A Multi-Dimensional Dynamic Resource Scheduling Optimization Decision-Making Method for Distribution Network Construction Sites

By constructing a dynamic risk evolution model and multi-objective resource scheduling optimization, resource allocation is adjusted in real time, solving the problem of insufficient risk adaptability in the construction process in existing technologies, and realizing a dynamic balance between safety and efficiency at the power distribution network construction site.

CN123117643APending Publication Date: 2026-11-17JIAOZUO POWER SUPPLY COMPANY OF STATE GRID HENAN ELECTRIC POWER
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611305925.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-26
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

Existing resource scheduling methods for power distribution network construction fail to effectively consider the dynamic evolution of risks such as live-line work, cross-operation risks, and personnel fatigue risks during construction. This results in an inability to dynamically balance safety and efficiency, a lack of closed-loop adjustment capabilities in scheduling schemes, and insufficient adaptability of resource allocation.

Method used

By collecting data from construction sites and power grid operations, a dynamic risk evolution model is constructed to identify multiple core risks. A multi-objective resource scheduling optimization model is established to monitor risk values ​​in real time and trigger a re-optimization process, updating model parameters and constraint boundaries to achieve closed-loop iterative adjustment of resource allocation.

Benefits of technology

It achieves a dynamic balance between construction safety and operational efficiency, improves the risk adaptability and dynamic response capability of resource scheduling, and ensures the safety of the construction process and the efficiency of resource allocation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123117643A_ABST
    Figure CN123117643A_ABST
Patent Text Reader

Abstract

This invention discloses a multi-dimensional resource dynamic scheduling optimization decision-making method for power distribution network construction sites, relating to the field of power distribution network construction scheduling technology. The method includes: S1, collecting basic data from the construction site and corresponding regional power grid operation data, dividing construction resource dimensions, and clarifying the attribute parameters and scheduling constraints of each dimension of resources. This invention constructs a dynamic evolution model of risks throughout the construction process, enabling dynamic quantitative assessment of various risks such as live-line work, overlapping work areas, and personnel fatigue. This replaces the traditional scheduling mode that uses safety requirements as fixed constraints. By establishing a risk-driven closed-loop optimization mechanism for resource scheduling, real-time risk values ​​are used as dynamic weights for scheduling optimization, triggering proactive iterative adjustments to resource allocation. This achieves a dynamic balance between construction safety and operational efficiency, effectively improving the risk adaptability and dynamic response capability of power distribution network construction resource scheduling, and fully ensuring operational safety and efficient multi-dimensional resource allocation throughout the construction process.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of power distribution network construction scheduling technology, specifically a multi-dimensional dynamic resource scheduling optimization decision-making method for power distribution network construction sites. Background Technology

[0002] Distribution network construction refers to the entire process of engineering operations, including overhead line erection, cable laying, power distribution equipment installation, and grid upgrading, carried out in accordance with power grid construction and renovation plans. It is a core implementation link for improving the distribution network structure, enhancing power supply security, and supporting the steady growth of regional electricity load, directly affecting the overall power supply reliability and operational safety of the distribution network. Distribution network construction site resource scheduling optimization decision-making refers to the technical activities of planning, adjusting, and optimizing resource allocation schemes based on multiple dimensions of resources involved in the construction process, such as personnel teams, construction machinery, engineering materials, and safety assurance, combined with construction procedure logic, schedule targets, site conditions, and power grid operation requirements. It is a core management tool for ensuring controllable construction progress, controlling project cost input, and managing on-site operational risks.

[0003] However, existing resource scheduling methods for power distribution network construction typically embed safety requirements as fixed constraint thresholds into the optimization model, failing to consider the dynamic evolution characteristics of risks such as live-line work, cross-operation risks, and personnel fatigue risks during construction. This makes it difficult to achieve a dynamic balance between safety and efficiency. Furthermore, the scheduling scheme lacks dynamic closed-loop adjustment capabilities and cannot proactively optimize resource allocation based on real-time changes in on-site risks, easily leading to problems such as lagging safety management and insufficient resource allocation adaptability. Therefore, developing a multi-dimensional dynamic resource scheduling optimization decision-making method for power distribution network construction sites is of great significance. Summary of the Invention

[0004] The purpose of this invention is to overcome the shortcomings of the prior art and provide a multi-dimensional dynamic resource scheduling optimization decision-making method for power distribution network construction sites. It can overcome the defects of existing power distribution network construction site resource scheduling schemes that set safety requirements as fixed constraints, do not consider the dynamic evolution characteristics of risks such as live-line operation risks, cross-operation risks, and personnel fatigue risks during construction, lack closed-loop dynamic adjustment capabilities in scheduling schemes, and have poor adaptability of resource allocation to real-time risk conditions on site.

