A method and system for intelligent joint scheduling of batteries in a battery swapping cabinet
By using information interaction and dual-channel decision-making between the battery swapping station and the distribution network, a four-tuple allocation action is generated and multi-layer physical constraint verification is performed. This solves the problems of station-network coordination and photovoltaic consumption in battery scheduling of battery swapping cabinets, and realizes safe and efficient battery scheduling and charging management.
Patent Information
- Application Number
- CN202611611610.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-19
- Publication Date
- 2026-11-17
AI Technical Summary
The existing battery swapping cabinets lack a station-network coordination mechanism for battery scheduling, lack multi-layer physical constraint verification for cross-cabinet battery transfer, and have rigid charging power allocation, making it difficult to balance the safety of battery swapping scheduling with the photovoltaic consumption of the distribution network.
Through information exchange and dual-channel decision-making between the battery swapping station and the distribution network, a four-tuple allocation action is generated, and a chain-like verification of the number of healthy empty batteries, type compatibility, and battery space conservation is performed. This drives the battery pick-and-place actuator, calculates the battery space demand weight through charging and discharging power commands, and realizes on-demand current allocation.
It enables dual-channel coordinated scheduling of battery swapping stations and distribution networks, improving battery scheduling efficiency and charging safety, and enhancing photovoltaic absorption capacity.
Smart Images

Figure CN123121816A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of intelligent battery scheduling technology for battery swapping cabinets, and specifically to an intelligent joint scheduling method and system for batteries in battery swapping cabinets. Background Technology
[0002] Most existing battery scheduling solutions for battery swapping stations are managed independently at the local swapping station, lacking a joint collaborative decision-making mechanism between the swapping station and the distribution network. This makes it impossible to coordinate battery charging and discharging and cross-slot allocation based on the distribution network's operating conditions and photovoltaic output. At the same time, the battery allocation strategy does not have multi-layer physical constraint verification, which can easily lead to problems such as overcapacity of battery compartments and mismatched battery models. Furthermore, the charging power allocation method is fixed and rigid, and it cannot dynamically adjust the charging current according to the real-time power of each battery compartment. This makes it difficult to simultaneously ensure the safety of battery allocation operation, improve the efficiency of battery scheduling within the station, and effectively support the local consumption of photovoltaic power on the distribution network side.
[0003] The existing battery swapping cabinets lack a station-grid coordination mechanism for battery scheduling, and the cross-cabinet battery transfer lacks multi-layer physical constraint verification and the charging power allocation is rigid, making it difficult to balance the technical issues of battery swapping scheduling safety and photovoltaic power grid absorption. Summary of the Invention
[0004] This application provides an intelligent joint scheduling method and system for batteries in battery swapping cabinets, which addresses the technical problems of existing battery swapping cabinets lacking a station-network coordination mechanism, lacking multi-layer physical constraint verification for cross-cabinet battery transfer, rigid charging power allocation, and difficulty in balancing battery swapping scheduling safety with photovoltaic power grid absorption.
[0005] In view of the above problems, this application provides an intelligent joint scheduling method and system for batteries in a battery swapping cabinet.
[0006] The first aspect of this application provides an intelligent joint scheduling method for batteries in a battery swapping cabinet, the method comprising:
[0007] On the battery swapping station side and the distribution network side, information exchange and dual-channel decision-making are performed. The decision results are combined with the current full-charge surplus and demand gap of each battery swapping cabinet to map a four-element allocation action representing the source cabinet - target cabinet - battery type to be transferred out - battery type to be transferred in. The four-element allocation action is input constraint check threshold, and a chain check is performed with the number of healthy empty compartments, type compatibility and compartment conservation as the verification targets. If the check passes, the four-element allocation action and charging / discharging power command are transmitted to the register, which adopts an overwrite storage method. According to the scheduling cycle, the four-element allocation action and charging / discharging power command are retrieved from the register. The battery pick-and-place execution mechanism is driven according to the four-element allocation action. The compartment demand weight is calculated through the charging / discharging power command. The PWM half-bridge duty cycle of the multi-output circuit of the battery swapping cabinet is modulated, and the current is allocated on demand by allocating the phase share of each output circuit in the conduction sequence.
[0008] A second aspect of this application provides an intelligent joint scheduling system for batteries in a battery swapping cabinet, the system comprising:
[0009] The quaternion allocation action acquisition module is used for information exchange and dual-channel decision-making between the battery swapping station side and the distribution network side. It combines the decision results with the current full-charge surplus and demand gap of each battery swapping cabinet to map a quaternion allocation action representing the source cabinet - target cabinet - battery type to be transferred - battery type to be transferred in. The chain verification module checks the input constraints of the quaternion allocation action against thresholds, using the number of healthy empty battery compartments, type compatibility, and battery compartment conservation as verification targets. If the verification passes, the quaternion allocation action and charging / discharging power command are transmitted to a register, which uses an overwrite storage method. The current on-demand allocation module retrieves the quaternion allocation action and charging / discharging power command from the register according to the scheduling cycle. Based on the quaternion allocation action, it drives the battery pick-and-place actuator, calculates the battery compartment demand weight using the charging / discharging power command, modulates the PWM half-bridge duty cycle of the battery swapping cabinet's multi-output circuit, and performs current on-demand allocation by allocating the phase share of each output circuit in the conduction sequence.
[0010] One or more technical solutions provided in this application have at least the following technical effects or advantages:
[0011] The system, operating between the battery swapping station and the distribution network, performs information exchange and dual-channel decision-making, mapping a four-tuple allocation action representing the source cabinet, target cabinet, outgoing battery type, and incoming battery type. This four-tuple allocation action is then used to input constraint check thresholds, with healthy empty battery compartment counts, type compatibility, and battery compartment conservation as verification targets, performing a chain-like check. If the check passes, the four-tuple allocation action and charging / discharging power command are transmitted to a register. The register retrieves the four-tuple allocation action and charging / discharging power command, driving the battery pick-and-place mechanism based on the four-tuple allocation action. The battery compartment demand weight is calculated using the charging / discharging power command, and the PWM half-bridge duty cycle of the multi-output circuit of the battery swapping cabinet is modulated. Current is allocated on demand by distributing the phase share of each output circuit in the conduction sequence. This achieves dual-channel collaborative scheduling between the battery swapping station and the distribution network, enabling cross-cabinet battery allocation, improving battery scheduling efficiency and charging safety, and enhancing photovoltaic absorption capacity. Attached Figure Description
[0012] To more clearly illustrate the technical solutions in the embodiments of the present invention, the accompanying drawings used in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0013] Figure 1 This is a schematic flowchart of an intelligent joint scheduling method for batteries in a battery swapping cabinet, provided in an embodiment of this application.
