A method for graded dewatering and recharge control in deep foundation pits of riverside tunnels
By acquiring tidal forecasts and real-time water level monitoring data, the operation mode of the precipitation recharge system is dynamically adjusted, solving the problem of delayed response in traditional methods and achieving safe and efficient precipitation control in the deep foundation pit of the Linjiang Tunnel.
Patent Information
- Application Number
- CN202610948832.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-06-29
- Publication Date
- 2026-11-17
AI Technical Summary
Traditional precipitation control methods cannot be matched with the dynamic hydrological environment of the deep foundation pit of the Linjiang Tunnel affected by tides, resulting in increased risk of sudden inrush at the bottom of the foundation pit and energy waste due to delayed response.
By acquiring hourly tidal forecast data and real-time water level monitoring data, the lag time constant is determined using cross-correlation analysis, and the expected fluctuation time axis of the foundation pit water level is generated. It is divided into the active precipitation stage of ebb tide, the balance stage of slack tide, and the buffer recharge stage of rising tide. The operation mode of the precipitation recharge system is dynamically adjusted, and the parameters are optimized by combining the matching degree relationship of risk intervals and emergency control.
The system achieved synchronized operation of the rainwater recharge system with the tidal cycle, reducing the risk of sudden inrush in the foundation pit, lowering energy consumption, and improving the adaptability and efficiency of the control strategy.
Smart Images

Figure CN123109189A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of deep foundation pit construction dewatering engineering technology, specifically a graded dewatering and recharge control method for deep foundation pits in riverside tunnels. Background Technology
[0002] In the construction of the deep foundation pit project of the Linjiang Tunnel, groundwater control is a crucial aspect to ensure construction safety and the stability of the surrounding environment. Because the foundation pit is adjacent to the river, the groundwater level fluctuates periodically due to the influence of river tides, posing significant challenges to dewatering control. Traditional dewatering control methods typically use water level thresholds as the control benchmark, meaning that dewatering equipment is activated or deactivated when the water level exceeds or falls below a set threshold. This control method is essentially a delayed response; the system only begins to adjust after a water level change occurs, making it difficult to match the rhythm of tidal changes. During high tide, when the water level rises rapidly, the system may experience increased risk of sudden inrush at the bottom of the foundation pit due to the delayed response. Conversely, during low tide, when the water level naturally drops, the system may continue to operate at the set flow rate, potentially leading to excessive dewatering and energy waste.
[0003] In existing technologies, the amount of precipitation reinjection water is calculated using area equivalence and the principle of equivalent large wells, providing a design basis for well placement schemes. This method focuses on static water volume calculation in the early stages of construction and does not address real-time dynamic control of tidal fluctuations during construction. Another technology achieves reinjection control by configuring three precipitation wells corresponding to two reinjection wells and comparing water levels. However, this method uses a passive response approach of fixed-ratio well placement and water level comparison, which is suitable for general hydrological conditions but difficult to adapt to the large dynamic hydrological fluctuations caused by tides in riverside areas.
[0004] Therefore, a graded dewatering and recharge control method for deep foundation pits in riverside tunnels is proposed to address the above problems. Summary of the Invention
[0005] To address the shortcomings of existing technologies, this invention provides a graded dewatering and recharge control method for deep foundation pits in riverside tunnels. This method solves the problem that traditional dewatering and recharge control methods, which rely on water level thresholds for a delayed response, cannot match the dynamic hydrological environment of deep foundation pits in riverside tunnels affected by tides.
[0006] To achieve the above objectives, the present invention provides the following technical solution: a method for graded dewatering and recharge control of deep foundation pits in riverside tunnels, comprising the following steps: S1: Obtain hourly tidal forecast data for the river section where the deep foundation pit of the Linjiang Tunnel is located, as well as real-time water level monitoring data of the confined aquifer collected by water level sensors deployed along the depth of the foundation pit. ; The acquired tidal forecast data is used to predict the hydrological change trend outside the foundation pit, while the real-time water level monitoring data is used to provide feedback on the actual water level status inside the foundation pit, providing basic data for subsequent analysis of the response relationship between the two.
[0007] S2: Based on the response relationship between the hourly tidal forecast data and the real-time water level monitoring data, determine the lag time constant of the transmission of river water level tidal changes to the confined aquifer within the foundation pit. And according to the said lag time constant The hourly tidal forecast data is converted into a time axis for expected fluctuations in the foundation pit water level. The time axis for expected fluctuations in the foundation pit water level marks the expected rise and fall periods of the foundation pit water level at each hour in the next 24 hours. Through the lag time constant By converting tidal forecasts into expected water levels in the foundation pit, uncontrollable tidal fluctuations are transformed into predictable time coordinates, providing a benchmark for proactive control.
