Energy dissipation structures and layout methods for mountain streams that combine energy dissipation downstream of sluice gates and scouring and sedimentation
By combining aprons and stilling basins in mountain streams, and employing a zoned and tiered gate scheduling method, the problem that a single energy dissipation method cannot simultaneously address flood discharge safety and riverbed scouring and silting was solved, achieving both engineering safety and riverbed stability.
Patent Information
- Application Number
- CN202611640983.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-22
- Publication Date
- 2026-11-17
AI Technical Summary
In existing technologies for dam and gate projects on mountain streams, a single stilling basin or apron-type energy dissipation method is insufficient to simultaneously address flood discharge safety and riverbed scouring and silting issues, leading to wasted project investment or riverbed instability.
A combination of apron energy dissipation structure and stilling basin energy dissipation structure is adopted. The flood discharge is carried out in zones and stages by setting the gate opening degree. The gate opening mode is adjusted according to the river conditions and water level. Priority is given to using the apron rapid flow scouring or stilling basin energy dissipation.
This approach has enabled the maintenance of riverbed stability, ensured safe flood discharge operations, and improved the flood discharge capacity and engineering safety of the river channel while reducing engineering investment and foundation excavation.
Smart Images

Figure CN123109117A_ABST
Abstract
Description
Technical Field
[0001] This application pertains to the field of flood discharge and energy dissipation facilities in water conservancy and hydropower projects, and particularly relates to an energy dissipation structure and arrangement method for mountain streams that combines energy dissipation downstream of sluice gates with scouring and silting. Background Technology
[0002] In the design of dam and sluice gate projects, the spillway structures must not only meet their functional requirements but also ensure the safety and stability of the dam body, surrounding structures, and downstream river channel when discharging standard floods. After the construction of a dam and sluice gate project, local hydrodynamic conditions change significantly, resulting in localized concentrated flow, high velocity, and sufficient energy during flood discharge, which can easily cause significant scouring and damage to the riverbed. Therefore, it is necessary to strictly control the scouring effect of the downstream flow on the riverbed, ensure the overall stability of the project, and implement energy dissipation design downstream of the dam.
[0003] The energy dissipation and scour prevention design of dams and gates widely employs bottom flow energy dissipation, which involves setting up stilling basins and stilling sills on the downstream side of the gate chamber outlet. This causes the water flow to generate a hydraulic jump within the basin, and the energy is dissipated through mutual friction, air mixing, and collision, thereby reducing the downstream flow velocity of the water.
[0004] In the prior art, patent CN101215828A proposes a high-low sill bottom flow stilling basin arrangement, patent CN101624818A proposes a differential split inlet stilling basin arrangement, and patent CN103669310A proposes a double-layer layered energy dissipation high-low sill stilling basin to further solve the problems of severe water flow turbulence and unstable flow pattern in the stilling basins of the above two patents. The above-mentioned existing patent technologies focus on solving the problem of flood discharge energy dissipation under high head and large unit width flow rates, and through various arrangement structures, the flood discharge energy is dissipated in the stilling basin.
[0005] However, for mountain streams with abundant gravel and siltation, flood discharge and energy dissipation have two sides. On the one hand, it is necessary to dissipate the flood discharge energy to ensure the safety of the engineering facilities; on the other hand, it is necessary to utilize the flood discharge energy to flush away local riverbed siltation downstream of the sluice gate to ensure the smooth flow of the flood discharge channel. Specifically: Firstly, the riverbed of mountain streams is mostly composed of gravel and pebbles mixed with sand, with coarse particles and a wide gradation distribution. Under the influence of water flow, the riverbed material undergoes rolling and sliding on the bed surface, forming localized deposits, which reduces the flood discharge capacity of the river to some extent. To solve the above problems, the engineering energy dissipation method attempts to eliminate the stilling basin, that is, the gate outlet is directly connected to the apron, and the apron section has no tailsill, reducing the downstream resistance of the water flow. The outflow connects with the downstream river flow in a rapid flow manner, thereby improving the problem of localized gravel siltation. The above-mentioned existing patented technology has a good energy dissipation effect of stilling basins, but it cannot use flood discharge energy to solve the problem of localized gravel erosion and siltation in mountain streams.
[0006] Secondly, another problem faced by dam and gate projects on mountain streams is the sudden and short-lived upstream flow during flood season, with rapid rises and falls in river flow. The most unfavorable stage for scour prevention downstream is the initial flood discharge period when a few gates are partially opened. At this time, the downstream water level is low or even dry, making the end of the downstream apron easily susceptible to scouring. Therefore, energy dissipation structures are needed for initial flood discharge to reduce riverbed scouring. As the discharge flow increases, the downstream water level rises, the water cushion thickens, the flow velocity along the flow path decreases, the energy dissipation rate of the stilling basin decreases, and the energy dissipation effect weakens or even disappears. If the aforementioned existing patented technologies are used to design the stilling basin according to the high-standard full-section flood design, it often results in wasted project investment.
[0007] In summary, both single stilling basins and apron-type energy dissipation methods have limitations in the engineering application of mountain stream dam projects. Single stilling basins meet flood discharge safety requirements during design floods, but their construction standards are high, and their efficiency is insufficient during non-flood seasons or when downstream water levels are high. Apron-type energy dissipation is beneficial for handling bedload deposition in the river channel, but severe scouring occurs at the apron's end, jeopardizing project safety in the long term. Overall, a single energy dissipation arrangement cannot simultaneously address both project investment and operational safety. Summary of the Invention
[0008] To overcome the aforementioned engineering and technical problems, this invention provides an energy dissipation structure and arrangement method for mountain streams that takes into account both downstream energy dissipation and scouring and silting. In the overall plane of the downstream energy dissipation section, a retaining wall is set up for energy dissipation after most of the gate openings, and a stilling basin is set up downstream of a few gate openings for bottom flow energy dissipation.
