A combined TBM and drill-and-blast construction method for water conveyance tunnels
By setting up a vertical shaft outside the high-speed railway line protection zone as the TBM exit point, and combining TBM with drill-and-blast construction, the problem of high construction costs within the high-speed railway line protection zone was solved, achieving safe, economical, and efficient water conveyance tunnel construction. Furthermore, the vertical shaft can be reused, reducing project costs.
Patent Information
- Application Number
- CN202611325858.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-28
- Publication Date
- 2026-11-17
AI Technical Summary
When constructing water conveyance tunnels within the protection zone of high-speed railway lines, the existing TBM method is expensive and the excavated material is difficult to utilize, while the drill-and-blast method is prohibited within the protection zone, leading to increased project costs.
The construction method combines TBM and drill-and-blast, with a vertical shaft set up outside the high-speed railway line protection zone as the TBM exit point. TBM and drill-and-blast methods are used for construction inside and outside the protection zone respectively, and the vertical shaft also serves as a pressure regulating well during operation.
It enables the safe and economical construction of water conveyance tunnels within the protection zone of high-speed railway lines, reduces project investment, makes flexible use of terrain, and allows for the reuse of vertical shaft functions, reducing the need for dedicated tunnel exit structures and improving construction efficiency.
Smart Images

Figure CN123109683A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of tunnel construction technology in water conservancy and hydropower projects, specifically to a combined construction method for constructing water conveyance tunnels within the protection zone of high-speed railway lines in water diversion projects. This method involves using TBM pipe construction for mountain tunnels within the protection zone and drilling and blasting construction for mountain tunnels outside the protection zone. Background Technology
[0002] Water diversion and transfer projects, as a major technical means to optimize water resource allocation, are an important part of the national water network project.
[0003] The main construction methods for water conveyance tunnels are drill-and-blast (DUB) and tunnel boring machine (TBM) methods. DUB is widely used in water conservancy and hydropower projects due to its strong adaptability to geological formations, low cost, and the ability to comprehensively utilize excavated material. However, considering ventilation and excavation requirements, it necessitates the construction of adits to achieve "short-term excavation of long tunnels," with a single working face length generally not exceeding 3.0 km, and ideally not exceeding 3.5 km under extreme conditions. TBM, on the other hand, is largely unrestricted by ventilation limitations, boasts a high degree of automation, and minimizes disturbance to the surrounding rock. However, excavated material is difficult to comprehensively utilize, resulting in a higher overall excavation unit price. TBM is frequently used for long-distance water conveyance tunnels where adits are not feasible, or when water conveyance tunnels intersect closely with sensitive structures such as high-speed rail tunnels or highway tunnels. When the total length of the water conveyance tunnel is less than 7.0 km, the excavation unit price for TBM-constructed water conveyance tunnels, after amortizing the cost of newly purchased equipment, is generally nearly double that of the DUB method. According to engineering examples, the unit price of TBM construction excavation is approximately 1.8 to 2.0 times that of the drill-and-blast method, and the excavated material is difficult to utilize comprehensively, further increasing the project cost. Furthermore, although the rock jacking method can also be used for railway tunnel construction, the TBM method has advantages over the rock jacking method, such as longer single-heading excavation distance, less disturbance to the surrounding rock, and wider adaptability to geological conditions, making it particularly suitable for long-distance water conveyance tunnels crossing high-speed railway protection zones.
[0004] The protection zone of a high-speed railway line is 1 km. Water conveyance tunnels constructed within the protection zone are not allowed to use the drill-and-blast method. The only conventional construction method is the TBM method, which results in a higher overall project cost for railway-related tunnels.