[0008] S3: Based on the expected fluctuation timeline of the foundation pit water level, the 24-hour period is divided into three consecutive and interconnected dynamic operating segments: the ebb tide active precipitation segment, the slack tide balance maintenance segment, and the rising tide buffer recharge segment. The ebb tide active precipitation segment corresponds to the expected decline period, the slack tide balance maintenance segment corresponds to the transition period from the end of the expected decline to the beginning of the expected rise, and the rising tide buffer recharge segment corresponds to the expected rise period. Each dynamic operating segment corresponds to a preset precipitation recharge operation mode, which includes the number of precipitation wells opened during that period. single-well flow rate of precipitation wells Number of recharge wells opened and the flow rate of a single injection well The set value; By dividing the time periods, the operation rhythm of the precipitation recharge system is matched with the natural tidal cycle, and corresponding control strategies are adopted at different tidal stages.
[0009] S4: Using the expected fluctuation time axis of the foundation pit water level as the control benchmark, when the current time reaches the start time of a certain dynamic operation period, the precipitation recharge system will be switched to the precipitation recharge operation mode corresponding to that period. In this way, the system can predict water level trends and adjust its operating status in advance before tidal changes are transmitted to the foundation pit.
[0010] Furthermore, the lag time constant is determined in S2. The steps include: before excavation of the foundation pit, setting up a temporary water level observation well at the center of the foundation pit, continuously collecting water level data of the confined aquifer at a sampling frequency of 1 time per hour, and simultaneously obtaining measured data of the river water level for the corresponding time period. ; The river water level change sequence was calculated using cross-correlation analysis. Sequence of water level changes in the foundation pit cross-correlation coefficient The time shift corresponding to the maximum cross-correlation coefficient. As a time lag constant ; By quantitatively determining the response delay between the river water level and the foundation pit water level through cross-correlation analysis, a quantitative basis is provided for converting tidal forecasts into foundation pit water level predictions.
[0011] Furthermore, during the excavation of the foundation pit, after each 5-meter excavation depth, the measurement of the lag time constant is repeated to obtain an updated lag time constant. and will With the initial lag time constant according to Perform a weighted average, where the weighting coefficients are... With cumulative excavation depth Decrease linearly from 1 to 0.5. , The unit is meters, and the comprehensive lag time constant of the current construction phase is obtained. ; As the excavation depth increases, the seepage path of the confined aquifer changes. By dynamically updating the lag time constant, the generation of the time axis is always adapted to the current hydrogeological conditions.
[0012] Furthermore, before using the cross-correlation analysis method to calculate the lag time constant, the monitoring data is first screened: if rainfall occurs during the monitoring period, the water level data during the rainfall period and the following 12 hours are removed; If the maximum cross-correlation coefficient of three consecutive cross-correlation analyses is less than 0.6, the monitoring period will be extended to 14 days. By filtering data, the influence of interference factors such as rainfall on the determination of lag time constant is eliminated, ensuring the accuracy of core parameters.
[0013] Furthermore, it also includes the following steps: Based on the foundation pit support design and anti-surge calculation results, the upper limit safety threshold of the foundation pit water level is determined. and lower limit safety threshold ; Upper security threshold and lower limit safety threshold By overlaying it with the expected fluctuation time axis of the foundation pit water level, an allowable water level operating zone that changes over time is generated; According to real-time water level Based on their relative positions within the permissible water level operating zone, the water level status of the foundation pit is divided into a first risk zone, a second risk zone, and a third risk zone, wherein the first risk zone is... or The second risk zone is and The third risk zone is and ; By dividing water levels into risk zones, the degree to which water levels deviate from the safe range is quantified, providing a basis for precise control.
[0014] Furthermore, the following steps are also included: establishing the matching degree relationship between the ebb tide active precipitation section, the slack tide balance maintenance section, the flood tide buffer and backflow section and the first risk zone, the second risk zone, and the third risk zone, forming a two-dimensional matching table; During the execution of S4, the matching degree between the current dynamic running segment and the risk zone where the current water level is located is calculated in real time in the two-dimensional matching table, and the precipitation reinjection operation mode corresponding to the dynamic running segment with the highest matching degree is selected as the main control mode for execution. Calculate the matching degree of the master control mode. Second highest matching degree The difference ,when When the main control mode precipitation recharge operation parameters are fully executed, when At that time, a 10% proportional adjustment is made based on the precipitation reinjection operation parameters in the main control mode. The operating parameters of the main control mode are then matched with the operating parameters of the second-highest matching mode. and The ratios are weighted and merged before execution; By calculating the matching degree and judging the difference, the operating parameters are dynamically adjusted when there are errors in the tide forecast or when a sudden situation occurs, so that the control strategy can adapt to the actual water level changes.