[0005] To solve the above-mentioned technical problems, the present invention provides the following technical solution: a multi-dimensional dynamic resource scheduling optimization decision-making method for power distribution network construction sites, the method comprising the following steps: S1. Collect basic data from the construction site and power grid operation data from the corresponding area, divide the construction resources into dimensions, and clarify the attribute parameters and scheduling constraints of each dimension of resources. S2. Based on the collected multi-source data, identify the core risk types, construct a dynamic risk evolution model covering the entire construction cycle, and output the comprehensive safety risk value for each time period and each work surface; S3. Using resource scheduling constraints, construction procedure logic constraints, and power grid operation safety constraints as constraints, and construction period, project cost, and comprehensive safety risk as optimization objectives, and taking the comprehensive safety risk value as the dynamic weight coefficient of the optimization objective, a multi-objective resource scheduling optimization model is constructed and solved to generate a multi-dimensional initial resource scheduling scheme. S4. During the construction process, real-time data collection of on-site operations and power grid operation data is performed to calculate the actual comprehensive safety risk value. This value is then compared with the preset risk warning threshold to determine the scheduling execution deviation and trigger the re-optimization process. S5. Update the risk weight coefficients and resource constraint boundaries in the optimization model, adjust resource allocation and process sequence, solve to generate the updated resource scheduling scheme and issue it for execution.

[0006] Furthermore, step S2, in constructing the dynamic evolution model of risks throughout the construction process, includes the following steps: Identify four core risk types during the construction process: risks of live-line work, risks of overlapping work areas, risks of personnel fatigue, and risks of power grid operation coupling; and analyze the influencing factors and evolution patterns of each type of risk. For each type of risk, a corresponding quantitative assessment function is constructed, the value rules and calculation methods of each risk factor are determined, and the quantitative value of a single type of risk at each time point is obtained; Combining the temporal progression of construction procedures with changes in the spatial scope of operations, a time-weighted fusion method is used to calculate the comprehensive safety risk value at each moment. The calculation formula is as follows: ,in Let t be the comprehensive safety risk value. Let be the quantified value of the i-th type of core risk at time t. Let be the temporal weight coefficient of the i-th type of core risk at time t, and let the temporal weight coefficient satisfy the normalization constraint. By combining the analytic hierarchy process (AHP) with historical power distribution network construction risk sample data for calibration, and dynamically updating the data as construction progresses, the dynamic change process of risk values ​​under different process combinations and resource allocation schemes is simulated.

[0007] Furthermore, step S3, in constructing the multi-objective resource scheduling optimization model, includes the following steps: The scheduling constraints of resources in each dimension, the logical constraints of construction procedures, and the safety constraints of power grid operation are identified, and the boundary range and restriction rules of each type of constraint are clarified. The comprehensive safety risk value output by the dynamic risk evolution model is transformed into dynamic weight coefficients for the optimization objective, establishing a mapping relationship between the objective function and the risk value. The formula for calculating the dynamic weight coefficients of the safety objective is as follows: ,in Here, k represents the dynamic weighting coefficient for the safety objective, and k represents the baseline weighting coefficient for the safety objective. For risk sensitivity coefficient, The comprehensive safety risk value at the corresponding time is determined by the safety target benchmark weighting coefficient based on the project safety level, and the risk sensitivity coefficient is determined based on the safety management and control regulations for power distribution network construction sites and on-site risk calibration tests. A multi-objective optimization algorithm is used to solve the model, and the time-series configuration plan and spatial deployment location of various resources are output.

