A method for hoisting large nuclear power equipment using a ring rail crane
Through the systematic layout and intelligent monitoring of specially designed ring rail cranes, the extreme requirements of weight and distance in the hoisting of large nuclear power equipment have been solved, achieving high safety and high efficiency in hoisting, which is particularly suitable for nuclear power construction in coastal typhoon-prone areas.
Patent Information
- Application Number
- CN202611145604.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-07-30
- Publication Date
- 2026-11-17
AI Technical Summary
Existing heavy-duty crawler cranes or large truck cranes are insufficient to meet the requirements of maximum lifting capacity exceeding 1,100 tons, maximum operating radius of 210 meters, and resistance to extreme wind loads of 50 m/s or more when hoisting core equipment in nuclear power plants, and they also lack systematic safety risk control solutions.
By employing a specially designed ring rail crane, combined with a systematic site layout, meticulous installation process, intelligent real-time monitoring, and redundant safety design, a high-safety hoisting solution is formed, including real-time grounding pressure monitoring, multi-level wind protection warning, and electrical system redundancy, ensuring the safety and accuracy of the hoisting process.
It achieves safety and precision in lifting ultra-large tonnage and ultra-long distance equipment, and has the ability to withstand extreme winds of 50m/s in all 360° directions, significantly improving the safety and stability of lifting large nuclear power equipment, and increasing construction efficiency and safety.
Smart Images

Figure CN123105478A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of large equipment hoisting technology in nuclear power engineering construction, and in particular to a high-safety, large-tonnage circular rail crane hoisting method for modular installation of core large equipment in nuclear power plants. Background Technology
[0002] With the development of third-generation nuclear power technology, key equipment in nuclear power plants (such as large structural modules of reactor buildings and electrical buildings) are showing a significant trend towards large-scale, modular, and integrated hoisting. Core equipment modules in nuclear power plants are characterized by their enormous weight, large dimensions, high lifting height, and extremely high positioning accuracy requirements. Some equipment weighs over a thousand tons and requires precise hoisting and placement over long distances and across structures within limited spaces.
[0003] Traditional heavy-duty crawler cranes or large truck cranes generally face the following technical problems when dealing with extreme working conditions involving excessive weight and large lifting radius: First, the maximum lifting capacity is insufficient to meet the lifting requirements of equipment weighing over 1,000 tons; second, the operating radius is limited by the boom structure and mechanism capacity, making it unable to effectively cover long-distance lifting points exceeding 200 meters; third, it requires extremely high foundation bearing capacity, resulting in large-scale and costly foundation treatment work and the risk of uneven settlement; fourth, nuclear power plant construction sites often involve multiple units operating in parallel, with complex spatial intersections, requiring lifting equipment to have a wide coverage area and flexible position adjustment capabilities, making the movement and repositioning of traditional equipment difficult. Furthermore, nuclear power plant construction has a long cycle, and construction sites may face extreme weather such as typhoons, posing a severe challenge to the wind resistance of lifting equipment in non-operating states. Existing conventional lifting equipment and methods cannot simultaneously meet the dual requirements of a maximum lifting capacity exceeding 1,100 tons, a maximum operating radius of 210 meters, and resistance to extreme wind loads exceeding 50 m / s. Meanwhile, there is a lack of systematic solutions for safety risks such as real-time monitoring of foundation stability, dynamic response control of wind load, and emergency protection for electrical system failures during the hoisting process.
[0004] Therefore, given the unique and high-risk nature of hoisting large nuclear power equipment, there is an urgent need to develop a systematic hoisting method based on ultra-large capacity ring rail cranes, integrating intelligent monitoring and multiple safety protections, in order to overcome the technical challenges of hoisting ultra-large tonnage and ultra-long distances, and ensure the safety, efficiency and reliability of nuclear power engineering construction. Summary of the Invention
[0005] This invention provides a method for hoisting large nuclear power equipment using a ring rail crane. The aim is to form a complete high-safety hoisting solution by selecting a ring rail crane with specific parameters, combining a systematic site layout, a refined installation process, intelligent real-time monitoring, and redundant safety design, in order to solve the problem of safe and precise hoisting of large nuclear power equipment under long-radius, large-tonnage, and complex environmental conditions.
