Water diversion structure based on TBM tunneling and construction method
By adopting a water diversion structure based on TBM excavation in the water diversion system of the pumped storage power station, it is changed to a first-level inclined shaft and set up vertical shafts and construction branch holes, the problems of poor construction safety and large head losses in the existing technology are solved, and water diversion is achieved Shorten system length and improve construction efficiency.
Patent Information
- Application Number
- CN202411128533.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-16
- Publication Date
- 2024-11-26
AI Technical Summary
In the existing water diversion system of pumped storage power stations, the construction safety of the two-stage water diversion inclined shafts is poor and the number of turns is large, resulting in an increase in the length of the water diversion system and an increase in the head loss.
The water diversion structure based on TBM excavation is adopted, and it is changed to a first-level inclined shaft, vertical shafts and construction branch holes are set up to simplify the construction process, improve construction efficiency, and waste slag is transported out and ventilation through vertical shafts and construction branch holes, enhancing safety.
Effectively shorten the length of the water diversion system, reduce head losses, improve construction efficiency and safety, simplify construction processes, and provide the possibility of ventilation and post-maintenance.
Smart Images

Figure CN119021582A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of water conservancy and hydropower engineering, and in particular to a water diversion structure based on TBM excavation and a construction method. Background Art
[0002] At present, most of the water diversion systems of pumped storage power stations in China use two-stage water diversion inclined shafts to divert water from the upstream reservoir to the downstream reservoir through the inclined shafts. A horizontal flat tunnel is excavated between the two-stage water diversion inclined shafts to connect them. An upper flat tunnel is constructed at the upper part of the water diversion inclined shaft, and a lower flat tunnel is constructed at the lower part of the water diversion inclined shaft. This existing construction method has poor construction safety, and the inclined shaft is composed of two-stage inclined shafts, which increases the number of turns, prolongs the length of the water diversion system, and increases the head loss. Summary of the invention
[0003] The invention provides a water diversion structure based on TBM excavation, aiming to change the inclined well from two levels to one level and shorten the length of the water diversion system.
[0004] The present invention is implemented by the following technical scheme: a water diversion structure based on TBM excavation, comprising an inclined shaft and a lower horizontal tunnel, wherein the lower horizontal tunnel is connected to the bottom of the inclined shaft, and the upper part of the inclined shaft is connected to a water diversion well, and the water diversion well is connected to an upstream reservoir;
[0005] It also includes a vertical shaft and a construction branch hole, wherein the construction branch hole is horizontally excavated from the ground to be connected with the inclined shaft, and the vertical shaft is vertically excavated from the ground to be connected with the inclined shaft, and the vertical shaft passes through the construction branch hole.
[0006] Compared with the prior art, the present invention has the following advantages and beneficial effects:
[0007] The present invention adopts a first-level inclined well for water diversion, so that the traditional two-level inclined well is changed to one-level, which can effectively shorten the length of the water diversion system and reduce the head loss. At the same time, compared with the construction of a two-level inclined well, the construction of the first-level inclined well can simplify the construction process and improve the construction efficiency.
[0008] In addition, the present invention also provides a vertical shaft and a construction branch hole, wherein the construction branch hole is horizontally excavated from the ground to be connected with the inclined shaft, so that in the actual process of constructing the inclined shaft, the waste slag generated during the construction process can be transported out of the construction branch hole, and in this scheme, the tunnel boring machine excavates from top to bottom to the construction branch hole, dismantles the machine and then transports it out of the construction branch hole, and the tunnel boring machine enters the lower flat hole and excavates from bottom to top to the construction hole, dismantles the machine and then transports it out of the construction branch hole. This scheme adopts the construction steps from top to bottom and from bottom to top, which can shorten the construction length of the inclined shaft, improve the construction efficiency, and the construction branch hole and the vertical shaft can also play a role in safe rescue and escape, and have higher safety.
[0009] The setting of the vertical shaft provides the possibility for later maintenance. At the same time, the vertical shaft can also play a ventilation role, allowing ventilation during the excavation process and the use of the water diversion system.
[0010] In this scheme, since the ends of the construction branch tunnel and the vertical shaft are connected with the inclined shaft, the vertical shaft and the construction branch tunnel can be excavated to a certain position according to the design requirements during the excavation process. In this way, when the inclined shaft is excavated, the position of the vertical shaft and the construction branch tunnel can play a guiding and correcting role, avoiding a large degree of deviation of the inclined shaft during the excavation process, thereby further ensuring the construction quality.