[0015] Furthermore, it also includes emergency control measures: real-time monitoring of the water level in the foundation pit. ,when Exceed When necessary, the system will be forcibly switched to emergency precipitation mode, causing all precipitation wells to operate at their rated flow rate. when Below When necessary, the system will be forcibly switched to emergency reinjection mode, so that all reinjection wells will operate at the rated flow rate. treat Restore to to Once the area is within the specified range, the hierarchical control based on the expected fluctuation time axis of the foundation pit water level will be restored. Emergency control measures provide safety assurance under extreme conditions and prevent engineering accidents caused by water levels exceeding limits.
[0016] Furthermore, it also includes parameter optimization steps: performing cross-correlation analysis on the accumulated operating data every 30 days and recalculating the lag time constant; The frequency of water levels exceeding the allowable operating range during each dynamic operating period is statistically analyzed. When the frequency of exceeding the limit exceeds 20% in a certain period, the single-well flow rate of the precipitation well during that period is recorded. Or the flow rate of a single injection well Increase by 10% based on the original setting; By optimizing parameters, the system gains self-learning capabilities, enabling it to adapt to changes in geological conditions and construction progress, and gradually bringing control parameters closer to the optimal level.
[0017] Furthermore, the start and end times of each dynamic running segment in S3 are adjusted in a rolling manner according to the daily updated tidal forecast data, so that the time period division is synchronized with the peak tide time and trough tide time in the latest tidal forecast data. Rolling adjustments ensure that the time period division always matches the latest tide forecast, avoiding inaccurate time period division due to tide forecast errors.
[0018] A graded dewatering and recharge control system for deep foundation pits in riverside tunnels is provided. The system uses the method described in any one of the above methods to perform graded control of dewatering wells and recharge wells. The system uses the above method as the control logic, and generates control commands by acquiring tidal forecast and water level monitoring data and sends them to the control units of each dewatering well and recharge well.
[0019] This invention provides a method for graded dewatering and recharge control in deep foundation pits of riverside tunnels. Compared with existing technologies, it has the following advantages: This invention acquires hourly tidal forecast data and real-time water level monitoring data, and uses cross-correlation analysis to determine the lag time constant of the transmission of river water level changes to the confined aquifer within the foundation pit. This lag time constant reflects the time difference between river water level changes and the foundation pit water level response. By applying this to the tidal forecast timetable, a time axis for expected water level fluctuations in the foundation pit is generated. This time axis marks the expected water level state at each moment within the next 24 hours as a rising or falling period, transforming uncontrollable tidal fluctuations into predictable time coordinates. Using this time axis as a control benchmark, the precipitation recharge system can predict water level trends before tidal changes are transmitted to the foundation pit and adjust its operating status in advance, thereby overcoming the inherent lag defects of traditional water level threshold control methods.
[0020] This invention divides a 24-hour period into three dynamic operating segments based on the expected fluctuation timeline of the foundation pit water level. The ebb tide active precipitation segment corresponds to the expected decline period, during which the river water level drops and the foundation pit water level naturally tends to decrease; the system operates precipitation wells at a higher flow rate during this period. The rising tide buffer recharge segment corresponds to the expected rising period, during which the river water level rises and the external water pressure in the foundation pit increases; the system reduces the number of operating precipitation wells and activates recharge wells during this period. The slack tide balance maintenance segment corresponds to the transition period, during which the system maintains only the minimum precipitation requirement. This tiered operation mode, matching the tidal phases, allows the precipitation recharge strategy to conform to natural hydrological rhythms, taking corresponding control measures at different tidal phases, thus improving the adaptability of traditional single control modes to dynamic environments.
[0021] This invention establishes a dynamic matching relationship between operating periods and risk zones. The current risk zone is determined by real-time water level, and the matching degree between the current time period and each risk zone is calculated. The operating mode corresponding to the time period with the highest matching degree is selected as the main control mode. Simultaneously, three parameter execution modes—full execution, proportional adjustment, or weighted fusion—are determined based on the magnitude of the matching degree difference. When the matching degree difference is large, the main control mode is executed fully. When the matching degree difference is moderate, proportional flow adjustment is performed based on the main control mode. When the matching degree difference is small, the parameters of the main control mode and the mode with the second highest matching degree are weighted and fused according to the matching degree. This control mechanism can dynamically adjust operating parameters according to the degree to which the actual water level deviates from the ideal trajectory when there are errors in tidal forecasts or unexpected situations such as rainfall, improving the system's adaptability to uncertainties.