[0006] To achieve the above objectives, the present invention provides a method for hoisting large nuclear power equipment using a ring rail crane, the method comprising the following steps:
[0007] Step S10, Site planning and foundation laying: Based on the overall layout plan of the nuclear power unit, the foundation of the area occupied by the ring rail crane in the area between the center distance of the two units is leveled and compacted. Then, the main road box and ring rail beam are laid, and the ring road plate is used for foundation laying to ensure uniform load distribution.
[0008] Step S20, Install the main unit of the ring rail crane: On the laid ring rail, install the balance beams of each level of the front and rear slewing trolleys and the walkway in sequence, and connect the corresponding hydraulic pipelines and electrical lines; connect the front and rear slewing trolleys into an integral structure through the front and rear crossbeams of the turntable, and use an auxiliary crane to lift and install the middle platform of the turntable.
[0009] Step S30: Assemble the upper structure and boom system of the ring rail crane: On the installed turntable intermediate platform, install the operator's cab, winch mechanism and power box in sequence; then assemble the superlift mast, superlift vertical support, superlift backpack and superlift counterweight; install the main boom by combining ground pre-assembly and auxiliary crane lifting, connect the variable-width tie plate, and finally assemble the fixed auxiliary boom and its tie plate.
[0010] Step S40, Rope threading and system debugging: Wind the main hook wire rope and the fast hook wire rope, connect the power box pipeline, and then conduct a comprehensive debugging of the electrical system and control system;
[0011] Step S50, boom lifting and hoisting operation: Using the self-lifting function of the ring crane, the boom system is lifted from the horizontal position to the working angle, and the hoisting operation of the large nuclear power equipment is performed according to the predetermined hoisting condition parameters.
[0012] A further technical solution of the present invention includes a real-time grounding specific voltage monitoring step:
[0013] The real-time grounding specific pressure calculation software embedded in the crane monitoring system calculates and displays the grounding specific pressure value under the current working state in real time based on dynamic load, grounding area variables and data collected by PLC. When the grounding specific pressure value is detected to be close to the preset critical value, an audible and visual alarm is triggered, and the hoisting strategy is prompted to be adjusted.
[0014] A further technical solution of the present invention is that, after step S50, it further includes:
[0015] Step S60: In the working state, the wind speed is monitored by the wind speed monitor installed on the ring rail crane. When the wind speed reaches 10.8 m / s, the system automatically issues an audible and visual warning; when the wind speed approaches 15 m / s, the system automatically alarms and controls the crane to stop the lifting operation, while performing a hook stabilization operation.
[0016] Step S70: In the non-working state, adjust the main boom of the crane to a position with an angle of 60° to 70° with the ground, and fix it with the ground anchoring system to enable the crane to withstand extreme wind speeds of 50m / s in all 360° wind directions.
[0017] A further technical solution of the present invention is that the winch mechanism adopts a zigzag drum and a high-performance anti-rotation steel wire rope, and is equipped with a three-turn protection device. The winch mechanism has stepless speed regulation performance, and when performing micro-motion operations, its lifting and lowering displacement accuracy is controlled within a range of no more than 25mm. When the operating lever returns to the zero position, the braking device automatically locks the winch drum.
[0018] A further technical solution of the present invention is that the electrical and control systems of the ring rail crane adopt a redundant design, and the main power input of the ring rail crane is configured with two independent power supplies, namely a 10kV mains power supply and a 660V generator power supply; when the main circuit of the hoisting mechanism malfunctions, it automatically switches to the generator power supply; the capacity of the box-type substation supplying power to the ring rail crane is not less than 1.2 times the rated capacity required by the ring rail crane.
[0019] A further technical solution of the present invention is that, in step S30, the installation of the main boom adopts a combination of ground pre-assembly and auxiliary crane lifting, specifically: firstly, one side of the boom is connected in sections on the ground, and two auxiliary cranes are used to lift it to the predetermined position on the turntable and connect it; the other side of the boom is installed in the same way; finally, the upper horizontal boom section, the lower horizontal boom section and the boom head of the main boom are connected in sequence.