[0009] According to a first aspect of the embodiments of this application, an energy dissipation structure that takes into account both energy dissipation below the gate and scouring and silting is provided for mountain streams. The energy dissipation structure is arranged downstream of some gate openings and includes a control section gate chamber. Downstream of the gate chamber, at least one apron energy dissipation structure and at least one stilling basin energy dissipation structure are alternately arranged. The energy dissipation structure of the apron includes a first slope section and an apron section connected sequentially from upstream to downstream; The stilling basin energy dissipation structure is an excavated type, including a second inclined section, a horizontal section of the stilling basin, a tail sill, and a rear apron connected sequentially from upstream to downstream; Both the end of the apron section of the apron energy dissipation structure and the end of the apron behind the stilling pool energy dissipation structure are equipped with anti-scour facilities. When there is localized gravel accumulation below the sluice gate, the gate openings of the corresponding apron energy dissipation structure are opened to discharge floodwater and flush away the silt. When there is no local siltation downstream or the downstream water level is lower than the preset threshold, the gates of the corresponding stilling basin energy dissipation structure are opened to discharge floodwater at the preset opening degree. After the downstream water level rises, other gates are opened in different areas and at different levels.
[0010] According to a second aspect of the embodiments of this application, a method for arranging an energy dissipation structure in a mountain stream channel that combines energy dissipation downstream of a sluice gate and scouring and silting, as described in the first aspect, is provided, comprising the following steps: S1: Determine the dimensional parameters of the tanker energy dissipation structure, including the tanker elevation and tanker length; S2: Based on the premise that the downstream of the gate is a protective apron energy dissipation structure, the depth and length of the stilling basin are initially determined using the pre-set gate opening and the unit width of the flood discharge as the design calculation parameters. S3: Determine the flow regime of the pool water based on the relationship between the downstream normal water level and the critical water depth, determine the elevation of the downstream apron based on the flow regime type, and verify the depth of the stilling basin; wherein, the elevation of the downstream apron is based on the aforementioned apron elevation; when the flow regime is rapid flow, the downstream apron is excavated to form a low apron, and the depth of the stilling basin is verified based on the elevation of the downstream apron after excavation. S4: Based on the apron elevation and length, the stilling basin length, the apron elevation downstream of the basin, and the verified stilling basin depth, hydraulic calculations are performed by assuming no stilling basin is provided to determine the downstream water level and corresponding flow rate required for the apron end to form a stable hydraulic jump by operating the gate preset opening of the apron energy dissipation structure area. Then, the minimum number of gate openings required to set up a stilling basin is obtained, and the layout location of the stilling basin on the plane is determined by combining the terrain, flow pattern, and gate scheduling principles. S5: Based on the number of gate openings and the different locations of energy dissipation structures downstream of the gate, and according to the downstream riverbed conditions and water level, implement zoned and graded gate scheduling operations: when there is local gravel accumulation downstream of the gate, open the gate openings of the corresponding apron energy dissipation structure area for flood discharge and silt flushing; when there is no local siltation downstream of the gate or the downstream water level is lower than the preset threshold, open the gate openings of the corresponding stilling basin energy dissipation structure area for flood discharge at the preset opening degree, and after the downstream water level rises, open other gate openings in stages.
[0011] The technical solutions provided by the embodiments of this application may include the following beneficial effects: Given that mountain streams are characterized by rapid rises and falls in floodwaters and a riverbed that is prone to erosion and siltation, this application adopts an energy dissipation arrangement combining aprons and stilling basins. This overcomes the technical problem of local erosion prevention and siltation contradictions that exist in the existing single energy dissipation arrangement below the sluice gate in mountain streams, and achieves the effect of maintaining the stability of the riverbed below the sluice gate and ensuring the safe operation of the project during flood discharge.
[0012] Using the pre-set gate opening and discharge unit width as design calculation parameters, the size of the downstream stilling basin is determined. Based on this, the downstream water level and corresponding discharge flow required to form a stable hydraulic jump at the end of the stilling basin energy dissipation structure area are determined, and then the minimum number of gate openings required for the stilling basin energy dissipation structure is calculated. Existing technology designs full-section bottom flow energy dissipation works based on the most unfavorable combination of upstream and downstream water levels, resulting in excessively large energy dissipation works. This application overcomes this defect, which can save on project investment and shorten the construction period.
[0013] The energy dissipation structure and layout method of this invention, which combines energy dissipation downstream of mountain stream dams and sluice gates, can construct local stilling basins and aprons without extensive excavation of the downstream riverbed. In the initial stage of flood discharge, when there is no need for scouring and sedimentation and the downstream water level is low, the gates in the area with the stilling basin are opened at the preset opening degree to ensure sufficient energy dissipation of the downstream flow within the stilling basin. If a larger flood discharge is required after the downstream water level rises, the gates in the area without the stilling basin (the apron energy dissipation structure area) are opened to achieve safe flood discharge. If local sedimentation exists downstream of the dam, the gates in the area with only the apron energy dissipation structure are opened first to discharge floodwater, utilizing the rapid flow in the apron to scour and sedimentate the localized silt and pebbles.