[0008] Furthermore, step S5, when performing closed-loop iterative optimization of resource scheduling, includes the following steps: Based on the current real-time risk value and scheduling execution deviation, update the risk weight coefficients and resource constraint boundaries of the multi-objective optimization model, and adjust the model's input parameters and constraints. The optimization direction is to minimize the cost of resource adjustment and maximize the speed of risk reduction. The adjustment directions for personnel team arrangement, safety monitoring force configuration, high-risk process sequence, and live-line work resource allocation are determined. The formula for calculating the cost of resource adjustment is: ,in The total cost of resource adjustment For the unit adjustment cost of construction resources of type j, The unit adjustment cost of each type of construction resource is determined based on the standard quota for construction resources in the power distribution network and the on-site operation cost data. The updated resource scheduling scheme is generated and sent to the on-site execution terminal.

[0009] Furthermore, the dimensional division of construction resources in step S1 includes four dimensions: personnel operation resources, construction machinery resources, engineering material resources, and safety assurance resources. The attribute parameters of each dimension of resources include quantity parameters, location parameters, and operation capability parameters. The scheduling constraints include time constraints, spatial constraints, and operation rule constraints. The parameters and constraints of each dimension of resources are entered into the basic database of the scheduling optimization model as the basic input for model solving.

[0010] Furthermore, the basic construction site data collected in step S1 includes construction process node logic, personnel team configuration information, equipment deployment location status, material entry plan, and work space distribution range. The collected power grid operation data includes energized area division, line load status, and voltage operation parameters. All collected data are standardized and preprocessed before being stored in the data layer of the dispatching system.

[0011] Furthermore, the initial scheduling scheme generated in step S3 includes the entry time nodes of various resources, the division of work areas, the sequence of work processes, and the deployment of safety monitoring points. The initial scheduling scheme sets risk warning thresholds and allowable scheduling deviation ranges for each construction stage, which serve as the scheduling benchmark for subsequent construction execution processes.

[0012] Furthermore, the basis for determining the scheduling execution deviation in step S4 includes the actual execution progress and configuration status of resources in each dimension. The preset risk warning threshold is set in stages according to the construction preparation stage, the main operation stage, and the final acceptance stage. When the actual comprehensive safety risk value exceeds the preset risk warning threshold of the corresponding stage, or the scheduling execution deviation exceeds the allowable range, the scheduling scheme re-optimization process is triggered.

[0013] Furthermore, the real-time construction site operation data collected in step S4 includes personnel work location, equipment operation status, process progress, and work area space. The real-time power grid operation data includes line energization status, load fluctuation data, and equipment operation parameters. The real-time data is uploaded to the scheduling and optimization system at fixed intervals to update the risk calculation input.

[0014] Furthermore, the adjustment of resource allocation and process sequence in step S5 includes rearranging the work areas of personnel teams, increasing the number of safety monitoring points, adjusting the work periods of high-risk processes, and optimizing the quantity and location of live-line work resources. The adjusted scheduling scheme is updated synchronously with risk warning thresholds and allowable scheduling deviation ranges.

[0015] Compared with existing technologies, this multi-dimensional dynamic resource scheduling optimization decision-making method for power distribution network construction sites has the following beneficial effects: This invention constructs a dynamic evolution model of risks throughout the entire construction process, enabling dynamic quantitative assessment of various risks such as live-line work, overlapping work areas, and personnel fatigue. It replaces the traditional scheduling mode that treats safety requirements as fixed constraints. By establishing a risk-driven closed-loop optimization mechanism for resource scheduling, it uses real-time risk values ​​as dynamic weights for scheduling optimization, triggering proactive iterative adjustments to resource allocation. This achieves a dynamic balance between construction safety and operational efficiency, effectively improving the risk adaptability and dynamic response capability of power distribution network construction resource scheduling, and fully ensuring operational safety and efficient allocation of multi-dimensional resources throughout the entire construction process.

[0016] Other advantages, objectives and features of the invention will be set forth in part in the description which follows, and in part will be apparent to those skilled in the art from the following examination or study, or may be learned from the practice of the invention. Attached Figure Description

[0017] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the accompanying drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are merely some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without any creative effort.

[0018] Figure 1 A flowchart of a multi-dimensional dynamic resource scheduling optimization decision-making method for power distribution network construction sites; Figure 2 A flowchart illustrating the steps of a multi-dimensional dynamic resource scheduling optimization decision-making method for power distribution network construction sites; Figure 3 This is a flowchart for constructing a dynamic evolution model of risks throughout the entire construction process. Detailed Implementation

[0019] To further illustrate the technical means and effects of the present invention in achieving its intended purpose, the following detailed description of the specific implementation methods, structures, features, and effects of the present invention, in conjunction with the accompanying drawings and preferred embodiments, is provided below.

