Mobile backfilling and compaction device for excavation systems

By using mobile backfilling and compaction equipment to carry out tunnel construction underground, the problems of traffic congestion and high costs caused by the open-cut method have been solved, and efficient and continuous tunnel construction operations have been achieved.

CN123125401APending Publication Date: 2026-11-17KOREA BRIDGE DEV RES INST CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202480091161.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Priority Date
2024-04-23
Filing Date
2024-04-29
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

Existing cut-and-cover methods cause traffic congestion and high costs when constructing subway stations and underground passages, and cannot be used to excavate underground without damaging the ground.

Method used

A mobile backfilling and compaction device for an excavation system is provided, including a main frame and a backfilling and compaction module, which can carry out the installation of tunnel structures, backfilling and compaction of soil and sand in the ground, and perform the excavation hole formation operation simultaneously.

Benefits of technology

It significantly shortens construction time, reduces construction costs, avoids ground damage, and enables efficient and continuous tunnel construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123125401A_ABST
    Figure CN123125401A_ABST
Patent Text Reader

Abstract

The mobile backfilling and compaction device of the excavation system of the present invention is characterized by comprising: a main frame; a backfilling and compaction module forming an inner empty space communicating with the inner area of ​​the main frame, and backfilling the excavated soil and sand on the outer side of the tunnel structure located behind it, while being able to compact the backfilled excavated soil and sand, the backfilling and compaction module comprising: a backfilling unit for transporting the excavated soil and sand to the rear of the main frame to backfill the excavated soil and sand to the corresponding outer side of the tunnel structure; and a compaction unit for compacting the soil and sand backfilled by the backfilling unit in a horizontal direction relative to the excavation bottom surface.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to a mobile backfilling and compaction device for an excavation system. Unlike open-cut methods, the device performs excavation work only in the ground without damaging the ground (road). Background Technology

[0002] Currently, both domestically and internationally, the open-cut method is used when constructing underground structures such as subway stations, tunnels, and underground passages.

[0003] This construction method involves excavating from the road surface into the ground, and then backfilling with soil and sand once the structure is completed. Specifically, road traffic is blocked starting from one lane, H-beams are vertically installed from the road surface, and temporary tarpaulins are laid on top of the H-beams and temporary tarpaulins to allow vehicles to pass. Then, the same method is used to complete the construction in the other lane area before excavation work is carried out underground.

[0004] When construction is carried out using this open-cut method, severe traffic congestion inevitably occurs for a long period of time, from the start of construction to the completion of the project.

[0005] Furthermore, in terms of construction costs, there are also drawbacks such as the installation costs of H-beams, temporary cover plates, walers, and soil anchors required for retaining works used for underground excavation; the costs of excavating large amounts of soil and sand generated during underground excavation; the costs of transporting and removing soil and sand from the external site; and the costs of transporting the soil and sand that has been removed for backfilling back to the construction site after the structure is completed. Summary of the Invention

[0006] Technical issues

[0007] This invention is proposed to solve the problems of the prior art. Its purpose is to provide a mobile backfilling and compaction device for an excavation system that can solve the problems of the open-cut method. Unlike the currently used open-cut method, when carrying out tunnel engineering operations such as setting up subway operating sections and underground passages in the ground, it only carries out excavation operations in the ground without damaging the ground surface (road).

[0008] Another objective of this invention is to provide a mobile backfilling and compaction device for an excavation system that can significantly shorten the time required for the entire construction operation and greatly reduce the required costs. While excavating holes for forming tunnels are sequentially formed in the ground, the installation of tunnel structures that substantially form tunnels, the backfilling of soil and sand around the tunnel structures, and the formation of tunnel excavation holes are carried out simultaneously and continuously.

[0009] Technical solutions to the problem

[0010] According to one aspect of the present invention, a mobile backfilling and compaction device for an excavation system is provided, comprising: a main frame on which a tunnel structure can be arranged, and the inner area of ​​the tunnel structure arranged is open to the outside along the excavation direction; and a backfilling and compaction module installed on the main frame, forming an inner empty space communicating with the inner area of ​​the main frame, and backfilling the excavated soil and sand on the outer side of the tunnel structure located behind it, while compacting the backfilled excavated soil and sand, the backfilling and compaction module comprising: a backfilling unit installed on the main frame, which transports the excavated soil and sand excavated in front of the tunnel structure according to the excavation direction to the rear of the main frame to backfill the excavated soil and sand to the corresponding outer side of the tunnel structure; and a compaction unit installed at the rear of the main frame according to the excavation direction, which compacts the soil and sand backfilled by the backfilling unit in a horizontal direction relative to the excavation bottom surface.