[0020] A further technical solution of the present invention is that the maximum torque of the ring rail crane is 250,000 t·m, the main boom length is 137m, the fixed auxiliary boom is 66m, and the included angle between the main boom and the fixed auxiliary boom is 15°.
[0021] A further technical solution of the present invention is that the hoisting conditions include the hoisting condition of the heaviest component and the hoisting condition of the farthest component.
[0022] The method for hoisting large nuclear power equipment using a ring-rail crane of the present invention has the following significant advantages:
[0023] 1. Comprehensive lifting capacity: By selecting a 250,000 t·m ultra-large lifting moment ring rail crane and combining it with a specific boom combination (137m+66m), it effectively covers the heaviest (over 1100t) and farthest (radius over 200m) extreme lifting conditions in nuclear power construction, solving the problem of insufficient capacity of traditional equipment.
[0024] 2. Significantly improved safety and reliability: It integrates multiple active and passive safety technologies such as real-time grounding specific pressure monitoring, multi-level wind prevention early warning, and electrical system redundancy, and constructs a full-process, multi-dimensional safety protection system, which greatly reduces major risks such as foundation instability, wind disasters, and system failures.
[0025] 3. Excellent wind resistance: The innovative non-working boom angle maintenance (60°-70°) combined with the anchoring system enables it to withstand extreme winds of 50m / s in all wind directions, making it particularly suitable for nuclear power plant construction in coastal typhoon-prone areas.
[0026] 4. High positioning accuracy: The high-performance hoisting system and stepless speed control enable high-precision micro-motion operation under heavy load, ensuring the accurate installation of heavy equipment modules.
[0027] 5. Good construction efficiency and adaptability: The circular track-based walking method facilitates the adjustment of the station position in a limited space and has a wide coverage area; the modular installation process reduces high-altitude operations and improves installation efficiency and safety.
[0028] This invention presents a complete and reliable method for hoisting large equipment. It employs a specially designed ultra-large lifting moment ring rail crane, meticulous site planning based on the unit layout, high-standard foundation treatment and ring rail laying, efficient installation processes using modular and double-arm assembly, and a fully integrated intelligent monitoring system encompassing real-time grounding pressure monitoring, multi-level wind warning, and electrical redundancy control. This method effectively solves technical challenges related to foundation stability, wind resistance, and precise positioning during the hoisting of ultra-heavy and ultra-large equipment in nuclear power plant construction. It significantly improves the safety, stability, and overall risk resistance of hoisting operations, demonstrating significant engineering application value. Attached Figure Description
[0029] Figure 1 This is a flowchart illustrating a preferred embodiment of the nuclear power plant large equipment ring rail crane hoisting method of the present invention;
[0030] Figure 2 This is a three-dimensional structural diagram of a ring rail crane in operation.
[0031] Figure 3 This is a schematic diagram of the boom structure of a ring rail crane in a windproof, non-working state.
[0032] Explanation of icon numbers:
[0033] 1. Ring track beam; 2. Roadbed plate; 3. Main boom; 4. Fixed auxiliary boom; 5. Slewing trolley; 6. Superlift mast; 7. Superlift counterweight; 8. Main hook; 9. Quick hook; 10. Auxiliary boom mast. Detailed Implementation
[0034] To make the objectives, technical solutions, and advantages of this invention clearer, the invention will be further described in detail below with reference to the accompanying drawings and embodiments.
[0035] This invention proposes a method for hoisting large nuclear power equipment using a ring-rail crane, such as... Figures 1 to 3 As shown, a preferred embodiment of the nuclear power plant large equipment ring rail crane hoisting method of the present invention includes the following steps:
[0036] Step S10, Site Planning and Foundation Laying: Based on the overall layout plan of the nuclear power unit, the foundation of the area occupied by the ring rail crane in the area between the center distance of the two units is leveled and compacted. Then, the main road box and ring rail beam 1 are laid, and the ring road plate 2 is used for foundation laying to ensure uniform load distribution.
[0037] In this embodiment, a ring rail crane with a maximum lifting torque of 250,000 t·m is used. The main boom of the ring rail crane is 137m long, the fixed auxiliary boom is 66m long, and the included angle between the main boom and the fixed auxiliary boom is 15°.
