Multi-stage foundation pit surface settlement prediction methods, devices, electronic equipment and storage media
By establishing a multi-level foundation pit surface settlement prediction model and utilizing the Weiber distribution decay model and nonlinear regression fitting, the problem of inaccurate surface settlement control for multi-level foundation pits was solved, achieving more accurate settlement prediction and engineering design support.
Patent Information
- Application Number
- CN202611635912.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-22
- Publication Date
- 2026-11-17
AI Technical Summary
In existing technologies, the standards for controlling surface settlement of multi-level foundation pits lack specific considerations, leading to inaccurate control, blind spots and uncertainties, which may result in increased project costs or safety risks.
By determining the geometric and geological parameters and settlement control parameters of the target multi-level foundation pit, a target prediction model is established. Using the Weiber distribution decay model and nonlinear regression fitting, combined with surface settlement monitoring data or numerical simulation, the surface settlement value is predicted.
It improves the accuracy and reliability of surface settlement control in multi-level foundation pits, provides a scientific basis for engineering design, and reduces the cost and cycle of on-site testing.
Smart Images

Figure CN123116746A_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of geotechnical engineering technology, specifically to a method, device, electronic equipment, and storage medium for predicting surface settlement of multi-stage foundation pits. Background Technology
[0002] Currently, most standards for controlling surface settlement in foundation pit projects are designed for single-level foundation pit projects. For multi-level foundation pit projects, especially those with intermediate platforms of different widths, the existing standards lack specific considerations regarding the impact on surface settlement.
[0003] In practical engineering, the formulation of control standards for multi-stage foundation pits often relies on engineering analogies or limited experience-based judgments, which introduces a degree of blindness and uncertainty, leading to inaccurate control of surface settlement in multi-stage foundation pits. Therefore, it is urgent to address the problem of insufficient accuracy in controlling surface settlement of multi-stage foundation pits. Summary of the Invention
[0004] In view of the above-mentioned shortcomings of related technologies, this application provides a method, device, electronic equipment and storage medium for predicting surface settlement of multi-stage foundation pits, which effectively improves the accuracy of surface settlement control of multi-stage foundation pits.
[0005] In a first aspect, this application provides a method for predicting surface settlement of multi-stage foundation pits, the method comprising: Determine the geometric and geological parameters and settlement control parameters of the target multi-stage foundation pit; Based on the engineering design information of the target multi-level foundation pit, determine the model parameters of the target prediction model; The geometric geological parameters, the settlement control parameters, and the model parameters are input into the target prediction model to predict the settlement, thereby obtaining the predicted surface settlement value of the target multi-level foundation pit.
[0006] In an optional implementation, the model expression of the target prediction model is as follows: ; In the above formula, This represents the predicted surface settlement value of the target multi-level foundation pit. k 1 represents the settlement control coefficient of the first stage of the multi-stage foundation pit. H 1 represents the depth of the first stage of the multi-stage foundation pit. k i The first stage of the target multi-level foundation pit represents the... i Settlement control coefficient for foundation pits. H i The first stage of the target multi-level foundation pit represents the... i The depth of the foundation pit, W i-1The first stage of the target multi-level foundation pit represents the... i -1 level foundation pit and the first i The width of the intermediate platform between the foundation pits. In the target prediction model, the first... i Settlement attenuation parameters for a Class -1 foundation pit In the target prediction model, the first... i The curve shape parameters of the -1 level foundation pit, where exp[] represents the natural exponential function, where i =2, 3, ..., N , N This indicates the total number of stages in the target multi-stage foundation pit.
[0007] In an optional implementation, determining the model parameters of the target prediction model based on the engineering design information of the target multi-level foundation pit includes: Based on the engineering design information, the surface settlement monitoring data of the target multi-stage foundation pit is determined, and statistical regression processing is performed on the surface settlement monitoring data and the target prediction model to obtain the model parameters; Alternatively, numerical simulation of the target multi-level foundation pit can be performed based on the engineering design information to obtain numerical simulation results, and the model parameters can be determined based on the numerical simulation results and the target prediction model.
[0008] In an optional implementation, statistical regression processing is performed based on the surface subsidence monitoring data and the target prediction model to obtain the model parameters, including: Based on the surface settlement monitoring data and the geometric geological parameters, a target dataset is constructed with the width of the intermediate platform of the target multi-level foundation pit as the independent variable and the surface settlement value as the dependent variable. The model parameters are obtained by performing nonlinear regression fitting based on the target dataset and the target prediction model.
[0009] In an optional implementation, numerical simulation of the target multi-stage foundation pit is performed based on the engineering design information to obtain numerical simulation results, and the model parameters are determined based on the numerical simulation results and the target prediction model, including: Based on the engineering design information, a three-dimensional numerical calculation model of the target multi-level foundation pit is constructed; In the three-dimensional numerical calculation model, different combinations of intermediate platform widths of the target multi-level foundation pit are set up, and the corresponding allowable values of surface settlement are simulated and calculated under each combination of intermediate platform widths. A sample dataset is constructed based on the combined working conditions of the intermediate platform width and the allowable value of surface subsidence; The model parameters are obtained by performing nonlinear regression fitting based on the sample dataset and the target prediction model.
[0010] In an optional implementation, constructing a three-dimensional numerical calculation model of the target multi-level foundation pit based on the engineering design information includes: Based on the engineering design information, determine the modeling scope and soil parameters of the target multi-level foundation pit; Based on the modeling scope and the soil parameters, an initial finite element model is constructed; The initial finite element model is meshed and its boundaries are defined to obtain the initial three-dimensional numerical calculation model; Gravity load is applied to the initial three-dimensional numerical calculation model, the calculation is run until the initial geostress equilibrium state is reached, and the displacement field is cleared to zero to obtain the three-dimensional numerical calculation model.
[0011] In an optional implementation, the geometric geological parameters include at least the depth of each level of the target multi-level foundation pit and the width of the intermediate platform between each level of the foundation pit; the settlement control parameters include the settlement control coefficient of each level of the foundation pit; and determining the geometric geological parameters and settlement control parameters of the target multi-level foundation pit includes: Based on the engineering survey and design data of the target multi-level foundation pit, determine the depth of each level of foundation pit and the width of the intermediate platform between each level of foundation pit; Based on the engineering safety level and surrounding environmental conditions of the target multi-level foundation pit, the settlement control coefficient of each level of foundation pit is determined.
[0012] Secondly, this application provides a multi-stage foundation pit surface settlement prediction device, the device comprising: The first determining module is used to determine the geometric geological parameters and settlement control parameters of the target multi-stage foundation pit; The second determining module is used to determine the model parameters of the target prediction model based on the engineering design information of the target multi-level foundation pit; The numerical prediction module is used to input the geometric geological parameters, the settlement control parameters and the model parameters into the target prediction model to predict the settlement and obtain the predicted surface settlement value of the target multi-level foundation pit.
[0013] Thirdly, this application provides an electronic device, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor executes the computer program to implement the multi-level foundation pit surface settlement prediction method as described in the first aspect of this application.