[0020] This invention provides a multi-dimensional dynamic resource scheduling optimization decision-making method for power distribution network construction sites. It collects multi-source basic data from the construction site and power grid operation, classifies construction resources into four dimensions: personnel operations, construction machinery, engineering materials, and safety assurance, and clarifies their attributes and constraints. Based on this, it identifies the core risk types throughout the construction process, constructs a dynamic risk evolution model to achieve time-series weighted fusion and quantification of multiple risk types, and then uses risk values ​​as dynamic weight coefficients to construct a multi-objective resource scheduling optimization model. This model solves and generates an initial scheduling scheme. During the construction execution phase, real-time data collection at the site calculates the actual risk value. A re-optimization process is triggered by dual judgments of risk thresholds and scheduling deviations, updating model parameters and constraint boundaries to generate an adjusted scheduling scheme. This forms a risk-driven closed-loop optimization mechanism, achieving a dynamic balance between construction safety and operational efficiency. A detailed description is provided below with reference to specific embodiments.

[0021] This embodiment is applied to the construction site of a 10kV distribution network overhead line renovation project in a certain urban area. The project includes three main processes: pole erection, cable laying, and ring main unit installation. It involves three independent work areas, four construction work teams, two crane operators, three material delivery units, and two safety monitoring teams. The corresponding power supply area includes five 10kV distribution lines, with two distributed photovoltaic power sources connected along the lines. Power outage work windows need to be arranged in coordination with the power grid operation during construction. The overall implementation process of this embodiment is as follows: Figure 1 As shown, the overall framework of the method steps is as follows: Figure 2 As shown.

[0022] First, conduct multi-source data collection and resource dimension classification for construction. Collect basic data from the construction site and power grid operation data for the corresponding area. The basic data from the construction site covers the logical sequence of construction procedures, personnel team configuration information, equipment deployment status, material arrival plans, and the distribution range of the work space. Among them, the logical sequence of construction procedures clearly defines the order and connection of each procedure; the personnel team configuration information records the number of personnel, their qualifications, and their capabilities in each team; the equipment deployment status records the parking location, working radius, and available time period of various types of equipment; the material arrival plan records the transportation time, arrival time, and stacking location of various materials; and the distribution range of the work space delineates the geographical boundaries and active areas of each work surface.

[0023] The power grid operation data encompasses energized area delineation, line load status, and voltage operation parameters. The energized area delineation clearly defines the energized line sections and safety distance requirements within the construction area. Line load status records the real-time and predicted load curves for each line. Voltage operation parameters record the voltage level and fluctuation range at each node. All collected data undergoes standardized preprocessing, including data cleaning to remove outliers and linear normalization to map various data types to a unified numerical range, eliminating calculation discrepancies caused by different units of measurement. After processing, the data is stored in the data layer of the dispatch system. Construction resources are dimensionally categorized into four dimensions: personnel resources, construction machinery resources, engineering material resources, and safety resources. The attribute parameters and scheduling constraints for each dimension are clearly defined. Attribute parameters include quantity, location, and operational capacity parameters, while scheduling constraints include temporal, spatial, and operational rule constraints. The parameters and constraints for each dimension are entered into the basic database of the dispatch optimization model as the fundamental input for model solving.

[0024] Next, a dynamic evolution model of risks throughout the entire construction process is constructed. The implementation process for this step is as follows: Figure 3 As shown, the paper first identifies four core risk types in the construction process: risks associated with live-line work, risks of overlapping work areas, risks of personnel fatigue, and risks of coupling with power grid operation. It then analyzes the influencing factors and evolution patterns of each type of risk. Factors influencing live-line work risks include the voltage level of the work site, the distance between personnel and the live conductor, and the humidity of the work environment. Risk increases as the distance to the live conductor decreases and accumulates with increasing work duration.