[0011] Furthermore, there are three vertical shafts, one ends of which are respectively connected to the upper, middle and lower parts of the inclined shaft, and there are two construction branch holes, which are arranged horizontally with each other, and one of the construction branch holes is connected to the upper part of the inclined shaft, and the other construction branch hole is connected to the middle or lower part of the inclined shaft.
[0012] Beneficial effects: In this scheme, three vertical shafts are set up, and they are respectively located in the upper, middle and lower parts of the inclined shaft. At the same time, two construction branch holes are equipped to increase the positions for ventilation and rescue. This can improve the ventilation effect and safety at the same time, and facilitate later maintenance. The two construction branch holes can be used for slag discharge, maintenance or disassembly of the TBM machine at the upper and middle and lower parts of the inclined shaft, which is flexible and convenient to use.
[0013] Furthermore, one end of the construction branch tunnel passes through the inclined shaft to form an extended tunnel.
[0014] Beneficial effect: The setting of the extended hole in this solution can increase the space for disassembling the machine, making it easier for manual walking to disassemble the machine.
[0015] Furthermore, a machine dismantling hole is excavated at the intersection of the lower horizontal tunnel and the inclined shaft.
[0016] Beneficial effect: The setting of the disassembly hole in this solution facilitates assembly or disassembly at this position. The disassembly hole is set separately, the space is larger, and the operation is more convenient and quick.
[0017] Furthermore, the water guide well is arranged at an inclination, and the inclination angle of the water guide well is smaller than the inclination angle of the inclined well.
[0018] Beneficial effect: The inclined setting of the water diversion well can better guide the water flow, so that the water in the upstream reservoir can quickly enter the inclined well from the water diversion well to the downstream reservoir.
[0019] Furthermore, it also includes a gate well, which is connected to the water diversion well, and a gate for controlling the opening or closing of the water diversion well is installed in the gate well.
[0020] Beneficial effect: A separate gate well is set up to facilitate the control of the opening and closing between the gate well and the water diversion well, thereby controlling the on and off of the water flow.
[0021] Furthermore, the inclined shaft extends upward to the ground.
[0022] Beneficial effects: In this solution, the inclined shaft extends upward to the ground, which makes it easy to assemble the tunnel boring machine on the ground and then start the inclined shaft construction, reducing the work of constructing the flat tunnel, thereby reducing costs and shortening construction period.
[0023] Furthermore, the ground at the top of the inclined shaft is flat.
[0024] Beneficial effect: The ground at the top of the inclined shaft is flattened to facilitate assembly of the tunnel boring machine.
[0025] A construction method of a water diversion structure based on TBM excavation, comprising the following steps:
[0026] Step 1, horizontally excavating a construction branch hole, and then excavating a vertical shaft, the vertical shaft passing through the construction branch hole;
[0027] Step 2, horizontally excavating a lower flat tunnel, and excavating a machine dismantling hole at the end of the lower flat tunnel;
[0028] Step 3: Assemble the TBM on the upstream ground, and start digging the inclined shaft from the upstream ground from top to bottom. When the TBM is excavated until it is connected with the construction branch tunnel, the excavated waste is transported out of the construction branch tunnel, and the TBM is disassembled from the construction branch tunnel and transported out of the construction branch tunnel;
[0029] Step 4: Assemble the TBM in the dismantling tunnel, then start excavating from bottom to top until it connects with the construction branch tunnel. The waste slag produced by excavation is transported out from the lower horizontal tunnel at the bottom, and the TBM is dismantled in the construction branch tunnel and then transported out of the construction branch tunnel.
[0030] Beneficial effects: The construction method of this scheme can change the traditional two-stage inclined well into a single-stage one, which can effectively shorten the length of the water diversion system and reduce the head loss. At the same time, compared with the construction of a two-stage inclined well, the construction of a one-stage inclined well can simplify the construction process and improve construction efficiency.
[0031] Furthermore, the construction branch tunnel extends through the inclined shaft, and the portion of the construction branch tunnel extending out of the inclined shaft is an extension tunnel, and the TBM tunneling machine performs dismantling operations in the extension tunnel and the construction branch tunnel.
[0032] Beneficial effect: In this scheme, the construction branch tunnel extends through the inclined shaft, which is convenient for expanding the space for dismantling the machine or loading slag and making the operation more convenient. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] The drawings described herein are used to provide a further understanding of the embodiments of the present invention, constitute a part of this application, and do not constitute a limitation of the embodiments of the present invention. In the drawings:
[0034] Figure 1 It is a structural schematic diagram of a water diversion structure embodiment 1 based on TBM excavation of the present invention;
[0035] Figure 2 This is a schematic diagram of the structure after the water diversion pipe is installed in the inclined shaft in Example 1 of a water diversion structure based on TBM excavation of the present invention;
[0036] Figure 3 This is a structural schematic diagram of Example 2 of a water diversion structure based on TBM excavation according to the present invention.
