An environmental control method for environmentally friendly compaction construction of collapsible loess
By eliminating the risk of oil leakage through electric compaction pile drivers and fully enclosed lubrication structures, and by combining dust and moisture content control with wastewater reuse, the environmental pollution and resource waste problems in the compaction construction of collapsible loess have been solved, achieving green construction and ensuring construction quality.
Patent Information
- Application Number
- CN202610993766.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-07-06
- Publication Date
- 2026-11-17
AI Technical Summary
Existing compaction construction methods for collapsible loess suffer from problems such as oil leakage and exhaust gas emissions, disconnect between dust control and moisture content regulation, disorderly discharge of wastewater, and transportation of excavated soil. These issues lead to serious environmental pollution and resource waste, and make it difficult to guarantee construction quality.
Electric compaction piles are used for compaction and hole formation, and a fully enclosed lubrication structure is used to eliminate the risk of fuel exhaust emissions and oil leakage. During the screening and mixing of filler, dust concentration and filler moisture content are collected to control the opening, closing and spraying volume of the atomizing spray device. Construction wastewater is treated by sedimentation and reused for dust suppression and site watering. The extruded native loess is screened and used as filler for backfilling, realizing the in-situ resource utilization of excavated soil.
It has achieved the complete elimination of oil leakage, precise control of dust and moisture content, full reuse of construction wastewater and zero external transportation of excavated soil, ensuring construction quality and solving the problems of environmental pollution and resource waste.
Smart Images

Figure CN123109134A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of foundation treatment and green construction technology, and in particular to an environmental control method for environmentally friendly compaction construction of collapsible loess. Background Technology
[0002] Collapsible loess is a special type of soil characterized by large porosity and significant water sensitivity. In Class IV self-weight collapsible loess sites, the thickness of the collapsible soil layer can reach over 20 meters, and the foundation settlement after immersion in water can reach 700-1200 mm, posing a serious threat to engineering safety. Compaction pile construction is one of the mainstream technologies for treating collapsible loess foundations above the groundwater level. It compacts the soil between piles through lateral compression during drilling, and then forms a composite foundation through layered compaction, thereby eliminating collapsibility and improving bearing capacity. It is widely used in the treatment of this type of foundation.
[0003] However, the aforementioned compaction pile construction process is accompanied by significant environmental pollution problems. The drilling and filling material screening and mixing stages generate substantial amounts of dust; traditional fuel-powered equipment emits harmful exhaust gases; hydraulic systems are prone to oil leakage under high-frequency vibration conditions; and the disorderly discharge of construction wastewater and the transportation of extruded native loess as waste soil are common occurrences, placing considerable pressure on the construction site and surrounding ecological environment. To address these issues, several improvement solutions have been proposed in existing technologies. These include replacing traditional diesel power with electric drive to reduce exhaust emissions, using mist cannons and water trucks around the site for wet dust suppression, treating construction wastewater in sedimentation tanks before discharge, and transporting waste soil to designated spoil disposal sites. These measures have alleviated environmental problems such as construction dust, exhaust gases, and wastewater to some extent.
[0004] However, the existing environmental control solutions still have the following technical shortcomings. First, the hydraulic system of the equipment is prone to oil leakage under high-frequency vibration conditions in deep collapsible loess layers. The high permeability of loess causes oil to seep rapidly, resulting in long-term pollution of the soil and groundwater. Second, existing dust suppression methods lack coordinated control with the moisture content of the filler material. Blindly spraying can easily cause the moisture content of the filler material to deviate from the optimal value, which in turn affects the compaction quality and results in serious water waste. Third, the direct discharge of construction wastewater causes resource waste, while the transportation of large amounts of native loess as waste soil increases land occupation, transportation energy consumption, and carbon emissions, failing to achieve on-site recycling of resources. Therefore, there is an urgent need to provide a systematic method that deeply integrates compaction construction with comprehensive environmental control to achieve green construction goals while ensuring the quality of foundation treatment. Summary of the Invention
[0005] The purpose of this invention is to provide an environmental control method for environmentally friendly compaction construction of collapsible loess, which solves the problems of serious environmental pollution, resource waste and difficulty in ensuring construction quality caused by oil leakage and exhaust gas emission, the disconnect between dust reduction and moisture content control, disorderly discharge of wastewater and transportation of excavated soil in the existing compaction pile construction process.