[0014] It should be understood that the above general description and the following detailed description are exemplary and explanatory only, and do not limit this application. Attached Figure Description
[0015] The accompanying drawings, which are incorporated in and form part of this specification, illustrate embodiments consistent with this application and, together with the description, serve to explain the principles of this application.
[0016] Figure 1 This is a three-dimensional structural diagram of an energy dissipation structure for a mountain stream that combines energy dissipation downstream of a sluice gate and scouring and silting, according to Embodiment 1 of the present invention.
[0017] Figure 2 This is a schematic diagram of the planar structure of an energy dissipation structure for a mountain stream that combines energy dissipation downstream of a sluice gate and scouring and silting, according to Embodiment 1 of the present invention.
[0018] Figure 3 for Figure 2 Sectional view along the AA direction.
[0019] Figure 4 for Figure 2 Sectional view along the BB direction.
[0020] Figure 5 This is a three-dimensional structural diagram of an energy dissipation structure for a mountain stream river that combines energy dissipation below the sluice gate and scouring and silting in Embodiment 1 of the present invention (excavation under the revetment behind the pool).
[0021] In the picture: 1. Gate chamber; 11. Side gate piers; 12. Intermediate gate piers; 13. Gate; 14. Overflow weir; 2. Energy dissipation structure of the apron; 21. First slope section; 22. Apron section; 3. Energy dissipation structure of the stilling basin; 31. Second slope section; 32. Horizontal section; 33. Tail sill; 34. Rear apron of the stilling basin; 4. Anti-erosion wall; 5. Anti-collision groove. Detailed Implementation
[0022] Exemplary embodiments will now be described in detail, examples of which are illustrated in the accompanying drawings. When the following description relates to the drawings, unless otherwise indicated, the same numbers in different drawings denote the same or similar elements. The embodiments described in the following exemplary embodiments do not represent all embodiments consistent with this application. Rather, they are merely examples of apparatuses and methods consistent with some aspects of this application.
[0023] The terminology used in this application is for the purpose of describing particular embodiments only and is not intended to be limiting of the application. The singular forms “a,” “the,” and “the” used herein are also intended to include the plural forms unless the context clearly indicates otherwise. It should also be understood that the term “and / or” as used herein refers to and includes any and all possible combinations of one or more of the associated listed items.
[0024] It should be understood that although the terms first, second, third, etc., may be used in this application to describe various information, such information should not be limited to these terms. These terms are only used to distinguish information of the same type from one another. For example, without departing from the scope of this application, first information may also be referred to as second information, and similarly, second information may also be referred to as first information. Depending on the context, the word "if" as used herein may be interpreted as "when," "when," or "in response to determination."
[0025] Example 1: refer to Figures 1-4 This invention provides an energy dissipation structure for mountain streams that combines energy dissipation downstream of sluice gates and scour and sedimentation. The energy dissipation structure is arranged downstream of some sluice gate openings and includes a control section sluice chamber 1. The control section sluice chamber 1 consists of multiple sluice gate openings. Each sluice gate opening mainly consists of a side gate pier 11 or a middle gate pier 12, a gate 13, and an overflow weir 14. Downstream of the sluice gate openings of the sluice chamber 1, at least one apron energy dissipation structure 2 and at least one stilling basin energy dissipation structure 3 are alternately arranged. The apron energy dissipation structure 2 includes a first slope section 21 and an apron section 22 connected sequentially from upstream to downstream. The stilling basin energy dissipation structure 3 is an excavated type and includes a second slope section 31, a horizontal section 32, a tail sill 33, and a rear apron 34 connected sequentially from upstream to downstream. Anti-scour facilities are provided at the end of the apron section 22 of the apron energy dissipation structure 2 and at the end of the rear apron 34 of the stilling basin energy dissipation structure 3.
[0026] In one embodiment, the elevation of the apron energy dissipation structure 2 is the same as the main elevation of the existing riverbed surface downstream of the sluice gate in the project area. This elevation is the stable riverbed elevation after long-term flood control. Taking the existing riverbed elevation as the apron elevation can reduce foundation excavation.
[0027] In one embodiment, the scour protection facility includes a riprap scour channel 5 and / or a vertical scour wall 4, wherein the scour wall 4 is generally constructed using concrete piles or scour caissons. The scour channel 5 can generally be constructed using riprap, masonry, or alloy steel mesh.
[0028] The above-mentioned combination of apron and stilling basin energy dissipation structure can solve the problems of energy dissipation and scour prevention, as well as gravel deposition, in mountain streams with pebble riverbeds. It greatly reduces foundation excavation, lowers project construction investment, and offers flexible scheduling and operation, as detailed below: When there is localized gravel accumulation downstream of the sluice gate, the gate gate 13 of the sluice gate downstream of the gate is opened first. The downstream water flow forms a rapid flow through the energy dissipation structure 2 of the apron to flush away the localized gravel accumulation downstream.
[0029] There was no localized siltation of pebbles downstream of the sluice gate, and the downstream water level was [miss When a low (or even no) flood discharge flow forms a secondary hydraulic jump at the end of the anti-scour channel 5 or further downstream, the gate 13 of the corresponding gate of the local gate is opened first. The discharged water flow dissipates energy through the stilling pool. As the water level below the gate gradually rises, other gate gates 13 are opened. Finally, the discharged water flow dissipates energy through the combination of the stilling pool and the apron, achieving safe discharge.