[0037] Marks and corresponding parts names in the attached drawings:
[0038] Inclined shaft 1, water diversion shaft 2, extension section 3, lower horizontal tunnel 4, vertical shaft 5, construction branch tunnel 6, extension tunnel 7, machine dismantling tunnel 8, gate shaft 9, level ground 10, and water diversion pipe 11. DETAILED DESCRIPTION
[0039] In order to make the objectives, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with embodiments and drawings. The exemplary embodiments of the present invention and their description are only used to explain the present invention and are not intended to limit the present invention.
[0040] Example 1
[0041] like Figure 1-Figure 2 As shown, this embodiment 1 provides a water diversion structure based on TBM excavation, including an inclined shaft 1 and a lower horizontal tunnel 4, the lower horizontal tunnel 4 is connected to the bottom of the inclined shaft 1, the upper part of the inclined shaft 1 is connected to a water diversion shaft 2, and the water diversion shaft 2 is connected to an upstream reservoir.
[0042] like Figure 1 As shown, the water guide shaft 2 is inclined, and the inclination angle of the water guide shaft 2 is smaller than the inclination angle of the inclined shaft 1. The water guide shaft 2 and the upper arc transition of the inclined shaft 1 can reduce the water flow loss. A water diversion structure based on TBM excavation in this embodiment also includes a gate shaft 9, which is connected to the water guide shaft 2. A gate for controlling the opening or closing of the water guide shaft 2 is installed in the gate shaft 9. By opening the gate, the water in the upstream reservoir can start to be diverted to the downstream reservoir through the inclined shaft 1, and closing the gate can stop the water diversion.
[0043] In this embodiment, a water diversion pipe 11 is arranged in the water diversion well 2, the inclined well 1 and the lower adit 4. The water diversion pipe 11 in this embodiment is a pressure pipe.
[0044] In this embodiment, the inclined shaft 1 extends upward to the ground. A section of the extended inclined shaft 1 is an extension section 3. The extension section 3 is used to lower a TBM tunneling machine. During the actual construction process, the ground shovel at the top of the inclined shaft 1 is flat ground, which is used to assemble the TBM tunneling machine. In this way, there is no need to excavate a separate upper flat hole as in the prior art, thereby improving construction efficiency and saving construction costs.
[0045] The water diversion structure in this embodiment also includes a vertical shaft 5 and a construction branch hole 6. The construction branch hole 6 is horizontally excavated from the ground to communicate with the inclined shaft 1. The vertical shaft 5 is vertically excavated from the ground to communicate with the inclined shaft 1, and the vertical shaft 5 passes through the construction branch hole 6. The vertical shaft 5 can ventilate the inclined shaft 1 and the construction branch hole 6. At the same time, the setting of the vertical shaft 5 is also convenient for later maintenance and rescue escape during construction.
[0046] In the present embodiment, one end of the construction branch tunnel 6 passes through the inclined shaft 1 to form an extension tunnel 7, and a dismantling hole 8 is excavated at the intersection of the lower horizontal tunnel 4 and the inclined shaft 1. The extension tunnel 7 and the dismantling hole 8 can be used to dismantle or assemble the tunnel boring machine. The extension tunnel 7 can expand the space for dismantling or transporting slag during actual use, and is convenient for manual operations such as repairing, excavating, removing slag and placing tools of the inclined shaft 1 in the extension tunnel 7. It is equivalent to a transfer station and is very practical. In addition, the construction branch tunnel 6 in the present embodiment can be set at a position that passes through the middle of the inclined shaft 1. The vertical shaft 5 and the construction branch tunnel 6 can be excavated to a certain position according to the design requirements during the excavation process. In this way, when the inclined shaft 1 is excavated, the positions of the vertical shaft 5 and the construction branch tunnel 6 can play a role in guiding and correcting, thereby avoiding a large degree of deviation of the inclined shaft 1 during the excavation process, thereby further ensuring the construction quality.
