficiency optimization at both ends of the roadside power supply network and the transportation network.

[0028] Step S30: In the prediction time domain, a multi-objective cost function is constructed using the microgrid operating cost and peak load penalty, vehicle traffic delay penalty, and terminal charging target mandatory constraint penalty. The weights of each penalty are adjusted according to the real-time load rate of the microgrid. Under the constraints of microgrid capacity, road vehicle speed and speed change rate, transmitter power and vehicle receiver power, the coil transmitter power sequence and the suggested cruise speed sequence are solved in a rolling manner.

[0029] Specifically, in this embodiment, this step mainly performs online rolling optimization based on model predictive control (MPC), such as... Figure 2 As shown. Within the edge computing server, a finite discrete prediction time domain length is set as... Assume that the total number of controlled target intelligent vehicles entering the power supply section during the current control cycle is... The global optimization objective is to minimize the comprehensive operating cost of the microgrid side and the multi-vehicle delay cost on the traffic side within the predicted time domain. A multi-objective cost function J is constructed as follows: ; In the formula, This represents the absolute discrete time step (i.e., the current moment) at which the system is currently performing real-time control. This represents the prediction step size index in MPC, and its value range is... ; This indicates the number of the controlled vehicle (and its corresponding transmitting coil) currently within the dynamic wireless power supply zone, and its value range is... .

[0030] The roles of each penalty term in the cost function are as follows: The first item is the microgrid operating cost and peak load penalty: To achieve passive peak shaving, the cost function in this scheme uses a specific cost function. It is not the well-known simple linear electricity price function, but rather a convex function constructed with a quadratic penalty function for exceeding the limit. Its calculation formula is as follows: In the formula, This indicates the total power distributed by the microgrid to all coils in this section; This represents the base time-of-use electricity price coefficient; This indicates the set peak shaving warning threshold for power distribution network safety. This represents the nonlinear over-limit penalty factor; When multiple vehicles charge at high power concurrently, causing the total demand to approach or exceed the threshold, the penalty function grows quadratically, thus generating gradient resistance when solving the sequential quadratic programming problem. This forces the system to actively reduce the allocated power or fine-tune the vehicle speed to achieve load shifting.

[0031] The second item is the penalty for traffic delays: This is the expected free-flow speed for this section of road. This parameter is used to constrain the degree to which the controlled speed deviates from the normal traffic speed, preventing traffic congestion behind the vehicle due to excessive speed reduction.

[0032] The third item is a mandatory constraint and penalty for terminal charging targets: clearly defining the vehicle... Expected charge at departure time Achieve the set goal This section uses... The asymmetric one-sided penalty mechanism: a quadratic penalty is incurred only when the final charge level fails to meet the target; if the target is reached on time or overcharged, no penalty is incurred. This applies when the microgrid's extreme current-limiting conditions (i.e., capacity limit) are triggered. When the traffic delay index is significantly reduced, the multi-objective cost function forces the sacrifice of the second term through internal weight game, issues braking command to take advantage of the greatly extended vehicle dwell time window, and performs time integral compensation under limited and extremely low safe power, thereby ensuring that the terminal charging target is met across domains, forming a closed-loop fault tolerance mechanism that trades time for limit power.

[0033] This embodiment is about , , The methods for determining normalized weight coefficients include: Because the three penalty terms in the cost function have different dimensions and numerical magnitudes, direct summation would render the optimization matrix unsolvable. This invention uses a reciprocal normalization method based on extreme values ​​to determine the weights: During system initialization, set the maximum single-step electricity cost that the system can withstand. Maximum tolerance speed variance maximum value Maximum tolerable power gap The actual formula for calculating the normalized weights used in optimization is: , , ; In the formula, , , Dimensionless scenario preference factor (constantly satisfied) To avoid imbalance of static weights under different operating conditions, this application constructs a system based on the real-time load rate of the microgrid. The adaptive piecewise linear allocation rule is used. The current real-time load factor of the microgrid is defined. And set power grid security early warning thresholds. (The typical value for this project is 0.8).

[0034] Conventional power supply conditions ( At this point, the microgrid has ample capacity, and the system prioritizes traffic efficiency and charging targets. The bias factor is set to a fixed constant. , , ; In this embodiment of the invention, the empirical value is... , , In other words, when there is no risk of exceeding the limits on the power grid, only basic economic penalties are retained, with a focus on restricting vehicle speed and power shortages.