[0030] Based on the above structure, this embodiment of the invention also provides a method for arranging the energy dissipation structure of the above-mentioned mountain stream waterway that takes into account both downstream energy dissipation and scouring and sedimentation. The arrangement includes the following steps: S1: Determine the dimensional parameters of the tanker energy dissipation structure 2, including the tanker elevation. and tank length ; ① Determine the apron elevation: To facilitate scouring and silting downstream of the sluice gate and reduce the need for riverbed excavation, the apron elevation is the same as the main elevation of the riverbed downstream of the sluice gate in the project area. .
[0031] ② Calculation of abutment length: Mountain streams often have pebble beds. To cope with the scouring of pebbles, short, flat abutments are occasionally used downstream of sluice gates. There are no specific regulations for calculating the abutment length; it is mostly estimated by engineers based on their experience and on-site conditions. Currently, engineers generally use the length calculation method for abutments in the "Sluice Gate Design Code" (SL 265—2016) to estimate the abutment length. The final value was determined after adjustments based on the actual terrain and geological conditions at the site. The relevant calculation formulas are as follows: (1) In the formula: The length of the shield (m); ; The difference in water level (m) between upstream and downstream when the gate is releasing water. To calculate the unit width flow rate (m 2 / s, i.e., m³ / (s·m)); For the calculation coefficients, the values are 14-13 for silt and fine sand, and 12-11 for medium sand, coarse sand, and silty loam.
[0032] S2: Based on the fact that the downstream of the gate is a protective apron energy dissipation structure 2, and using the pre-set opening of gate 13 and the unit width flow rate of the flood discharge as the design calculation parameter, the depth of the stilling basin energy dissipation structure 3 is preliminarily determined. and stilling basin length ; Specifically, the dimensional parameters of the stilling basin energy dissipation structure 3 include the stilling basin depth. stilling basin length Normal water level at the sluice gate Considering the normal water level downstream of the sluice gate, the upstream flow of the mountain stream is sudden and short-lived, with rapid rises and falls in the river flow. In combination with the characteristics of the flood, the initial opening of sluice gate 13 is generally operated at the preset opening degree. The discharge unit width flow rate is based on the preset opening degree e of sluice gate 13 (generally 0.5m~1.0m, in this example e=1.0m, the same below). As design calculation parameters, the dimensions of the stilling basin downstream of the sluice gate are calculated according to the calculation formulas in the "Design Code for Sluice Gates" (SL 265—2016), and the depth of the stilling basin is determined. stilling basin length .
[0033] (2) (3) (4) (5) (6) (7) In the formula: The depth of the stilling basin (m); The hydraulic jump submersion coefficient is 1.05~1.10; The water depth after the jump (m); The water depth before the jump (m); The water kinetic energy correction factor is 1.00~1.05; The flow rate per unit width of the gate (m) 2 / s, i.e., m 3 / (s·m)); For gravitational acceleration, 9.81 (m / s²) can be used. 2 ); The velocity coefficient is 0.95~1.00; Width of the stilling basin (m); The width of the stilling basin end (m); The total potential energy (m) is calculated from the top surface of the stilling basin bottom plate. The drop in elevation at the bottom of the pool (m); The depth of the riverbed outside the pool (m); The length of the stilling basin is (m). The horizontal projection length (m) of the stilling basin slope section; This is the correction factor for the hydraulic jump length, typically taken as 0.7~0.8; The length of the hydraulic jump is (m).
[0034] In this example, the slope ratio of the second slope section 31 of the stilling basin energy dissipation structure 3 is gentler than 1:4, and the gate is set at the normal water level. The downstream water level is the normal water level when the dam site flow is zero. The riverbed elevation is Assume the stilling basin depth is... The pre-jump contraction depth can be obtained using formula (3). The depth of the water after the jump can then be obtained from formula (4). The result can be obtained from formula (5). Substituting into formula (2), we obtain If we assume depth If the depth is close to the calculated depth, then it is the depth of the stilling basin; otherwise, continue with trial calculations. Finally, calculate the length of the stilling basin according to formulas (6) and (7) and relevant parameters. .
[0035] S3: Based on the downstream normal water level and depth With critical water depth The relationship is used to determine the flow regime of the pool water, and the elevation of the rear apron 34 is determined according to the flow regime type, and the depth of the stilling basin is verified. The elevation of the rear apron 34 is based on the apron elevation and can be adjusted by excavation. When the flow regime is rapid flow, the rear apron 34 is excavated to form a low apron, and the depth of the stilling basin is verified based on the elevation of the rear apron 34 after excavation. Specifically, based on the downstream normal water level depth With critical water depth The relationship between the two can be used to determine the flow regime of the pool water; if it is a slow flow or critical flow, the elevation of the 34-meter abutment behind the pool can be set as the existing riverbed elevation. Alternatively, partial excavation may be carried out; if it is a rapid current, the downstream apron 34 may be excavated to form a low apron, increasing the downstream water depth, and the depth of the stilling basin may be recalculated.