[0022] This invention also includes emergency control and parameter optimization steps. The emergency control step monitors the pit water level in real time. When the water level exceeds 90% of the upper safety threshold, it forcibly switches to emergency dewatering mode; when the water level falls below 110% of the lower safety threshold, it forcibly switches to emergency recharge mode, providing safety assurance for extreme working conditions. The parameter optimization step performs cross-correlation analysis on accumulated operating data every 30 days to recalculate the lag time constant. It also re-measures the lag time constant after each 5-meter excavation depth and weights it with the initial value to obtain a comprehensive lag time constant that varies with excavation depth. By statistically analyzing the frequency of water level exceeding limits in different time periods, it automatically increases the single-well flow rate for periods with an exceedance frequency exceeding 20%, helping the system adapt to changes in geological conditions during construction and gradually bringing the control parameters closer to optimal. Attached Figure Description
[0023] Figure 1 This is a flowchart illustrating the method execution of the present invention; Figure 2 This is a detailed control flowchart of the method of the present invention. Detailed Implementation
[0024] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0025] Example 1 As attached Figures 1 to 2 The following is a method for graded dewatering and recharge control in a deep foundation pit of a riverside tunnel, and its specific implementation details are as follows: The foundation pit of a certain riverside tunnel project is located in a typical section of the lower reaches of the Yangtze River. The geological conditions of the site are covered by Quaternary loose layer, with underlying bedrock. The main aquifer is a confined aquifer. The designed excavation depth of the foundation pit is 30m, the thickness of the confined aquifer is 20m, the permeability coefficient is 50m / d, the initial confined water head is 6m, and the outline of the foundation pit is rectangular with dimensions of 80m×120m.
[0026] Thirty-two dewatering wells were evenly arranged along the outline of the foundation pit. Each dewatering well was a complete well with a depth of 5m below the confined aquifer. Twenty-four recharge wells were arranged along the surrounding building protection zone. The depth of the recharge wells was the same as that of the dewatering wells.
[0027] All dewatering wells and recharge wells are equipped with flow regulating valves and intelligent control units, which can remotely control start / stop and flow. The central control system is deployed at the site monitoring center and is connected to the control units of each well, water level sensors, and tidal data interfaces via a wireless network.
[0028] S1: Data Acquisition The system connects to the tide forecast service interface provided by the local maritime authority to obtain hourly tide forecast data for the river section where the project is located. This data is pushed in JSON format and contains the predicted tide level for every hour within the next 72 hours, with an accuracy of 0.01m. The data is updated hourly, and the system reception delay is less than 1 minute. After being parsed, the tide forecast data is stored in a real-time database, and the timestamp is synchronized with the system time.
[0029] Meanwhile, a temporary water level observation well was set up at the center of the foundation pit. A vibrating wire water level sensor was installed every 5 meters along the depth of the well, for a total of 6 monitoring points, located at 5m, 10m, 15m, 20m, 25m, and 30m below the ground surface. The sensors output a 4-20mA analog signal, which is converted into a digital signal by the data acquisition module and transmitted to the central control system via an RS485 bus. The sampling frequency was set to once per hour.
[0030] The system establishes an independent configuration table for each sensor, storing information such as sensor number, installation depth, measurement range, and calibration coefficient.
[0031] During data acquisition, the system converts the 4-20mA signal into the actual water level value according to the calibration coefficient and removes outliers: if the reading of a certain sensor deviates from that of the adjacent sensor by more than 2m, it is judged as an anomaly and that point is not included in the average value calculation.
[0032] At each hour on the hour, the system reads the effective water level values from each sensor and takes the arithmetic mean as the measured value of the pit water level at that moment. The data is then stored in a database. All monitoring data is compiled into a time series for subsequent analysis.
[0033] S2: Determination of hysteresis time constant and generation of expected fluctuation time axis of foundation pit water level Before the formal excavation of the foundation pit, continuous water level monitoring was conducted using temporary water level observation wells, with a monitoring period of 7 days. At the same time, actual measured water level data of the river for the corresponding 7-day period were obtained from the local hydrological department. This data was in hourly units and aligned with the timestamp of the foundation pit water level monitoring.
[0034] The measured data sequence of the river water level is denoted as... The measured data sequence of the foundation pit water level is denoted as ,in For time indexing, , (7 days x 24 hours).
[0035] Cross-correlation analysis was used to determine the lag relationship between the two sets of sequences. Cross-correlation coefficient. The calculation formula is: ; in for The measured value of the river water level at that moment. for The measured value of the water level in the foundation pit at that moment. The arithmetic mean of the river water level series. This represents the arithmetic mean of the water level sequence in the foundation pit. This is a time shift, ranging from 0 to 72 hours, with a step size of 1 hour. The system calculates each value in a loop through programming. corresponding This yields a sequence of cross-correlation coefficients.
[0036] The cross-correlation analysis procedure uses a sliding window calculation with a window length of 72 hours to avoid boundary effects. Each calculation yields... After sequencing, the system automatically identifies local peaks and records the corresponding peak values. value.