[0025] Factors influencing the risk of overlapping work areas include the overlapping area of ​​different work areas, the personnel density in the overlapping area, and the degree of overlap in the operating range of machinery. The risk increases with the expansion of the overlapping area and the increase in personnel density. Factors influencing the risk of personnel fatigue include the continuous working time, work intensity, and rest interval. The risk increases non-linearly with the increase of continuous working time. Factors influencing the risk of grid operation coupling include the load factor of the corresponding line, voltage deviation, and the output fluctuation amplitude of distributed power sources. The risk increases with the increase of load factor and voltage deviation.

[0026] For each type of risk, a corresponding quantitative assessment function is constructed, and the rules for determining the values ​​and calculation methods of each risk factor are established to obtain the quantitative value of each type of risk at each time point. The quantitative value of live-line working risk is calculated based on the safety distance benchmark stipulated in the power safety work regulations, combined with the distance correction coefficient calculated from real-time monitored live-line distance, and multiplied by the benchmark risk value for the corresponding voltage level. The quantitative value of work surface intersection risk is calculated by calculating the proportion of the spatial overlap area of ​​different work surfaces to the total area of ​​a single work surface, combined with the personnel density coefficient within the intersection area. The quantitative value of personnel fatigue risk is calculated based on the ratio of continuous working time to standard working time, combined with the correction coefficient corresponding to the work intensity level. The quantitative value of power grid operation coupling risk is calculated based on the real-time line load rate, combined with the correction coefficient for node voltage deviation.

[0027] In the specific implementation of this embodiment, the comprehensive safety risk value at each moment is calculated by combining the temporal progression of construction procedures with changes in the spatial operation scope. The calculation formula is as follows: ,in Let t be the comprehensive safety risk value. Let be the quantified value of the i-th type of core risk at time t. Let be the temporal weight coefficient of the i-th type of core risk at time t, and let the temporal weight coefficient satisfy the normalization constraint. The time-series weighting coefficients are calibrated using the analytic hierarchy process (AHP) combined with historical distribution network construction risk sample data. Specifically, the calibration process involves selecting historical risk event samples from similar distribution network construction projects, constructing a relative importance judgment matrix for four types of risks, and calculating the initial weights for each construction stage after a consistency check. These weights are then dynamically updated as the construction stage progresses. The construction preparation stage focuses on grid operation coupling risks and material arrival risks; the main construction stage focuses on live-line work risks and work area intersection risks; and the final acceptance stage focuses on personnel fatigue risks and work completion safety risks. Through the above calculations, the dynamic changes in risk values ​​under different process combinations and resource allocation schemes are simulated, outputting the comprehensive safety risk value for each work area at each time period, forming a dynamic risk evolution model covering the entire construction cycle.

[0028] Then, a multi-objective resource scheduling optimization model is constructed and solved. Three types of constraints are determined: scheduling constraints for resources across various dimensions, logical constraints for construction procedures, and safety constraints for power grid operation. The boundary range and limiting rules for each type of constraint are clarified. Resource scheduling constraints include constraints on the working time periods of personnel teams, the working radius of construction machinery, the arrival time of engineering materials, and the coverage range of safety assurance resources. Logical constraints on construction procedures include constraints on the sequence of each procedure and the time interval between procedures. Safety constraints for power grid operation include constraints on the time period of power outage work windows, safe distance constraints for live-line work, and upper limit constraints on line load.

[0029] In the specific implementation of this embodiment, the comprehensive safety risk value output by the risk dynamic evolution model is transformed into the dynamic weight coefficient of the optimization target, and a mapping relationship between the objective function and the risk value is established. The calculation formula for the dynamic weight coefficient of the safety target is as follows: ,in Here, k represents the dynamic weighting coefficient for the safety objective, and k represents the baseline weighting coefficient for the safety objective. For risk sensitivity coefficient, This represents the comprehensive safety risk value at the corresponding moment.

[0030] The baseline weighting coefficient for safety targets is preset based on the project's safety level. This project belongs to the Class II renovation project of a 10kV distribution network, and the baseline weighting coefficient is set in accordance with the power grid construction safety management specifications. The risk sensitivity coefficient is determined based on the safety control regulations for distribution network construction sites and on-site risk calibration tests. By conducting on-site calibration tests on the control effects under different risk levels, the correlation between risk values ​​and safety control inputs is fitted to obtain the value of the risk sensitivity coefficient. This coefficient reflects the growth rate of the safety target weight when the overall safety risk increases; the higher the risk, the faster the safety target weight increases.