[0036] Furthermore, combined with the downstream normal water level and depth Using critical water depth Perform flow pattern determination. If > To slow the flow, the elevation of the rear retaining wall at 34 meters can be [missing information]. ;like = As for the critical flow, the elevation of the 34-meter-high revetment behind the pool can be considered the current riverbed elevation. Alternatively, a shallow excavation can be carried out to form a low embankment; if < The rapids are caused by the excavation of the terrain behind the pool to a certain depth. (1.05~1.10) - Therefore, the elevation of the 34-meter-high protective pool was determined. ,like Figure 5 As shown. The downstream abutment 34 was excavated, increasing the downstream water depth. The water level difference in the pool was recalculated. Further verification of the stilling pool depth The relevant formulas are as follows: (8) (9) The calculated dimensions of the stilling basin were reviewed, as follows: The elevation of the downstream abutment 34 was lowered, and the downstream water depth increased. For safety reasons, the water depth can be approximated as (1.05~1.10). Before jumping, the water depth is reduced. After jumping, the water depth Unaffected, the water level difference in the pool is recalculated using formula (5). The depth of the stilling basin is determined by verifying the formula (2). .
[0037] S4: Based on the apron elevation and length, the stilling basin length, the apron elevation 34 downstream of the basin, and the verified stilling basin depth, hydraulic calculations are performed by assuming no stilling basin is provided to determine the downstream water level and corresponding flow rate required to form a stable hydraulic jump at the end of the apron. Then, the minimum number of gate openings required to set up a stilling basin is obtained, and the layout of the stilling basin on the plane is determined by combining the terrain, flow pattern, and gate scheduling principles. In the absence of sluice gate scouring, to prevent the water flow from cascading down at the end of the apron in the area without stilling basin energy dissipation structure 3 (i.e., apron energy dissipation structure 2) and causing scouring of the riverbed, the water flow needs to form a stable hydraulic jump upstream of the apron end. This requires a certain downstream water level. The hydraulic calculations are performed using the theoretical formulas in the "Design Code for Sluice Gates" (SL 265—2016), including the following sub-steps: S41: Calculate the downstream water level and corresponding discharge rate required to form a stable hydraulic jump at the end of the apron energy dissipation structure 2; Specifically, assuming no stilling basin is provided, the depth of the stilling basin is set as follows: The gate opening is set to 0.0m, and the discharge unit width is used as the design calculation parameter based on the preset gate opening (e=1.0m). The pre-jump contraction depth is calculated according to formulas (2) to (5). Water depth after jumping And calculate the downstream water depth Combining the main elevations of the riverbed surface Estimate downstream water level (approximately) The downstream water level was determined by the relationship between the dam site water level and flow rate. Time corresponding flow Its flow is generated by flood discharge through the energy dissipation zone of the stilling basin.
[0038] S42: Calculate the number of gate openings to be opened based on the preset opening and discharge capacity of single-gate 13. The number of gate openings n is the minimum number of gate openings required for the stilling basin energy dissipation structure 3; Specifically, in situations where siltation is not required downstream of the gate, the gate openings in Zone 2 of the apron energy dissipation structure participate in safe flood discharge. This is to achieve the aforementioned flow rate. and corresponding downstream water levels The flow is released by operating the gate 13 at a preset opening degree corresponding to the energy dissipation structure of the stilling basin in zone 3. According to the theoretical calculation formula of the gate outlet (see formula (10)), the discharge flow rate when the preset opening degree of the single gate 13 is 1.0m is calculated. Then calculate the number of gate openings that need to be opened when the preset opening of gate 13 is 1.0m. Finally, the smallest integer not less than the above calculated value is taken as the number of gate openings for setting the energy dissipation structure 3 of the stilling pool.
[0039] (10) In the formula: The comprehensive outflow coefficient of the sluice gate (the parameter is selected according to the weir type and relevant design specifications); The net width of a single gate opening (m); The total head (m) at the gate is included in the head of the flowing velocity.
[0040] S43: Determine the location of the stilling basin in the plan based on the riverbed topography, downstream water flow connection conditions and gate 13 scheduling principles; Specifically, the design of the stilling basin energy dissipation structure 3 should be determined based on three factors: topography, flow pattern, and gate scheduling principles. First, topographic conditions: the construction of the stilling basin requires the excavation of the riverbed base. To reduce the amount of excavation work, it should be prioritized to be located on the side of the deep channel of the riverbed to make full use of the topographic advantages. Second, water flow connection conditions: the downstream water level and river course should be considered to ensure a good connection between the outflow from the stilling basin and the downstream river channel during flood discharge. Third, gate scheduling principles: the stilling basin should be located on the downstream side of the gates that are prioritized for opening, based on the gate scheduling method.
[0041] S5: Based on the number of gate openings and the different downstream energy dissipation structures, and according to the downstream riverbed conditions and water level, the zoned and graded gate 13 scheduling operation is performed, specifically including: S51: Based on the determined location of the stilling basin and the minimum number of gate openings, divide the gate opening range corresponding to the energy dissipation structure 2 area of the apron and the energy dissipation structure 3 area of the stilling basin. Specifically, mountain stream floods are characterized by rapid rises and falls. After a certain flood flow is discharged, the water level downstream of the sluice gate rises rapidly, and the water depth increases. According to the method of this invention, the energy dissipation structure downstream of the sluice gate is mainly composed of abutment energy dissipation structures. To meet the energy dissipation requirements of flood discharge when the water level downstream of the sluice gate is low or there is no siltation downstream of the sluice gate, an energy dissipation structure 3, such as a stilling basin, is set downstream of some sluice gate openings.
[0042] The scope of the energy dissipation structure zone 3 of the stilling basin: According to the specific implementation method S41~S42, determine the number of gate openings corresponding to the energy dissipation structure zone 3 of the stilling basin when the gate opening is 1.0m for flood discharge. The principle of the planar location arrangement of this zone is determined as described in step S43.