[0037] If multiple consecutive corresponding If the values are close (difference less than 0.05), then take these values. The weighted average value is used as the lag time constant. To improve the stability of the measurement. The calculations in this project yielded... hour The maximum value is 0.85, therefore Hour.
[0038] Obtain the lag time constant Then, the system will shift each hour in the hourly tide forecast timetable backwards. Hourly timelines are generated to predict the water level fluctuations in the foundation pit. Specifically, for each hour in the tidal forecast... Assign its tidal value to time. And determine the expected state at that moment based on the tidal phase.
[0039] like During low tide, Mark as the expected decline period; if During high tide, Mark as the expected upward period; if During the tidal transition period, This is marked as a transition period. The expected state at each hour within the next 24 hours is then obtained and stored as an array in the shared memory of the control system for real-time querying by subsequent steps.
[0040] S3: Dynamic operation segment division and preset precipitation recharge operation mode Based on the expected fluctuation timeline of the foundation pit water level, the system divides each 24-hour day into three consecutive dynamic operating segments.
[0041] The division method is as follows: starting from 0:00 on the day, the expected state at each moment on the time axis is scanned. Periods continuously marked as expected to decrease are merged into the ebb tide active precipitation period, and periods continuously marked as expected to rise are merged into the flood tide buffer and backflow period. The gap between the two is the slack tide balance maintenance period. The start and end times of each period are accurate to the minute and stored in the control plan table.
[0042] Each dynamic operation segment corresponds to a preset precipitation recharge operation mode, and the mode parameters are based on the total design flow rate of the foundation pit dewatering. The number of wells is predetermined. The total design precipitation flow rate for this project is... m 3 / h corresponds to a single-well flow rate of 50m³ / h for all 32 precipitation wells. 3 / h.
[0043] The preset modes for each time period are as follows: Active precipitation phase during low tide: Number of precipitation wells opened Single well flow rate m 3 / h, number of recharge wells opened Single well reinjection volume .
[0044] Tidal Balance Maintenance Section: Number of Rainwater Wells Open Single well flow rate m 3 / h, number of recharge wells opened Single well reinjection volume .
[0045] High tide buffer and recharge section: Number of dewatering wells opened Single well flow rate m 3 / h, number of recharge wells opened Single well reinjection volume Based on 80% of the total precipitation flow for the current period, that is: m 3 / h.
[0046] After the time period is divided, the system generates a time period switching schedule, which includes the start and end times of each time period on the next day, accurate to the second. This schedule is stored in JSON format and is synchronously backed up to a redundant server.
[0047] If the tidal forecast data is updated, the system will automatically compare the differences between the old and new time periods. If the start and end times of a certain time period change by more than 15 minutes, the control plan will be regenerated and the on-duty personnel will be notified.
[0048] The start and end times of the above-mentioned periods are adjusted on a rolling basis according to the daily updated tidal forecast data. At 0:00 every day, the control system recalculates the start and end times of each period of the next day based on the latest 72-hour tidal forecast and updates the control plan table.
[0049] S4: Hierarchical Control Execution The central control system uses the expected fluctuation timeline of the foundation pit water level as a benchmark to monitor the current moment in real time (accurate to the minute). The system maintains a timer that compares the current time with the current time every second. When the current moment reaches the start time of a certain dynamic operating segment, the system reads the corresponding operating mode parameters from the control plan table and sends instructions to the control units of all dewatering wells and recharge wells to execute the switching operation.
[0050] The switching process adopts a soft switching method: the system calculates the target opening degree of the flow regulating valve of each well through the PID controller and adjusts it step by step in the form of a ramp function. The switching time is preset to 5 minutes. During this period, the actual flow rate transitions to the target value in a linear manner to avoid sudden changes.
[0051] During the soft handover process, the system collects feedback values from the flow meters of each well in real time and compares them with the target flow rate. If the actual flow rate deviates from the target flow rate by more than 5% for more than 1 minute, the system triggers a flow anomaly alarm and automatically adjusts the PID parameters for compensation. After the handover is completed, the system records indicators such as handover time and maximum flow deviation, and stores them in the performance log.
[0052] During each dynamic operating period, the system does not simply run according to fixed parameters, but continuously performs refined control, dynamically adjusting the operating parameters based on real-time water level feedback. The refined control program is executed in a 1-minute cycle until the start time of the next period arrives, at which point the period switching is re-executed.
[0053] The refined control based on risk range and matching degree is as follows: First, based on the foundation pit support design and anti-surge calculation results, the upper limit safety threshold of the confined aquifer at the bottom of the foundation pit is determined. and lower limit safety threshold In this project, the safety factor for surge resistance is taken as 1.2, and the calculated value is... m (relative to the ground surface); based on the surrounding environment's settlement control requirements. m.