[0005] If the water conveyance tunnel adopts the conventional diameter and rents existing equipment, and then switches to the drill-and-blast method for construction after it exceeds the high-speed rail protection zone, the project investment can be effectively saved. However, if there are no terrain conditions outside the high-speed rail protection zone to set up a construction adit as the TBM outlet, the construction cost will be passively increased when the water conveyance tunnel constructed using the TBM method is forced to extend outside the high-speed rail protection zone. Summary of the Invention
[0006] To address the problems existing in the prior art, this invention provides a combined TBM and drill-and-blast method for constructing water conveyance tunnels. The TBM is used to traverse the protection zone of the high-speed railway line. Outside the protection zone, a vertical shaft is set up at a suitable location in the water conveyance tunnel as the TBM exit point. Outside the vertical shaft, the drill-and-blast method is used for construction. The vertical shaft also serves as a surge tank during the operation of the water conveyance tunnel.
[0007] To achieve the above objectives, the present invention adopts the following technical solution: A method for constructing a water conveyance tunnel using a combination of TBM (Tunnel Boring Machine) and drill-and-blast method includes the following steps: S1. Assemble the TBM at a site with assembly conditions outside the high-speed railway line protection zone of the water conveyance tunnel, and use the drill-and-blast method to excavate a construction adit as a passage for the TBM to advance to the edge of the high-speed railway line protection zone. S2 and TBM were pushed into the construction adit to the edge of the high-speed railway line protection zone, and then the TBM was used to excavate the water conveyance tunnel and cross the high-speed railway line protection zone. S3. Construct water conveyance tunnels from other working faces using the drill-and-blast method, excluding the vertical shaft section, until the bottom of the vertical shaft is reached; the vertical shaft is located outside the boundary of the high-speed railway line protection zone. S4. The vertical shaft is constructed using the drill-and-blast method, with the shaft being constructed from the front and the slag being removed from the back. S5 and TBM were dismantled and lifted out of the shaft after construction reached the vertical shaft; S6. Lin the drilled and blasted section and vertical shaft of the water conveyance tunnel, and seal the construction adit at the junction of the main and adit tunnels.
[0008] Furthermore, the turning radius of the construction adit and the TBM section of the water conveyance tunnel is required to be no less than 500m. The construction adit adopts a portal-type tunnel, and the excavation diameter is determined to be 8.1m × 8.3m (width × height) according to the TBM equipment passage requirements. The first 250m section is still constructed using the drill-and-blast method. The TBM section uses a conventional TBM, with an excavation diameter of 6.5m, a lining diameter of 5.5m, a tunnel segment ring width of 1.2m, a thickness of 35cm, and an outer diameter of 6.2m. Gravel is backfilled between the segments and the tunnel wall, and cement grout is injected. The vertical shaft is located outside the boundary of the high-speed railway protection zone, with an excavation diameter of no less than 10.0m. First, a geological drilling rig is used to drill to the bottom of the water conveyance tunnel, and then reverse drilling is used to enlarge the diameter to 1.0m. The vertical shaft is excavated by blasting in layers from top to bottom, and the rock debris falls from the enlarged hole, passing through the already... The excavated water conveyance tunnel drill-blast section undergoes slag removal; after the TBM is constructed to the shaft, the main unit is disassembled and hoisted out of the shaft first, then the supporting components are gradually pushed into the shaft, section by section, disassembled section by section, and quickly hoisted out of the shaft; the thickness of the single-reinforced concrete lining in the drill-blast section of the water conveyance tunnel is not less than 30cm, and the thickness of the double-reinforced concrete lining is not less than 40cm. After the lining is completed, consolidation grouting is required, with the grouting pressure not less than 1.5 times the water pressure during the operation of the water conveyance tunnel. The consolidation grouting hole at the top also serves as backfill grouting, with a backfill grouting pressure of 0.3-0.4MPa; after the shaft lining is completed, consolidation grouting is required, with the grouting pressure not less than 1.5 times the water pressure during the operation of the shaft; after the lining and grouting work of the water conveyance tunnel is completed, the construction adit is sealed with concrete on the side of the main adit junction closest to the construction adit.