[0035] Extreme peak shaving conditions At this point, the microgrid faces overload risk, and the system must forcibly shift its optimization focus, significantly increasing the grid penalty weight to trigger vehicles to actively reduce speed. The tendency factor is linearly and dynamically adjusted based on the depth of load factor exceeding the limit. ; ; ; In the formula, This represents a minimal safety margin to prevent a single weight from tending to 1 and causing matrix singularities; a typical value is 0.05. This linear mapping rule ensures that the microgrid penalizes the weights when the load factor approaches 1.0. It holds an absolute dominant position (approaching 0.95), while traffic delay weighting With charging target weight The speed is compressed proportionally, thus forcing the MPC solver to sacrifice vehicle speed to ensure the safety of the microgrid.

[0036] When solving this optimization problem, the decision control variables must comply with the following boundary constraints: (1) Microgrid capacity safety constraint: The sum of the distributed power of all coils operating on track at any given time must not exceed the safety limit of the distribution network, i.e. ; (2) The suggested cruise speed and its rate of change issued by the system must be subject to both traffic regulations and human physiological limits: ① Absolute speed boundary constraints: It is recommended that the vehicle speed must be within the road speed limit range, i.e. In the formula, This indicates the legal maximum speed limit (e.g., 120 km / h) of the road where the dynamic charging section is located. This indicates the legal minimum speed limit for the road (e.g., 60 km / h). This lower limit is designed to ensure basic traffic efficiency and prevent congestion caused by excessive speed reduction for charging.

[0037] ② Longitudinal Acceleration and Comfort Constraints: Since the system's decision control variable is vehicle speed, this scheme uses the discrete backward difference method to constrain its rate of change (i.e., equivalent longitudinal acceleration), ensuring it remains within the limits of human safety and comfort. Between. Its discrete mathematical constraint equations are: ; In the formula, This represents the set time step of the discrete control cycle; the intermediate fractional term is the expected longitudinal acceleration of the system calculated from the commands of adjacent control cycles; This represents the maximum positive drive acceleration allowed to ensure passenger comfort (based on standard vehicle engineering ergonomic calibration, typically ranging from 1.5 to 2.5 m / s²).2 ; This indicates the maximum permissible negative braking deceleration extreme value of the system (typically ranging from -3.0 to -2.0 m / s²). 2 Using comfort boundaries rather than vehicle chassis limits can effectively prevent occupant dizziness during dynamic speed adjustment.

[0038] (3) Dual constraints on charging and discharging hardware limits: The instantaneous power distribution of a single coil is limited by a dual physical and electrochemical bottleneck between the roadside transmitter and the vehicle-mounted receiver, and must meet the following requirements: ; In the formula, This is the upper limit of the rated maximum output power of a single ground-based dynamic transmitting coil and its associated inverter hardware. For the vehicle's battery management system (BMS) to determine the current battery state of charge The system also considers cell temperature and dynamically feeds back the maximum safe received power. Within an edge computing server, the system uses nonlinear optimization algorithms such as sequential quadratic programming to solve the multi-objective cost function online within the solution space defined by the boundaries of the aforementioned multi-dimensional feasible region. The minimum value of the value is obtained, thus yielding the optimal coil power sequence and the optimal suggested vehicle speed sequence in the future prediction time domain.

[0039] This embodiment significantly improves the charging task completion rate and system service reliability under extreme current-limiting conditions by providing an effective time compensation mechanism. Addressing the pain point of existing unidirectional scheduling mechanisms, which are forced to unilaterally reduce the power allocated to a single vehicle when facing microgrid capacity limits or multiple vehicles charging concurrently, resulting in insufficient effective charging time and severely inadequate actual battery level when vehicles leave, this application's two-dimensional joint control strategy endows the system with proactive compensation capabilities along the time axis. When it is predicted that the system's concurrent load will exceed the safety limit and power current-limiting protection must be implemented, the system will synchronously calculate and guide the restricted vehicles to further reduce their speed. By proactively extending the effective power receiving time under low-power supply conditions, the power supply gap caused by the instantaneous power drop is filled. This cross-domain time compensation mechanism ensures that vehicles can still receive sufficient net charge under conditions of localized power distribution limitations, guaranteeing that they meet the preset target state of charge (SOC) when leaving the dynamic power supply section, effectively alleviating range anxiety during long-distance heavy-load transportation.