[0054] Will and By overlaying this data with the expected fluctuation timeline of the foundation pit water level, an allowable water level operating zone that varies over time is generated. The upper boundary of this operating zone is... The lower boundary is This indicates that the water level in the foundation pit should always be controlled within this range.
[0055] According to real-time water level (Taking the average value of 6 monitoring points) Based on their relative positions within the allowable water level operating zone, the water level status of the foundation pit is divided into three risk zones: First risk zone: or In this project m, m, meaning that water levels above -4m or below -18m are considered high-risk zones.
[0056] Second risk zone: and . m, that is, water levels between -2.5m and -4m and above -18m are considered to be within the normal fluctuation range.
[0057] Third risk zone: and That is, water levels below -2.5m and above -18m are considered low-risk areas.
[0058] A matching degree relationship was established between the active precipitation section of ebb tide, the balance maintenance section of slack tide, the buffer and backflow section of flood tide, and the three risk zones, forming a two-dimensional matching table. The matching degree values were calibrated through previous numerical simulations and adjusted after trial operation. The matching degrees used in this project are shown in Table 1:
[0059] Table 1. Matching Degree Between Dynamic Runtime Segments and Risk Zones In the refined control loop, the system first queries the expected fluctuation timeline of the foundation pit water level at the current moment to determine the current dynamic operating segment, and then determines the current water level based on the timeline. Once the risk range is determined, the corresponding matching score is read from the matching table.
[0060] The matching degree of the three time periods is compared, and the time period corresponding to the maximum value is selected as the master control mode. If the time period corresponding to the maximum value is the same as the current actual time period, the master control mode is the current time period mode; if they are different, the master control mode is the other time period mode with the highest matching degree. At this time, the system will temporarily adopt the running parameters of this mode, but the time axis will still serve as the basis for switching at the next moment.
[0061] Calculate the matching degree of the master control mode. Second highest matching degree The difference ,according to The magnitude determines the specific execution method of the main control mode precipitation recharge operation parameters: when At this time, the master control mode is significantly better than other modes. The system fully adopts the operating parameters of the master control mode, that is, the number of dewatering wells opened, the flow rate of a single well, the number of recharge wells opened, and the recharge volume of a single well are all executed according to the set values of the master control mode.
[0062] when At this time, the main control mode is superior but competition exists, so the system makes proportional adjustments based on the parameters of the main control mode. The adjustment direction is determined by the trajectory of the current water level and the ideal water level. The deviation determines.
[0063] Ideal water level trajectory Generated by combining the expected fluctuation timeline with a safety threshold: during the active precipitation phase of ebb tide, It decreases linearly from 0.8P to 1.2Q; In the high tide buffer and backflow section It rises linearly from 1.2Q to 0.8P; During the period of slack tide balance Keep as .
[0064] The system calculates the ideal water level at the current moment in minutes, based on the current time period type and the proportion of elapsed time within that period. For example, during the ebb tide active precipitation phase, if the total length of the time period is... The current time is the time since the start of the time period. ,but .
[0065] like This indicates insufficient drawdown, and the system will increase the single-well flow rate of the drawdown wells in the main control mode by 10% based on the original value; like This indicates excessive precipitation, and the system will reduce the flow rate of each precipitation well by 10%. The adjustment only applies to the precipitation flow rate; the reinjection volume remains unchanged.
[0066] when When the matching degree of two modes is close, the system will weight and fuse the operating parameters of the master mode with the operating parameters of the mode with the second highest matching degree according to the matching degree. The fused parameters Calculate using the following formula: ; in The set of operating parameters for the master control mode includes the number of dewatering wells opened. single-well flow rate of precipitation wells Number of recharge wells opened Single well flow rate of reinjection well ; This is the set of operating parameters for the pattern corresponding to the second-highest matching degree.
[0067] The calculated fusion parameters may be non-integers. The system achieves continuous control by adjusting the flow rate ratio of each well: for example, if the number of dewatering wells that are open is a decimal, the flow rate is proportionally allocated to some wells that are fully open and some wells that are partially open.
[0068] The specific emergency control steps are as follows: The system monitors the water level in the foundation pit at a 1-minute interval. ,when Exceed At this time, the emergency precipitation mode is triggered. The system immediately interrupts all normal control logic and sends a forced full-open command to all 32 precipitation wells, adjusting the flow rate of each well to the rated value of 50m³. 3 / h, simultaneously shut down all recharge wells and issue an audible and visual alarm.
[0069] when Below At that time, the emergency reinjection mode is triggered, forcing all 24 reinjection wells to operate at their rated flow rates. The total reinjection volume is calculated based on 80% of the current total precipitation flow and evenly distributed. Simultaneously, all other precipitation wells except the two emergency precipitation wells at the deepest part of the foundation pit are shut down, and the emergency precipitation wells operate at a minimum flow rate of 10m³ / h. 3 / h maintain.