[0011] The backfilling unit may include: a conveyor belt for transporting excavated soil and sand excavated on the front side of the tunnel structure and placing it into a chute installed on the rear side of the main frame; a first excavated soil and sand conveying actuator installed in the chute to cause the excavated soil and sand placed into the chute and collected to move upward toward the upper side, which is the outer side of the chute; and a second excavated soil and sand conveying actuator to cause the excavated soil and sand that has moved upward through the first excavated soil and sand conveying actuator to fall onto the outer side of the tunnel structure located behind the backfilling and compaction module for backfilling.

[0012] The first excavated soil and sand conveying actuator may have a baffle that can close the front of the conveyor belt to prevent excavated soil and sand from being dumped into the chute through the conveyor belt during upward movement.

[0013] The compaction unit may include: an upper compaction unit for compacting the backfill soil and sand located on the upper side of the tunnel structure relative to the excavation bottom surface; and left and right compaction units arranged on the left and right sides with the tunnel structure as the center, for compacting the backfill soil and sand located on the left and right sides of the tunnel structure. The upper compaction unit and the left and right compaction units respectively include: a first compaction part having a flat plate and a first backfill soil and sand compaction actuator that moves the flat plate forward or backward toward the backfill soil and sand around the tunnel structure; and a second compaction part having a plurality of compaction blocks corresponding to and inserted into a plurality of through holes formed on the flat plate and a second backfill soil and sand compaction actuator that moves the plurality of compaction blocks forward or backward toward the backfill soil and sand around the tunnel structure.

[0014] The backfilling and compaction module further includes: a lifting actuator, fixedly installed at the rear of the main frame, with a lifting block connected to its rod end; and a third compaction part, connected to the lifting block, having a bottommost plate located below the plate of the left and right backfilling and compaction modules and a third backfilling and compaction actuator that moves the bottommost plate forward or backward toward the backfilled soil and sand around the tunnel structure.

[0015] The lifting actuator can cause the lowest side plate and the third backfill soil and sand compaction actuator to rise and move a certain distance from the excavation bottom surface.

[0016] The plate of the upper compaction unit can be tilted, and when viewed from the side, its lower end is closer to the main frame than its upper end. The plate of the left and right compaction units can also be tilted, and when viewed from the side, their lower ends are closer to the main frame than their upper ends.

[0017] When viewed from the side, the flat plate of the upper compaction unit and the flat plates of the left and right compaction units can be connected flatly as a whole and located on a virtual plane.

[0018] The upper compaction unit and the left and right compaction units each include a shell that forms the appearance and is fitted with the first compaction part and the second compaction part. An empty space is formed between the shells of the upper compaction unit and the left and right compaction units to arrange the tunnel structure. A brush can be provided on the side of the shell close to the tunnel structure to prevent gaps from forming between the brush and the tunnel structure.

[0019] The brush can be made of any of the following materials: metal, rubber, or plastic.

[0020] The effects of the invention

[0021] According to the above description, the mobile backfilling and compaction device of the excavation system of the present invention can simultaneously and continuously perform the tunnel structure installation work that substantially forms a tunnel and the soil and sand backfilling work that backfills soil and sand around the tunnel structure with the tunnel excavation hole formation work while forming excavation holes in the ground, thereby significantly shortening the time required for the entire construction operation and greatly reducing the required cost. Attached Figure Description

[0022] Figure 1 This is a perspective view of an excavation system having a mobile backfilling and compaction device according to an embodiment of the present invention.

[0023] Figure 2 yes Figure 1 Partially exploded 3D diagram.

[0024] Figure 3 yes Figure 1 Top view.

[0025] Figure 4 This is a diagram showing the driving state of the main frame moving adjustment unit of an excavation system having a mobile backfilling and compaction device according to an embodiment of the excavation system.

[0026] Figure 5 and Figure 6 This is a side view of an excavation system having a mobile backfilling and compaction device according to an embodiment of the present invention.

[0027] Figure 7 This is a diagram showing the inner wall support of the excavation unit of the excavation system having a mobile backfilling and compaction device according to an embodiment of the excavation system, which is closely attached to and supported by the tunnel excavation face.