[0006] To achieve the above objectives, this invention provides an environmental control method for environmentally friendly compaction construction of collapsible loess, comprising the following steps: An electric compaction pile machine is used for compaction and hole formation. The electric compaction pile machine has a fully enclosed lubrication structure. It eliminates the risk of fuel exhaust emissions and oil leakage through pure electric motor drive and enclosed lubrication medium. During the screening and mixing of filler materials, dust concentration and moisture content of filler materials are collected in conjunction with each other. The opening, closing and spraying volume of the atomizing spray device are controlled according to the dust concentration and moisture content of filler materials to simultaneously reduce dust concentration and regulate the moisture content of filler materials. Wastewater generated during construction is collected in a sedimentation system, and after sedimentation treatment, it is reused in the atomizing spray device and / or site dust suppression. The original loess extruded during the compaction and drilling process is screened and mixed, and then backfilled into the compaction pile hole as filler, thus realizing the in-situ resource utilization of the excavated soil.
[0007] The system involves the coordinated collection of dust concentration and packing material moisture content, and the control of the atomizing spray device's activation, deactivation, and spray volume based on these parameters. Specifically, this includes: When the dust concentration exceeds a preset threshold and the moisture content of the filler is lower than the lower limit of the preset optimal moisture content range, the atomizing spray device is activated. When the moisture content of the filler reaches the upper limit of the preset optimal moisture content range, the atomizing spray device is stopped or switched to physical dust suppression mode.
[0008] Specifically, wastewater generated during construction will be collected in a sedimentation system, treated by sedimentation, and then reused in the atomizing spray device and / or for dust suppression on site. The wastewater includes equipment flushing wastewater, rainwater, and recycled water that has not evaporated after being sprayed by the atomizing spray device; The sedimentation system is a three-stage series sedimentation tank; The supernatant after treatment in the three-stage series sedimentation tank is supplied to the atomizing spray device and the site sprinkler truck through a pressurized reuse pipeline.
[0009] The filler material is plain soil or cement-soil, and the cement-soil is made by mixing extruded native loess with cement according to the designed mix ratio. Both the original loess and the filler were screened to control the particle size to be no greater than 15 mm.
[0010] The preset optimal moisture content range is ±3% of the optimal moisture content, and the optimal moisture content is determined in advance by a compaction test.
[0011] The excess native loess squeezed out during the compaction and pore-forming process is used for site leveling or bedding layer filling, ensuring that no waste soil is transported out of the entire construction area.
[0012] The compaction and hole formation is carried out in a staggered, alternating row drilling sequence, and the backfilling and compaction work is completed on the same day after the holes are formed.
[0013] The noise level at the site boundary during operation of the electric compaction pile machine shall be controlled to be no more than 70 dB during the day and no more than 55 dB at night.
[0014] The construction site is surrounded by drainage slopes and drainage ditches. The slope of the drainage slopes is 4%, and the drainage ditches are connected to the sedimentation system to guide rainwater and construction wastewater to the sedimentation system.
[0015] The filling material screening and mixing area is equipped with a closed soundproof operating shed, and the atomizing spray device is installed inside the closed soundproof operating shed and around the construction operation area.