[0070] The system continuously monitors the water level, pending... Once the water level returns to the range of 0.8P to 1.2Q, the system will automatically exit emergency mode and resume tiered control based on the expected fluctuation time axis of the pit water level.
[0071] The specific steps for parameter optimization are as follows: The system records the actual water level change curve and daily tidal data daily, storing them in a historical database. A parameter optimization process is triggered every 30 days: First, cross-correlation analysis is performed on the river water level and foundation pit water level data from the past 30 days, and the lag time constant is recalculated, denoted as... .like If the time interval is 1 hour, then update the overall lag time constant. And regenerate the subsequent expected fluctuation timeline of the foundation pit water level.
[0072] Comprehensive lag time constant Dynamic updates during construction: After excavation to a depth of 5 meters, the lag time constant measurement in S2 is repeated to obtain the updated value at the current depth. .Will With initial value According to the weighted average formula Calculate the new composite lag time constant The weighting coefficient , This represents the cumulative excavation depth (in meters).
[0073] This formula makes the initial measured values dominant during shallow excavation, while the weight of the updated values gradually increases during deep excavation.
[0074] Meanwhile, the system counts the cumulative number of times the water level exceeded the allowable water level operating zone during each dynamic operating period in the past 30 days, and records each over-limit event at the hourly granularity, including the start time of the over-limit, the end time of the over-limit, and the maximum over-limit range.
[0075] Calculate the frequency of exceeding limits for each time period (number of times exceeding limits / 30). When the frequency of exceeding limits for a certain time period exceeds 20%, the system will automatically increase the flow rate of the single well of the precipitation well or the single well of the recharge well for that time period by 10% based on the original set value.
[0076] If the limit is exceeded for three consecutive optimization cycles in the same period, the single adjustment range will be increased to 15% until the frequency of exceeding the limit drops below 20%.
[0077] All adjustment records are stored in the log, including the operator, operation time, and parameters before and after the adjustment, forming an audit trail that can be manually reviewed.
[0078] Through the above implementation methods, this approach achieves synchronized operation of the rainwater recharge system with tidal rhythms. While ensuring the safety of the foundation pit and controlling surrounding settlement, it improves rainwater efficiency and reduces energy consumption. In actual system operation, the water level in the foundation pit is consistently controlled between -5m and -15m, with no sudden surges or excessive settlement events occurring. The average daily power consumption is reduced by approximately 25% compared to traditional constant-flow rainwater methods.
[0079] Some of the data in the above formulas are numerical calculations with dimensions removed, and the contents not described in detail in this specification are all prior art known to those skilled in the art.
[0080] The above embodiments are only used to illustrate the technical methods of the present invention and are not intended to limit it. Although the present invention has been described in detail with reference to preferred embodiments, those skilled in the art should understand that modifications or equivalent substitutions can be made to the technical methods of the present invention without departing from the spirit and scope of the technical methods of the present invention.
Claims
1. A method for graded dewatering and recharge control in deep foundation pits of riverside tunnels, characterized in that, Includes the following steps: S1: Obtain hourly tidal forecast data for the river section where the deep foundation pit of the Linjiang Tunnel is located, as well as real-time water level monitoring data of the confined aquifer collected by water level sensors deployed along the depth of the foundation pit. S2: Based on the response relationship between the hourly tide forecast data and the real-time water level monitoring data, determine the lag time constant of the transmission of river water level tidal changes to the confined aquifer in the foundation pit, and convert the hourly tide forecast data into the expected fluctuation time axis of the foundation pit water level based on the lag time constant. S3: Based on the expected fluctuation time axis of the foundation pit water level, the 24 hours are divided into three continuous and interconnected dynamic operating periods: the ebb tide active precipitation period, the slack tide balance maintenance period, and the rising tide buffer recharge period. S4: Using the expected fluctuation time axis of the foundation pit water level as the control benchmark, when the current time reaches the start time of a certain dynamic operating period, the precipitation recharge system is switched to the precipitation recharge operation mode corresponding to that period.
2. The method for graded dewatering and recharge control of deep foundation pits in riverside tunnels according to claim 1, characterized in that, In step S3, the ebb tide active precipitation segment corresponds to the expected descent period, the slack tide balance maintenance segment corresponds to the transition period from the end of the expected descent to the start of the expected rise, and the rising tide buffer recharge segment corresponds to the expected rise period. Each dynamic operation segment corresponds to a preset precipitation recharge operation mode. The precipitation recharge operation mode includes the set values of the number of precipitation wells opened, the flow rate of a single precipitation well, the number of recharge wells opened, and the flow rate of a single recharge well within that period.