[0014] Fourthly, this application provides a computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the multi-level foundation pit surface settlement prediction method as described in the first aspect of this application.
[0015] This application provides a method, device, electronic equipment, and storage medium for predicting surface settlement of multi-stage foundation pits. It determines the geometric and geological parameters and settlement control parameters of the target multi-stage foundation pit; determines the model parameters of the target prediction model based on the engineering design information of the target multi-stage foundation pit; and inputs the geometric and geological parameters, settlement control parameters, and model parameters into the target prediction model to predict settlement, obtaining the predicted surface settlement value of the target multi-stage foundation pit. Based on theoretical analysis and numerical simulation of the engineering parameters of the target multi-stage foundation pit, and comprehensively considering the influence of the depth of the multi-stage foundation pit and the width of the intermediate platform, this application establishes a target prediction model for predicting surface settlement control values. This model can more accurately and conveniently predict the surface settlement control values of multi-stage foundation pits under different working conditions, providing a scientific basis for engineering design. Attached Figure Description
[0016] To more clearly illustrate the technical solutions of the embodiments of this application, the accompanying drawings used in the embodiments will be briefly introduced below. It should be understood that the following drawings only show some embodiments of this application and should not be regarded as a limitation of the scope. For those skilled in the art, other related drawings can be obtained based on these drawings without creative effort.
[0017] Figure 1 This is a first schematic diagram of the multi-level foundation pit surface settlement prediction method provided in the embodiments of this application; Figure 2 This is a second schematic diagram of the multi-level foundation pit surface settlement prediction method provided in the embodiments of this application; Figure 3 This is the third schematic diagram of the multi-level foundation pit surface settlement prediction method provided in the embodiments of this application; Figure 4 This is the fourth schematic diagram of the multi-level foundation pit surface settlement prediction method provided in the embodiments of this application; Figure 5 This is a schematic diagram of the nonlinear regression fitting curve corresponding to the historical foundation pit project in the embodiments of this application; Figure 6 This is a schematic diagram of the multi-level foundation pit surface settlement prediction device provided in the embodiments of this application; Figure 7 This is a schematic diagram of the structure of an electronic device provided in an embodiment of this application.
[0018] Explanation of key component symbols: 600. Multi-stage foundation pit surface settlement prediction device; 610. First determination module; 620. Second determination module; 630. Numerical prediction module; 700. Electronic equipment; 710. Processor; 720. Communication interface; 730. Memory; 740. Communication bus. Detailed Implementation
[0019] To make the objectives, technical solutions, and advantages of this application clearer, the technical solutions of this application will be further described clearly and completely below with reference to the accompanying drawings of the embodiments. It should be noted that the described embodiments are merely some embodiments of this application, and not all embodiments. All other embodiments obtained by those skilled in the art based on the embodiments of this application without creative effort are within the scope of protection of this application.
[0020] Furthermore, the terms "first" and "second" are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of this application, "multiple" means two or more, unless otherwise explicitly specified.
[0021] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application belongs. The terminology used in this specification is for the purpose of describing particular embodiments only and is not intended to be limiting of this application.
[0022] Currently, most standards for controlling surface settlement in foundation pit engineering rely on empirical control values based on the pit depth, as specified in engineering standards and specifications for single-stage foundation pits. However, for multi-stage foundation pits, especially those with intermediate platforms of varying widths, the distribution pattern of surface settlement differs significantly from that of single-stage pits. Existing standards lack specific consideration of the impact of the width of the intermediate platform—a crucial factor—on settlement in multi-stage foundation pits. This leads to a reliance on engineering analogies or limited empirical judgment in actual engineering projects, resulting in a degree of blindness and uncertainty in the formulation of control standards. This can lead to overly stringent controls that increase unnecessary engineering costs, or overly lenient controls that introduce safety risks. Therefore, it is urgent to address the problem of inaccurate surface settlement control in multi-stage foundation pits.
[0023] To address the aforementioned shortcomings in related technologies, this application provides a method for predicting surface settlement in multi-level foundation pits, effectively solving the problem of inaccurate surface settlement control in multi-level foundation pits. Figure 1 This is a first schematic diagram of the multi-level foundation pit surface settlement prediction method provided in the embodiments of this application, as shown below. Figure 1 As shown, the method may include steps S100 to S300.
[0024] S100. Determine the geometric and geological parameters and settlement control parameters of the target multi-level foundation pit.
[0025] In the embodiments of this application, a multi-level target foundation pit refers to an engineering project in which a large foundation pit is divided into multiple smaller foundation pit areas of different depths according to the function or topography of the underground structure, and the construction is carried out in a certain order. The multi-level target foundation pit includes at least two levels of foundation pits.
[0026] In some implementations, geometric geological parameters are used to characterize the morphology, size, and structural relationships of each level of the excavation pit. These parameters include at least the depth of each level of the target multi-level excavation pit and the width of the intermediate platform between each level. The width of the intermediate platform is defined as the horizontal clearance from the outer edge of the support structure (or slope toe) of the previous level excavation pit to the outer edge of the excavation line (or slope crest) of the next level excavation pit. Settlement control parameters include settlement control coefficients for each level of the excavation pit, which represent the proportional relationship between allowable deformation and pit depth for different excavation pit levels. Figure 2 This is a second schematic diagram of the multi-level foundation pit surface settlement prediction method provided in the embodiments of this application, as shown in the figure. Figure 2 As shown, determining the geometric geological parameters and settlement control parameters of the target multi-level foundation pit may include steps S110 to S120.
[0027] S110. Based on the engineering survey and design data of the target multi-level foundation pit, determine the depth of each level of foundation pit and the width of the intermediate platform between each level of foundation pit.
[0028] Optionally, the engineering survey and design data may include the engineering geotechnical investigation report and the foundation pit support design scheme for the target multi-level foundation pit. Based on the above data, the depth of each level of foundation pit can be determined. H 1. H 2、…、 H N ), and the width of the intermediate platform between each level of foundation pit ( W 1. W 2、…、 W N ),in N This indicates the total number of stages in a multi-stage foundation pit project. For example, for a two-stage foundation pit, the depth of the first stage can be determined based on engineering survey and design data. H 1. Depth of the second-stage foundation pit H 2. And the width of the intermediate platform between the two levels of foundation pits. W .
[0029] In this embodiment, the width of the intermediate platform is a key control parameter for multi-stage foundation pits. A reasonable intermediate platform width can exert a counter-pressure effect, reducing the support load and deformation of the lower-level foundation pits. Simultaneously, the width of the intermediate platform can enhance the synergistic effect of the rigid frames of the two-stage support, effectively limiting surface settlement outside the pit. Therefore, this embodiment uses the width of the intermediate platform as a core design parameter for predicting surface settlement in multi-stage foundation pits.