[0040] (4) System security degradation constraints under extreme operating conditions: In actual open traffic environments, when a microgrid encounters extreme current limiting leading to a capacity limit The speed dropped sharply, and the vehicle was already at the legal minimum speed limit. When conflicts arise in the multidimensional constraint space, the MPC nonlinear solver may enter a state where no solution is available. At this point, the system triggers a safety degradation control strategy under multidimensional constraint conflicts: the edge computing server temporarily releases the mandatory constraint on the terminal charging SOC target and clamps the inverter output to the minimum sustaining power that meets the microgrid safety margin or executes a zero-power disconnect command to prevent inverter overload or no-load thermal runaway; simultaneously, the edge computing server actively releases the longitudinal speed control authority in the traffic domain and smoothly transfers it to the vehicle-side adaptive cruise control (ACC) active collision avoidance system to ensure that the target vehicle safely leaves the power supply section under the boundary conditions that meet the legal minimum speed limit.

[0041] This embodiment overcomes the limitations of unidirectional power dispatching, achieving passive peak shaving of microgrids through spatiotemporal substitution, significantly reducing infrastructure and operation and maintenance costs. Addressing the shortcomings of existing technologies where high-speed vehicle passage results in extremely short effective power reception time, forcing the microgrid to output extremely high peak power instantaneously, thus relying on large-capacity distribution transformers and expensive fixed energy storage battery arrays for passive peak shaving, this application innovatively introduces a vehicle speed active intervention mechanism. When the system predicts that the total load of the microgrid is approaching the safe capacity limit, it proactively issues a moderately reduced suggested cruising speed to high-energy-consuming vehicles urgently needing charging. This mechanism effectively extends the time window for the vehicle chassis to cross the transmitting coil by reducing speed, allowing the microgrid to charge the vehicle's power battery with the same amount of energy at a lower and smoother instantaneous power. This proactive intervention strategy, trading time for space and vehicle speed for power, fundamentally smooths out power peaks in the microgrid, eliminating the rigid dependence on large-capacity distribution redundancy and expensive roadside energy storage devices, and reducing the initial infrastructure investment and subsequent equipment operation and maintenance costs of electrified highways. A time-series comparison diagram of the effects of existing unidirectional passive power allocation methods and the active joint optimization method of this embodiment is shown below. Figure 3 As shown.

[0042] Step S40: Extract the coil transmission power command and suggested cruise speed command of the first control cycle, control the roadside transmitting coil and the vehicle longitudinal speed actuator respectively, and perform feedforward compensation on the effective position of the suggested cruise speed command based on the system-level integrated time delay.

[0043] Specifically, in this embodiment, this step mainly performs decoupled issuance of cross-domain control commands and anti-delay feedforward synchronization.

[0044] Extract the first control period from the predicted sequence obtained in step S30. The optimal instruction set is decoupled and distributed separately to the actuators in the system's electrical and transportation domains: (1) For the electrical domain execution side: the edge computing server converts the optimal coil transmission power value into a PWM control signal, which is sent to the corresponding roadside high-frequency inverter through the high-speed industrial communication bus to drive the corresponding underground transmission coil to output alternating electromagnetic energy at the planned power threshold; (2) For the traffic domain execution side: Considering the objective time delay between V2X wireless communication and edge computing system operation. If the vehicle executes the command directly at the moment of receiving, it will cause a spatial misalignment and lag between the actual position of the high-speed vehicle and the energy projection area of ​​the underground coil, resulting in undercharging or electromagnetic radiation exceeding the limit.

[0045] To this end, when the edge computing server issues the optimal suggested cruise speed command via the RSU, it simultaneously encapsulates an absolute timestamp. Upon receiving the command, the target vehicle's chassis drive-by-wire module initiates a position feedforward compensation operator based on the vehicle's longitudinal dynamics: combining the vehicle's current real instantaneous speed... and measured longitudinal acceleration Calculate the deviation distance the vehicle has slid during the period from the generation of the instruction to its execution. The module is based on this spatial compensation amount. The timing of torque adjustment for triggering the drive motor is corrected in advance to ensure that the physical trajectory of the vehicle's speed response is perfectly aligned with the electromagnetic activation range of the underground coil in absolute three-dimensional space. Subsequently, if the target vehicle has not activated fully automated driving assistance, the command is converted into a visual / voice interaction signal via the in-vehicle central control screen or HUD head-up display to guide the driver to actively adjust the vehicle speed.