[0047] This embodiment also provides a construction method of a water diversion structure based on TBM excavation, comprising the following steps:
[0048] Step 1: According to the design requirements, a construction branch hole 6 is excavated horizontally, and the end of the construction branch hole 6 passes through 3m outside the designed inclined shaft 1, and then a vertical shaft 5 is excavated. The vertical shaft 5 passes through the construction branch hole 6, and the bottom end of the construction branch hole 6 extends and passes through the inclined shaft 1. The part of the construction branch hole 6 extending out of the inclined shaft 1 is the extension hole 7. The TBM tunneling machine performs dismantling operations in the extension hole 7 and the construction branch hole 6;
[0049] Step 2, horizontally excavating a lower flat tunnel 4, and excavating a machine dismantling hole 8 at the end of the lower flat tunnel 4;
[0050] Step 3, assembling the TBM on the upstream ground. In this embodiment, the ground is flattened on the upstream ground to facilitate the assembly of the TBM on the flat ground. In this embodiment, an inclined extension hole 7 is first excavated from the upstream ground, and then the TBM is allowed to enter the extension hole 7, and the TBM starts to excavate the inclined shaft 1 from the upstream ground from top to bottom. When the TBM excavates and penetrates the construction branch hole 6, the excavated waste slag is transported out of the construction branch hole 6, and the TBM is dismantled from the construction branch hole 6, and then transported out of the construction branch hole 6. When the TBM is dismantled, it can be dismantled in the extension hole 7, so that the dismantling operation can be carried out without affecting the slag transportation, and this provides more space for dismantling.
[0051] Step 4, transport the assembled parts of the TBM tunneling machine from the lower horizontal tunnel 4 to the disassembly tunnel 8, and then assemble the TBM tunneling machine in the disassembly tunnel 8. After the assembly is completed, the tunneling machine starts to excavate from bottom to top until it is connected with the construction branch tunnel 6. The waste slag generated by the excavation is transported out from the lower horizontal tunnel 4 at the bottom, and the TBM tunneling machine is disassembled from the construction branch tunnel 6. The disassembled TBM tunneling machine is then transported out of the construction branch tunnel 6.
[0052] By adopting the construction method of this embodiment, the traditional two-stage inclined well can be changed to a one-stage one, which can effectively shorten the length of the water diversion system and reduce the head loss. At the same time, compared with the construction of a two-stage inclined well, the construction of a one-stage inclined well can simplify the construction process and improve construction efficiency.
[0053] Example 2
[0054] The difference between this embodiment and embodiment 1 is that Figure 3 As shown, a water diversion structure based on TBM excavation is provided. In this embodiment, three vertical shafts 5 are provided. The three vertical shafts 5 are distributed at intervals, and one end of the three vertical shafts 5 is respectively connected to the upper part, the middle part and the lower part of the inclined shaft 1.
[0055] In this embodiment, two construction branch holes 6 are provided, and the two construction branch holes 6 are arranged horizontally with each other, and one of the construction branch holes 6 is connected to the upper part of the inclined shaft 1, and the other construction branch hole 6 is connected to the middle or lower part of the inclined shaft 1.
[0056] In the present embodiment, three vertical shafts 5 are provided, and are respectively located at the upper, middle and lower parts of the inclined shaft 1, and are equipped with two construction branch holes 6, which increase the positions for ventilation and seeking help. This can improve the ventilation effect, while improving safety and facilitating later maintenance. The two construction branch holes 6 can be used for slag discharge and maintenance or disassembly of the TBM machine at the upper and middle and lower parts of the inclined shaft 1, which is flexible and convenient to use.
[0057] It should be noted that the above description of the disclosed embodiments enables professionals and technicians in the field to implement or use the present application. Various modifications to these embodiments will be apparent to professionals and technicians in the field, and the general principles defined herein can be implemented in other embodiments without departing from the scope of the present application. Therefore, the present application will not be limited to the embodiments shown herein, but should conform to the widest scope consistent with the principles and novel features disclosed herein.
[0058] In the description of the present invention, it should be noted that the terms "first", "second", "third", etc. are only used to distinguish the description and cannot be understood as indicating or implying relative importance.
[0059] In the description of this document, terms such as "up", "down", "left", "right", "front", "back", "top", "bottom", "inside", "outside", "middle", "vertical", "horizontal", "lateral", and "longitudinal" indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only used to illustrate the relative positional relationships between the various components or components, and do not particularly limit the specific installation orientations of the various components or components.
[0060] In the description of this document, some terms may be used to express other meanings in addition to indicating orientation or positional relationship. For example, the term "on" may also be used to express a certain dependency or connection relationship in some cases. For those of ordinary skill in the art, the specific meanings of these terms in this application can be understood according to the specific circumstances.