[0030] It should be noted that most multi-stage foundation pits have regular pit dimensions, so the width of the intermediate platform between each pit level remains constant, with only one value. In this case, the intermediate platform width can be directly obtained. However, if the multi-stage foundation pits are not regular, there may be multiple monitoring points between each pit level. The intermediate platform width may differ between different monitoring points, resulting in multiple intermediate platform widths. Since a smaller intermediate platform width corresponds to a smaller surface settlement limit, the smallest intermediate platform width among the multiple monitoring points is selected as the intermediate platform width between the corresponding two pit levels.
[0031] For example, if the engineering survey and design data of a certain secondary foundation pit shows that the secondary foundation pit is an irregular foundation pit and three monitoring points are set up, with the width of the intermediate platform set at each monitoring point being 5m, 3m and 8m respectively, then 3m is selected as the width of the intermediate platform of the secondary foundation pit for subsequent surface settlement prediction.
[0032] S120. Based on the engineering safety level and surrounding environmental conditions of the target multi-level foundation pit, determine the settlement control coefficient of each level of foundation pit.
[0033] Understandably, based on the importance level of the target multi-level foundation pit and the protection requirements of the surrounding environment (such as adjacent buildings and pipelines), and referring to the relevant provisions of the current technical specifications for foundation pit support, the allowable ground settlement value corresponding to the depth of each level of foundation pit can be determined. The settlement control coefficient for each level of foundation pit can then be obtained by calculating the ratio of the allowable ground settlement value to the corresponding foundation pit depth. k 1. k 2、…、 k N For example, if δ The settlement control coefficient for the first-level foundation pit is determined based on the allowable surface settlement value according to the corresponding foundation pit grade and environmental requirements. k 1= δ / H 1. Settlement control coefficient of the second-stage foundation pit k 2= δ / H 2. In addition, the settlement control coefficient, determined according to the engineering safety level and standard engineering specifications, generally ranges from 0.1% to 0.3%.
[0034] It should be noted that the allowable surface settlement value is selected independently based on the design safety level, surrounding environmental sensitivity, and geological conditions of the first-level and second-level foundation pits, respectively. The two values can be the same or different. When the current standards and specifications do not directly provide specific values, the allowable surface settlement value can be determined by combining engineering analogies, expert experience, or by back-analyzing monitoring data of similar local projects.
[0035] Based on this, by determining the depth of each level of the multi-level foundation pit, the width of the intermediate platform, and the settlement control coefficient, we can provide a parameter basis for the subsequent implementation of graded unloading and active deformation control. Furthermore, we can fully consider the effect of the intermediate platform width on the counter-pressure soil and the rigid frame to reduce settlement outside the pit, ensure that the deformation is measurable and controllable, and protect the safety of the surrounding environment.
[0036] S200. Based on the engineering design information of the target multi-level foundation pit, determine the model parameters of the target prediction model.
[0037] In this embodiment of the application, the engineering design information of the target multi-level foundation pit can be information related to the support scheme and design parameters determined by the system based on the target multi-level foundation pit design scheme, site engineering geological survey data and surrounding environmental investigation report. The engineering design information includes, but is not limited to, information such as support structure selection, geometric structural parameters, excavation support sequence and deformation control parameters.
[0038] As an optional implementation method of this application, the target prediction model can be a prediction model of the surface settlement control volume determined by numerical simulation based on the superposition mechanism of multi-level foundation pit deformation and the Weber distribution attenuation model.
[0039] It should be noted that the essence of surface settlement in multi-stage foundation pits is the transmission, diffusion, and dissipation of the additional stress field caused by the excavation of multiple foundation pits in the soil medium. In geotechnical engineering, this spatial attenuation behavior generally manifests in three stages: First, the slow attenuation stage in the near zone, where the deformation changes little with distance because the soil has not been fully unloaded in the vicinity of the foundation pit; second, the accelerated attenuation stage in the middle zone, where the soil undergoes shear deformation, compression, and energy dissipation, and the deformation decreases rapidly with distance; and finally, the stable convergence stage in the far zone, where the stress and deformation fields basically dissipate as the distance continues to increase, and the settlement tends to stabilize. Based on the above-mentioned "slow-steep-stable" nonlinear attenuation law, mathematically corresponding to an S-shaped attenuation curve with an inflection point, numerical simulations were conducted using attenuation curve models such as the single exponential attenuation model, the Gaussian attenuation model, and the Weiber distribution attenuation model. Finally, the Weiber distribution attenuation model was selected as the attenuation factor to construct the target prediction model.
[0040] This target prediction model treats the settlement of the first-stage foundation pit in a multi-stage foundation pit as a constant, and the settlement of the remaining stages as variables that decrease with the width of the intermediate platform. A Weiber distribution attenuation factor is introduced to reduce the contribution of the remaining stages, and the weakening effect of the intermediate platform width on the cumulative settlement of each stage is quantified. The settlements of each stage are linearly superimposed. The model expression for the target prediction model is as follows: ; In the above formula, This represents the predicted surface settlement value for the target multi-stage foundation pit. k 1 represents the settlement control coefficient of the first stage of the multi-stage foundation pit. H 1 indicates the depth of the first stage of the multi-stage excavation pit. k i Indicates the first stage of the multi-level foundation pit. i Settlement control coefficient for foundation pits. H i Indicates the first stage of the multi-level foundation pit. i The depth of the foundation pit, W i-1 Indicates the first stage of the multi-level foundation pit. i -1 level foundation pit and the first i The width of the intermediate platform between the foundation pits. In the target prediction model, the first... i Settlement attenuation parameters for a Class -1 foundation pit In the target prediction model, the first... i The curve shape parameters of the -1 level foundation pit, where exp[] represents the natural exponential function, where i =2, 3, ..., N , N This indicates the total number of levels in the target multi-level foundation pit.
[0041] For example, if the target multi-level foundation pit is a two-level foundation pit, the expression of the corresponding target prediction model is as follows: ; In the above formula, k 1 represents the settlement control coefficient of the first stage of the multi-stage foundation pit. k 2 represents the settlement control coefficient of the second-stage foundation pit in a multi-stage foundation pit project. H 2 indicates the depth of the second-level pit in a multi-level excavation project. W 1 represents the width of the intermediate platform between the first and second levels of the multi-level excavation pit. This represents the settlement attenuation parameter of the first-stage foundation pit in the target prediction model. The curve shape parameters represent the first-level foundation pit in the target prediction model.
[0042] In this embodiment, the model parameters are mathematical fitting parameters in the target prediction model that comprehensively characterize the influence of engineering geological conditions such as soil stiffness and homogeneity on the spatial attenuation law of settlement in the multi-stage foundation pit. These model parameters include the settlement attenuation parameters of the target prediction model. and curve shape parameters d Among them, the settlement attenuation parameter The settlement attenuation parameters of the current foundation pit comprehensively reflect the soil stiffness and overall stability. The larger the value of , the higher the relative stiffness of the soil, and the faster the settlement effect from the next level of foundation pit decreases as the width of the intermediate platform increases. Curve morphology parameters d The value of this parameter affects the inflection point characteristics of the attenuation curve, reflecting the homogeneity of the soil and the complexity of the geological structure. For example, this settlement attenuation parameter... The value can be taken as 0.05 to 0.5, which is the curve shape parameter. d The value can be 1 to 10, and both can be obtained through optimization algorithms such as the least squares method.