[0014] Figure 2 A bar chart comparing the performance indicators of different scheduling strategies in an intelligent joint scheduling method for batteries in a battery swapping cabinet provided in an embodiment of this application;
[0015] Figure 3 This is a schematic diagram of an intelligent joint scheduling system for battery swapping cabinets provided in an embodiment of this application.
[0016] Figure labeling: Quadruple transfer action acquisition module 10, chain verification module 20, current on-demand allocation module 30. Detailed Implementation
[0017] This application provides an intelligent joint scheduling method and system for batteries in battery swapping cabinets, which addresses the technical problems of existing battery swapping cabinets lacking a station-network coordination mechanism, lacking multi-layer physical constraint verification for cross-cabinet battery transfer, rigid charging power allocation, and difficulty in balancing battery swapping scheduling safety with photovoltaic power grid absorption.
[0018] The technical solutions of the embodiments of this application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only a part of the embodiments of this application, and not all of them. All other embodiments obtained by those skilled in the art based on the embodiments of this application without creative effort are within the scope of protection of this application.
[0019] Example 1, as Figure 1 As shown, this application provides an intelligent joint scheduling method for batteries in a battery swapping cabinet, the method comprising:
[0020] Step S100: The station side and the distribution network side perform information exchange and dual-channel decision-making. The decision results are combined with the current full-charge surplus and demand gap of each battery swapping cabinet to map the four-tuple allocation action representing the source cabinet-target cabinet-out battery type-in battery type.
[0021] Specifically, an information exchange channel is established between the battery swapping station and the distribution network. The battery swapping station collects the current charging and discharging power time-series data of each local battery swapping cabinet and transmits it to the distribution network via the information exchange channel to execute the first channel decision. The first channel decision aims to minimize voltage deviation and photovoltaic curtailment, and uses capacitor bank switching actions and photovoltaic inverter reactive power regulation actions as decision variables to calculate and output the first output. The distribution network collects the current grid voltage and power flow status data and transmits it back to the battery swapping station via the information exchange channel to execute the second channel decision. The second channel decision aims to maximize the battery swapping operation revenue and uses the charging and discharging power of each cabinet as decision variables to calculate and output the second output. Simultaneously, the full-charge surplus and battery demand gap data obtained from the real-time statistics of all battery swapping cabinets are read. The first and second outputs are used as constraint inputs for greedy matching. Combined with the full-charge surplus and demand gap of each battery swapping cabinet, a greedy matching calculation is performed. After mapping and transformation, a four-tuple allocation action containing four dimensions of information, including the source cabinet, target cabinet, type of battery to be transferred out, and type of battery to be transferred in, is generated. This four-tuple allocation action is used for subsequent input constraint check thresholds to complete compliance verification.
[0022] Step S200: Input constraint check threshold for the quadruple allocation action, perform chain verification with healthy empty warehouse number, type compatibility and warehouse conservation as verification targets. If the verification is successful, transfer the quadruple allocation action and charging / discharging power command to the register, wherein the register adopts an overwrite storage method.
[0023] Specifically, the output quadruple transfer action input constraint check threshold is used to perform a three-level chained verification according to the business physical dependency relationship. The first-level threshold retrieves a real-time inventory snapshot of the battery swapping cabinet, using the healthy empty capacity of the source cabinet and the target cabinet as the verification target. If the quantity transferred out exceeds the current fully charged surplus of the source cabinet or the quantity transferred in exceeds the current healthy empty capacity of the target cabinet, the verification is deemed to have failed. The second-level threshold uses type compatibility as the verification target, reading the pre-stored cabinet-battery type compatibility relationship table for comparison. If the type of battery transferred out is not in the compatible type set of the source cabinet, or the type of battery transferred in is not in the compatible type set of the target cabinet, the verification is deemed to have failed. The third-level threshold uses the storage space conservation as the verification target. The system simultaneously verifies two conditions: the total number of batteries in the target cabinet after the transfer does not exceed the number of healthy cells, and the total number of batteries in the source cabinet after the transfer does not fall below the preset minimum number of reserved empty cells. If either condition is not met, the verification is deemed unsuccessful. During the verification process, if any level of threshold verification fails, a verification failure action mask signal is generated, and the output probability corresponding to the quadruple transfer action is set to negative infinity to eliminate invalid scheduling actions. If all three levels of chain verification pass, the quadruple transfer action and the corresponding charging and discharging power command are pushed to the register. The register adopts an overwrite storage method, and the valid scheduling data of the new scheduling cycle directly overwrites the historical scheduling data of the previous cycle stored in the register for subsequent scheduling cycles to be retrieved and executed.
[0024] Step S300: According to the scheduling cycle, retrieve the quadruple allocation action and charging / discharging power command from the register, drive the battery pick-and-place execution mechanism according to the quadruple allocation action, calculate the bay demand weight through the charging / discharging power command, modulate the PWM half-bridge duty cycle of the multi-output circuit of the battery swapping cabinet, and allocate the current as needed by allocating the phase share of each output circuit in the conduction sequence.
[0025] Specifically, the scheduling execution process is triggered according to a preset scheduling cycle. The verified quadruple allocation action and charging / discharging power command are retrieved from the register using overlay storage. Based on the source cabinet, target cabinet, battery type being transferred out, and battery type being transferred in information recorded in the quadruple allocation action, a drive signal is output to drive the battery pick-and-place actuator to complete the cross-cabinet allocation operation for the corresponding battery. Simultaneously, the total power of the charging / discharging power command is used as the upper limit of the allocable power for the entire battery swapping cabinet. The initial demand weight for each battery compartment is calculated by combining the ratio of the predicted demand gap within each battery compartment's scheduling cycle to the sum of the predicted demand gaps for all battery compartments. Then, the deviation between the current SOC and the target full-charge threshold of each battery compartment is used as a correction factor to weight and correct the initial demand weight, resulting in a compartment correction weight. This compartment correction weight is then normalized and scaled based on the allocable power upper limit to calculate the final compartment demand weight for each battery compartment. The system calculates the weight of each battery compartment and the corresponding power allocation value. Based on the obtained compartment demand weight, the PWM half-bridge duty cycle of the multi-output circuit of the battery swapping cabinet is modulated. This multi-output circuit consists of multiple transformer primary windings connected in series and then connected to the output of the PWM half-bridge inverter. The input of the PWM half-bridge inverter is connected to the DC bus output by the AC / DC power module of the battery swapping cabinet. Each transformer forms an independent output circuit and is connected to the charging port of each battery compartment. By allocating the phase share of each output circuit within the conduction sequence, the current among the multiple battery compartments is allocated on demand. After the current allocation is performed, the actual charging current of each battery compartment is continuously monitored. When the actual charging current of a battery compartment reaches the maximum allowable current limit under the current SOC state, the battery compartment is marked as saturated charging state and its demand weight is automatically downgraded. The released power share is redistributed to the other battery compartments that are not in saturation state.