[0028] Figure 8 This is a perspective view of a moving pressurization unit of an excavation system having a mobile backfilling and compaction device for an excavation system according to an embodiment of the present invention.

[0029] Figure 9 , Figure 10 This is a cross-sectional view showing the connection and operational relationship between the inner wall support of the upper excavation unit and the moving pressurization unit of the excavation unit in an excavation system having a mobile backfilling and compaction device according to an embodiment of the present invention.

[0030] Figure 11 This is a diagram showing the housing of the excavation unit and the moving roller of the excavation unit in an excavation system having a mobile backfilling and compaction device according to an embodiment of the excavation system of the present invention.

[0031] Figure 12 This is a cross-sectional view showing the connection relationship between the inner wall support of the side excavation unit and the moving pressurization unit of the excavation unit in an excavation system having a mobile backfilling and compaction device according to an embodiment of the present invention.

[0032] Figure 13 This is a diagram illustrating a digging unit in a digging system having a mobile backfilling and compaction device according to an embodiment of the present invention.

[0033] Figure 14 , Figure 15 This is a block diagram illustrating the control relationship of an excavation system having a mobile backfilling and compaction device according to an embodiment of the present invention.

[0034] Figure 16 This is a front view of the backfilling and compaction module of an excavation system having a mobile backfilling and compaction device according to an embodiment of the present invention.

[0035] Figure 17 This is a side sectional view of the backfilling and compaction module of an excavation system having a mobile backfilling and compaction device according to an embodiment of the present invention.

[0036] Figures 18 to 21 This diagram sequentially illustrates the operational states of the backfilling and compaction modules in an excavation system equipped with a mobile backfilling and compaction device according to an embodiment of the present invention.

[0037] Figures 22 to 35 The diagram shows the construction process using a mobile backfilling and compaction device with an excavation system according to an embodiment of the present invention. Detailed Implementation

[0038] Hereinafter, embodiments of the present invention will be described in more detail with reference to the accompanying drawings.

[0039] However, the present invention is not limited to the embodiments disclosed below, but will be implemented in various forms that are different from each other. The purpose of providing these embodiments is only to make the disclosure of the present invention more complete and to fully inform those skilled in the art of the scope of the present invention.

[0040] In the accompanying drawings, the same reference numerals denote the same components.

[0041] The mobile backfilling and compaction device of the excavation system according to a preferred embodiment of the present invention, when performing tunnel engineering operations such as setting up subway operating sections and underground passages in the ground, differs from the open-cut method in that it only carries out excavation operations in the ground without damaging the ground surface (road), thereby solving the problems of the open-cut method.

[0042] Furthermore, the mobile backfilling and compaction device of the excavation system according to embodiments of the present invention can also be applied to tunnel engineering operations for the construction of above-ground tunnels.

[0043] In particular, the present invention allows the installation of tunnel structures that substantially form tunnels, the backfilling and compaction of soil and sand around tunnel structures, and the formation of tunnel excavation holes to be carried out simultaneously and continuously, thereby significantly shortening the time required for the entire construction operation and greatly reducing the required costs.

[0044] To further clarify, the tunnel excavation hole formation operation and the soil and sand backfilling and compaction operation are not carried out separately. Instead, the excavated soil and sand generated during the tunnel excavation hole formation operation can be used to carry out the excavated soil and sand backfilling and compaction operations at the same time as the tunnel excavation hole formation operation.

[0045] The present invention will now be described in detail with reference to various embodiments.

[0046] like Figures 1 to 4 As shown, an excavation system with a movable backfilling and compaction device according to an embodiment of the present invention is used to form a tunnel in the ground, including a main frame 100, a track 200, and a main frame movement adjustment unit 300 (see reference). Figure 5 ).

[0047] In addition, the excavation system also includes an excavation unit 400 and a backfilling and compaction module 500.

[0048] The main frame 100 is equipped with an excavation unit 400 and a backfilling and compaction module 500. The excavation unit 400 is used to excavate the soil and sand in front of the tunnel structure based on the excavation direction. The backfilling and compaction module 500 is used to backfill the excavated soil and sand generated during the excavation process by the excavation unit and the excavator (described later) around the tunnel structure and compact it. The main frame 100 acts as a skeleton to support external forces applied to the support device, such as soil and sand loads. Its shape and size can be appropriately selected to support external forces. Specifically, the excavation units 400 are installed on the upper part and left and right sides of the main frame 100, and the backfilling and compaction module 500 is installed at the rear of the main frame 100 based on the excavation direction.