[0043] Scope of the apron energy dissipation structure zone: The apron energy dissipation structure zone is located in area 3 where no stilling basin is constructed. The apron energy dissipation structure zone is primarily designed to address siltation in the riverbed downstream of the floodgate. To facilitate scouring and silting downstream of the gate and reduce riverbed excavation, the apron elevation can be taken from the main elevation of the riverbed surface downstream of the gate in the project area. .
[0044] S52: Set the downstream water level preset threshold ; Specifically, the preset threshold To enable flood discharge through a single gate in the apron energy dissipation structure area (gate opening e=1.0m), the downstream water level required for a stable submerged hydraulic jump must be formed at the end of the apron energy dissipation structure.
[0045] In the energy dissipation structure zone of the apron, there is no stilling basin downstream of the gate (stilling basin depth) The pre-jump contraction depth is calculated according to formulas (2) to (5), with the gate's preset opening (e=1.0m) and the discharge unit width flow rate as the design calculation parameter. Water depth after jumping The downstream water depth was calculated using trial and error. Combining the main elevations of the riverbed surface Estimate downstream water level (approximately) ).
[0046] The downstream water level was determined by measuring the water level and flow rate at the dam site in the engineering area. Time corresponding flow Its flow is generated by flood discharge through the gate openings of the energy dissipation structure in Zone 3 of the stilling basin.
[0047] S53: Real-time monitoring of local gravel accumulation downstream of the sluice gate and downstream water level. ; Specifically, the riverbed of mountain streams is mostly composed of pebbles. During flood discharge, the riverbed material is often carried downstream by the floodwaters, forming local deposits below the sluice gate. These deposit areas are mostly non-mainstream flood zones (areas with lower flow velocities), which affect the flood discharge of the river.
[0048] After routine operation, the elevation of local pebble siltation downstream of the gate in the engineering area should be monitored in real time. The elevation of pebble siltation should not be higher than the elevation of the top of the apron in the energy dissipation structure area. At the same time, downstream water level observation records should be kept to provide a basis for the selection of energy dissipation structure areas for subsequent flood discharge scheduling.
[0049] S54: When localized gravel accumulation is detected downstream of the sluice gate, the gate corresponding to the energy dissipation structure area of the apron should be opened first for flood discharge and silt flushing. Specifically, there is local siltation downstream of the sluice gate. The flood discharge is preferentially selected in the area of the apron energy dissipation structure 2. The water flow at the sluice gate is shallow and has a high velocity along the apron section 22. The rapid flow formed by the apron section 22 is used to flush away the local silt and gravel downstream, and maintain the normal flood passage of the river.
[0050] S55: When there is no local siltation downstream or the downstream water level is low Below the preset threshold When the water level rises, the gates corresponding to area 3 of the stilling basin's energy dissipation structure will be opened first for flood discharge at the preset opening degree; wait for the downstream water level to rise further. Raise to preset threshold After that, the other gate openings are opened in stages; Specifically, there is no siltation downstream of the sluice gate or the downstream water level is low. Below the preset threshold To prevent downstream riverbed scouring, the flood discharge operation prioritizes opening the gates of the stilling basin-equipped energy dissipation structure in Zone 3 at their preset opening degrees. The discharged floodwater undergoes thorough bottom flow energy dissipation within the stilling basin, reducing the outflow velocity and minimizing downstream riverbed scouring. As the discharge flow increases, the downstream water level... Higher than the preset threshold If it is necessary to increase the flood discharge flow, the corresponding gate gates of the apron energy dissipation structure in zone 2 should be opened in sequence for flood discharge. The gate opening should be carried out in zones and stages.
[0051] Zoned opening: Prioritize opening the gates corresponding to Zone 3 of the stilling basin energy dissipation structure, and then open the gates corresponding to Zone 2 of the apron energy dissipation structure.
[0052] Staged opening: For the first stage of gate opening, the gates in Zone 3 of the energy dissipation structure with stilling basin are opened to 1.0m. If it is necessary to increase the flood discharge flow, the gates in Zone 2 of the energy dissipation structure of the apron are opened to 1.0m in sequence. For the second stage of gate opening, after completing the first stage opening of all gates, the second stage of gate opening is completed in the same order as the first stage opening. The specific opening degree of the gates can be determined according to the actual gate scheduling principle of the project. Multi-stage opening follows the same principle and will not be elaborated further.
[0053] Example 2: In this embodiment, the energy dissipation structure and arrangement method that takes into account both energy dissipation downstream of the gate and scouring and silting of mountain streams are applied to the energy dissipation arrangement of a flood discharge gate project in a mountain stream in Zhejiang.
[0054] Basic data: The floodgate has 10 openings, each with a net width of 14.0m, for a total net floodgate width of 140m. The overflow weir (14) has a crest elevation of 24.0m, the main downstream riverbed elevation is 20.6m, the apron design length is 51.5m, and the vertical scour protection wall at the apron end (4) is 9.6m deep. The riprap scour protection channel (5) has a top elevation of 20.6m. The normal water level above the gate is 35.00m. When gate (13) is partially opened to 1.0m, the unit width flow rate is 11.1m. 2 / s, normal water level downstream of the sluice gate is 22.5m (water depth 1.9m).
[0055] The initial stage of a flood is the most unfavorable period for scour prevention downstream of the sluice gate. At this time, the downstream water level is low, or even dry, and the released floodwater can easily cause scouring of the riverbed behind the apron downstream of the sluice gate, making energy dissipation and scour prevention issues prominent. During the hydraulic model test, multiple schemes were compared and selected, and the energy dissipation arrangement of a combination of a partial apron and a partial stilling basin was finally adopted.