[0026] In one possible implementation, step S100 further includes:
[0027] Step S110: The battery swapping station reads the charging and discharging power timing data at the current moment, transmits it to the distribution network side through information interaction, and executes the first channel decision to obtain the first output.
[0028] Step S120: The distribution network side reads the current voltage and power flow status, transmits it to the battery swapping station side through information interaction, and executes the second channel decision to obtain the second output.
[0029] Step S130: Read the current full-charge surplus and demand gap of each battery swapping cabinet, perform greedy matching based on the first output and the second output, and map to obtain the quadruple allocation action.
[0030] Specifically, the battery swapping station collects and reads the charging and discharging power time-series data of each battery swapping cabinet at the current moment. This charging and discharging power time-series data includes the real-time charging power, discharging power, and the time sequence of power changes over time for each cabinet. The collected charging and discharging power time-series data is encapsulated into standardized interactive messages and transmitted to the distribution network side through a pre-established information interaction channel. After receiving the messages and parsing them to obtain the charging and discharging power time-series data, the distribution network side executes the first channel decision. The first channel decision takes minimizing voltage deviation and minimizing photovoltaic curtailment as optimization objectives. It constructs an optimization solution model with capacitor bank switching actions and photovoltaic inverter reactive power regulation actions as decision variables. After solving the model, it outputs a first output containing the grid-side control strategy. This first output is used to subsequently perform greedy matching with the second output to generate a quadruple allocation action.
[0031] The distribution network side collects and reads the node voltage data and branch power data of the power grid at the current moment to obtain complete power grid voltage and power flow status information. After encapsulating the voltage and power flow status data into standardized interactive messages, it sends them back to the battery swapping station side through the information interaction channel. The battery swapping station side parses the received messages, extracts the corresponding power grid voltage and power flow status information, and then executes the second channel decision. The second channel decision takes maximizing the battery swapping operation revenue as the optimization objective, uses the charging and discharging power of each battery swapping cabinet as the decision variable to construct a revenue optimization solution model, and solves the model in combination with the received power grid constraints. The output includes the power regulation strategy of the battery swapping station side. This second output, together with the obtained first output, is used as the input condition for greedy matching to map and generate a four-tuple allocation action.
[0032] The system reads the operational status data of all battery swapping cabinets in real time, and statistically obtains the current full-charge surplus and demand gap of each cabinet. The full-charge surplus refers to the number of fully charged batteries that can be transferred out of the cabinet, and the demand gap refers to the number of fully charged batteries that the cabinet needs to replenish to meet user battery swapping needs. The obtained first and second outputs are used as global constraints. The first output limits the scheduling boundaries at the grid voltage and photovoltaic absorption levels, while the second output limits the power regulation boundary for optimal operating revenue of the battery swapping station. Under these dual constraints, a greedy matching process is initiated. The objective function of the greedy matching is to maximize the comprehensive revenue of a single allocation combination. This comprehensive revenue simultaneously incorporates grid-side photovoltaic absorption gains, battery swapping service fulfillment revenue, and battery cross-cabinet allocation operation and maintenance losses. The objective function expression is: ;in This represents the photovoltaic absorption gain corresponding to the allocation combination. To fulfill the contractual obligations and generate revenue for the battery swapping business. To reduce maintenance and loss costs associated with cross-cabinet battery transfers. These are the grid absorption weight and the operational revenue weight, respectively, with the weight values jointly determined by the constraint boundaries of the first and second outputs. Ranking criteria: A candidate allocation pair set is constructed, generated by pairing source cabinets with full-capacity surplus power with target cabinets with demand gaps. For each candidate allocation pair, the comprehensive revenue value of the pair is calculated using the aforementioned objective function, and all candidate allocation pairs are arranged in descending order of comprehensive revenue contribution. Constraint handling: The grid voltage constraint and photovoltaic curtailment constraint corresponding to the first output, and the cabinet charging / discharging power constraint corresponding to the second output are used as hard constraints. During the candidate allocation pair screening and traversal process, if the execution of a candidate allocation pair would cause grid voltage to exceed limits, photovoltaic curtailment indicators to deteriorate, or exceed the cabinet charging / discharging power limit, then that candidate allocation pair is directly eliminated and does not participate in the ranking and pairing calculations. The algorithm iterates through the sorted candidate transfer pairs. For each confirmed source-target cabinet pair, it deducts the full-charge surplus of the corresponding source cabinet and the demand gap of the corresponding target cabinet, updates the real-time status of the surplus and gap of each battery swapping cabinet, and then continues to the next round of pairing and filtering. The greedy matching process terminates when any of the following conditions are met: 1. The candidate transfer pair set has been traversed; 2. There are no source cabinets with a full-charge surplus greater than 0; 3. There are no target cabinets with a demand gap greater than 0. After completing the greedy matching, each successfully matched transfer pair is encapsulated as a four-tuple transfer action containing four elements: source cabinet, target cabinet, type of battery being transferred out, and type of battery being transferred in. This action is then output to the subsequent constraint check threshold for chain-like verification.
[0033] In one possible implementation, step S100 further includes:
[0034] Step S140: In the first channel decision on the distribution network side, the optimization objectives are to minimize voltage deviation and minimize photovoltaic curtailment, and the decision variables are the switching action of the capacitor bank and the reactive power regulation action of the photovoltaic inverter.
[0035] Step S150: In the second channel decision-making on the battery swapping station side, the optimization objective is to maximize the battery swapping operation revenue, and the charging and discharging power of each cabinet is the decision variable.
[0036] Specifically, during the first-channel decision-making process executed on the distribution network side, the charging and discharging power time-series data of the battery swapping stations transmitted through information exchange is read. This data is then combined with real-time node voltage, power flow, and photovoltaic (PV) output operation data of the distribution network to construct an optimization solution model. Minimizing voltage deviation and minimizing PV curtailment are set as the model's dual optimization objectives. The voltage deviation minimization objective is used to suppress voltage overshooting at each node of the distribution network and reduce the deviation between the actual voltage and the rated voltage at each node. The PV curtailment minimization objective is used to maximize the absorption of local PV output and reduce the waste of PV power. The model incorporates capacitor bank switching actions and PV... The reactive power regulation actions of the inverter are set as decision variables. Among them, the decision variables for capacitor bank switching actions represent the state of each compensation capacitor bank being put on or off, and the decision variables for photovoltaic inverter reactive power regulation actions represent the adjustment level and adjustment amplitude of the reactive power output of each photovoltaic inverter. At the same time, grid power flow constraints, capacitor switching frequency constraints, and upper and lower limits of photovoltaic inverter reactive power output constraints are introduced as model boundary conditions. The optimization model is solved to obtain the optimal values of each decision variable, and then the first output containing the grid-side control strategy is generated, providing grid-level scheduling constraints for subsequent greedy matching and allocation of batteries.