[0046] Step S50: Collect the actual load of the microgrid, the actual location of the vehicle, the actual vehicle speed, and the measured state of charge after execution to update the prediction model and enter the next control cycle.

[0047] Specifically, in this embodiment, this step mainly performs dynamic environmental state observation updates and feedback closed-loop rolling corrections. After the current control cycle ends, the edge computing system re-collects the actual output load of the roadside microgrid and obtains the actual instantaneous speed, actual position, and the latest measured SOC reported by the BMS after the target vehicle performs speed adjustment actions through roadside sensing devices and V2X data feedback.

[0048] The system overwrites the previous prediction value with the latest measured data containing real-world environmental disturbances and inputs it into the prediction model in step S20 as a brand-new initial state of the system. The time window slides forward by one step and triggers step S30 again to start a new round of rolling solution calculation.

[0049] This embodiment constructs a cross-domain information closed-loop feedback and rolling optimization architecture, giving the system strong robustness against dynamic traffic flow disturbances. Addressing the weakness of existing open-loop scheduling plans based on static parameter prediction, which are prone to failure and collapse when encountering occasional disturbances in open roads such as road gradient variations, sudden braking by the vehicle ahead, and sudden changes in wind resistance due to severe weather, this application adopts a model predictive control (MPC) architecture based on bidirectional data feedback. At the end of each extremely short control cycle, the system acquires the actual instantaneous speed, actual position, and latest measured SOC state of the controlled vehicle after encountering a disturbance in real time via the V2X communication network, and uses this objective data containing characteristics of real-world environmental disturbances as the initial state input for the next prediction cycle. This high-frequency sliding correction and closed-loop adjustment mechanism can absorb and eliminate various unforeseen unstructured disturbances in real time, ensuring that the joint control commands maintain high execution accuracy and stability in complex open traffic environments.

[0050] Example 2 like Figure 4 As shown, this embodiment provides a dynamic wireless power supply and vehicle speed joint optimization system based on vehicle-network cooperation, including a state perception module 11, a cross-domain prediction module 12, a rolling optimization module 13, an instruction execution module 14, and a feedback update module 15; Among them, the state perception module 11 is used to obtain the vehicle state, target departure charge state and vehicle dynamic parameters of the target vehicle, obtain the remaining available safety capacity of the roadside microgrid, and determine the comprehensive time delay from the roadside to the vehicle actuator. The cross-domain prediction module 12 is used to establish a vehicle-to-network cross-domain prediction model with coil transmission power and suggested cruising speed as joint decision variables; The rolling optimization module 13 is used to solve the coil transmit power sequence and the suggested cruising speed sequence on a rolling basis, under the constraints of microgrid capacity, road traffic and wireless power supply hardware, based on microgrid operating cost and peak load penalty, vehicle traffic delay penalty and terminal charging target mandatory constraint penalty. The instruction execution module 14 is used to send the coil transmission power instruction and the suggested cruise speed instruction of the first control cycle to the roadside electrical execution side and the vehicle traffic execution side respectively, and to perform position feedforward compensation based on the comprehensive time delay; The feedback update module 15 is used to update the vehicle-grid cross-domain prediction model using the actual load of the microgrid, the actual location of the vehicle, the actual vehicle speed, and the latest state of charge.

[0051] For ease of description, the above system is described by dividing it into various modules based on their functions. Of course, in implementing the embodiments of this application, the functions of each module can be implemented in one or more software and / or hardware.

[0052] The system described in the above embodiments is used to implement the corresponding method in any of the foregoing embodiments and has the beneficial effects of the corresponding method embodiments, which will not be repeated here.