[0061] In the description of this document, the terms "installed", "set", "provided with", "connected", and "connected" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral structure; it can be a mechanical connection, or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be an internal connection between two devices, elements, or components. For those of ordinary skill in the art, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0062] The structures, proportions, sizes, etc. drawn in the drawings in this application are only used to match the contents disclosed in this technical briefing book for technical personnel in this field to understand and read, and are not used to limit the restrictive conditions for the implementation of this application. Therefore, they have no substantive technical significance. Any structural modification, change in proportional relationship or adjustment of size should still fall within the scope of the technical content disclosed in this application without affecting the effects and purposes that can be achieved by this application.
[0063] The terms used in this document are those common terms currently widely used in the art in consideration of the functions of the present disclosure, but these terms may vary according to the intention of a person of ordinary skill in the art, precedents, or new technologies in the art. In addition, specific terms may be selected by the applicant, and in this case, their detailed meanings will be described in the detailed description of the present disclosure. Therefore, the terms used in the document should not be understood as simple names, but rather as an overall description based on the meaning of the terms and the present disclosure.
[0064] Flowcharts or text are used in this document to illustrate the operating steps performed according to the embodiments of the present application. It should be understood that the operating steps in the embodiments of the present application are not necessarily accurately performed in the order of recording. On the contrary, various steps can be processed in reverse order or simultaneously as needed. At the same time, other operations can also be added to these processes, or a certain step or several steps can be removed from these processes.
[0065] The above are only preferred embodiments of the present application and are not intended to limit the present application. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present application should be included in the protection scope of the present application.
Claims
1. A water diversion structure based on TBM excavation, characterized in that: It includes an inclined well and a lower flat tunnel, wherein the lower flat tunnel is connected to the bottom of the inclined well, and the upper part of the inclined well is connected to a water guide well, and the water guide well is connected to an upstream reservoir; It also includes a vertical shaft and a construction branch hole, wherein the construction branch hole is horizontally excavated from the ground to be connected with the inclined shaft, and the vertical shaft is vertically excavated from the ground to be connected with the inclined shaft, and the vertical shaft passes through the construction branch hole.
2. A water diversion structure based on TBM excavation according to claim 1, characterized in that: There are three vertical shafts, one ends of which are respectively connected to the upper, middle and lower parts of the inclined shaft. There are two construction branch holes, which are arranged horizontally with each other, and one of the construction branch holes is connected to the upper part of the inclined shaft, and the other construction branch hole is connected to the middle or lower part of the inclined shaft.
3. A water diversion structure based on TBM excavation according to claim 1 or 2, characterized in that: One end of the construction branch tunnel passes through the inclined shaft to form an extended tunnel.
4. A water diversion structure based on TBM excavation according to claim 1, characterized in that: A machine dismantling hole is excavated at the intersection of the lower horizontal tunnel and the inclined shaft.
5. A water diversion structure based on TBM excavation according to claim 1, characterized in that: The water guide well is arranged inclined, and the inclination angle of the water guide well is smaller than the inclination angle of the inclined well.
6. A water diversion structure based on TBM excavation according to claim 1, characterized in that: It also includes a gate well, which is connected to the water guide well, and a gate for controlling the opening or closing of the water guide well is installed in the gate well.
7. A water diversion structure based on TBM excavation according to claim 1, characterized in that: The inclined shaft extends upward to the ground.
8. A water diversion structure based on TBM excavation according to claim 7, characterized in that: The ground at the top of the inclined shaft is flat.
9. A construction method of a water diversion structure based on TBM excavation, characterized in that: The following steps are involved: Step 1, horizontally excavating a construction branch hole, and then excavating a vertical shaft, the vertical shaft passing through the construction branch hole; Step 2, horizontally excavating a lower flat tunnel, and excavating a machine dismantling hole at the end of the lower flat tunnel; Step 3: Assemble the TBM on the upstream ground, and start digging the inclined shaft from the upstream ground from top to bottom. When the TBM is excavated until it is connected with the construction branch tunnel, the excavated waste is transported out of the construction branch tunnel, and the TBM is disassembled from the construction branch tunnel and transported out of the construction branch tunnel; Step 4: Assemble the TBM in the dismantling tunnel, then start excavating from bottom to top until it connects with the construction branch tunnel. The waste slag produced by excavation is transported out from the lower horizontal tunnel at the bottom, and the TBM is dismantled in the construction branch tunnel and then transported out of the construction branch tunnel.
10. A water diversion structure based on TBM excavation according to claim 9, characterized in that: The construction branch tunnel extends through the inclined shaft, and the portion of the construction branch tunnel extending out of the inclined shaft is an extension tunnel. The TBM tunneling machine performs dismantling operations in the extension tunnel and the construction branch tunnel.