[0037] During the second-channel decision-making process executed at the battery swapping station, the voltage and power flow status data of the distribution network side transmitted back via information exchange are analyzed. Simultaneously, the battery inventory status of each swapping cabinet, battery swapping order forecasts, and charging / discharging electricity price parameters are read to construct a revenue optimization solution model for the battery swapping station side. Maximizing battery swapping operation revenue is set as the model's optimization objective. The model comprehensively calculates battery external discharge revenue, charging electricity purchase costs, battery allocation and maintenance loss costs, and user battery swapping service fulfillment revenue, using the maximization of total revenue as the solution guide. The charging and discharging power of each cabinet is set as a decision variable, representing the charging and discharging power values of each swapping cabinet. The model also introduces upper and lower limits for the charging and discharging power of a single cabinet, battery storage capacity constraints, and power flow and voltage boundary constraints issued by the distribution network side as solution boundaries. The optimization model is then solved to obtain the optimal charging and discharging power of each cabinet, generating a second output containing the power control strategy of the battery swapping station. This provides scheduling constraints at the operation level for the subsequent greedy matching to generate the battery allocation quadruple action.
[0038] In one possible implementation, step S200 further includes:
[0039] Step S210: Input the quadruple transfer action into the constraint check threshold, perform chain verification according to the physical dependency relationship, and obtain the verification result.
[0040] Step S220: If any level of the verification result fails, a verification failure action mask signal is generated, and the charging / discharging power command corresponding to the quadruple transfer action is not transmitted to the register.
[0041] Step S230: If the verification result is successful, the quadruple transfer action and the corresponding charge / discharge power command are transferred to the register.
[0042] Specifically, the output quadruple transfer action is used to input constraint check thresholds. Based on the physical dependencies of the battery cross-cabinet transfer business, a chain of checks is performed sequentially according to the order of healthy empty warehouse count verification, battery type compatibility verification, and warehouse space conservation verification to obtain the verification results. First, the first-level verification is performed, which retrieves the real-time inventory snapshot data of the battery swapping cabinet, verifies the remaining amount of fully charged batteries that can be transferred from the source cabinet and the number of available healthy empty warehouses in the target cabinet, and determines whether the number of batteries transferred out exceeds the full-charge surplus of the source cabinet and whether the number of batteries transferred in exceeds the number of healthy empty warehouses in the target cabinet. After the first-level verification is completed, the second-level verification is performed, which retrieves the locally pre-stored cabinet-battery type compatibility table and verifies whether the transferred battery type is compatible. The system checks whether the source cabinet supports the set of compatible types and whether the type of battery being transferred belongs to the set of compatible types supported by the target cabinet. After the second-level verification passes, the third-level verification is performed. The total number of batteries in the target cabinet and the remaining number of batteries in the source cabinet are calculated after the transfer. The system verifies that the total number of batteries in the target cabinet must not exceed its healthy storage limit and that the total number of batteries in the source cabinet must not be lower than the minimum reserved empty storage number preset by the system. The chain-like verification is progressive. If the previous level verification fails, the subsequent level verification will not be performed. If any level verification condition is not met, the overall verification is judged to have failed. If all level verification conditions are met, the verification is judged to have passed. The corresponding verification result is output for subsequent generation of action mask signals or downward flow of scheduling instructions.
[0043] The system receives the chained verification results and analyzes and identifies the judgment status of each level of the three-level verification. When any level of verification result—healthy empty warehouse count, type compatibility, or warehouse conservation—fails, the system immediately generates a verification failure action mask signal. This action mask signal marks the corresponding quadruple allocation action as an invalid scheduling action, blocking the transmission path of this allocation action to the downstream register. At the same time, in the scheduling action probability space, the output probability corresponding to the verification failure quadruple allocation action is assigned a value of negative infinity. By forcibly modifying the probability value, this allocation action will not be selected for execution in subsequent scheduling strategy screening, thereby eliminating battery cross-cabinet allocation schemes that do not meet physical constraints from the algorithm level. If multiple levels of verification fail, only one action mask signal corresponding to this quadruple allocation action is generated. There is no need to generate it repeatedly. Only the output probability of this allocation action is set to negative infinity once, without affecting the normal flow of other quadruple allocation actions that pass verification.
[0044] The system receives the chain-like verification results. When all three levels of verification—healthy empty warehouse count, type compatibility, and warehouse conservation—pass, it extracts the qualified quadruple allocation action. Simultaneously, it retrieves the charging / discharging power command that matches the quadruple allocation action and is obtained through dual-channel decision-making. The quadruple allocation action and the charging / discharging power command are encapsulated to form a complete scheduling execution data packet. The encapsulated scheduling execution data packet is transmitted to a register. The register uses an overwrite storage mechanism. The scheduling data packet from the new scheduling cycle directly overwrites the old scheduling data left over from the previous scheduling cycle in the register. After the register completes the data writing, it retains complete information on the source cabinet, target cabinet, battery type, and battery type, as well as the charging / discharging power parameters of each cabinet. This provides a callable and effective data source for subsequent scheduling cycles to read scheduling data, drive battery pick-and-place actuators, and perform PWM modulation current allocation.
[0045] In one possible implementation, step S210 further includes:
[0046] Step S211: The first-level threshold in the constraint check threshold uses the number of healthy empty warehouses of each source cabinet and target cabinet in the current inventory snapshot as the verification target. Specifically, when the quantity transferred out exceeds the current fully charged surplus of the source cabinet or the quantity transferred in exceeds the current healthy empty warehouse number of the target cabinet, the verification is determined to fail.
[0047] Step S212: The secondary threshold uses type compatibility as the verification target. Based on the pre-stored cabinet-battery type compatibility relationship table, the set of compatible types for the source cabinet is retrieved, and the set of compatible types for the target cabinet is retrieved. If any of these sets are not satisfied, the verification is deemed to have failed.
[0048] Step S213: The three-level threshold is verified by the conservation of battery capacity. The first conservation condition is that the total number of batteries in the target cabinet after the transfer does not exceed the number of healthy battery capacity. The second conservation condition is that the total number of batteries in the source cabinet after the transfer does not fall below the preset minimum number of reserved empty battery capacity. If either condition is not met, the verification fails.
[0049] Specifically, in the first-level threshold verification stage of the constraint check, the system reads the current inventory snapshot of each battery swapping cabinet captured at the scheduling time. The inventory snapshot records the full-charge surplus of each source cabinet and the number of healthy empty slots of each target cabinet in real time. The number of healthy empty slots of the source cabinet and the target cabinet are used as the verification targets of this level. The system analyzes the number of batteries transferred out and transferred in the four-tuple transfer action to be verified. The number of batteries transferred out is compared with the current full-charge surplus of the source cabinet, and the number of batteries transferred in is compared with the current number of healthy empty slots of the target cabinet. If either the number of batteries transferred out set by the transfer action is greater than the full-charge surplus that the source cabinet can provide, or the number of batteries transferred in set by the transfer action is greater than the number of healthy empty slots that the target cabinet can use, then the first-level threshold verification is determined to be unsuccessful, and the second-level threshold verification process is not entered. The first-level verification failure flag is output and used to generate the action mask signal in the future, so as to avoid executing battery transfers that exceed the actual inventory capacity of the battery swapping cabinet.