[0009] Compared with the prior art, the present invention also has the following beneficial effects: (1) Safety: TBM causes little disturbance to the surrounding rock, meets the mandatory requirement that drilling and blasting are not allowed in the protection zone of high-speed railway lines, and ensures the safety of high-speed railway tunnels during operation; (2) Economic efficiency: The drill-and-blast method is used outside the protected area to avoid the amortization of the cost of new TBM equipment throughout the entire process, effectively reducing the project investment; (3) Functional reuse: The vertical shaft serves as both the TBM outlet and the pressure regulating well during operation, reducing the need for dedicated outlet structures and further saving investment; (4) Flexibility: The drill-and-blast method is flexible in layout and can be used to set up vertical shafts in suitable terrain, without being limited by the terrain conditions of whether there are ready-made construction adits outside the protected area. (5) Synergistic effect: The vertical shaft serves as both the TBM dismantling and lifting outlet and the pressure regulating well during operation, allowing temporary construction needs and permanent structural design functions to be reused. Compared with the scheme where the TBM is pushed through the protected area and then exits the tunnel at a distance, this method avoids the TBM being forced to extend a long distance by setting up a vertical shaft in a suitable terrain in advance, thus achieving a technical effect of 1+1>2. Attached Figure Description
[0010] Figure 1This is a schematic flowchart of a combined TBM and drill-and-blast method construction method for water conveyance tunnels in rock, provided by an embodiment of the present invention. Figure 2 This is a schematic diagram of the layout of a water conveyance tunnel using a combination of rock TBM and drill-and-blast method provided in an embodiment of the present invention. Figure 3 yes Figure 2 Sectional view A-A; Figure 4 yes Figure 2 B-B sectional view.
[0011] In the diagram: 1-Water conveyance tunnel; 11-Water conveyance tunnel TBM section; 12-Water conveyance tunnel drill and blast section; 2-Construction adit; 3-Vertical shaft; 4-High-speed railway line; 5-High-speed railway protection zone boundary. Detailed Implementation
[0012] The technical solution of the present invention will now be clearly and completely described with reference to the accompanying drawings. Obviously, the described embodiments are merely some embodiments of the present invention, and not all embodiments. All other embodiments obtained by those skilled in the art based on the embodiments of the present invention without creative effort are within the scope of protection of the present invention.
[0013] This invention is applicable to the construction of water conveyance tunnels crossing the protection zone of high-speed railway lines.
[0014] like Figures 2-4 As shown, the water conveyance tunnel 1 is divided into the water conveyance tunnel TBM section 11 and the water conveyance tunnel drill and blast section 12. A vertical shaft 3 is set at a suitable terrain location outside the high-speed railway protection zone 5 of the high-speed railway line 4. The construction adit 2 is connected to the water conveyance tunnel TBM section 11 for TBM assembly and propulsion. The vertical shaft 3 is located outside the protection zone and serves as both the vertical shaft 3 for disassembling and lifting the TBM and the pressure regulating well during operation.
[0015] like Figures 1-4 As shown, the present invention discloses a combined TBM and drill-and-blast method for constructing water conveyance tunnels, comprising the following steps: S1. Assemble the TBM at a site with assembly conditions outside the high-speed railway line protection zone of the water conveyance tunnel 1, and excavate construction adit 2. The site outside the tunnel entrance is required to have a plan dimension of not less than 20m × 80m. The turning radius between construction adit 2 and the TBM section 11 of the water conveyance tunnel is required to be not less than 500m. Construction adit 2 adopts a portal tunnel type, and the excavation diameter is determined to be 8.1m × 8.3m (width × height) according to the TBM equipment passage requirements. The first 250m section will still be constructed using the drill and blast method.