[0043] Based on this, the target prediction model provided in this application embodiment is consistent with the soil deformation mechanism, has strong morphological adjustability, and utilizes curve morphology parameters. d This model can flexibly characterize the differences in attenuation rates under various geological conditions, such as homogeneous soil, layered soil, and alternating layers of soft and hard soil. Furthermore, the target prediction model achieves a decoupled expression of the pit depth effect and the platform width attenuation effect, with clear physical meaning and strong engineering adaptability.
[0044] Furthermore, the specific values of the model parameters can be determined using statistical regression or numerical simulation methods based on the engineering design information of the target multi-stage foundation pit. If the surface settlement monitoring data of the target multi-stage foundation pit can be determined based on the engineering design information, then statistical regression processing can be performed on the surface settlement monitoring data and the target prediction model to obtain the model parameters.
[0045] Optionally, the surface settlement monitoring data determined based on the engineering design information can be either surface settlement test monitoring data or historical surface settlement monitoring data. Specifically, the engineering design information can be used to set up a construction test section for the target multi-stage foundation pit to conduct preliminary construction tests. The surface settlement test monitoring data can be obtained from the measured data of the preliminary construction test section of the target multi-stage foundation pit. Historical surface settlement monitoring data refers to the historical surface settlement monitoring data of similar historical projects in the region. Based on the engineering design information, historical multi-stage foundation pit projects that have been completed in the region and have similar geological and support conditions can be identified. Historical surface settlement monitoring data can be obtained based on the construction data of these historical multi-stage foundation pit projects.
[0046] In some implementations, statistical regression processing can be performed based on surface subsidence monitoring data and target prediction models to obtain model parameters. Figure 3 This is a third schematic diagram of the multi-level foundation pit surface settlement prediction method provided in the embodiments of this application, as shown in the figure. Figure 3 As shown, determining the model parameters may include steps S201 to S202.
[0047] S201. Based on surface settlement monitoring data and geometric geological parameters, construct a target dataset with the width of the intermediate platform of the target multi-level foundation pit as the independent variable and the surface settlement value as the dependent variable.
[0048] In this embodiment of the application, if the surface settlement monitoring data is surface settlement test monitoring data, for multiple monitoring points of the same intermediate platform width, the maximum settlement value among all valid monitoring points is selected as the surface settlement monitoring data corresponding to the intermediate platform width. At the same time, monitoring data affected by abnormal working conditions such as surrounding loads and sudden precipitation are removed to ensure that the target dataset only reflects the impact of the intermediate platform width on settlement.
[0049] It is understandable that when using the surface settlement test monitoring data of the target multi-level foundation pit as the surface settlement monitoring data, the independent variable is the width of the intermediate platform of the target multi-level foundation pit, that is, the width of the intermediate platform between each level of foundation pit determined in step S100 above. W 1. W 2、…、 W N When using historical surface settlement monitoring data from similar historical projects in the region as surface settlement monitoring data, the independent variable is the width of the intermediate platform between the various levels of foundation pits in the corresponding similar historical projects. In the subsequent nonlinear regression fitting process, the depth and settlement control coefficient of each level of foundation pit in the corresponding target prediction model are also adopted from the depth and settlement control coefficient of each level of foundation pit in the similar historical projects.
[0050] Based on the selected and excluded surface subsidence monitoring data and the corresponding intermediate platform width, a system is established with the intermediate platform width as the basis. W As the independent variable, the surface subsidence value is used. δ The target dataset for the dependent variable ( W i-1,j , δ ( W i-1,j )),in W i-1,j Indicates the first stage of the multi-level foundation pit. i -1 level foundation pit and the first i The width of the intermediate platform between the first and second foundation pits j One data point, δ ( W i-1,j )for W i-1,j The corresponding surface subsidence values, among whichi =2, 3, ..., N , j The width of the intermediate platform between different levels of foundation pits is determined by the number of possible values. N This indicates the total number of levels in the target multi-level foundation pit.
[0051] S202. Perform nonlinear regression fitting based on the target dataset and the target prediction model to obtain the model parameters.
[0052] Optionally, a nonlinear least squares regression fitting method can be used based on the target dataset. The sum of squared residuals is constructed as the objective function based on the expression of the target prediction model, as shown in the following expression: ; In the above formula, SSE This represents the sum of squared residuals corresponding to the target dataset.
[0053] Furthermore, by optimizing the algorithm to solve the problem... SSE Minimize each of the settlement attenuation parameters and various curve shape parameters For example, the optimization algorithm could be the Levenberg-Marquardt (LM) algorithm or the Gauss-Newton algorithm. The convergence condition for the fitting process is set as follows: the absolute value of the parameter update or the decrease in the objective function value is less than a preset tolerance, typically 1 × 10⁻⁶. -6 When the above convergence condition is met, the iteration stops, and the current model parameters are output as the optimal estimate. To evaluate the goodness of fit of the target prediction model, a coefficient of determination can be introduced. R² The calculation method for this is well-known in the field and will not be elaborated here. For example, when the coefficient of determination... R² When the value is greater than 0.85, the target prediction model is deemed to have an acceptable fitting effect, and the settlement attenuation parameters of each level of the foundation pit corresponding to the target prediction model are obtained. and curve shape parameters d The model parameters are obtained as follows: [( , d 1) ( , d 2), ..., ( , d N [ ] can be used for subsequent surface subsidence analysis and prediction.
[0054] Based on this, by constructing a target dataset with the width of the intermediate platform as the independent variable and the surface subsidence value as the dependent variable, and performing nonlinear regression fitting based on the target prediction model, the model parameters can be accurately identified, and dynamic matching between the target prediction model and the engineering measured data can be achieved, thereby improving the reliability and accuracy of surface subsidence prediction.
[0055] In some implementations, if effective surface settlement monitoring data cannot be obtained based on engineering design information, numerical simulation of the target multi-level foundation pit can be performed based on the engineering design information to obtain numerical simulation results, and model parameters can be determined based on the numerical simulation results and the target prediction model. Figure 4 This is the fourth schematic diagram of the multi-level foundation pit surface settlement prediction method provided in the embodiments of this application, as shown in the following figure. Figure 4 As shown, obtaining model parameters through numerical simulation may include steps S210 to S240.
[0056] S210. Based on the engineering design information, construct a three-dimensional numerical calculation model of the target multi-level foundation pit.