[0050] The system then enters the secondary threshold verification stage of the constraint check. This stage uses the type compatibility between the battery and the cabinet as the verification target. The system retrieves the locally pre-stored cabinet-battery type compatibility relationship table. This compatibility relationship table records all battery types that each battery swapping cabinet can support, forming a set of compatible types for each cabinet. The system analyzes the battery type being transferred out and the battery type being transferred in the transfer action of the four-tuple to be verified, and checks whether the battery type being transferred out belongs to the compatible type set of the source cabinet and whether the battery type being transferred in belongs to the compatible type set of the target cabinet. If either of these two conditions is not met, the secondary threshold verification is deemed to have failed, and the execution of the tertiary threshold verification is stopped. A secondary verification failure flag is output for use in the subsequent generation of action mask signals. This avoids performing cross-cabinet transfers of incompatible battery models, preventing problems such as inability to enter the cabinet or abnormal charging and discharging due to battery and cabinet hardware incompatibility.
[0051] The system then enters the third-level threshold verification stage of constraint checks. This stage uses the conservation of battery space as the verification target. Based on the original battery inventory of the source and target cabinets in the inventory snapshot, calculations are performed separately for the number of batteries transferred out and transferred in during the four-tuple transfer action. The first and second conservation conditions are extracted for verification. The first conservation condition calculates the total number of batteries in the target cabinet after the transfer is completed and determines whether this total number of batteries does not exceed the target cabinet's healthy storage capacity limit to avoid the target cabinet being overloaded and unable to accommodate batteries. The second conservation condition calculates the total number of batteries remaining in the source cabinet after the battery transfer is completed and determines whether this total number of batteries is not lower than the minimum reserved empty storage capacity pre-configured by the system to ensure that the source cabinet retains a basic storage capacity to meet immediate battery swapping needs. During the verification process, if either the first or second conservation condition is not met, the third-level threshold verification is directly determined to be unsuccessful, the subsequent verification process is terminated, and a third-level verification failure flag is output for subsequent generation of action mask signals. This ensures that the storage resources of each battery swapping cabinet are in a reasonable and controllable state before and after the transfer.
[0052] In one possible implementation, step S300 further includes:
[0053] Step S310: Use the verified quadruple allocation action and the corresponding charging / discharging power command as the charging scheduling input, and calculate the warehouse demand weight within the scheduling period.
[0054] Step S320: Based on the required weight of the storage space, modulate the duty cycle of the PWM half-bridge of the multi-output circuit of the battery swapping cabinet, and perform on-demand balanced and controllable current distribution by allocating the phase share of each output circuit in the conduction sequence.
[0055] Specifically, the four-tuple allocation action after chain verification and the matching charging and discharging power command are used as input data for charging scheduling. First, the total power of the charging and discharging power command is extracted as the upper limit of the allocable power of the entire battery swapping cabinet. The predicted demand gap of each battery compartment within the scheduling period is read, and the sum of the predicted demand gap of all battery compartments in the entire cabinet is statistically summarized. The ratio of the predicted demand gap of a single battery compartment to the sum of the predicted demand gap of the entire cabinet is calculated to obtain the initial demand weight of each battery compartment. Then, the current SOC value of each battery compartment is collected, and the deviation between the current SOC and the preset target full charge threshold is calculated. This deviation is used as a correction factor to weight and correct the initial demand weight, generating the compartment correction weight. Finally, based on the upper limit of the allocable power of the entire cabinet, the compartment correction weight of all battery compartments is normalized and scaled to obtain the compartment demand weight and the matching allocated power value of each battery compartment under the scheduling period. This compartment demand weight is used to modulate the PWM half-bridge duty cycle of the multi-output circuit of the battery swapping cabinet.
[0056] The calculated demand weights for each battery compartment are obtained. Control modulation is then applied to the multi-output circuit of the battery swapping cabinet, which consists of multiple transformer primary windings connected in series and then connected to the output of a PWM half-bridge inverter. The input of the PWM half-bridge inverter is connected to the DC bus output from the AC / DC power module of the battery swapping cabinet. Each transformer forms an independent output circuit and is connected to the positive and negative charging ports of each battery compartment. Based on the demand weight of each battery compartment, the duty cycle of the PWM half-bridge is differentially modulated. The phase share of each independent output circuit within the conduction sequence is divided according to the weight. Battery compartments with higher weights are allocated a larger proportion of the conduction phase, while those with lower weights are allocated a smaller proportion. Through precise allocation of the conduction phase share of each output circuit, the current among multiple battery compartments is distributed on demand, in a balanced and controllable manner, providing matching charging current to battery compartments with different needs.
[0057] In one possible implementation, step S310 further includes:
[0058] Step S311: Using the total amount of the charging and discharging power command as the upper limit of the allocable power of the entire cabinet, calculate the ratio of the predicted demand gap of each battery compartment during the scheduling cycle to the sum of the predicted demand gaps of all compartments in the entire cabinet, and determine the initial demand weight of each battery compartment.
[0059] Step S312: Using the deviation between the current SOC and the target full charge threshold of each battery compartment as a correction factor, the initial demand weight is weighted and corrected to obtain the compartment correction weight.
[0060] Step S313: Normalize and scale the compartment adjustment weights according to the upper limit of allocable power to obtain the compartment demand weights and corresponding allocated power values for each battery compartment.
[0061] Specifically, the total power of the charging and discharging power command is extracted and set as the upper limit of the allocable power of the entire battery swapping cabinet. This upper limit constrains the total output of charging power for all battery compartments within the current scheduling cycle. The predicted demand gap for each battery compartment within the scheduling cycle is read. The predicted demand gap is predicted based on the current remaining power of the battery compartment, the target full charge threshold, and historical battery swapping business data. The predicted demand gaps of all battery compartments are statistically summed to obtain the total predicted demand gap of all compartments in the entire cabinet. The predicted demand gap of a single battery compartment is divided by the total predicted demand gap of all compartments in the entire cabinet to calculate the initial demand weight for each battery compartment. The initial demand weight reflects the relative proportion of charging demand for each battery compartment and serves as the basis for subsequent weight adjustments.