[0049] The inner side of the main frame 100 has a sufficiently large empty space to install the tunnel structure 30, and the inner area where the tunnel structure 30 is arranged is formed to be open to the outside along the excavation direction.

[0050] Among them, such as Figure 23 As shown, the excavation unit 400 is configured to form a plurality of spaced-apart boreholes 10 on the soil / sand wall in front of the excavation direction that is blocking the tunnel to be formed. The plurality of boreholes 10 are formed at intervals corresponding to the cross-sectional shape of the tunnel structure 30, such as... Figure 35 As shown, when the tunnel structure is formed into a rectangular shape with sharp edges, the multiple boreholes 10 can also be formed into a rectangular shape corresponding to the terrain. When the tunnel structure is formed into an arch shape, the multiple boreholes 10 can also be formed into an arch shape corresponding to the terrain.

[0051] After forming multiple boreholes 10 as described above, an excavator or similar device arranged in the empty space inside the main frame 100 is used to excavate the remaining part of the soil and sand wall in front, thereby excavating and expanding the area to be excavated in front. The excavation unit 400 will be described in more detail below.

[0052] In an embodiment of the present invention, a backfilling and compaction module 500 is installed behind the main frame 100, with the excavation direction as the reference. When the excavation hole 20 formed by the excavation unit 400 and the excavator reaches a certain distance, the backfilling and compaction module 500 supplies excavated soil and sand to the area around the tunnel structure 30 located behind the main frame 100 and the backfilling and compaction module 500, and then compacts it.

[0053] To further explain, the tunnel structure 30 is initially fixed to the bottom surface of the excavation hole 20 within the empty space inside the main frame 100 through concrete curing and other methods. As the tunnel formation operation progresses, the main frame 100, excavation unit 400, and backfilling and compaction module 500 move forward, with the pre-installed tunnel structure 30 positioned behind the main frame 100 and the backfilling and compaction module 500. The backfilling and compaction module 500 compacts the excavated soil and sand around the tunnel structure 30.

[0054] The tunnel structure 30 is a concrete structure formed by curing concrete into a rectangular (U-shaped) or arch shape, etc. The inner side of the tunnel structure 30 becomes the actual driving space for subways, cars, etc.

[0055] In an embodiment of the present invention, the excavated soil and sand generated by the excavation unit 400 and the excavator are transported and supplied to the backfilling and compaction module 500 mounted on the main frame 100. The backfilling and compaction module 500 backfills the excavated soil and sand around the outside of the tunnel structure 30 and compacts it to complete the operation.

[0056] like Figures 1 to 6 As shown, track 200 is installed on the tunnel excavation face 40 used to form the tunnel (see reference). Figure 7 The bottom of the tunnel excavation face 40 is parallel to the excavation direction of the excavation unit 400. Sleepers 210 are provided on the bottom surface of the tunnel excavation face 40 to support the track 200 from below in a direction intersecting the length direction of the track 200.

[0057] The main frame movement adjustment unit 300 is installed on the main frame 100 to enable the main frame 100 to move along the track 200, or to prevent it from moving as appropriate.

[0058] To further explain, when the excavation unit 400 is excavating the soil and sand wall in front, or when the excavation unit 400 is moving forward relative to the main frame 100, it is preferable to keep the main frame 100 in a fixed state so that it cannot move on the track 200.

[0059] On the other hand, when it is necessary to move the main frame 100 to the excavated space in front, it is preferable to put the main frame 100 in a state that allows it to move on the track.

[0060] Specifically, such as Figure 4 , Figure 14 As shown, the main frame movement adjustment unit 300 includes a main frame movement roller 310, a main frame movement adjustment drive unit 320, a main frame movement roller drive unit 330, and a main frame movement adjustment control unit 340.

[0061] The main frame moving roller 310 is rotatably disposed on the lower side of the main frame 100, specifically on the bottom frame 110 of the main frame 100 described later, so as to be able to contact the track 200.

[0062] The main frame movement adjustment drive unit 320 moves the main frame 100 closer to or further away from the track 200, thereby enabling the main frame movement roller 310 to selectively contact the track 200.

[0063] Specifically, the main frame movement adjustment drive unit 320 is disposed on the lower side of the main frame 100, specifically on the bottom frame 110 described later, and moves the bottom frame 110 downward to bring it closer to the track 200, thereby enabling the main frame movement roller 310 to contact the track 200. At this time, since the main frame movement roller 310 is in contact with the track 200, the main frame 100 is able to move in the back-and-forth direction along the track 200.