[0038] The electrical and control systems of the ring rail crane adopt a redundant design. The main power input of the ring rail crane is configured with two independent power supplies: a 10kV mains power supply and a 660V generator power supply. When the main circuit of the hoisting mechanism malfunctions, it automatically switches to the generator power supply. The capacity of the box-type substation supplying power to the ring rail crane is not less than 1.2 times the rated capacity required by the ring rail crane.
[0039] The ring crane is equipped with an intelligent safety monitoring system, which integrates a real-time grounding specific pressure monitoring module, a multi-level wind prevention early warning and handling module, and an electrical and control redundancy module.
[0040] The real-time grounding specific pressure monitoring module calculates and displays the grounding specific pressure under different working conditions in real time through software, and compares it with the allowable bearing capacity of the foundation to provide early warning.
[0041] Multi-level wind warning and response module: wind speed graded alarm and automatic shutdown in working state, and ultra-high wind resistance by optimizing boom angle and anchoring system in non-working state.
[0042] The electrical and control redundancy module is powered by dual independent power supplies, and key mechanisms (such as hoists) are equipped with backup power circuits. The control system has fault self-diagnosis and safety locking functions.
[0043] In this embodiment, the ring rail crane is positioned in the middle area between the centers of the two units (reactor building) at a distance of 218m to 238m, so as to effectively cover the core hoisting area of the two units.
[0044] In this embodiment, the foundation of the station area, boom assembly area, and counterweight stacking area of the ring rail crane is leveled and compacted to ensure that the bearing capacity of the foundation in the station area is not less than 21t / m², and the bearing capacity of the foundation in the boom installation and counterweight installation area is not less than 20t / m². Subsequently, the main engine roadbed box and ring rail beam 1 are laid, and 96 high-strength ring roadbed plates 2 are used for the foundation laying to ensure uniform load distribution.
[0045] Step S20, Install the main unit of the ring rail crane: On the laid ring rail, install the balance beams and walkways of the front and rear slewing trolleys 5 in sequence, and connect the corresponding hydraulic pipelines and electrical lines; connect the front and rear slewing trolleys 5 into an integral structure through the front and rear crossbeams of the turntable, and use an auxiliary crane to lift and install the intermediate platform of the turntable.
[0046] In this embodiment, a ring-shaped track base plate 2, made of 96 high-strength steel plates, is precisely laid on a properly prepared foundation. A ring track beam 1 is then installed on the base plate to form a stable and uniformly stressed ring track foundation. Subsequently, the front and rear slewing trolleys 5 (including balance beams, walkways, etc.) of a ring track crane are installed on the ring track and connected to form an integral frame via a turntable crossbeam. A large auxiliary crane is then used to complete the installation of large structural components such as the turntable intermediate platform.
[0047] Step S30: Assemble the upper structure and boom system of the ring rail crane: On the installed turntable intermediate platform, install the operator's cab, winch mechanism and power box in sequence; then assemble the superlift mast 6, superlift vertical support rod, superlift backpack and superlift counterweight 7; install the main boom by combining ground pre-assembly and auxiliary crane lifting, connect the variable-thrust plate (i.e., auxiliary boom mast 10), and finally assemble and fix the auxiliary boom and its plate.
[0048] The winch mechanism uses a zigzag drum and a high-performance anti-rotation steel wire rope, and is equipped with a three-turn protection device. The winch mechanism has high-precision stepless speed regulation performance. When performing micro-motion operations, its lifting and lowering displacement accuracy is controlled within ±25mm, which meets the requirements for precise docking of large modules. When the operating lever returns to the zero position, the braking device automatically locks the winch drum.
[0049] In this embodiment, the operator's cab, hoisting mechanism (main lifting, fast hook 9, luffing, etc.), and power box are sequentially installed on the pre-installed turntable structure. Then, the super-lift system components (mast, vertical struts, backpack, etc.) are assembled on the ground and installed to the slewing trolley hinge point 5 using an auxiliary crane. The main boom is installed using a "ground-segmented pre-assembly, dual-machine lifting and positioning" process, effectively reducing the amount of high-altitude work and assembly time. Finally, the auxiliary boom is installed and fixed, and all tie rod wire ropes are connected.