[0062] Real-time SOC status data of each battery compartment is collected during the scheduling process. The system's preset target full-charge threshold for each battery compartment is retrieved, and the difference between the current SOC and the target full-charge threshold for each battery compartment is calculated. This difference is used as a correction factor for weight calculation. The larger the difference, the further the battery compartment is from full charge, and the higher the corresponding correction factor value. The correction factor corresponding to each battery compartment is multiplied by the obtained initial demand weight of that battery compartment to compensate and correct the original initial demand weight, resulting in the compartment correction weight corresponding to each battery compartment. The compartment correction weight takes into account both the predicted demand gap at the battery compartment business level and the remaining power status of the battery itself, providing corrected intermediate weight parameters for the subsequent normalized calculation of the final compartment demand weight.
[0063] The calculated compartment correction weights for each battery compartment are obtained. Using the upper limit of all available power in the entire cabinet, determined by the total charge and discharge power command, as the normalization scaling benchmark, the compartment correction weights of all battery compartments are first summed. The compartment correction weight of a single battery compartment is then divided by the sum of all compartment correction weights to complete the weight normalization process and obtain the normalized weight coefficient. Next, the normalized weight coefficient corresponding to each battery compartment is multiplied by the upper limit of all available power in the entire cabinet. After scaling and conversion, the final compartment demand weight and the corresponding allocated power value for each battery compartment within the scheduling cycle are obtained. This compartment demand weight and allocated power value take into account both the predicted battery compartment gap and the battery SOC state, serving as the direct calculation basis for subsequent PWM half-bridge duty cycle modulation and phase share allocation of each output circuit.
[0064] In one possible implementation, step S320 further includes:
[0065] Step S321: The multi-output circuit of the battery swapping cabinet is composed of the primary windings of multiple transformers connected in series and then connected to the output terminal of the PWM half-bridge inverter.
[0066] The input of the PWM half-bridge inverter is connected to the DC bus output by the AC / DC power module of the battery swapping cabinet. Each transformer forms an independent output circuit, which is connected to the positive and negative charging ports of each battery compartment.
[0067] Specifically, the multi-output circuit of the battery swapping cabinet adopts a multi-transformer primary-side series topology for hardware construction. The primary windings of multiple independent transformers are connected in series end to end to form a series winding. The two ends of the series winding are connected to the output terminals of the PWM half-bridge inverter. The input side of the PWM half-bridge inverter is connected to the DC bus output by the AC / DC power module of the battery swapping cabinet to obtain DC power supply. The secondary winding of each transformer forms an independent output circuit. Each independent output circuit is connected one-to-one to the charging positive and negative terminals of each battery compartment. This enables a single PWM half-bridge inverter to provide charging power to multiple battery compartments simultaneously. This provides the hardware circuit foundation for subsequent weighted modulation of the PWM half-bridge duty cycle based on compartment demand and allocation of the conduction timing phase share of each output circuit to complete the on-demand current distribution.
[0068] The input of the PWM half-bridge inverter is connected to the DC bus of the AC / DC power module of the battery swapping cabinet. The AC / DC power module converts the AC mains power into stable DC power and delivers it to the DC bus, providing DC input power for the PWM half-bridge inverter. Each transformer secondary winding constructs an independent output circuit. Each output circuit has separate charging positive and negative terminals connected to the charging positive and negative terminals of each battery compartment. The system adjusts the duty cycle of the PWM half-bridge and superimposes the compartment demand weight modulation logic on the series current sharing baseline brought by the series connection of the primary sides of multiple transformers. For battery compartments with higher compartment demand weight, a larger phase share is allocated during the PWM conduction sequence. Relying on this dynamic weight mechanism, the output current of each circuit is adjusted so that the output current of each circuit automatically follows the demand weight ratio of each battery compartment. After rectification and filtering, the power of each circuit outputs the appropriate charging power to supply the batteries in the corresponding compartment to complete the charging operation.
[0069] In one possible implementation, step S300 further includes:
[0070] After the current is allocated on demand, it is checked whether the actual charging current of each battery compartment reaches the maximum allowable current limit under the current SOC.
[0071] If the upper limit is reached, the corresponding battery compartment will be marked as fully charged and the demand weight will be automatically downgraded, redistributing the released power to the unsaturated battery compartments.
[0072] Specifically, after completing the on-demand current allocation control for each battery compartment, the current acquisition module collects the actual charging current of each battery compartment circuit in real time. At the same time, it reads the real-time SOC value of each battery compartment, retrieves the built-in battery charging characteristic parameter table, and queries the maximum allowable current limit of the battery corresponding to the SOC point. The collected actual charging current is compared with the corresponding upper limit value for each compartment to determine whether the actual charging current has reached the limit. If the actual charging current of a certain battery compartment reaches the maximum allowable current limit under the current SOC, the charging current of that battery compartment is locked and will not continue to increase. The excess power share of that compartment is released and re-participates in the power allocation of other battery compartments that have not reached the current limit, thereby protecting the battery from overcurrent charging and making full use of the available charging power of the whole machine.
[0073] When the actual charging current of the battery compartment reaches the maximum allowable current limit corresponding to the current SOC, the system marks the battery compartment as saturated charging state and performs automatic downgrading processing on the demand weight corresponding to the battery compartment, reducing its occupied power quota and releasing the corresponding power share. The system then re-incorporates the released power share into the allocable power pool of the whole machine, and then performs secondary allocation according to the demand weight ratio of the remaining unsaturated battery compartments. This dynamic power flow process is continuously iterated until all high-demand compartments reach their respective current limits, or the SOC values of each battery compartment tend to be balanced. Under the premise of meeting the battery safety charging constraints, the charging power of the entire battery swapping cabinet is maximized.
[0074] The following example uses a battery swapping station located on a city road as an implementation scenario. This station is equipped with four swapping cabinets and a total of 24 battery compartments, connected to the power distribution network and supported by distributed photovoltaic power. A continuous 72-hour comparative test was conducted using both the traditional local independent scheduling method and the intelligent joint scheduling method for the swapping cabinet batteries of this invention. The test data collected is shown in Table 1. The comparison of various performance indicators under different scheduling strategies is attached. Figure 2 As shown.
[0075] Table 1 Performance comparison between this method and conventional scheduling strategies. Testing strategy Battery transfer success rate Dynamic adaptability of charging current Local photovoltaic power consumption rate Regular local independent scheduling 81.2% Fixed power distribution 74.5% This application features dual-channel intelligent joint scheduling. 98.7% Dynamic weight allocation 92.3%
[0076] From Table 1 and Appendix Figure 2 It is evident that after adopting the dual-channel intelligent joint scheduling scheme of this invention, the success rate of battery cross-cabinet allocation is significantly improved after multi-layer chain constraint verification; the PWM half-bridge phase share is dynamically adjusted based on the warehouse demand weight to achieve adaptive allocation of charging current, while the station-network collaborative scheduling effectively improves the local consumption level of distributed photovoltaic power within the station.