[0016] This invention discloses an environmental control method for environmentally friendly compaction construction of collapsible loess. It employs an electric compaction pile machine with a fully enclosed lubrication structure for compaction and hole formation, eliminating the risk of fuel exhaust emissions and oil leakage at the source through pure electric motor drive and a closed lubrication medium. During the screening and mixing of filler materials, dust concentration and filler moisture content are collected in conjunction with the method. The opening, closing, and spraying volume of the atomizing spray device are controlled based on these parameters to simultaneously reduce dust concentration and regulate the filler moisture content to an optimal range, avoiding indiscriminate spraying that could lead to dust pollution. The moisture content of the filler deviates from the optimal value, affecting the compaction quality. Simultaneously, wastewater from equipment washing, rainwater, and spray recovery generated during construction are collected in a three-stage series sedimentation tank. The supernatant after sedimentation is supplied to the atomizing spray device and site water truck through a pressurized reuse pipeline, achieving zero discharge of construction wastewater and resource recycling. The original loess squeezed out during the compaction and drilling process is screened and mixed, then used as filler in the compaction pile holes. Excess soil is used for site leveling or bedding layer filling, achieving in-situ resource utilization of excavated soil and eliminating the need for external transportation. This invention, while ensuring a compaction coefficient of not less than 0.97 and that the composite foundation bearing capacity meets design requirements, completely eliminates the risk of oil leakage pollution to soil and groundwater. It achieves synergistic control of dust suppression and precise moisture content regulation, full reuse of construction wastewater, and zero external transportation of excavated soil, effectively solving the problems of severe environmental pollution, resource waste, and difficulty in guaranteeing construction quality in existing technologies. Attached Figure Description
[0017] To more clearly illustrate the technical solutions in the embodiments of this application or the prior art, the accompanying drawings used in the description of the embodiments or the prior art will be briefly introduced below.
[0018] Figure 1 This is a flowchart of the steps of the environmental control method for environmentally friendly compaction construction of collapsible loess according to the present invention. Detailed Implementation
[0019] The embodiments of the present invention are described in detail below. Examples of the embodiments are shown in the accompanying drawings. The embodiments described below with reference to the accompanying drawings are exemplary and intended to explain the present invention, but should not be construed as limiting the present invention.
[0020] Please refer to Figure 1 This invention provides an environmental control method for environmentally friendly compaction construction of collapsible loess, comprising the following steps: S101: An electric compaction pile machine is used for compaction and hole formation. The electric compaction pile machine has a fully enclosed lubrication structure. The risk of fuel exhaust emissions and oil leakage is eliminated by pure electric motor drive and enclosed lubrication medium. Specifically, before construction, site leveling, surveying and setting out, and positioning of the piling rig must be completed. During site leveling, excavation should be carried out to a depth of at least 100 cm above the designed pile top elevation. After leveling with a bulldozer, the excavation should be compacted with a road roller, and a drainage slope of 4% should be set. Drainage ditches should be excavated around the perimeter of the site. During surveying and setting out, GPS should be used to locate the pile positions. A steel pipe with a diameter of 40 mm and a length of at least 10 cm should be driven into the soil. After removing the pipe, the hole should be filled with quicklime as a pile position marker. When positioning the piling rig, move the drilling rig to the pile position location, slowly placing the drill bit on the pile position. A steel tape measure should be used to measure the pile position deviation, ensuring that the deviation value is no greater than 5% of the pile spacing.
[0021] This embodiment uses a JM-20 electric compaction pile driver as the drilling equipment. This equipment is equipped with a pure electric motor drive system, providing stable power output and eliminating any combustion exhaust emissions. The lubrication system of the electric compaction pile driver adopts a fully enclosed gearbox structure, filled with lubricating medium. All transmission components complete lubrication circulation within the closed cavity, eliminating the risk of hydraulic oil or lubricating oil leakage caused by aging and wear of seals in traditional hydraulic systems. The electric compaction pile driver also features a hydraulic vibration damping base, located at the contact point between the pile driver chassis and the ground. This base absorbs and attenuates the mechanical vibration generated during the drilling process through hydraulic damping elements, effectively reducing the propagation of vibration to the foundation soil and surrounding environment. Through the vibration reduction and noise reduction effect of this hydraulic vibration damping base, the boundary noise during the operation of the electric compaction pile driver can be controlled to no more than 70dB during the day and no more than 55dB at night.