[0016] S2. TBM will be used to excavate water conveyance tunnel 1 and cross the high-speed railway protection zone boundary 5 on both sides of the high-speed railway line 4, which is 1 km on each side. Considering equipment rental, conventional TBM will be used for water conveyance tunnel TBM section 11, with an excavation diameter of 6.5m, a lining diameter of 5.5m, a tunnel segment ring width of 1.2m, a thickness of 35cm, and an outer diameter of 6.2m. Gravel will be backfilled between the segments and the tunnel wall, and cement grout will be injected. S3. The drilling and blasting section 12 of the water conveyance tunnel, other than the shaft 3, is constructed from other working faces using the drilling and blasting method until the bottom of the shaft 3. The shaft 3 is located outside the high-speed railway protection zone 5 of the high-speed railway line 4. The drilling and blasting section 12 of the water conveyance tunnel is initially supported by methods such as concrete spraying, wire mesh anchoring, and steel supports during excavation, according to the actual surrounding rock conditions, to ensure construction safety.
[0017] S4. Shaft 3 will be constructed using the drill-and-blast method, with reverse blasting for slag removal. The excavation diameter will be no less than 10.0m. First, a geological drilling rig will be used to drill to the bottom of the water conveyance tunnel 1. Then, reverse drilling will be used to enlarge the shaft to a diameter of 1.0m. Shaft 3 will be excavated in layers from top to bottom using blasting. The rock debris will fall from the enlarged holes and be removed through the drill-and-blast section 12 of the already excavated water conveyance tunnel.
[0018] After the S5 and TBM are installed in shaft 3, they are disassembled and hoisted out from shaft 3. The main unit is disassembled and hoisted out of shaft 3 first, then the auxiliary components are gradually pushed into shaft 3, disassembled section by section, and quickly hoisted out from shaft 3. Before disassembly, ensure all TBM components are in the disassembly position, disconnect the connection between the main unit and the auxiliary components' connecting bridge, and reliably support the connecting bridge. Ensure all electrical equipment is powered off, and check and release any residual pressure in the hydraulic and compressed air systems. During disassembly, disassemble and hoist simultaneously to minimize the time disassembled components remain in shaft 3, creating space for subsequent disassembly work. S6. Lining of the drill-and-blast section 12 and shaft 3 of the water conveyance tunnel, and sealing of the construction adit 2 at the junction of the main and adit tunnels. The thickness of the single-reinforced concrete lining of the drill-and-blast section 12 of the water conveyance tunnel shall not be less than 30cm, and the thickness of the double-reinforced concrete lining shall not be less than 40cm. After the lining of the drill-and-blast section 12 of the water conveyance tunnel is completed, consolidation grouting shall be carried out. The consolidation grouting pressure shall not be less than 1.5 times the water pressure during the operation of the water conveyance tunnel 1. The consolidation grouting hole at the top shall also be used for backfill grouting, with a backfill grouting pressure of 0.3-0.4MPa. After the lining of shaft 3 is completed, consolidation grouting shall be carried out. The consolidation grouting pressure shall not be less than 1.5 times the water pressure during the operation of shaft 3. After the lining and grouting of the water conveyance tunnel 1 is completed, the construction adit 2 shall be sealed with concrete on the side of the junction of the main and adit tunnels near the construction adit 2.
[0019] The above description is merely a specific embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Any changes or substitutions that can be easily conceived by those skilled in the art within the scope of the technology disclosed in the present invention should be included within the scope of protection of the present invention.
Claims
1. A combined TBM and drill-and-blast method for constructing water conveyance tunnels, characterized in that: It includes the following steps: S1. Assemble the TBM at a site with assembly conditions outside the protection zone of the high-speed railway line of the water conveyance tunnel, and use the drill-and-blast method to excavate a construction adit as a passage for the TBM to advance to the edge of the high-speed railway line protection zone. The S2.TBM was pushed into the construction adit to the edge of the high-speed railway line protection zone, and then the TBM was used to excavate the water conveyance tunnel and cross the high-speed railway line protection zone. S3. Construct water conveyance tunnels from other working faces using the drill-and-blast method, excluding the vertical shaft section, until the bottom of the vertical shaft is reached; the vertical shaft is located outside the boundary of the high-speed railway line protection zone. S4. The vertical shaft is constructed using the drill-and-blast method, with the shaft being constructed from the front and the slag being removed from the back. After the S5 TBM is installed in the shaft, it is dismantled and lifted out from the shaft. S6. Lin the drilled and blasted section and vertical shaft of the water conveyance tunnel, and seal the construction adit at the junction of the main and adit tunnels.