[0077] Example 2, based on the same inventive concept as the intelligent joint scheduling method for battery swapping cabinets in the aforementioned examples, such as... Figure 3As shown, this application provides an intelligent joint scheduling system for batteries in a battery swapping cabinet. The system and method embodiments in this application are based on the same inventive concept. The system includes:
[0078] The quadruple allocation action acquisition module 10 is used to perform information exchange and dual-channel decision-making between the station side and the distribution network side. It combines the decision results with the current full-charge surplus and demand gap of each battery swapping cabinet to map the quadruple allocation action representing the source cabinet-target cabinet-out battery type-in battery type.
[0079] The chain verification module 20 is used to check the input constraint threshold of the quadruple allocation action. The chain verification is performed with the number of healthy empty warehouses, type compatibility and warehouse conservation as verification targets. If the verification is successful, the quadruple allocation action and charging / discharging power command are transmitted to the register. The register adopts an overwrite storage method.
[0080] The current on-demand allocation module 30 is used to retrieve the quadruple allocation action and charging / discharging power command from the register according to the scheduling cycle, drive the battery pick-and-place execution mechanism according to the quadruple allocation action, calculate the bay demand weight through the charging / discharging power command, modulate the PWM half-bridge duty cycle of the multi-output circuit of the battery swapping cabinet, and perform current on-demand allocation by allocating the phase share of each output circuit in the conduction sequence.
[0081] Furthermore, the system is also used to implement the following functions:
[0082] The battery swapping station reads the current charging and discharging power timing data and transmits it to the distribution network side through information interaction. It then executes the first channel decision to obtain the first output. The distribution network side reads the current voltage and power flow status and transmits it to the battery swapping station side through information interaction. It then executes the second channel decision to obtain the second output. The station reads the current full-charge surplus and demand gap of each battery swapping cabinet and performs greedy matching based on the first and second outputs to map and obtain the quadruple allocation action.
[0083] Furthermore, the system is also used to implement the following functions:
[0084] In the first channel decision-making process on the distribution network side, the optimization objectives are to minimize voltage deviation and minimize photovoltaic curtailment, with the switching actions of capacitor banks and the reactive power regulation actions of photovoltaic inverters as decision variables. In the second channel decision-making process on the battery swapping station side, the optimization objective is to maximize the operating revenue of battery swapping, with the charging and discharging power of each cabinet as the decision variable.
[0085] Furthermore, the system is also used to implement the following functions:
[0086] The input constraint check threshold of the quadruple allocation action is used to perform chain verification according to the physical dependency relationship to obtain the verification result. If any level of the verification result fails, a verification failure action mask signal is generated, and the charging and discharging power command corresponding to the quadruple allocation action is not transmitted to the register. If the verification result is successful, the quadruple allocation action and the corresponding charging and discharging power command are transmitted to the register.
[0087] Furthermore, the system is also used to implement the following functions:
[0088] The constraint check thresholds are as follows: Level 1 threshold uses the number of healthy empty slots in each source cabinet and target cabinet in the current inventory snapshot as the verification target. If the quantity transferred out exceeds the current fully charged surplus of the source cabinet or the quantity transferred in exceeds the current healthy empty slots in the target cabinet, the verification fails. Level 2 threshold uses type compatibility as the verification target. Based on the pre-stored cabinet-battery type compatibility relationship table, if either the transferred-out battery type belongs to the compatible type set of the source cabinet or the transferred-in battery type belongs to the compatible type set of the target cabinet, the verification fails. Level 3 threshold uses slot conservation as the verification target. The first conservation condition is that the total number of batteries in the target cabinet after the transfer does not exceed the healthy slots. The second conservation condition is that the total number of batteries in the source cabinet after the transfer is not lower than the preset minimum reserved empty slots. If either condition is not met, the verification fails.
[0089] Furthermore, the system is also used to implement the following functions:
[0090] The verified quadruple allocation action and the corresponding charging and discharging power command are used as the charging scheduling input to calculate the warehouse demand weight within the scheduling cycle. Based on the warehouse demand weight, the PWM half-bridge duty cycle of the multi-output circuit of the battery swapping cabinet is modulated, and the current is balanced and controllable on demand is performed by allocating the phase share of each output circuit in the conduction sequence.
[0091] Furthermore, the system is also used to implement the following functions:
[0092] The total amount of the charging and discharging power commands is used as the upper limit of the allocable power for the entire cabinet. The ratio of the predicted demand gap of each battery compartment during the scheduling cycle to the sum of the predicted demand gaps of all compartments in the entire cabinet is used to determine the initial demand weight of each battery compartment. The deviation between the current SOC of each battery compartment and the target full charge threshold is used as a correction factor to adjust the initial demand weight, resulting in a compartment adjustment weight. The compartment adjustment weight is then normalized and scaled according to the upper limit of the allocable power to obtain the compartment demand weight and the corresponding allocated power value for each battery compartment.
[0093] Furthermore, the system is also used to implement the following functions:
[0094] The multi-output circuit of the battery swapping cabinet is composed of the primary windings of multiple transformers connected in series and then connected to the output terminal of a PWM half-bridge inverter. The input terminal of the PWM half-bridge inverter is connected to the DC bus output by the AC / DC power module of the battery swapping cabinet, and each transformer forms an independent output circuit, which is connected to the positive and negative charging ports of each battery compartment.
[0095] Furthermore, the system is also used to implement the following functions:
[0096] After the current is allocated on demand, it is checked whether the actual charging current of each battery compartment reaches the maximum allowable current limit under the current SOC. If the limit is reached, the corresponding battery compartment is marked as saturated charging state and the demand weight is automatically downgraded, and the released power share is redistributed to the unsaturated battery compartments.
[0097] It should be noted that the order of the embodiments described above is for descriptive purposes only and does not represent the superiority or inferiority of the embodiments. Specific embodiments of this specification have been described above. Furthermore, the processes depicted in the accompanying drawings do not necessarily require a specific or sequential order to achieve the desired results. In some embodiments, multitasking and parallel processing are possible or may be advantageous.
[0098] The above description is only a preferred embodiment of this application and is not intended to limit this application. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this application should be included within the protection scope of this application.
[0099] This specification and accompanying drawings are merely illustrative examples of this application and are intended to cover any and all modifications, variations, combinations, or equivalents within the scope of this application. Clearly, those skilled in the art can make various alterations and modifications to this application without departing from its scope. Therefore, if such modifications and variations fall within the scope of this application and its equivalents, this application intends to include such modifications and variations.