[0057] In this embodiment of the application, a three-dimensional numerical calculation model can be established based on the multi-level foundation pit design scheme and site engineering geological survey data. This three-dimensional numerical calculation model can be constructed using computer three-dimensional numerical modeling software and may include the following steps: First, based on the engineering design information, the modeling scope and soil parameters of the target multi-level foundation pit are determined. The modeling scope can be determined based on the multi-level foundation pit design scheme, including but not limited to the depth of each level of foundation pit, the width of the intermediate platform, the horizontal outward extension distance of the foundation pit, the vertical depth below the foundation pit, and the length range of the model. Simultaneously, based on the site engineering geological survey data, the soil layer division and soil parameters for each layer are determined using the appropriate computer-aided three-dimensional numerical modeling software. These soil parameters include, but are not limited to, soil layer thickness, natural unit weight, saturated unit weight, elastic modulus, Poisson's ratio, cohesion, internal friction angle, permeability coefficient, void ratio, compression modulus, and undrained shear strength.
[0058] For example, the modeling range is determined based on two-stage excavation pits as follows: the horizontal boundary of the model is no less than 3 to 5 times the total excavation depth from the outermost edge of the excavation pit (i.e., H 1+ H 2) The bottom boundary of the model should be at least 2 to 3 times the total excavation depth from the bottom of the foundation pit, and the length along the direction of the foundation pit should be at least 2 times the total excavation depth, so as to avoid the boundary effect from interfering with the calculation results of surface settlement.
[0059] Another example is the rational division of soil layers in the target multi-level foundation pit based on site engineering geological survey data. Constitutive models reflecting the main mechanical behaviors of the soil, such as the Mohr-Coulomb model or the hardening soil model, can be used. Accurate mechanical parameters are assigned to each soil layer in the constitutive model, primarily including layer thickness, natural unit weight, and saturated unit weight. For the Mohr-Coulomb model, parameters such as elastic modulus or deformation modulus, Poisson's ratio, cohesion, and internal friction angle are also required. For the hardening soil model, parameters such as reference secant stiffness, reference unloading / reloading stiffness, reference tangent stiffness, and power exponent are also required. Furthermore, parameters such as lateral pressure coefficient and permeability coefficient need to be determined based on the actual situation.
[0060] Secondly, based on the modeling scope and soil parameters, an initial finite element model is constructed. Modeling is performed using the selected computer 3D numerical modeling software. The aforementioned structural values, soil layer divisions, and soil parameters for each layer are input. A 3D finite element or finite difference model is established based on the model scope and soil parameters to reconstruct the engineering entity, resulting in the initial finite element model. This initial finite element model fully includes the depth of each level of the foundation pit and the width of the intermediate platform, the support structure (e.g., piles, anchors, internal bracing, and cutoff wall), the typical soil layers of the foundation pit, and the corresponding physical and mechanical parameters of each soil layer. The parameter values are consistent with those in the survey report and design documents.
[0061] Then, the initial finite element model is meshed and its boundaries are defined to obtain the initial three-dimensional numerical calculation model. For example, an appropriately sized mesh is created for the initial finite element model. Mesh refinement can be performed in key areas (such as near the foundation pit or the intermediate platform area) to accurately capture displacement gradients and the development of the plastic zone. The mesh element size should not exceed 0.5 times the width of the intermediate platform. Simultaneously, the displacement boundary conditions are set as follows: the top surface of the model is a free surface without constraints; the bottom surface constrains vertical displacement to simulate the settlement limitation of bedrock or deep soil; the four sides constrain normal displacement, limiting horizontal extension while allowing vertical slippage.
[0062] Finally, a gravity load is applied to the initial three-dimensional numerical calculation model, and the calculation is run until the initial geostress equilibrium state is reached. The displacement field is then cleared to zero, resulting in the three-dimensional numerical calculation model. In the initial three-dimensional numerical calculation model, an initial geostress field formed by the soil's self-weight and displacement boundary conditions is first applied to simulate the stress state of the natural foundation. Then, the solver is run to perform calculations until the initial three-dimensional numerical calculation model reaches mechanical equilibrium, for example, when the ratio of the maximum unbalanced force is less than 1 × 10⁻⁶. -5 After the equilibrium calculation is completed, the initial displacement of all nodes in the field is reset to zero, thereby eliminating the virtual displacement caused by self-weight consolidation and ensuring that the displacements obtained in subsequent excavation steps are all net increments caused by construction disturbances, thus obtaining a three-dimensional numerical calculation model.
[0063] Based on this, by determining the modeling scope and soil parameters, an initial finite element model is constructed. Reasonable mesh and boundary settings can effectively eliminate boundary effects and accurately reflect the stress redistribution and surface settlement patterns during the foundation pit excavation process. Further construction of a three-dimensional numerical calculation model based on the initial finite element model can accurately recreate the initial stress-strain state before foundation pit excavation, providing a reliable starting benchmark for multi-stage foundation pit deformation prediction.
[0064] S220. In the three-dimensional numerical calculation model, set up different combinations of intermediate platform widths for the target multi-level foundation pit, and simulate and calculate the corresponding allowable values of surface settlement under each combination of intermediate platform widths.
[0065] In this embodiment, within the established three-dimensional numerical calculation model, various combinations of intermediate platform widths are set as calculation conditions based on the design scheme of the target multi-level foundation pit. For each intermediate platform width combination condition, the entire process of foundation pit slope protection, support procedures, and dewatering is simulated step-by-step in the three-dimensional numerical calculation model according to the actual construction sequence. The support procedures include specific operations such as pile driving, internal support erection, and anchor tensioning. Dewatering is implemented by setting groundwater level drawdown and cutoff wall effects based on hydrogeological parameters.
[0066] Furthermore, after each step of the construction simulation is completed, the solution is recalculated to a new mechanical equilibrium state. After all construction procedures are simulated, the surface settlement curves at different locations outside the pit obtained from the model calculation are extracted, and the calculated surface settlement values at each measuring point are recorded. These values are then compared with the allowable settlement control values for the project to assess whether the pit deformation under the combined working conditions of the intermediate platform width meets the design requirements. The calculated surface settlement value corresponding to meeting the design requirements is taken as the allowable surface settlement value.
[0067] It is understandable that by changing the values of different intermediate platform width combinations in the three-dimensional numerical calculation model and repeating the above simulation process, a series of allowable surface settlement values corresponding to different intermediate platform width combinations can be obtained.
[0068] S230. Based on the combined working conditions of the intermediate platform width and the allowable value of surface settlement, construct a sample dataset.
[0069] In this embodiment of the application, a sample dataset can be constructed based on the series of intermediate platform width combinations and corresponding allowable surface settlement values obtained above. W i-1,l , δ ( W i-1,l )),in W i-1,l Indicates the first stage of the multi-level foundation pit. i -1 level foundation pit and the firsti The width of the intermediate platform between the first and second foundation pits l One data point, δ ( W i-1,l )for W i-1,l The corresponding allowable values for surface settlement, among which i =2, 3, ..., N , l The width of the intermediate platform between different levels of foundation pits is determined by the number of possible values. N This indicates the total number of levels in the target multi-level foundation pit.
[0070] S240. Perform nonlinear regression fitting based on the sample dataset and the target prediction model to obtain the model parameters.