[0022] During borehole drilling, the electric compaction pile machine concentrates its own weight onto the auger bit. The lateral pressure generated by the rotation of the drill rod radially compresses the soil at the pile location, causing soil particles to rearrange and reducing the void ratio, thus forming a pile hole of the designed diameter and depth. Markers for observing the penetration depth are placed on the drill rod every 0.5 meters. In terms of drilling sequence, a skip-row drilling method is adopted, meaning drilling is performed in leaps every other row of pile positions to avoid stress superposition that could cause hole collapse. During drilling, the speed control principle of "slow at first, then fast, then uniform" is followed. The first 2 meters are drilled at a low speed to ensure the verticality of the drill rod; from 2 to 6 meters, the drilling speed is increased but not exceeding 2 meters per minute; thereafter, a stable speed is maintained until the designed hole depth. When the drill rod passes through the boundary between soft and hard soil layers, it is advisable to proceed slowly and keep the drill rod vertical. When drilling in miscellaneous fill containing bricks and stones or in soft plastic clay layers with high water content, drill rod swaying should be minimized to avoid enlarging the hole diameter. If any abnormalities occur, such as drill rod jumping, significant frame shaking, or failure to advance, stop the machine immediately for inspection. If underground obstacles such as boulders are encountered, remove them before resuming drilling or switch to percussion drilling. After each drilling cycle (approximately 3 meters), use a theodolite to check the drill rod's verticality, ensuring the verticality deviation does not exceed 1.0%. After drilling is completed, use a measuring rope to measure the hole depth and a steel tape measure to measure the hole diameter. The hole depth deviation must not be negative and must not exceed 500 mm of the designed pile length. The allowable deviation of the hole diameter must not exceed 20 mm. Only after passing these checks can the next process begin. After drilling is completed, backfilling and compaction should be completed on the same day to avoid prolonged exposure after drilling, which could lead to hole instability or hole shrinkage.
[0023] S102: During the screening and mixing of filler, the dust concentration and moisture content of the filler are collected in conjunction with each other. The opening, closing and spraying volume of the atomizing spray device are controlled according to the dust concentration and the moisture content of the filler to simultaneously reduce the dust concentration and regulate the moisture content of the filler. Specifically, this step is carried out in the filler preparation area, which is equipped with a WHB-200 soil screening machine-soil mixing machine for plain soil screening and cement-soil mixing. The soil screening machine-soil mixing machine is housed inside a closed, soundproof operating shed. This shed uses color steel sandwich panels as its enclosure structure, with sound-absorbing material pasted on the inner walls. This ensures internal ventilation and dust removal while effectively blocking the transmission of high-frequency noise generated during soil screening and mixing. A ring-shaped spray pipe is arranged above the screening and mixing area, connecting a high-pressure water pump and atomizing nozzles to form an atomizing spray device. This area is also equipped with a dust concentration sensor and a moisture content detection module. The dust concentration sensor is used to monitor the PM10 concentration in the air in real time, and the moisture content detection module is used to obtain the real-time moisture content of the filler during screening and mixing. The dust concentration sensor, moisture content detection module, high-pressure water pump, and atomizing spray device are all connected to a central control module, forming a closed-loop linkage control system.