[0031] With construction period, project cost, and comprehensive safety risk as optimization objectives, a multi-objective resource scheduling optimization model is constructed based on the above three types of constraints. An improved non-dominated sorting genetic algorithm is used to solve the model. Through iterative processes such as population initialization, fitness calculation, non-dominated sorting, and crossover mutation, a Pareto optimal solution set for multi-objective optimization is obtained. The final scheduling scheme is selected from the solution set based on the actual priority requirements of the project, and the temporal configuration plan and spatial deployment location of various resources are output, generating a multi-dimensional initial resource scheduling scheme. The initial scheduling scheme includes the arrival time nodes of various resources, the division of work areas, the sequence of work processes, and the deployment of safety monitoring points. The initial scheduling scheme sets risk warning thresholds and allowable scheduling deviation ranges for each construction stage, serving as the scheduling benchmark for subsequent construction execution.

[0032] Next, real-time risk monitoring and scheduling deviation assessment are performed. During construction, real-time data collection is conducted on both the construction site and power grid operation. Construction site data includes personnel location, equipment status, process progress, and work area scope. Power grid operation data includes line energization status, load fluctuation data, and equipment operating parameters. This real-time data is uploaded to the scheduling optimization system every 15 minutes to update the risk calculation input. The real-time data is then input into a dynamic risk evolution model to calculate the actual comprehensive safety risk value at the current moment. Preset risk warning thresholds are set in stages according to the construction preparation phase, main construction phase, and final acceptance phase. The threshold for each stage is determined based on the risk characteristics and control requirements of the corresponding stage.

[0033] The actual comprehensive security risk value is compared with the preset risk warning threshold for the corresponding stage. Simultaneously, the actual execution progress and configuration status of resources across all dimensions are collected to determine scheduling execution deviations. Scheduling execution deviations include progress deviations and resource configuration deviations. Progress deviations are calculated as the difference between the planned and actual completion progress of each process, while resource configuration deviations are calculated as the offset between the actual and planned deployment locations of various resources. Each type of deviation has corresponding allowable ranges. When the actual comprehensive security risk value exceeds the preset risk warning threshold for the corresponding stage, or when the scheduling execution deviation exceeds the allowable range, a scheduling scheme re-optimization process is triggered.

[0034] Finally, closed-loop iterative optimization of resource scheduling is carried out. Based on the current real-time risk value and scheduling execution deviation, the risk weight coefficients and resource constraint boundaries of the multi-objective optimization model are updated, and the input parameters and constraints of the model are adjusted. The optimization direction is to minimize resource adjustment costs and maximize risk reduction, determining the adjustment directions for personnel team arrangements, safety monitoring personnel configuration, high-risk process sequence, and live-line work resource configuration. When the risk increase is mainly caused by live-line work risks, priority is given to dispatching additional safety monitoring personnel to the corresponding work area, while adjusting live-line work processes to off-peak grid load periods to reduce grid operation coupling risks. When the risk increase is mainly caused by cross-work area risks, the work areas of each team are rearranged to reduce the overlap of work areas, and the work sequence of overlapping areas is staggered. When the risk increase is mainly caused by personnel fatigue risks, the personnel shift work rhythm is adjusted, intermediate rest intervals are increased, and backup personnel are added.

[0035] In the specific implementation of this embodiment, the formula for calculating the resource adjustment cost is as follows: ,in The total cost of resource adjustment For the unit adjustment cost of construction resources of type j, This represents the adjustment amount for the configuration of construction resources of type j. The unit adjustment cost of each type of resource is determined based on the standard quota for power distribution network construction resources and on-site operation cost data. Specifically, the unit adjustment cost of personnel operation resources corresponds to the labor costs of idle personnel and temporary dispatch; the unit adjustment cost of construction machinery resources corresponds to the cost of machinery relocation and idle shifts; the unit adjustment cost of engineering material resources corresponds to the cost of secondary handling and temporary storage of materials; and the unit adjustment cost of safety assurance resources corresponds to the labor costs of temporarily dispatching additional monitoring personnel.