[0050] In step S30, the main boom is installed using a combination of ground pre-assembly and auxiliary crane lifting. Specifically, one side of the boom is first connected in sections on the ground, then lifted to a predetermined position on the turntable using two auxiliary cranes and connected. The other side of the boom is installed using the same method. Finally, the upper crossarm section, lower crossarm section, and boom head of the main boom are connected in sequence. The entire installation process is completed within a 75m×75m main unit construction site and a 210m×25m dedicated boom construction site.
[0051] Step S40, Rope threading and system debugging: Wind the main hook 8 wire rope and the quick hook 9 wire rope, connect the power box pipeline, and then conduct a comprehensive debugging of the electrical system and control system.
[0052] In this embodiment, the wire ropes of the main hook 8 and the quick hook 9 are wound according to a predetermined winding method. After connecting all hydraulic and electrical pipelines, the crane's electrical control system and safety monitoring system (such as anti-collision, grounding pressure monitoring, anemometer, etc.) are comprehensively debugged and functionally verified to ensure that each system works normally and the interlocking is reliable.
[0053] Step S50, boom lifting and hoisting operation: Using the self-lifting function of the ring crane, the boom system is lifted from the horizontal position to the working angle, and the hoisting operation of the large nuclear power equipment is performed according to the predetermined hoisting condition parameters.
[0054] This embodiment utilizes the crane's own lifting mechanism or winch system to safely lift the assembled boom system from its horizontal position to the working angle. Based on the weight, dimensions, and placement location of the equipment to be lifted (such as the CL003 module, ECS fluctuation box, etc.), the specific lifting conditions (operating radius, boom angle, etc.) are calculated and determined. During the lifting process, key parameters such as wind speed, ground pressure, and load rate are monitored in real time. The winch mechanism's stepless speed regulation and micro-motion functions are used to achieve stable lifting of large equipment and millimeter-level precision placement.
[0055] The lifting conditions include the lifting condition for the heaviest component and the lifting condition for the farthest component.
[0056] Specifically, for the heaviest lifting operation, such as the electrical plant module CL003, the lifting weight is 1139t, and the operating radius is controlled within the range of 166m to 173m; under this operation, the rated lifting capacity of the ring rail crane is 1139t to 1415t, and the actual operating load rate is controlled between 80.5% and 82.5%.
[0057] For the lifting of the furthest components, such as the ECS oscillating box or the main oil storage tank of the SBO diesel generator set with a radius of 205m to 210m, the operating radius is controlled between 205m and 210m. Although the load rate is extremely low (about 3.4%), the focus is on monitoring the structural deformation and wind load effects under the long boom. Under this condition, the rated lifting capacity of the ring rail crane is 1010t to 1112t, and the actual operating load rate is controlled between 2.4% and 3.4%.
[0058] Furthermore, in this embodiment, the method for hoisting large nuclear power equipment using a ring-rail crane also includes a real-time grounding specific pressure monitoring step:
[0059] The real-time grounding specific pressure calculation software embedded in the crane monitoring system calculates and displays the grounding specific pressure value under the current working state in real time based on dynamic load, grounding area variables and data collected by PLC. When the grounding specific pressure value is detected to be close to the preset critical value of 25t / m², an audible and visual alarm is triggered, and the hoisting strategy is prompted to be adjusted.
[0060] Furthermore, in this embodiment, after step S50, the method further includes:
[0061] Step S60: In the working state, the wind speed is monitored by the wind speed monitor installed on the ring rail crane. When the wind speed reaches 10.8 m / s, the system automatically issues an audible and visual warning; when the wind speed approaches 15 m / s, the system automatically alarms and controls the crane to stop the lifting operation, while performing a hook stabilization operation.
[0062] Step S70: In the non-working state, adjust the main boom of the crane to a position with an angle of 60° to 70° with the ground, and fix it with the ground anchoring system to enable the crane to withstand extreme wind speeds of 50m / s in all 360° wind directions.
[0063] The following examples further illustrate the hoisting method of the circular rail crane for large nuclear power equipment of the present invention.