Claims
1. A method for intelligent joint scheduling of batteries in a battery swapping cabinet, characterized in that, The method includes: The station and the distribution network side perform information exchange and dual-channel decision-making, and combine the decision results with the current full-charge surplus and demand gap of each battery swapping cabinet to map the four-element allocation action representing the source cabinet-target cabinet-out battery type-in battery type. The input constraint check threshold of the quadruple allocation action is used to perform chain verification with the number of healthy empty warehouses, type compatibility and warehouse conservation as verification targets. If the verification is passed, the quadruple allocation action and charging / discharging power command are passed to the register, where the register adopts an overwrite storage method. According to the scheduling cycle, the quadruple allocation action and charging / discharging power command are retrieved from the register. The battery pick-and-place execution mechanism is driven according to the quadruple allocation action. The weight of the storage space demand is calculated through the charging / discharging power command. The PWM half-bridge duty cycle of the multi-output circuit of the battery swapping cabinet is modulated. The current is allocated as needed by allocating the phase share of each output circuit in the conduction sequence.
2. The intelligent joint scheduling method for batteries in a battery swapping cabinet as described in claim 1, characterized in that, The four-tuple transfer action of characterizing the source cabinet - target cabinet - retrieved battery type - retrieved battery type includes: The battery swapping station reads the charging and discharging power timing data at the current moment, transmits it to the distribution network side through information exchange, and executes the first channel decision to obtain the first output; The distribution network side reads the current voltage and power flow status, transmits it to the battery swapping station side through information exchange, and executes the second channel decision to obtain the second output; Read the current full charge surplus and demand gap of each battery swapping cabinet, perform greedy matching based on the first output and the second output, and map to obtain the quadruple allocation action.
3. The intelligent joint scheduling method for batteries in a battery swapping cabinet as described in claim 2, characterized in that, In the first channel decision-making on the distribution network side, the optimization objectives are to minimize voltage deviation and minimize photovoltaic curtailment, and the decision variables are the switching actions of capacitor banks and the reactive power regulation actions of photovoltaic inverters. In the decision-making process for the second channel on the battery swapping station side, the optimization objective is to maximize the operating revenue of battery swapping, and the charging and discharging power of each cabinet is the decision variable.
4. The intelligent joint scheduling method for batteries in a battery swapping cabinet as described in claim 1, characterized in that, Perform chained checks, including: The quadruple transfer action is input to the constraint check threshold, and a chain check is performed according to the physical dependency relationship to obtain the check result. If any level of the verification result fails, a verification failure mask signal is generated, and the charging / discharging power instruction corresponding to the quadruple transfer action is not transmitted to the register. If the verification result is successful, the quadruple transfer action and the corresponding charge / discharge power command are transmitted to the register.
5. The intelligent joint scheduling method for batteries in a battery swapping cabinet as described in claim 4, characterized in that, The first-level threshold of the constraint check threshold uses the number of healthy empty warehouses of each source cabinet and target cabinet in the current inventory snapshot as the verification target. Specifically, if the quantity transferred out exceeds the current fully charged surplus of the source cabinet or the quantity transferred in exceeds the current healthy empty warehouse of the target cabinet, the verification is deemed to fail. The secondary threshold uses type compatibility as the verification target. It is based on the pre-stored cabinet-battery type compatibility relationship table. The set of compatible types for the source cabinet is retrieved, and the set of compatible types for the target cabinet is retrieved. If any of these sets are not satisfied, the verification is deemed to have failed. The three-level threshold uses the conservation of battery capacity as the verification condition. The first conservation condition is that the total number of batteries in the target cabinet after the transfer does not exceed the number of healthy batteries. The second conservation condition is that the total number of batteries in the source cabinet after the transfer does not fall below the preset minimum number of reserved empty batteries. If either condition is not met, the verification fails.
6. The intelligent joint scheduling method for batteries in a battery swapping cabinet as described in claim 1, characterized in that, The execution current is distributed on demand, including: The verified quadruple allocation action and the corresponding charging and discharging power command are used as the charging scheduling input to calculate the warehouse demand weight within the scheduling period. Based on the required weight of the battery swapping station, the duty cycle of the PWM half-bridge of the multi-output circuit of the battery swapping station is modulated, and the current is balanced and controllable on demand is achieved by allocating the phase share of each output circuit in the conduction sequence.
7. The intelligent joint scheduling method for batteries in a battery swapping cabinet as described in claim 6, characterized in that, Calculate the weight of warehouse demand within the scheduling period, including: The total amount of the charging and discharging power command is used as the upper limit of the allocable power of the entire cabinet. The ratio of the predicted demand gap of each battery compartment during the scheduling cycle to the sum of the predicted demand gaps of all compartments in the entire cabinet is calculated to determine the initial demand weight of each battery compartment. The deviation between the current SOC and the target full charge threshold of each battery compartment is used as a correction factor to adjust the initial demand weight, thus obtaining the compartment adjustment weight. The compartment adjustment weights are normalized and scaled according to the upper limit of allocable power to obtain the compartment demand weights and corresponding allocated power values for each battery compartment.
8. The intelligent joint scheduling method for batteries in a battery swapping cabinet as described in claim 7, characterized in that, The multi-output circuit of the battery swapping cabinet is composed of the primary windings of multiple transformers connected in series and then connected to the output terminal of a PWM half-bridge inverter. The input of the PWM half-bridge inverter is connected to the DC bus output by the AC / DC power module of the battery swapping cabinet. Each transformer forms an independent output circuit, which is connected to the positive and negative charging ports of each battery compartment.
9. The intelligent joint scheduling method for batteries in a battery swapping cabinet as described in claim 1, characterized in that, After the current is allocated on demand, it is checked whether the actual charging current of each battery compartment reaches the maximum allowable current limit under the current SOC. If the upper limit is reached, the corresponding battery compartment will be marked as fully charged and the demand weight will be automatically downgraded, redistributing the released power to the unsaturated battery compartments.
10. An intelligent joint scheduling system for batteries in a battery swapping cabinet, characterized in that, The system is used to implement the intelligent joint scheduling method for batteries in a battery swapping cabinet as described in any one of claims 1-9, and the system comprises: The quadruple allocation action acquisition module is used to perform information interaction and dual-channel decision-making between the station side and the distribution network side. It combines the decision results with the current full-charge surplus and demand gap of each battery swapping cabinet to map the quadruple allocation action representing the source cabinet-target cabinet-out battery type-in battery type. The chain verification module is used to check the input constraint threshold of the quadruple allocation action. The chain verification is performed with the number of healthy empty warehouses, type compatibility and warehouse conservation as verification targets. If the verification is successful, the quadruple allocation action and charging / discharging power command are passed to the register. The register adopts an overwrite storage method. The current on-demand allocation module is used to retrieve the quadruple allocation action and charging / discharging power command from the register according to the scheduling cycle, drive the battery pick-and-place execution mechanism according to the quadruple allocation action, calculate the compartment demand weight through the charging / discharging power command, modulate the PWM half-bridge duty cycle of the multi-output circuit of the battery swapping cabinet, and perform current on-demand allocation by allocating the phase share of each output circuit in the conduction sequence.