[0071] Understandably, following the same processing method in step S202 above, the nonlinear least squares regression fitting process can be performed on the sample dataset obtained from the numerical simulation, combined with the target prediction model, to back-calculate the settlement attenuation parameters corresponding to each level of the foundation pit in the target prediction model. and curve shape parameters d The model parameters are obtained as follows: [( , d 1) ( , d 2), ..., ( , d N )].
[0072] Based on this, a three-dimensional numerical calculation model was constructed to generate the settlement response under different intermediate platform widths. Then, the model parameters were obtained by nonlinear fitting and back-calculation. This broke through the limitation of lack of monitoring data, provided a way to obtain model parameters for the initial design of multi-level foundation pits, and significantly reduced the cost and cycle of field tests, while improving the adaptability and reliability of surface settlement prediction.
[0073] S300. Input the geometric geological parameters, settlement control parameters and model parameters into the target prediction model to predict the settlement and obtain the predicted surface settlement value of the target multi-level foundation pit.
[0074] In this embodiment of the application, the depth of each level of the target multi-level foundation pit ( H 1. H 2、…、 H N ), the width of the intermediate platform between each level of foundation pit ( W 1. W 2、…、 W N ), settlement control coefficients of foundation pits at all levels ( k1. k 2、…、 k N ) and determined model parameters [( , d 1) ( , d 2), ..., ( , d N By inputting the data into the target prediction model and solving for settlement prediction, the predicted surface settlement value of the target multi-level foundation pit under the corresponding parameters mentioned above can be obtained.
[0075] It is understandable that the width of the intermediate platform between different levels of excavation pits has a decisive impact on the boundary of the target prediction model. Taking a two-level excavation pit as an example, when the width of the intermediate platform between the two levels of excavation pits... W When =0, ,but At this point, the target prediction model degenerates into treating the two-stage foundation pit as a single entity with a depth of [missing value]. H 1+ H In the equivalent single-stage foundation pit case 2, the predicted surface settlement value is the direct sum of the control values of the two stages of foundation pits, which conforms to the principle of most unfavorable superposition. When the width of the intermediate platform... W When it approaches infinity, ,but At this point, the distance between the two foundation pits is far enough that their mutual influence is negligible. The total settlement prediction is controlled only by the deeper or more dangerous first-stage foundation pit. At this point, the model accurately reflects the weakening effect of the increased platform width on the second-stage foundation pit through the exponential decay term, and the physical meaning is clear.
[0076] It should be noted that when two foundation pits are adjacent to each other, with no platform in between or the width of the intermediate platform is much smaller than the depth of the foundation pit, for example... W < 0.2×min( H 1, H When 2), it can be approximated as W = 0. When the width of the intermediate platform is large enough that the settlement influence zones of the two-stage foundation pits almost do not overlap, for example... W > 3× H 1+ H When the value is 2, it can be approximated as the width of the intermediate platform. W Operating conditions approaching infinity.
[0077] As a further implementation of this application, the predicted surface settlement values can be used to guide design and construction, that is, the calculated predicted surface settlement values... δ ( W ), as the target multi-level foundation pit project at a specific intermediate platform width WThe following surface settlement control standard is established. This surface settlement control standard can be used in the construction design stage, construction preparation stage, and construction process stage.
[0078] Among them, the construction design stage can be based on the predicted value of surface settlement. δ ( W Assess the acceptability of the environmental impact of different support structure schemes and platform width designs, and compare and optimize different schemes. During the construction preparation stage, the predicted surface settlement values can be used as a basis. δ ( W Develop a construction monitoring plan, determining the layout of monitoring points, monitoring frequency, and settlement early warning thresholds. During the construction phase, real-time on-site monitoring data of surface settlement can be compared with predicted surface settlement values. δ ( W By comparing these data, dynamic and precise safety risk management can be achieved.
[0079] For example, based on predicted surface subsidence values δ ( W By setting tiered control thresholds, the settlement warning value can be set as the predicted value for surface settlement. δ ( W 70% of the total settlement alarm value will be set as the predicted surface settlement value. δ ( W 90% of the monitored surface settlement data should be monitored. When the monitored surface settlement data reaches the settlement warning value, the monitoring frequency should be increased and the cause analyzed. When the monitored surface settlement data reaches or exceeds the settlement alarm value, the emergency plan should be activated immediately and corresponding engineering measures should be taken to ensure the construction safety of the target multi-level foundation pit project.
[0080] As an exemplary implementation of this application, a large-scale integrated transportation hub project is selected as an example, and the multi-level foundation pit surface settlement prediction method provided in this application is applied for settlement prediction. This project adopts the open-cut method for construction. To meet the functional requirements of multiple transportation modes, its underground structure system has a multi-layered layout, constructed step-by-step from top to bottom. Specifically, this large-scale integrated transportation hub project consists of two-level foundation pits. The first-level foundation pit is mainly used for constructing the surface public transportation functional layer, with an excavation depth of approximately 11.793 meters. The second-level foundation pit is for the underground transfer hall, with a single-layer excavation depth of approximately 7.85 meters. The total depth of the project is nearly 19.643 meters. Based on the project's safety level and surrounding environmental conditions, the settlement control coefficient for both the first and second-level foundation pits is determined to be 0.2%. Furthermore, this large-scale integrated transportation hub project is not a regular two-level foundation pit platform; the width of the intermediate platform is not a fixed value. Therefore, three monitoring points are set up, and the surface settlement safety reserve margin provided by each monitoring point in the construction design scheme is 25%.
[0081] Historical surface settlement monitoring data was obtained from a nearby historical foundation pit project with similar geological and support conditions to determine the model parameters. The first-stage foundation pit of this historical foundation pit project has a depth of 9.8 m, and the second-stage foundation pit has a depth of 7.35 m. The settlement control coefficient for both the first and second-stage foundation pits is 0.2%. The expression for the objective function model corresponding to this historical foundation pit project is as follows: ; The relationship between historical monitoring data of surface subsidence and the width of the intermediate platform is shown in Table 1 below.
[0082] Table 1. Schematic diagram of the correspondence between historical surface settlement monitoring data and the width of the intermediate platform in a certain historical foundation pit project.
[0083] Construct the intermediate platform width based on Table 1 above. W As the independent variable, the surface subsidence value is used. δ Using the target dataset as the dependent variable, a nonlinear regression fitting process is performed on the target prediction model corresponding to the historical foundation pit project to obtain the nonlinear regression fitting curve. Figure 5 This is a schematic diagram of the nonlinear regression fitting curve corresponding to the historical foundation pit project in the embodiments of this application, such as... Figure 5 As shown, the mathematical expression for the nonlinear regression fitting curve is as follows: ; The settlement attenuation parameter can be determined based on the above mathematical expression. =0.136 and curve shape parameters d= 5.33, the above model parameters can be used as model parameters for the target prediction model of large-scale integrated transportation hub projects.