[0064] Conversely, the main frame movement adjustment drive unit 320 moves the bottom frame 110 upwards to move it away from the track 200, thereby making the main frame movement roller 310 non-contact with the track 200. At this time, since the main frame movement roller is in a non-contact state with the track, the main frame 100 is unable to move along the track.

[0065] In an embodiment of the present invention, the main frame movement adjustment drive unit 320 may be a hydraulic jack or the like mounted on the bottom frame 110, and multiple such units are spaced apart from each other along the length direction of the main frame corresponding to the digging advance direction of the digging unit 400. The main frame movement adjustment drive unit 320 includes a hydraulic jack body and a reciprocating moving rod configured to extend and retract outward from the hydraulic jack body, and the reciprocating moving rod is configured to be closer to the track 200 than the hydraulic jack body.

[0066] The main frame moving roller drive unit 330 is used to rotate the multiple main frame moving rollers 310 in both directions. By rotating the main frame moving rollers in both directions, the main frame 100 can move along the track 200 in the digging direction or the opposite direction. The main frame moving roller drive unit 330 can be, for example, a hydraulic motor.

[0067] In embodiments of the present invention, multiple main frame moving rollers 310 are rotatably disposed on the bottom frame 110 and rotated by a main frame moving roller drive unit 330. These multiple main frame moving rollers can be driven simultaneously by one or more main frame moving roller drive units. Furthermore, unlike the embodiment in which all main frame moving rollers 310 are driven to move the main frame 100, it is also possible to drive only a portion of the multiple main frame moving rollers 310 according to the load used to move the main frame 100.

[0068] like Figure 4 As shown, the track 200 is continuously provided with a first groove tooth 220 along its length direction, and the main frame moving roller 310 is formed with a second groove tooth 311 along its circumference direction so as to mesh with the first groove tooth 220.

[0069] Through the meshing structure between the first groove tooth 220 and the second groove tooth 311, when the main frame moving roller drive unit 330 rotates the main frame moving roller 310, the main frame 100 can move smoothly along the track 200. Of course, at this time, the main frame moving roller 310 and the track 200 are in contact with each other through the main frame moving adjustment drive unit 320, i.e., a hydraulic jack, etc.

[0070] The main frame movement adjustment control unit 340 controls the driving of the main frame movement adjustment drive unit 320 and the main frame movement roller drive unit 330. That is, the main frame movement adjustment control unit 340 can control the driving of the hydraulic jack, which serves as the main frame movement adjustment drive unit, and the hydraulic motor, which serves as the main frame movement roller drive unit.

[0071] The main frame movement adjustment control unit 340 transmits a drive signal to the main frame movement roller drive unit 330 (i.e., the hydraulic motor) only when the main frame movement adjustment drive unit 320 is driven and the main frame movement roller 310 is in contact with the track 200, so that the main frame movement roller 310 rotates in the forward or reverse direction.

[0072] That is, the main frame movement adjustment control unit controls the main frame movement roller 310 so that it does not rotate when it is in a non-contact state with the track 200.

[0073] In this embodiment, the movement of the main frame 100 via the main frame moving roller 310 and the track 200 is described as an example. However, the present invention is not limited to this, and various forms can be used as long as the main frame 100 can be moved. Furthermore, in this embodiment, a hydraulic jack or the like is used as an example to restrict the movement of the main frame 100. However, the present invention is not limited to this, and various forms of movement restriction means can be used as long as the movement of the main frame 100 can be restricted.

[0074] On the other hand, it is necessary to adjust the height of the upper part of the main frame 100 and the position of the excavation unit 400 installed on the upper side of the main frame 100 relative to the bottom of the tunnel excavation face, depending on the working environment. To further explain, it is necessary to finely adjust the height of the excavation unit 400 relative to the bottom of the tunnel excavation face according to the height of the excavation area (excavation hole) to be excavated.

[0075] Therefore, such as Figure 1 , Figure 2 , Figure 5 , Figure 6 , Figure 28 As shown, the main frame 100 includes a bottom frame 110, an upper frame 120, and a lifting unit 140.

[0076] Multiple bottom frames 110 are spaced apart along the width direction of the excavation hole 20, and are equipped with main frame moving rollers 310 and main frame moving adjustment drive units 320, forming the lowest part of the main frame 100.