[0053] Furthermore, such as Figure 5 As shown, the joint optimization method described in this embodiment relies on a "vehicle-road-cloud integrated" edge computing hardware platform. This system architecture mainly includes the following entities: (1) Roadside control and power supply system: including roadside edge computing servers (MEC) and roadside communication units (RSU) deployed along the dynamic power supply section of the highway; step-down transformers connected to the roadside power distribution network, multiple sets of high-frequency inverters, and dynamic wireless transmission coil arrays buried under the lanes. The edge computing server serves as the operating platform for the joint optimization algorithm and controls the output power of each inverter through an industrial fieldbus.

[0054] (2) Vehicle terminal subsystem: Intelligent connected electric vehicles entering the power supply section are equipped with a dynamic wireless power receiving coil and rectifier voltage regulation module, an on-board communication unit (OBU) for low-latency communication with the RSU, a battery management system (BMS) for real-time monitoring of battery status, and an adaptive cruise control (ACC) chassis drive module for receiving external speed commands and automatically adjusting the vehicle drive system.

[0055] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, and not to limit them. Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that modifications can still be made to the technical solutions described in the foregoing embodiments, or equivalent substitutions can be made to some or all of the technical features therein. Such modifications or substitutions do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention, and they should all be covered within the scope of the claims and specification of the present invention.

[0056] The embodiments of this application are intended to cover all such substitutions, modifications, and variations that fall within the broad scope of the appended claims. Therefore, any omissions, modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the embodiments of this application should be included within the protection scope of this application.

Claims

1. A dynamic wireless power supply and vehicle speed joint optimization method based on vehicle-to-grid cooperation, characterized in that, include: The system acquires the real-time location, speed, and state of charge of target vehicles entering the dynamic wireless power supply zone, as well as the remaining safe capacity of the roadside microgrid and the overall system-level latency. Using the state of charge and vehicle speed as state variables, and the coil transmission power and suggested cruising speed as joint decision variables, a vehicle-to-grid cross-domain spatiotemporal coupling prediction model is established to simultaneously characterize vehicle traction energy consumption and wireless power replenishment. The vehicle's mechanical traction power is determined based on the suggested cruising speed, and the vehicle's state of charge is predicted based on the coil transmission power, wireless power supply transmission efficiency, and the mechanical traction power. In the prediction time domain, a multi-objective cost function is constructed using microgrid operating costs and peak load penalties, vehicle traffic delay penalties, and terminal charging target mandatory constraint penalties. The weights of each penalty term are adjusted according to the real-time load rate of the microgrid. Under the constraints of microgrid capacity, road vehicle speed and speed change rate, transmitter power and vehicle receiver power, the coil transmitter power sequence and the suggested cruise speed sequence are solved in a rolling manner. Extract the coil transmission power command and suggested cruise speed command of the first control cycle, control the roadside transmitting coil and the vehicle longitudinal speed actuator respectively, and perform feedforward compensation on the effective position of the suggested cruise speed command based on the system-level integrated time delay; The actual load of the microgrid, the actual location of the vehicle, the actual vehicle speed, and the measured state of charge are collected and the prediction model is updated before entering the next control cycle.

2. The method according to claim 1, characterized in that, The system-level integrated latency includes dynamic network communication latency and vehicle chassis mechanical response hysteresis; The dynamic network communication latency is obtained through time synchronization and timestamp interaction between the roadside edge computing server and the vehicle communication unit. The vehicle chassis mechanical response hysteresis is obtained by matching the vehicle identification information, vehicle curb weight and current vehicle speed from the preset vehicle model chassis response calibration database, and the latency after the two are superimposed is filtered and updated using an exponential moving average method.

3. The method according to claim 1, characterized in that, The vehicle-to-network cross-domain spatiotemporal coupling prediction model is constructed according to a discrete control cycle; The vehicle's traction energy consumption is determined based on at least the vehicle's power transmission efficiency, air density, drag coefficient, frontal area, vehicle curb weight, rolling resistance coefficient, recommended cruising speed, and onboard auxiliary load. The vehicle's state of charge is updated discretely based on the dynamic wireless power transmission efficiency, coil transmission power, the vehicle's traction energy consumption, and the rated capacity of the power battery.

4. The method according to claim 1, characterized in that: The microgrid operating cost and peak load penalty include the operating cost corresponding to the basic time-of-use electricity price and the nonlinear over-limit penalty generated when the predicted total coil transmission power exceeds the distribution network safety peak shaving early warning threshold; The terminal charging target mandatory constraint penalty term adopts a one-sided penalty, which is generated when the predicted terminal state of charge is lower than the target state of charge, and is not generated when the target state of charge is reached or higher.