[0056] First, the dimensions of the abutment were determined using the abutment size calculation method. Based on the topographic data, the abutment elevation was taken as 20.6m. Use a value of 11 to estimate the length of the tank shield. The original length was 68.9m. Considering the site topography, the designers determined that a deep pool existed downstream, which could be used as a backfill area for future siltation from upstream. Therefore, the final horizontal length of the revetment was revised to 51.5m.
[0057] Secondly, the stilling basin dimensions are initially calculated using the aforementioned stilling basin size design method. The downstream water depth is 1.9m, and the stilling basin depth is assumed to be... After multiple trials, the water depth was reduced before the jump. 0.7m, post-jump water depth Approximately 5.9m Approximately 1.7m Taking 1.05, the calculated depth of the stilling basin is approximately 2.6m, and the length is approximately 38.0m.
[0058] Secondly, the critical water depth of the rear abutment is 34. It is 2.3m, which is greater than the normal water level depth. The elevation is 1.9m, indicating a rapid current in the pool. The elevation of the rear abutment (34m) needs to be lowered, and the water depth after lowering should be 1.1 times the elevation. The new water depth behind the pool The depth is 2.5m, and the rear abutment 34 reduces the depth. The depth of the rear apron 34 is 0.6m. To avoid the lateral diffusion of the outflow from the pool in the rear apron 34 section, the design unit reduced the depth of the rear apron 34 by 1.0m to form a low apron to constrain the outflow from the pool and stabilize the hydraulic jump energy dissipation of the stilling pool.
[0059] Check the depth of the stilling basin , , All values remain unchanged. The depth of the water outlet is taken as 2.9m. The water level difference in the pool is recalculated using formula (5). The depth of the stilling basin is 0.6m, determined by formula (2). It is 2.7m.
[0060] Finally, the layout area of the stilling basin energy dissipation structure 3 and the preset threshold for safe flood discharge of the apron energy dissipation structure 2 were determined. At approximately 26.0m, based on the dam site water level and flow rate, the discharge flow at this point is approximately 585.1m³. 3 / s. A single-orifice gate with an opening of 1.0m has a free outflow rate of 155.4m³ / s. 3 / s, the calculation requires setting the number of gate openings corresponding to the excavated stilling basin to 4.
[0061] Finally, the layout was determined based on the method of combining the apron and the excavated stilling basin. Taking into account the current riverbed topography and future scheduling and operation methods, the stilling basin of the flood discharge gate is located downstream of gates 2, 5, 6 and 9.
[0062] The floodgate adopts the content described in this invention, and finally forms a combination of high and low aprons and stilling basin for energy dissipation. The hydraulic model test verifies that when the gate 13 opening e=1.0m, the end of the apron energy dissipation structure 2 forms a good scouring and silting effect. At the same time, under typical characteristic working conditions, the scouring depth at the end of the apron 34 behind the stilling basin energy dissipation structure 3 in the main channel area of the river is reduced from the original design of 5.7m to 2.3m, and the scouring pit depth is reduced by about 60%.
[0063] The combined energy dissipation structure and arrangement method of the stilling basin and the apron of the present invention can raise the downstream water level when the gate 13 is initially opened for flood discharge, which has a good effect on reducing the scouring of the riverbed bed and improving local scouring and silting.
[0064] Other embodiments of this application will readily occur to those skilled in the art upon consideration of the specification and practice of the disclosure herein. This application is intended to cover any variations, uses, or adaptations of this application that follow the general principles of this application and include common knowledge or customary techniques in the art not disclosed herein. The specification and embodiments are to be considered exemplary only.
[0065] It should be understood that this application is not limited to the precise structure described above and shown in the accompanying drawings, and various modifications and changes can be made without departing from its scope.
Claims
1. An energy dissipation structure for mountain streams that combines energy dissipation downstream of sluice gates with scouring and sedimentation, characterized in that, The energy dissipation structure is arranged downstream of some gate openings, including the control section gate chamber. Downstream of the gate chamber, at least one apron energy dissipation structure and at least one stilling basin energy dissipation structure are alternately arranged. The energy dissipation structure of the apron includes a first slope section and an apron section connected sequentially from upstream to downstream; The stilling basin energy dissipation structure is an excavated type, including a second inclined section, a horizontal section of the stilling basin, a tail sill, and a rear apron connected sequentially from upstream to downstream; Both the end of the apron section of the apron energy dissipation structure and the end of the apron behind the stilling pool energy dissipation structure are equipped with anti-scour facilities. When there is localized gravel accumulation below the sluice gate, the gate openings of the corresponding apron energy dissipation structure are opened to discharge floodwater and flush away the silt. When there is no local siltation downstream or the downstream water level is lower than the preset threshold, the gates of the corresponding stilling basin energy dissipation structure are opened to discharge floodwater at the preset opening degree. After the downstream water level rises, other gates are opened in different areas and at different levels.
2. The energy dissipation structure for mountain streams that combines energy dissipation downstream of sluice gates and scouring / deposition as described in claim 1, characterized in that, The elevation of the apron of the energy dissipation structure is the same as the main elevation of the existing riverbed downstream of the sluice gate in the project area.
3. The energy dissipation structure for mountain streams that combines energy dissipation downstream of sluice gates and scouring / deposition as described in claim 1, characterized in that, The anti-erosion facilities include riprap anti-erosion channels and / or vertical anti-erosion walls.