[0084] Furthermore, based on the first-stage foundation pit depth of 11.793m and the second-stage foundation pit depth of 7.85m for this large-scale integrated transportation hub project, the settlement control coefficient for both the first and second-stage foundation pits is 0.2%, and the aforementioned determined settlement attenuation parameters... =0.136 and curve shape parameters d= 5.33 The target prediction model is constructed as follows: ; In the above formula, a This represents the constant settlement term for the first-stage foundation pit. b The coefficient of the variable term represents the attenuation of the second-stage foundation pit as the width of the intermediate platform decreases.
[0085] Among them, the constant settlement term a Based on the first-stage foundation pit depth of 11.793m and the settlement control coefficient of 0.2%, the following calculations can be performed:a= 1179.3mm × 0.2% ≈ 23.6mm. According to the requirements for foundation pit deformation control values in the "Technical Specification for Foundation Pit Support", the constant settlement term is taken. a=20mm Coefficients of the variable term b Based on the second-stage foundation pit depth of 7.85m and the settlement control coefficient of 0.2% for the second-stage foundation pit, the following calculations can be performed: b= 7850 × 0.2% = 15.7 mm. Therefore, the surface settlement prediction formula for this large-scale integrated transportation hub project is as follows: ; Furthermore, based on the design and construction plan of this large-scale integrated transportation hub project, the width of the intermediate platform at each monitoring point... W The corresponding predicted values of land subsidence can be calculated. The comparison results between the predicted and measured values of land subsidence are shown in Table 2 below.
[0086] Table 2. Comparison of predicted and measured surface settlement values at various monitoring points of a large-scale integrated transportation hub project.
[0087] As shown in Table 2 above, the measured values of surface settlement at each monitoring point are all less than the predicted values of surface settlement, and the safety margin is about 30%, which is slightly higher than the safety reserve margin of 25% provided in the construction design scheme. This ensures both the safety of the construction project and takes into account the economic situation of the project. Therefore, the surface settlement prediction method and corresponding target prediction model for multi-level foundation pits provided in this application are safe, reliable and economical.
[0088] Based on the same technical concept as the above embodiments, the multi-level foundation pit surface settlement prediction method provided in this application can be implemented by a multi-level foundation pit surface settlement prediction device. This application uses the example of a multi-level foundation pit surface settlement prediction device implementing the multi-level foundation pit surface settlement prediction method to illustrate the multi-level foundation pit surface settlement prediction device provided in this application. Figure 6 This is a schematic diagram of the multi-stage foundation pit surface settlement prediction device provided in the embodiments of this application, as shown below. Figure 6 As shown, the multi-stage foundation pit surface settlement prediction device 600 includes: The first determining module 610 is used to determine the geometric geological parameters and settlement control parameters of the target multi-stage foundation pit.
[0089] The second determining module 620 is used to determine the model parameters of the target prediction model based on the engineering design information of the target multi-level foundation pit; The numerical prediction module 630 is used to input geometric geological parameters, settlement control parameters and model parameters into the target prediction model to predict settlement and obtain the predicted surface settlement value of the target multi-level foundation pit.
[0090] The multi-level foundation pit surface settlement prediction device provided in this application embodiment scientifically and quantitatively considers the influence of the width of the intermediate platform in the multi-level foundation pit, and predicts surface settlement through a target prediction model, providing accurate and reliable control basis for the design and construction of multi-level foundation pit projects.
[0091] It is understood that the implementation methods of the multi-level foundation pit surface settlement prediction method in the above embodiments are also applicable to this embodiment and can achieve the same technical effect, so they will not be described again here.
[0092] Based on the same concept, this application also provides an electronic device. Figure 7 This is a schematic diagram of the structure of an electronic device provided in an embodiment of this application, such as... Figure 7 As shown, the electronic device 700 may include a processor 710, a communication interface 720, a memory 730, and a communication bus 740, wherein the processor 710, the communication interface 720, and the memory 730 communicate with each other via the communication bus 740. The processor 710 can call logical instructions in the memory 730 to execute the steps of the multi-level foundation pit surface settlement prediction method as described in the above embodiments. For example, it includes: S100. Determine the geometric and geological parameters and settlement control parameters of the target multi-stage foundation pit; S200. Based on the engineering design information of the target multi-level foundation pit, determine the model parameters of the target prediction model; S300. Input the geometric geological parameters, settlement control parameters and model parameters into the target prediction model to predict the settlement and obtain the predicted surface settlement value of the target multi-level foundation pit.
[0093] The processor 710 can be a central processing unit (CPU). The processor can also be other general-purpose processors, digital signal processors (DSPs), application-specific integrated circuits (ASICs), field-programmable gate arrays (FPGAs), or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, or combinations of the above types of chips.
[0094] Furthermore, the logical instructions in the aforementioned memory 730 can be implemented as software functional units and, when sold or used as independent products, can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of this application, in essence, or the part that contributes to related technologies, or a portion of the technical solution, can be embodied in the form of a software product. This computer software product is stored in a storage medium and includes several instructions to cause a computer device (which may be a personal computer, server, or network device, etc.) to execute all or part of the steps of the methods described in the various embodiments of this application. The aforementioned storage medium includes various media capable of storing program code, such as USB flash drives, portable hard drives, read-only memory (ROM), random access memory (RAM), magnetic disks, or optical disks.
[0095] The memory 730 may include a program storage area and a data storage area. The program storage area may store the operating system and applications required for at least one function; the data storage area may store data created by the processor, etc. Furthermore, the memory may include high-speed random access memory and non-transitory memory, such as at least one disk storage device, flash memory device, or other non-transitory solid-state storage device. In some embodiments, the memory may optionally include memory remotely located relative to the processor, which can be connected to the processor via a network. Examples of such networks include, but are not limited to, the Internet, corporate intranets, local area networks, mobile communication networks, and combinations thereof.
[0096] Based on the same concept, embodiments of this application also provide a computer-readable storage medium storing a computer program containing at least one piece of code executable by a master control device to control the master control device to implement the steps of the multi-level foundation pit surface settlement prediction method as described in the above embodiments. For example, it includes: S100. Determine the geometric and geological parameters and settlement control parameters of the target multi-stage foundation pit; S200. Based on the engineering design information of the target multi-level foundation pit, determine the model parameters of the target prediction model; S300. Input the geometric geological parameters, settlement control parameters and model parameters into the target prediction model to predict the settlement and obtain the predicted surface settlement value of the target multi-level foundation pit.
[0097] Based on the same technical concept, this application also provides a computer program, which, when executed by a main control device, is used to implement the above-described method embodiments.
[0098] The computer program may be stored, in whole or in part, on a computer-readable storage medium packaged with the processor, or in part or in whole on a memory not packaged with the processor.
[0099] Based on the same technical concept, this application also provides a processor for implementing the above-described method embodiments. The processor can be a chip.