3. The method for graded dewatering and recharge control of deep foundation pits in riverside tunnels according to claim 1, characterized in that, The step of determining the lag time constant in step S2 includes: S21. Before the excavation of the foundation pit, a temporary water level observation hole is set at the center of the foundation pit to continuously collect the water level data of the confined aquifer at a sampling frequency of 1 time / hour, and at the same time obtain the measured data of the river water level during the corresponding period. S22. The cross-correlation coefficient between the river water level change sequence and the foundation pit water level change sequence is calculated using the cross-correlation analysis method. The time shift corresponding to the maximum value of the cross-correlation coefficient is taken as the lag time constant. ; S23. During the excavation of the foundation pit, after each 5-meter excavation depth is completed, the measurement of the lag time constant is repeated to obtain the updated lag time constant. and will and according to Perform a weighted average, where With cumulative excavation depth Decrease linearly from 1 to 0.
5. , The unit is meters, and the comprehensive lag time constant of the current construction phase is obtained. .
4. The method for graded dewatering and recharge control of deep foundation pits in riverside tunnels according to claim 3, characterized in that, In step S22, before calculating the lag time constant using the cross-correlation analysis method, the monitoring data is first screened: If rainfall occurs during the monitoring period, water level data for the period of rainfall and the following 12 hours will be excluded. If the maximum cross-correlation coefficient of three consecutive cross-correlation analyses is less than 0.6, the monitoring period will be extended to 14 days.
5. The method for graded dewatering and recharge control of deep foundation pits in riverside tunnels according to claim 1, characterized in that, This also includes the process of determining the risk range: Based on the foundation pit support design and anti-surge calculation results, the upper limit safety threshold of the foundation pit water level is determined. and lower limit safety threshold ; Will and By overlaying it with the expected fluctuation time axis of the foundation pit water level, an allowable water level operating zone that changes over time is generated; According to real-time water level Based on their relative positions within the permissible water level operating zone, the water level status of the foundation pit is divided into a first risk zone, a second risk zone, and a third risk zone, wherein the first risk zone is... or The second risk zone is and The third risk zone is and .
6. The method for graded dewatering and recharge control of deep foundation pits in riverside tunnels according to claim 5, characterized in that, It also includes the adjustment process of precipitation reinjection operation parameters: Establish the matching degree relationship between the ebb tide active precipitation section, the slack tide balance maintenance section, the flood tide buffer and backflow section and the first risk zone, the second risk zone, and the third risk zone, and form a two-dimensional matching table; During the execution of S4, the matching degree between the current dynamic running segment and the risk zone where the current water level is located is calculated in real time in the two-dimensional matching table, and the precipitation reinjection operation mode corresponding to the dynamic running segment with the highest matching degree is selected as the main control mode for execution. Calculate the matching degree of the master control mode. Second highest matching degree The difference ,when When the main control mode precipitation recharge operation parameters are fully executed, when At that time, a 10% proportional adjustment is made based on the precipitation recharge operation parameters in the main control mode. The operating parameters of the main control mode are then matched with the operating parameters of the second-highest matching mode. and The ratios are weighted and then merged before execution.
7. A method for graded dewatering and recharge control of deep foundation pits in riverside tunnels according to claim 5, characterized in that, It also includes emergency control procedures: Real-time monitoring of foundation pit water level ,when Exceed When necessary, the system will be forcibly switched to emergency precipitation mode, causing all precipitation wells to operate at their rated flow rate. when Below When necessary, the system will be forcibly switched to emergency reinjection mode, so that all reinjection wells will operate at the rated flow rate. treat Restore to to Once the area is within the specified range, the hierarchical control based on the expected fluctuation time axis of the foundation pit water level will be restored.
8. A method for graded dewatering and recharge control of deep foundation pits in riverside tunnels according to claim 5, characterized in that, It also includes parameter optimization steps: Perform a cross-correlation analysis on the accumulated operating data every 30 days and recalculate the lag time constant; The frequency of water levels exceeding the allowable operating range during each dynamic operating period is counted. When the frequency of exceeding the limit exceeds 20% in a certain period, the flow rate of a single well in the precipitation well or the flow rate of a single well in the recharge well during that period is increased by 10% based on the original set value.
9. A method for graded dewatering and recharge control of deep foundation pits in riverside tunnels according to claim 1, characterized in that, In step S3, the start and end times of each dynamic running segment are adjusted on a rolling basis according to the daily updated tide forecast data, so that the time period division is synchronized with the peak tide time and the trough tide time in the latest tide forecast data.
10. A graded dewatering and recharge control system for deep foundation pits in riverside tunnels, wherein the method described in any one of claims 1 to 9 is used to grade the dewatering wells and recharge wells.