4. A method for arranging an energy dissipation structure in a mountain stream channel that combines energy dissipation downstream of a sluice gate and scouring / deposition, as described in any one of claims 1-3, characterized in that... Includes the following steps: S1: Determine the dimensional parameters of the tanker energy dissipation structure, including the tanker elevation and tanker length; S2: Based on the premise that the downstream of the gate is a protective apron energy dissipation structure, the depth and length of the stilling basin are initially determined using the pre-set gate opening and the unit width of the flood discharge as the design calculation parameters. S3: Determine the flow regime of the pool water based on the relationship between the downstream normal water level and the critical water depth, and determine the elevation of the downstream apron and verify the depth of the stilling basin based on the flow regime type; wherein, the elevation of the downstream apron is based on the aforementioned apron elevation; when the flow regime is a rapid flow, the downstream apron is excavated to form a low apron, and the depth of the stilling basin is verified based on the elevation of the downstream apron after excavation. S4: Based on the apron elevation and length, the stilling basin length, the apron elevation downstream of the basin, and the verified stilling basin depth, hydraulic calculations are performed by assuming no stilling basin is provided to determine the downstream water level and corresponding flow rate required for the apron end to form a stable hydraulic jump by operating the gate preset opening of the apron energy dissipation structure area. Then, the minimum number of gate openings required to set up a stilling basin is obtained, and the layout location of the stilling basin on the plane is determined by combining the terrain, flow pattern, and gate scheduling principles. S5: Based on the number of gate openings and the different locations of energy dissipation structures downstream of the gate, and according to the downstream riverbed conditions and water level, implement zoned and graded gate scheduling operations: when there is local gravel accumulation downstream of the gate, open the gate openings of the corresponding apron energy dissipation structure area for flood discharge and silt flushing; when there is no local siltation downstream of the gate or the downstream water level is lower than the preset threshold, open the gate openings of the corresponding stilling basin energy dissipation structure area for flood discharge at the preset opening degree, and after the downstream water level rises, open other gate openings in stages.
5. The arrangement method according to claim 4, characterized in that, The elevation of the revetment is the same as the main elevation of the riverbed surface.
6. The arrangement method according to claim 4, characterized in that, The length of the embankment was estimated using the sea length calculation method in the "Sluice Gate Design Code".
7. The arrangement method according to claim 4, characterized in that, Determine the elevation of the post-stillation basin apron and verify the depth of the stilling basin based on the flow regime, including: S31: Determine the flow regime of the pool water based on the relationship between the downstream normal water level depth and the critical water depth; S32: If the flow is slow or critical, the elevation of the rear apron should be set to the existing riverbed elevation or a local excavation should be carried out. S33: If it is a rapid current, the apron behind the pool will be dredged to form a low apron, increasing the downstream water depth and reducing the elevation of the apron behind the pool to the apron elevation of S1 minus the dredging depth. S34: Based on the elevation of the apron after excavation, recalculate the depth of the stilling basin and compare it with the depth of the stilling basin determined in S2. Take the larger value as the verified depth of the stilling basin.
8. The arrangement method according to claim 4, characterized in that, By performing hydraulic calculations assuming no stilling basin is required, the downstream water level and corresponding flow rate needed to form a stable hydraulic jump at the end of the apron are determined. This allows for the calculation of the minimum number of gate openings required for a stilling basin. Furthermore, the planar layout of the stilling basin is determined by considering topography, flow regime, and gate scheduling principles. S41: Considering the absence of a stilling basin, calculate the downstream water level and corresponding flow rate required to form a stable hydraulic jump at the end of the apron energy dissipation structure; S42: Calculate the number of gate openings to be opened based on the preset opening and discharge flow of a single gate. This number of gate openings is the minimum number of gate openings required to install an energy dissipation pool structure. S43: Determine the location of the stilling basin in the plane by taking into account the riverbed topography, downstream water flow connection conditions and gate scheduling priority.
9. The arrangement method according to claim 8, characterized in that, Assuming no stilling basin is required, calculate the downstream water level and corresponding flow rate needed to form a stable hydraulic jump at the end of the apron energy dissipation structure, including: Set the stilling basin depth to 0, and assume that no stilling basin is required. Calculate the pre-jump contraction water depth and post-jump water depth, as well as the downstream water depth. Combine this with the main elevations of the riverbed to estimate the downstream water level required to form a stable hydraulic jump and the corresponding flow rate at which the downstream water level is formed.
10. The arrangement method according to claim 4, characterized in that, S5 specifically includes: S51: Based on the determined location of the stilling basin and the minimum number of gate openings, divide the energy dissipation structure area of the apron and the gate opening range corresponding to the energy dissipation structure area of the stilling basin. S52: Set the preset threshold for downstream water level; S53: Real-time monitoring of local gravel accumulation and downstream water level; S54: When localized gravel accumulation is detected downstream of the sluice gate, the gate corresponding to the energy dissipation structure area of the apron should be opened first for flood discharge and silt flushing. S55: When there is no local siltation downstream or the downstream water level is lower than the preset threshold, the gates corresponding to the energy dissipation structure area of the stilling basin shall be opened first to discharge floodwater at the preset opening degree; after the downstream water level rises above the preset threshold, other gates shall be opened in stages.
Citation Information
Patent Citations
High and low ridge underflow stilling basin
CN101215828A
Differential column-splitting inlet energy dissipater
CN101624818A
Tank-type and drum-type oil recycling device
CN103669310A