[0100] In summary, the multi-stage foundation pit surface settlement prediction method, device, electronic equipment, and storage medium provided in this application determine the geometric and geological parameters and settlement control parameters of the target multi-stage foundation pit; determine the model parameters of the target prediction model based on the engineering design information of the target multi-stage foundation pit; and input the geometric and geological parameters, settlement control parameters, and model parameters into the target prediction model to predict settlement, thereby obtaining the predicted surface settlement value of the target multi-stage foundation pit. This application, based on theoretical analysis and numerical simulation of the engineering parameters of the target multi-stage foundation pit, comprehensively considers the influence of the multi-stage foundation pit depth and the width of the intermediate platform to establish a target prediction model for predicting surface settlement control values. This model can more accurately and conveniently predict the surface settlement control values of multi-stage foundation pits under different working conditions, providing a scientific basis for engineering design.
[0101] In this document, the term "embodiment" means that a particular feature, structure, or characteristic described in connection with an embodiment may be included in at least one embodiment of this application. The appearance of this phrase in various places throughout the specification does not necessarily refer to the same embodiment, nor is it a separate or alternative embodiment mutually exclusive with other embodiments. It will be explicitly and implicitly understood by those skilled in the art that the embodiments described herein can be combined with other embodiments.
[0102] The embodiments described above are merely examples of several implementation methods of this application, and while the descriptions are specific and detailed, they should not be construed as limiting the scope of this patent application. It should be noted that those skilled in the art can make various modifications and improvements without departing from the concept of this application, and these modifications and improvements all fall within the protection scope of this application.
[0103] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of this application, and are not intended to limit them. Although this application has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that modifications can still be made to the technical solutions described in the foregoing embodiments, or equivalent substitutions can be made to some of the technical features. Such modifications or substitutions do not cause the essence of the corresponding technical solutions to deviate from the spirit and scope of the technical solutions of the embodiments of this application.
Claims
1. A method for predicting ground surface settlement of a multi-stage foundation pit, characterized by, The method includes: Determine the geometric and geological parameters and settlement control parameters of the target multi-stage foundation pit; Based on the engineering design information of the target multi-level foundation pit, determine the model parameters of the target prediction model; The geometric geological parameters, the settlement control parameters, and the model parameters are input into the target prediction model to predict the settlement, thereby obtaining the predicted surface settlement value of the target multi-level foundation pit.
2. The multi-stage foundation pit ground surface settlement prediction method according to claim 1, characterized by, The model expression for the target prediction model is as follows: ; in the above formula, denotes the ground settlement prediction value of the target multi-stage foundation pit, k 1 denotes the settlement control coefficient of the first-stage foundation pit of the target multi-stage foundation pit, H 1 denotes the depth of the first-stage foundation pit of the target multi-stage foundation pit, k i denotes the settlement control coefficient of the i -1 stage foundation pit of the target multi-stage foundation pit, H i denotes the depth of the i -1 stage foundation pit of the target multi-stage foundation pit, W i-1 denotes the intermediate platform width between the i -1 stage foundation pit and the i -1 stage foundation pit of the target multi-stage foundation pit, denotes the settlement decay parameter of the i -1 stage foundation pit in the target prediction model, denotes the curve shape parameter of the i -1 stage foundation pit in the target prediction model, exp[] denotes the natural exponential function, wherein i = 2, 3, …, N , N denotes the total number of stages of the target multi-stage foundation pit.
3. The method for predicting surface settlement of multi-stage foundation pits according to claim 1, characterized in that, The step of determining the model parameters of the target prediction model based on the engineering design information of the target multi-level foundation pit includes: Based on the engineering design information, the surface settlement monitoring data of the target multi-stage foundation pit is determined, and statistical regression processing is performed on the surface settlement monitoring data and the target prediction model to obtain the model parameters; Alternatively, numerical simulation of the target multi-level foundation pit can be performed based on the engineering design information to obtain numerical simulation results, and the model parameters can be determined based on the numerical simulation results and the target prediction model.
4. The method for predicting surface settlement of multi-stage foundation pits according to claim 3, characterized in that, Based on the surface subsidence monitoring data and the target prediction model, statistical regression processing is performed to obtain the model parameters, including: Based on the surface settlement monitoring data and the geometric geological parameters, a target dataset is constructed with the width of the intermediate platform of the target multi-level foundation pit as the independent variable and the surface settlement value as the dependent variable. The model parameters are obtained by performing nonlinear regression fitting based on the target dataset and the target prediction model.
5. The method for predicting surface settlement of multi-stage foundation pits according to claim 3, characterized in that, Numerical simulations of the target multi-stage foundation pit are performed based on the engineering design information to obtain numerical simulation results. The model parameters are then determined based on the numerical simulation results and the target prediction model, including: Based on the engineering design information, a three-dimensional numerical calculation model of the target multi-level foundation pit is constructed; In the three-dimensional numerical calculation model, different combinations of intermediate platform widths of the target multi-level foundation pit are set up, and the corresponding allowable values of surface settlement are simulated and calculated under each combination of intermediate platform widths. A sample dataset is constructed based on the combined working conditions of the intermediate platform width and the allowable value of surface subsidence; The model parameters are obtained by performing nonlinear regression fitting based on the sample dataset and the target prediction model.
6. The method for predicting surface settlement of multi-stage foundation pits according to claim 5, characterized in that, The step of constructing a three-dimensional numerical calculation model of the target multi-level foundation pit based on the engineering design information includes: Based on the engineering design information, determine the modeling scope and soil parameters of the target multi-level foundation pit; Based on the modeling scope and the soil parameters, an initial finite element model is constructed; The initial finite element model is meshed and its boundaries are defined to obtain the initial three-dimensional numerical calculation model; Gravity load is applied to the initial three-dimensional numerical calculation model, the calculation is run until the initial geostress equilibrium state is reached, and the displacement field is cleared to zero to obtain the three-dimensional numerical calculation model.
7. The method for predicting surface settlement of multi-stage foundation pits according to claim 1, characterized in that, The geometric geological parameters include at least the depth of each level of the target multi-level foundation pit and the width of the intermediate platform between each level of foundation pit. The settlement control parameters include the settlement control coefficients of each level of foundation pit. Determining the geometric geological parameters and settlement control parameters of the target multi-level foundation pit includes: Based on the engineering survey and design data of the target multi-level foundation pit, determine the depth of each level of foundation pit and the width of the intermediate platform between each level of foundation pit; Based on the engineering safety level and surrounding environmental conditions of the target multi-level foundation pit, the settlement control coefficient of each level of foundation pit is determined.
8. A multi-stage foundation pit surface settlement prediction device, characterized in that, The device includes: The first determining module is used to determine the geometric geological parameters and settlement control parameters of the target multi-stage foundation pit; The second determining module is used to determine the model parameters of the target prediction model based on the engineering design information of the target multi-level foundation pit; The numerical prediction module is used to input the geometric geological parameters, the settlement control parameters and the model parameters into the target prediction model to predict the settlement and obtain the predicted surface settlement value of the target multi-level foundation pit.
9. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that, The processor executes the computer program to implement the multi-level foundation pit surface settlement prediction method as described in any one of claims 1-7.
10. A computer-readable storage medium having a computer program stored thereon, characterized in that, When the computer program is executed by the processor, it implements the multi-level foundation pit surface settlement prediction method as described in any one of claims 1-7.