[0024] Before construction, representative soil samples were sent to a qualified geotechnical laboratory for compaction tests to determine the optimum moisture content and maximum dry density of the fill material. In this embodiment, the optimum moisture content of the plain soil fill material was 19.0%, and the optimum moisture content of the cement-soil fill material was 17.2%. The preset optimum moisture content range was ±3% of the optimum moisture content (for example, if the optimum moisture content of the cement-soil fill material is 17.2%, then the optimum moisture content range is 16.7% to 17.7%). The plain soil in the fill material was sourced from collapsible loess excavated from the foundation pit within the construction area and from nearby resources. PC42.5 low-energy cement was selected. All fill materials were screened before use to control the particle size to no more than 15 mm. Clayey soil with an organic matter content exceeding 5% was strictly prohibited, as were silt, silty soil, and clayey soil with a moisture content that did not meet the backfill compaction requirements. The cement-soil mixture is made by mixing screened native loess with cement in a mixing machine according to the designed mix ratio (e.g., 1:7 volume ratio). The mixing time is not less than 2 minutes, and the mixture must be used up within 24 hours.
[0025] Once the filler screening and mixing operations begin, the dust concentration sensor continuously collects the dust concentration in the work area, while the moisture content detection module simultaneously collects the filler moisture content and transmits the data to the central control module in real time. The central control module has preset dust concentration thresholds and optimal moisture content ranges. When the central control module determines that the dust concentration exceeds the preset threshold and the filler moisture content is below the lower limit of the optimal moisture content range, it automatically starts the high-pressure water pump and activates the atomizing spray device for dust suppression. The water mist generated during the spraying process collides and adsorbs the dust particles produced during screening and mixing, causing the dust to settle rapidly. Simultaneously, the moisture in the water mist is absorbed by the filler, gradually increasing its moisture content towards the optimal range. When the central control module determines that the filler moisture content has reached the upper limit of the optimal moisture content range, regardless of whether the dust concentration still exceeds the limit, the central control module stops the high-pressure water pump, shuts off the atomizing spray device, or switches to a physical dust suppression method (such as starting a fan for adsorption) to prevent excessive spraying from causing the filler moisture content to exceed the optimal range and affecting the subsequent compaction quality. Throughout the entire spray control process, the spray volume is dynamically adjusted based on the difference between the dust concentration and the preset threshold, as well as the deviation between the moisture content of the packing and the optimal moisture content range, to achieve the optimal balance between dust reduction efficiency and packing moisture content control.
[0026] S103: Collect the wastewater generated during construction into a sedimentation system, and after sedimentation treatment, reuse it for the atomizing spray device and / or site dust suppression. Specifically, a drainage slope with a 4% gradient is set around the construction site, and drainage ditches are excavated at the site edges, connecting to the sedimentation system. A screen is installed between the drainage ditches and the sedimentation system to intercept large particles (such as gravel and plastic fragments) carried in the wastewater, preventing them from entering the sedimentation tank and clogging the pressurized reuse pipeline. The sedimentation system uses a three-stage series sedimentation tank system, with the first, second, and third sedimentation tanks connected in series. All types of wastewater generated during construction, including but not limited to equipment flushing wastewater, rainwater, and condensate from the atomizing spray device in step S102, are collected and guided to the sedimentation system through the drainage slope and drainage ditches. The wastewater first enters the first sedimentation tank for preliminary sedimentation to remove large suspended solids; the supernatant flows into the second sedimentation tank for further sedimentation to remove medium-sized suspended solids; finally, it flows into the third sedimentation tank for fine sedimentation to obtain a clarified supernatant. A water level sensor is installed in the third sedimentation tank. When the water level exceeds a preset value, the pressurized reuse pump automatically starts, forcibly delivering the supernatant to each water-using terminal to prevent the sedimentation tank from overflowing. The supernatant after tertiary sedimentation is transported to the atomizing spray device and the site sprinkler truck through the pressurized reuse pipeline, and is used for dust suppression in the soil screening and mixing process in step S102, and for watering and dust suppression on the site roads, respectively. The sludge deposited at the bottom of the sedimentation tank is cleaned regularly. After natural drying, the cleaned sludge can be used for site leveling or mixed with filler materials.
[0027] S104: The original loess extruded during the compaction and drilling process is screened and mixed, and then backfilled into the compaction pile hole as filler, so as to realize the in-situ resource utilization of the excavated soil.