2. The combined TBM and drill-and-blast method for constructing water conveyance tunnels according to claim 1, characterized in that: In step S1, the turning radius of both the construction adit and the TBM section of the water conveyance tunnel is not less than 500m.
3. The combined TBM and drill-and-blast method for constructing water conveyance tunnels according to claim 2, characterized in that: In step S1, the construction adit adopts a city gate-type tunnel, and its excavation diameter (width × height) is not less than 8.1m × 8.3m.
4. The combined TBM and drill-and-blast method for constructing water conveyance tunnels according to claim 3, characterized in that: In step S1, the planar dimensions of the site are not less than 20m × 80m, and the first section of the construction adit is constructed using the drill-and-blast method.
5. The combined TBM and drill-and-blast method for constructing water conveyance tunnels according to claim 1, characterized in that: In step S2, the water conveyance tunnel TBM section is excavated using conventional TBM, and gravel is backfilled between the tunnel segments and the tunnel wall, followed by the injection of cement grout.
6. The combined TBM and drill-and-blast method for constructing water conveyance tunnels according to claim 5, characterized in that: The TBM has an excavation diameter of 6.5m and a lining diameter of 5.5m; the tunnel segment ring is 1.2m wide, 35cm thick, and has an outer diameter of 6.2m.
7. The combined TBM and drill-and-blast method for constructing water conveyance tunnels according to claim 1, characterized in that: In step S3, the water conveyance tunnel drilling and blasting section adopts one or more combinations of concrete spraying, wire mesh anchor spraying, or steel support for initial support during excavation, based on the actual surrounding rock conditions.
8. The combined TBM and drill-and-blast method for constructing water conveyance tunnels according to claim 1, characterized in that: In step S4, the excavation diameter of the shaft is not less than 10.0m; first, a geological drilling rig is used to drill to the bottom of the water conveyance tunnel, and then reverse drilling is used to enlarge the diameter to 1.0m; the shaft is excavated by blasting from top to bottom, and the rock debris falls from the enlarged hole and is discharged through the excavated water conveyance tunnel; the shaft also serves as the TBM dismantling and hoisting outlet and the surge tank during the operation of the water conveyance tunnel, so that the temporary construction needs and the permanent structural design functions can be reused.
9. The combined TBM and drill-and-blast method for constructing water conveyance tunnels according to claim 1, characterized in that: In step S5, after the main unit of the TBM is disassembled, it is first hoisted out of the shaft, and then the rear accessories are gradually pushed into the shaft. The TBM is then disassembled section by section and hoisted out of the shaft. Before disassembly, the connection between the main unit and the rear accessories connecting bridge is disconnected and the connecting bridge is supported.
10. The combined TBM and drill-and-blast method for constructing water conveyance tunnels according to claim 1, characterized in that: In step S6, when the drilling and blasting section lining of the water conveyance tunnel is made of single-reinforced concrete, the thickness shall not be less than 30 cm; when double-reinforced concrete lining is used, the thickness shall not be less than 40 cm. After the drilling and blasting section lining of the water conveyance tunnel is completed, consolidation grouting shall be performed. The consolidation grouting pressure shall not be less than 1.5 times the water pressure during the operation of the water conveyance tunnel. The consolidation grouting hole at the top of the drilling and blasting section of the water conveyance tunnel shall also serve as backfill grouting, with a backfill grouting pressure of 0.3–0.4 MPa. After the lining of the vertical shaft is completed, consolidation grouting shall be performed. The consolidation grouting pressure shall not be less than 1.5 times the water pressure during the operation of the vertical shaft. After the lining and grouting work of the water conveyance tunnel is completed, the construction adit shall be sealed with concrete on the side of the main adit junction near the construction adit.