[0036] Based on the adjustment direction and cost calculation results, the work areas of personnel teams are rearranged, the number of safety monitoring points is increased, the work periods of high-risk processes are adjusted, and the quantity and location of live-line work resources are optimized. An updated resource scheduling plan is then generated and distributed to the field execution end. The adjusted scheduling plan simultaneously updates the risk warning threshold and the allowable range of scheduling deviation. After the updated plan is implemented, it returns to the real-time risk monitoring stage for continuous cyclical judgment and optimization, forming a complete closed-loop scheduling mechanism.

[0037] In summary, this embodiment constructs a dynamic evolution model of risks throughout the entire construction process, enabling dynamic quantification and temporal fusion of various construction risks. This replaces the traditional scheduling mode that treats safety requirements as fixed constraints. By establishing a risk-driven closed-loop optimization mechanism for resource scheduling, real-time risk values ​​are transformed into dynamic weights for scheduling optimization, triggering proactive iterative adjustments to resource allocation. This achieves a dynamic balance between construction safety and operational efficiency, improves the risk adaptability and dynamic response capability of power distribution network construction resource scheduling, and ensures operational safety and efficient allocation of multi-dimensional resources throughout the entire construction process.

[0038] The above description is merely a preferred embodiment of the present invention and is not intended to limit the present invention in any way. Although the present invention has been disclosed above with reference to preferred embodiments, it is not intended to limit the present invention. Any person skilled in the art can make some modifications or alterations to the above-disclosed technical content to create equivalent embodiments without departing from the scope of the present invention. Any simple modifications, equivalent changes and alterations made to the above embodiments based on the technical essence of the present invention without departing from the scope of the present invention shall still fall within the scope of the present invention.

Claims

1. A multi-dimensional dynamic resource scheduling optimization decision-making method for power distribution network construction sites, characterized in that, The method includes the following steps: S1. Collect basic data from the construction site and power grid operation data from the corresponding area, divide the construction resources into dimensions, and clarify the attribute parameters and scheduling constraints of each dimension of resources. S2. Based on the collected multi-source data, identify the core risk types, construct a dynamic risk evolution model covering the entire construction cycle, and output the comprehensive safety risk value for each time period and each work surface; S3. Using resource scheduling constraints, construction procedure logic constraints, and power grid operation safety constraints as constraints, and construction period, project cost, and comprehensive safety risk as optimization objectives, and taking the comprehensive safety risk value as the dynamic weight coefficient of the optimization objective, a multi-objective resource scheduling optimization model is constructed and solved to generate a multi-dimensional initial resource scheduling scheme. S4. During the construction process, real-time data collection of on-site operations and power grid operation data is performed to calculate the actual comprehensive safety risk value. This value is then compared with the preset risk warning threshold to determine the scheduling execution deviation and trigger the re-optimization process. S5. Update the risk weight coefficients and resource constraint boundaries in the optimization model, adjust resource allocation and process sequence, solve to generate the updated resource scheduling scheme and issue it for execution.

2. The method for dynamic scheduling and optimization decision-making of multi-dimensional resources at a power distribution network construction site according to claim 1, characterized in that, Step S2, when constructing the dynamic evolution model of risks throughout the construction process, includes the following steps: Identify four core risk types during the construction process: risks of live-line work, risks of overlapping work areas, risks of personnel fatigue, and risks of power grid operation coupling; and analyze the influencing factors and evolution patterns of each type of risk. For each type of risk, a corresponding quantitative assessment function is constructed, the value rules and calculation methods of each risk factor are determined, and the quantitative value of a single type of risk at each time point is obtained; Combining the temporal progression of construction procedures with changes in the spatial scope of operations, a time-weighted fusion method is used to calculate the comprehensive safety risk value at each moment. The calculation formula is as follows: ,in Let t be the comprehensive safety risk value. Let be the quantified value of the i-th type of core risk at time t. Let be the temporal weighting coefficient of the i-th type of core risk at time t, which is dynamically updated as the construction phase progresses, simulating the dynamic change process of risk value under different combinations of work processes and resource allocation schemes.