[0028] Specifically, during the drilling process in step S101, the auger drill bit rotates and compresses the soil, bringing the original loess out of the pile hole and accumulating it around the hole opening. This original loess is collapsible loess in its original state, and its mineral composition and physical and mechanical properties are naturally consistent with the soil between the piles, making it an ideal backfill material for the pile body. In this embodiment, the original loess extruded from the drilling is directly transported to the soil screening machine-ash-soil mixing machine in step S102 via a loader or belt conveyor for screening. The screening process controls the particle size to be no greater than 15 mm, removing soil clods, stones, and debris. The screened loess is used directly as plain soil filler according to design requirements, or mixed with PC42.5 cement according to the design mix ratio to form cement-soil filler. If the moisture content of the extruded original loess deviates from the optimal design moisture content, the moisture content is adjusted during the screening process through the linkage spraying system in step S102 to ensure that the moisture content of the filler meets the requirement of ±3% of the optimal moisture content.
[0029] After screening and moisture content adjustment, the fill material is transported to the pile hole location by a loader for layered backfilling. Before backfilling, the bottom of the hole is tamped 6 to 8 times. During layered backfilling, the loose thickness of each layer should not exceed 800 mm. To control the amount of fill material in each layer, a fixed baffle is installed at the bottom of the loader bucket. The amount of fill material per batch is controlled by calculating the bucket volume to avoid excessive fill material and resulting in an excessively thick loose layer. After each layer of fill material is filled, a 1.5-ton tamping hammer is lifted to a height of 3 meters and then dropped freely to compact it, with no less than 8 tamping blows per layer. When a crisp sound is heard, the rebound is obvious, and a noticeable vibration is felt around the pile hole, the next layer of fill material can be filled and tamped in the same way. During the tamping process, the pile hammer, wire rope, and center line of the pile hole should be kept consistent to avoid uneven tamping caused by the pile hammer tilting. The tamping end height of the pile hole is more than 500 mm higher than the design elevation of the pile top. The remaining pile hole is then lightly tamped backfilled with other soil materials to the ground level. Through layered compaction, the pile compaction coefficient is not less than 0.97. 28 days after the cement-soil compaction piles are completed, and 14 days after the plain soil compaction piles are completed, core sampling of the soil between the piles and testing of the composite foundation bearing capacity are conducted. The tests show that the minimum compaction coefficient of the soil between the piles is not less than 0.9, and the composite foundation bearing capacity meets the design requirements (not less than 250 kPa for cement-soil compaction piles, and not less than 180 kPa for plain soil compaction piles).
[0030] The total amount of native loess extruded during the drilling process is usually greater than the amount required for backfilling the pile holes. The excess native loess is used for site leveling and backfilling or for filling the bedding layer, ensuring that no soil is transported out of the entire construction area. Through the above treatment, the native loess, which was originally considered construction waste, is 100% utilized in situ, completely eliminating the occupation of land resources by soil transportation and the energy consumption and carbon emissions during transportation.
[0031] In summary, this invention, while ensuring a compaction coefficient of not less than 0.97 and that the bearing capacity of the composite foundation meets design requirements, completely eliminates the risk of oil leakage to soil and groundwater pollution. It achieves synergistic control of dust reduction and moisture content, full reuse of construction wastewater, and zero external transportation of excavated soil, effectively solving the technical problems of serious environmental pollution, resource waste, and difficulty in ensuring construction quality in existing technologies.
[0032] The above-disclosed embodiments are merely one or more preferred embodiments of this application and should not be construed as limiting the scope of this application. Those skilled in the art can understand that all or part of the processes for implementing the above embodiments and equivalent changes made in accordance with the claims of this application still fall within the scope of this application.