5. The method according to claim 1 or 4, characterized in that, The weights of each cost item are first normalized based on the allowable extreme value of the corresponding cost item, and then adaptively allocated based on the real-time load rate of the microgrid. When the real-time load rate is not higher than the grid security warning load rate, a preset scenario preference factor is used. When the real-time load rate is higher than the grid security warning load rate, the weight of microgrid operation and peak load costs is increased with the depth of exceeding the limit, and the weight of traffic delay costs and terminal charge insufficiency costs is reduced accordingly.

6. The method according to claim 1, characterized in that, The constraints include at least: The sum of the allocated power of the transmitting coils corresponding to each target vehicle shall not exceed the remaining available safety capacity of the microgrid; The recommended cruise speed is between the minimum and maximum speeds allowed by the road, and the longitudinal acceleration corresponding to the rate of change of the recommended cruise speed in adjacent control cycles is within the preset comfort range. The power allocated to a single transmitting coil shall not exceed the smaller of the rated maximum output power of the transmitting coil and its inverter and the maximum safe receiving power fed back by the vehicle battery management system.

7. The method according to claim 1, characterized in that, When the remaining available safe capacity of the microgrid decreases and the target vehicle has reached the minimum speed allowed by the road, making it impossible for the objective function to have a feasible solution under the constraints, the mandatory constraint of the target leaving the state of charge is released, the output of the corresponding inverter is limited to the maintenance power that meets the safety margin of the microgrid or zero power disconnection is performed, and the longitudinal speed control authority of the vehicle is transferred to the active collision avoidance control of the vehicle's adaptive cruise control.

8. The method according to claim 1, characterized in that, The position feedforward compensation includes: An absolute timestamp is encapsulated in the suggested cruise speed command. The vehicle actuator determines the vehicle coasting deviation distance from command generation to execution based on the actual vehicle speed, measured longitudinal acceleration, and the comprehensive time delay at the time of command reception. The torque adjustment timing of the drive motor is then corrected in advance based on the coasting deviation distance to ensure that the vehicle speed response trajectory is spatially aligned with the electromagnetic activation range of the corresponding transmitting coil.

9. A dynamic wireless power supply and vehicle speed joint optimization system based on vehicle-to-grid cooperation, characterized in that, It includes a state awareness module, a cross-domain prediction module, a rolling optimization module, an instruction execution module, and a feedback update module; The state perception module is used to acquire the vehicle state, target departure charge state and vehicle dynamic parameters of the target vehicle, acquire the remaining available safety capacity of the roadside microgrid, and determine the comprehensive time delay from the roadside to the vehicle actuator. The cross-domain prediction module is used to establish a vehicle-to-grid cross-domain prediction model with coil transmission power and suggested cruising speed as joint decision variables. The rolling optimization module is used to solve the coil transmit power sequence and the suggested cruising speed sequence on a rolling basis, under the constraints of microgrid capacity, road traffic and wireless power supply hardware, based on microgrid operating cost and peak load penalty, vehicle traffic delay penalty and terminal charging target mandatory constraint penalty. The instruction execution module is used to send the coil transmission power instruction and the suggested cruise speed instruction of the first control cycle to the roadside electrical execution side and the vehicle traffic execution side respectively, and to perform position feedforward compensation based on the comprehensive time delay; The feedback update module is used to update the vehicle-grid cross-domain prediction model using the actual load of the microgrid, the actual location of the vehicle, the actual vehicle speed, and the latest state of charge.

10. The system according to claim 9, characterized in that, The system includes a roadside control and power supply system and a vehicle terminal subsystem; The roadside control and power supply system includes a roadside edge computing server, a roadside communication unit, a distribution transformer connected to the roadside power distribution network, multiple sets of high-frequency inverters, and a transmitting coil array buried in the dynamic wireless power supply section. The roadside edge computing server is communicatively connected to the roadside communication unit and the high-frequency inverters. The vehicle terminal subsystem includes a dynamic wireless power receiving coil and rectifier voltage regulation module, an on-board communication unit, a battery management system, and an adaptive cruise chassis drive-by-wire module for receiving suggested cruise speed commands and adjusting the longitudinal movement of the vehicle.