3. The method for dynamic scheduling and optimization decision-making of multi-dimensional resources at a power distribution network construction site according to claim 1, characterized in that, Step S3, when constructing the multi-objective resource scheduling optimization model, includes the following steps: The scheduling constraints of resources in each dimension, the logical constraints of construction procedures, and the safety constraints of power grid operation are identified, and the boundary range and restriction rules of each type of constraint are clarified. The comprehensive safety risk value output by the dynamic risk evolution model is transformed into dynamic weight coefficients for the optimization objective, establishing a mapping relationship between the objective function and the risk value. The formula for calculating the dynamic weight coefficients of the safety objective is as follows: ,in Here, k represents the dynamic weighting coefficient for the safety objective, and k represents the baseline weighting coefficient for the safety objective. For risk sensitivity coefficient, This represents the comprehensive safety risk value at the corresponding moment. A multi-objective optimization algorithm is used to solve the model, and the time-series configuration plan and spatial deployment location of various resources are output.

4. The method for multi-dimensional dynamic resource scheduling and optimization decision-making at a power distribution network construction site according to claim 1, characterized in that, Step S5, when performing closed-loop iterative optimization of resource scheduling, includes the following steps: Based on the current real-time risk value and scheduling execution deviation, update the risk weight coefficients and resource constraint boundaries of the multi-objective optimization model, and adjust the model's input parameters and constraints. The optimization direction is to minimize the cost of resource adjustment and maximize the speed of risk reduction. The adjustment directions for personnel team arrangement, safety monitoring force configuration, high-risk process sequence, and live-line work resource allocation are determined. The formula for calculating the cost of resource adjustment is: ,in The total cost of resource adjustment For the unit adjustment cost of construction resources of type j, Given the configuration adjustment amount of the j-th type of construction resources, solve for and generate an updated resource scheduling scheme and send it to the on-site execution terminal.

5. The method for multi-dimensional dynamic resource scheduling and optimization decision-making at a power distribution network construction site according to claim 1, characterized in that, The dimensional division of construction resources in step S1 includes four dimensions: personnel operation resources, construction machinery resources, engineering material resources, and safety assurance resources. The attribute parameters of each dimension of resources include quantity parameters, location parameters, and operation capability parameters. The scheduling constraints include time constraints, spatial constraints, and operation rule constraints. The parameters and constraints of each dimension of resources are entered into the basic database of the scheduling optimization model as the basic input for model solving.

6. The method for multi-dimensional dynamic resource scheduling and optimization decision-making at a power distribution network construction site according to claim 1, characterized in that, The basic data collected in step S1 includes the logic of construction process nodes, personnel team configuration information, equipment deployment location status, material entry plan, and work space distribution range. The collected power grid operation data includes the division of energized areas, line load status, and voltage operation parameters. All collected data are standardized and preprocessed before being stored in the data layer of the dispatching system.

7. The method for dynamic scheduling and optimization decision-making of multi-dimensional resources at a power distribution network construction site according to claim 1, characterized in that, The initial scheduling scheme generated in step S3 includes the entry time nodes of various resources, the division of work areas, the sequence of work processes, and the deployment of safety monitoring points. The initial scheduling scheme sets risk warning thresholds and allowable scheduling deviation ranges for each construction stage, which serve as the scheduling benchmark for subsequent construction execution.

8. The method for dynamic scheduling and optimization decision-making of multi-dimensional resources at a power distribution network construction site according to claim 1, characterized in that, The basis for determining the scheduling execution deviation in step S4 includes the actual execution progress and configuration status of resources in each dimension. The preset risk warning threshold is set in stages according to the construction preparation stage, the main operation stage, and the final acceptance stage. When the actual comprehensive safety risk value exceeds the preset risk warning threshold of the corresponding stage, or the scheduling execution deviation exceeds the allowable range, the scheduling scheme re-optimization process is triggered.

9. The method for dynamic scheduling and optimization decision-making of multi-dimensional resources at a power distribution network construction site according to claim 1, characterized in that, The real-time construction site operation data collected in step S4 includes personnel work location, equipment operation status, process progress, and work area space. The real-time power grid operation data includes line energization status, load fluctuation data, and equipment operation parameters. The real-time data is uploaded to the dispatch optimization system at fixed intervals to update the risk calculation input.

10. The method for multi-dimensional dynamic resource scheduling optimization decision-making at a power distribution network construction site according to claim 1, characterized in that, The adjustment of resource allocation and process sequence in step S5 includes rearranging the work areas of personnel teams, increasing the number of safety monitoring points, adjusting the work periods of high-risk processes, and optimizing the quantity and location of live-line work resources. The adjusted scheduling scheme is updated synchronously with risk warning thresholds and allowable scheduling deviation ranges.