[0064] I. Equipment Selection and Overall Layout
[0065] In this embodiment, a super-large ring rail crane with a maximum lifting moment of 250,000 t·m is selected as the main lifting equipment. The basic parameters of the crane are: main boom length of 137m, fixed jib length of 66m, main boom-jib angle of 15°, and it has strong self-lifting capability and super-lifting system.
[0066] According to the project's overall layout plan, the center-to-center distance between the reactor buildings is 238m. A ring-rail crane will be positioned in the area between the two units, with its ring track aligned with the centerlines of the two units. Calculations show that this location allows the crane to effectively cover the equipment hoisting needs of key areas such as the reactor buildings and electrical buildings of both units within its main working radius, especially the heaviest CL003 module and the ECS fluctuation box with the furthest placement radius.
[0067] II: Foundation Treatment and Foundation Construction
[0068] First, a geological survey and foundation treatment were conducted on the planned crane station area (circular track area). Heavy rollers were used for layered compaction and partial replacement of substandard soil layers to ensure the foundation bearing capacity of this area reached the design requirement of 21 t / m² or higher. The same treatment was applied to the boom assembly area and counterweight storage area, achieving a bearing capacity of 20 t / m².
[0069] After the foundation passes inspection, the ring foundation construction begins. Along the designed ring track, 96 specially made high-strength ring track slabs 2 (material conforming to GB / T 3811 specifications) are precisely laid. Each track slab 2 is connected with high-strength bolts to form a robust, integrated ring-shaped rigid foundation. Subsequently, the ring track beam 1 is installed on the track slabs 2, and the track's flatness and levelness are precisely adjusted.
[0070] Part Three: Crane Installation and Assembly
[0071] The installation process strictly follows established steps to ensure safety and accuracy:
[0072] (1) Main unit installation: On the adjusted ring rail, the base frame, balance beam, traveling trolley and walkway of the front and rear slewing trolleys 5 are hoisted in sequence. After connecting the hydraulic pipelines and electrical lines, the front and rear slewing trolleys 5 are connected into a stable portal frame using the front and rear crossbeams of the turntable. Finally, two 500t crawler cranes are used as auxiliary cranes to lift the huge turntable middle platform and precisely connect it with the front and rear crossbeams.
[0073] (2) Installation of the superstructure: Install the cab, main hoisting winch, fast hook 9 winch, luffing winch and power boxes on the turntable.
[0074] (3) Installation of the superlift system: Assemble the superlift mast 6 into a whole on the ground in sections, and use two 500t crawler cranes to lift it to the hinge point on the top of the front slewing trolley 5 and connect it, and temporarily level it. Then install the superlift vertical support and the "backpack" structure. Use the traction winch to wind the luffing wire rope, slowly lift the superlift mast 6 to the design angle and fix it.
[0075] (4) Installation of main boom and jib (using a two-boom step-by-step hoisting method): First, in the boom assembly area (210m×25m), connect one side of the main boom into a long segment on the ground. Use two large auxiliary cranes to lift the segment and connect its base to the corresponding hinge point on the turntable. Repeat this process to install the other side of the boom. Then, install the upper and lower cross boom sections and the boom head in sequence. Finally, hoist and fix the jib, and connect all luffing plates and super-lifting plates wire ropes.
[0076] (5) Rope threading and debugging: Complete the threading of the wire ropes for the main hook 8 and the fast hook 9. Conduct comprehensive electrical system debugging, including the joint debugging and testing of the PLC control program and safety monitoring system (grounding voltage calculation software, wind speed alarm system, anti-collision system, etc.) to ensure that all functions are normal.
[0077] 4. Implementation of hoisting typical large equipment
[0078] (1) Heaviest component hoisting - Electrical plant module CL003
[0079] The CL003 module, weighing 1139 tons, was the heaviest component in the project. Before hoisting, the working radius was calculated to be between 166m (corresponding to a rated lifting capacity of 1415t) and 173m (corresponding to a rated lifting capacity of 1139t) based on its placement. During the actual hoisting, the working radius was stabilized at approximately 169m by precisely controlling the crane's position and boom angle. At this point, the crane's load rate was approximately 81%, far below the safety requirements. During the hoisting process, the intelligent monitoring system displayed a real-time ground pressure of 20.63t / m² (<25t / m² limit), and the wind speed was within safe limits. The operator utilized the winch mechanism's stepless speed regulation and micro-motion function (accuracy ±25mm) to smoothly hoist the module to the predetermined height, slowly rotating and adjusting its amplitude to ultimately achieve precise docking with the substructure.