Claims
1. An environmental control method for environmentally friendly compaction construction of collapsible loess, characterized in that, Includes the following steps: An electric compaction pile machine is used for compaction and hole formation. The electric compaction pile machine has a fully enclosed lubrication structure. The pure electric motor drive and the closed lubrication medium eliminate the risk of fuel exhaust emissions and oil leakage. During the screening and mixing of filler materials, dust concentration and moisture content of filler materials are collected in conjunction with each other. The opening, closing and spraying volume of the atomizing spray device are controlled according to the dust concentration and moisture content of filler materials to simultaneously reduce dust concentration and regulate the moisture content of filler materials. Wastewater generated during construction is collected in a sedimentation system, and after sedimentation treatment, it is reused in the atomizing spray device and / or site dust suppression. The original loess extruded during the compaction and drilling process is screened and mixed, and then backfilled into the compaction pile hole as filler, thus realizing the in-situ resource utilization of the excavated soil.
2. The environmental control method for environmentally friendly compaction construction of collapsible loess as described in claim 1, characterized in that, The system integrates the collection of dust concentration and packing material moisture content, and controls the opening, closing, and spray volume of the atomizing spray device based on the dust concentration and packing material moisture content. Specifically, this includes: When the dust concentration exceeds a preset threshold and the moisture content of the filler is lower than the lower limit of the preset optimal moisture content range, the atomizing spray device is activated. When the moisture content of the filler reaches the upper limit of the preset optimal moisture content range, the atomizing spray device is stopped or switched to physical dust suppression.
3. The environmental control method for environmentally friendly compaction construction of collapsible loess as described in claim 1, characterized in that, Wastewater generated during construction is collected in a sedimentation system, and after sedimentation treatment, it is reused in the atomizing spray device and / or for dust suppression on site, specifically including: The wastewater includes equipment flushing wastewater, rainwater, and recycled water that has not evaporated after being sprayed by the atomizing spray device; The sedimentation system is a three-stage series sedimentation tank; The supernatant after treatment in the three-stage series sedimentation tank is supplied to the atomizing spray device and the site sprinkler truck through a pressurized reuse pipeline.
4. The environmental control method for environmentally friendly compaction construction of collapsible loess as described in claim 1, characterized in that, The filler is plain soil or cement-filled soil. The cement-filled soil is made by mixing extruded native loess with cement according to the designed mix ratio. Both the original loess and the filler were screened to control the particle size to be no greater than 15 mm.
5. The environmental control method for environmentally friendly compaction construction of collapsible loess as described in claim 2, characterized in that, The preset optimal moisture content range is ±3% of the optimal moisture content, and the optimal moisture content is determined in advance by a compaction test.
6. The environmental control method for environmentally friendly compaction construction of collapsible loess as described in claim 1, characterized in that, The excess native loess squeezed out during the compaction and pore-forming process is used for site leveling or bedding layer filling, so that no waste soil is transported out of the entire construction area.
7. The environmental control method for environmentally friendly compaction construction of collapsible loess as described in claim 1, characterized in that, The compaction and hole formation is carried out in a staggered, alternating row drilling sequence, and the backfilling and compaction work is completed on the same day after the holes are formed.
8. The environmental control method for environmentally friendly compaction construction of collapsible loess as described in claim 1, characterized in that, The noise level at the site boundary during the operation of the electric compaction pile machine is controlled to be no more than 70dB during the day and no more than 55dB at night.
9. The environmental control method for environmentally friendly compaction construction of collapsible loess as described in claim 1, characterized in that, Drainage slopes and drainage ditches are set up around the construction site. The slope of the drainage slopes is 4%. The drainage ditches are connected to the sedimentation system to guide rainwater and construction wastewater to the sedimentation system.
10. The environmental control method for environmentally friendly compaction construction of collapsible loess as described in claim 1, characterized in that, The filling material screening and mixing operation area is equipped with a closed soundproof operating shed, and the atomizing spray device is installed inside the closed soundproof operating shed and around the construction operation area.