[0080] (2) Hoisting of the furthest component - ECS wave box
[0081] The ECS (Electronic Control System) fluctuating box weighs approximately 34 tons, but its positioning radius reaches 210 meters, making it the lifting condition with the largest lifting radius in this project. Under this condition, the crane's rated lifting capacity is 1010 tons, but the actual load rate is only 3.4%, far below the rated load, providing an extremely high safety margin. During the lifting process, the structural deformation and wind load response of the boom system under the ultra-large radius are closely monitored. Intelligent anti-sway and micro-motion control systems ensure stable lifting. Throughout the operation, wind protection monitoring and ground pressure monitoring systems are integrated to verify the crane's wind resistance stability and foundation bearing capacity under the extreme working radius, achieving precise and safe lifting of long-distance, small-tonnage equipment.
[0082] The method for hoisting large nuclear power equipment using a ring-rail crane of the present invention has the following significant advantages:
[0083] 1. Comprehensive lifting capacity: By selecting a 250,000 t·m ultra-large lifting moment ring rail crane and combining it with a specific boom combination (137m+66m), it effectively covers the heaviest (over 1100t) and farthest (radius over 200m) extreme lifting conditions in nuclear power construction, solving the problem of insufficient capacity of traditional equipment.
[0084] 2. Significantly improved safety and reliability: It integrates multiple active and passive safety technologies such as real-time grounding specific pressure monitoring, multi-level wind prevention early warning, and electrical system redundancy, and constructs a full-process, multi-dimensional safety protection system, which greatly reduces major risks such as foundation instability, wind disasters, and system failures.
[0085] 3. Excellent wind resistance: The innovative non-working boom angle maintenance (60°-70°) combined with the anchoring system enables it to withstand extreme winds of 50m / s in all wind directions, making it particularly suitable for nuclear power plant construction in coastal typhoon-prone areas.
[0086] 4. High positioning accuracy: The high-performance hoisting system and stepless speed control enable high-precision micro-motion operation under heavy load, ensuring the accurate installation of heavy equipment modules.
[0087] 5. Good construction efficiency and adaptability: The circular track-based walking method facilitates the adjustment of the station position in a limited space and has a wide coverage area; the modular installation process reduces high-altitude operations and improves installation efficiency and safety.
[0088] This invention presents a complete and reliable method for hoisting large equipment. It employs a specially designed ultra-large lifting moment ring rail crane, meticulous site planning based on the unit layout, high-standard foundation treatment and ring rail laying, efficient installation processes using modular and double-arm assembly, and a fully integrated intelligent monitoring system encompassing real-time grounding pressure monitoring, multi-level wind warning, and electrical redundancy control. This method effectively solves technical challenges related to foundation stability, wind resistance, and precise positioning during the hoisting of ultra-heavy and ultra-large equipment in nuclear power plant construction. It significantly improves the safety, stability, and overall risk resistance of hoisting operations, demonstrating significant engineering application value.
[0089] The above description, in conjunction with specific preferred embodiments, provides a further detailed explanation of the present invention. It should not be construed that the specific implementation of the present invention is limited to these descriptions. For those skilled in the art, various simple deductions or substitutions can be made without departing from the concept of the present invention, and all such modifications and substitutions should be considered within the scope of protection of the present invention.
Claims
1. A method for hoisting large nuclear power equipment using a ring rail crane, characterized in that, The method includes the following steps: Step S10, Site planning and foundation laying: Based on the overall layout plan of the nuclear power unit, the foundation of the area occupied by the ring rail crane in the area between the center distance of the two units is leveled and compacted. Then, the main road box and ring rail beam are laid, and the ring road plate is used for foundation laying to ensure uniform load distribution. Step S20, Install the main unit of the ring rail crane: On the laid ring rail, install the balance beams of each level of the front and rear slewing trolleys and the walkway in sequence, and connect the corresponding hydraulic pipelines and electrical lines; connect the front and rear slewing trolleys into an integral structure through the front and rear crossbeams of the turntable, and use an auxiliary crane to lift and install the middle platform of the turntable. Step S30: Assemble the upper structure and boom system of the ring rail crane: On the installed turntable intermediate platform, install the operator's cab, winch mechanism and power box in sequence; then assemble the superlift mast, superlift vertical support, superlift backpack and superlift counterweight; install the main boom by combining ground pre-assembly and auxiliary crane lifting, connect the variable-width tie plate, and finally assemble the fixed auxiliary boom and its tie plate. Step S40, Rope threading and system debugging: Wind the main hook wire rope and the fast hook wire rope, connect the power box pipeline, and then conduct a comprehensive debugging of the electrical system and control system; Step S50, boom lifting and hoisting operation: Using the self-lifting function of the ring crane, the boom system is lifted from the horizontal position to the working angle, and the hoisting operation of the large nuclear power equipment is performed according to the predetermined hoisting condition parameters.
2. The method for hoisting large nuclear power equipment using a ring-rail crane according to claim 1, characterized in that, It also includes a real-time grounding specific pressure monitoring step: The real-time grounding specific pressure calculation software embedded in the crane monitoring system calculates and displays the grounding specific pressure value under the current working state in real time based on dynamic load, grounding area variables and data collected by PLC. When the grounding specific pressure value is detected to be close to the preset critical value, an audible and visual alarm is triggered, and the hoisting strategy is prompted to be adjusted.
3. The method for hoisting large nuclear power equipment using a ring rail crane according to claim 2, characterized in that, The step S50 is followed by: Step S60: In the working state, the wind speed is monitored by the wind speed monitor installed on the ring rail crane. When the wind speed reaches 10.8 m / s, the system automatically issues an audible and visual warning; when the wind speed approaches 15 m / s, the system automatically alarms and controls the crane to stop the lifting operation, while performing a hook stabilization operation. Step S70: In the non-working state, adjust the main boom of the crane to a position with an angle of 60° to 70° with the ground, and fix it with the ground anchoring system to enable the crane to withstand extreme wind speeds of 50m / s in all 360° wind directions.
4. The method for hoisting large nuclear power equipment using a ring rail crane according to claim 3, characterized in that, The winch mechanism uses a zigzag drum and a high-performance anti-rotation steel wire rope, and is equipped with a three-turn protection device. The winch mechanism has stepless speed regulation performance, and its lifting and lowering displacement accuracy is controlled within a range of no more than 25mm when performing micro-motion operations. When the operating lever returns to the zero position, the braking device automatically locks the winch drum.
5. The method for hoisting large nuclear power equipment using a ring rail crane according to claim 4, characterized in that, The electrical and control systems of the ring rail crane adopt a redundant design. The main power input of the ring rail crane is configured with two independent power supplies: a 10kV mains power supply and a 660V generator power supply. When the main circuit of the hoisting mechanism malfunctions, it automatically switches to the generator power supply. The capacity of the box-type substation supplying power to the ring rail crane is not less than 1.2 times the rated capacity required by the ring rail crane.
6. The method for hoisting large nuclear power equipment using a ring rail crane according to claim 5, characterized in that, In step S30, the main boom is installed using a combination of ground pre-assembly and auxiliary crane lifting. Specifically, one side of the boom is first connected in sections on the ground, and then lifted to a predetermined position on the turntable using two auxiliary cranes and connected. The other side of the boom is installed using the same method. Finally, the upper horizontal boom section, lower horizontal boom section, and boom head of the main boom are connected in sequence.
7. The method for hoisting large nuclear power equipment using a ring-rail crane according to any one of claims 1 to 7, characterized in that, The maximum torque of the ring crane is 250,000 t·m, the main boom length is 137m, the fixed jib length is 66m, and the angle between the main boom and the fixed jib is 15°.
8. The method for hoisting large nuclear power equipment using a ring-rail crane according to any one of claims 1 to 7, characterized in that, The lifting conditions include the lifting condition for the heaviest component and the lifting condition for the farthest component.