[0077] The upper frame 120 is connected to the upper side of the bottom frame 110 and is configured to install the excavation unit 400.

[0078] The lifting unit 140 is disposed between the bottom frame 110 and the upper frame 120 and is configured to lift the upper frame 120 relative to the bottom frame 110.

[0079] Specifically, such as Figure 5 , Figure 6 As shown, the lifting unit 140 includes a lifting bracket 141 and a lifting jack 143.

[0080] The lifting bracket 141 is disposed on the upper part of the bottom frame 110 and is configured with a channel-shaped cross section, thereby forming a recessed support groove 142 on the inner side. In contrast, the main frame moving roller 310 and the main frame moving adjustment drive unit 320 are disposed on the lower part of the bottom frame 110 opposite to the track 200.

[0081] The lifting jack 143 is a hydraulic jack installed at the bottom of the support groove 142. Its drive can be controlled by the same control unit as the main frame moving roller control unit used to control the drive of the aforementioned main frame moving adjustment drive unit 320, or by other separate hydraulic control units.

[0082] In an embodiment of the present invention, when the upper frame 120 is raised or lowered by the lifting drive of the lifting unit 140, in order to make the upper frame 120 rise and fall stably in an upright state without swaying left or right or back and forth, it is preferable that the lower side of the upper frame 120 is partially inserted into the support groove 142.

[0083] In addition, to ensure that the upper frame 120 can be raised and lowered more stably and without wobbling, such as Figure 5 As shown, guide grooves 145 and guide protrusions 146 for guiding vertical sliding are provided on the inner side of the lifting bracket 141 and the outer side of the upper frame 120.

[0084] Multiple guide grooves 145 and guide protrusions 146 are provided and extend along the height direction of the upper frame 120 for lifting. When the guide protrusion 146 is formed on the inner side of the lifting bracket 141, the guide groove 145 is formed at the corresponding position on the outer side of the upper frame 120. Alternatively, the guide groove and guide protrusion can be formed at the opposite position.

[0085] In embodiments of the present invention, such as Figures 1 to 6 As shown, the upper frame 120 includes a plurality of left vertical frames 121, a plurality of right vertical frames 122 spaced apart from the plurality of left vertical frames 121, a plurality of horizontal frames 124 connected to the upper ends of the plurality of left vertical frames 121 and right vertical frames 122, and a digging unit support frame 125 connected to the upper part of the plurality of horizontal frames 124 and supporting a portion of the digging unit 400 from below.

[0086] The left vertical frame 121 and the right vertical frame 122 serve as supports for the main frame 100 and can have sufficient dimensions to support the load. The accompanying drawings show that the front-to-back (excavation direction) width of the vertical frames 121 and 122 is smaller than the front-to-back width of the main frame movement adjustment unit 300. However, the front-to-back width of the vertical frames 121 and 122 can be greater than the width of the main frame movement adjustment unit 300. In this case, the movement adjustment unit 300 is located inside the width of the main frame movement adjustment unit 300 in the front-to-back direction.

[0087] The excavation unit support frame 125 extends along the direction intersecting with multiple horizontal frames 124, that is, in a direction that is approximately perpendicular to the excavation propulsion direction of the excavation unit 400, and multiple such frames are spaced apart from each other along one direction of the horizontal frames corresponding to the excavation propulsion direction.

[0088] Among them, a space with a certain volume is provided in the inner area of ​​multiple left vertical frames 121, right vertical frames 122, and horizontal frames 124, so that excavating equipment such as the excavator mentioned above can be arranged.

[0089] Furthermore, as described above, during tunnel excavation, the installation of the tunnel structure 30 can be carried out in the inner areas of the left vertical frame 121, the right vertical frame 122, and the horizontal frame 124. To further clarify, the installation of this tunnel structure can be performed regardless of whether excavation work is being carried out by the excavation unit 400.

[0090] In an embodiment of the present invention, the excavation unit 400 is respectively installed on a plurality of left-side vertical frames 121, a plurality of right-side vertical frames 122 and an excavation unit support frame 125.

[0091] In addition, multiple excavation units 400 are arranged at intervals between each other, and multiple units are arranged at intervals between each other along the height direction of multiple left vertical frames 121 and right vertical frames 122.

[0092] In addition, the excavation unit 400 is provided on the upper side of the multiple excavation unit support frames 125 in a direction that intersects perpendicularly with the direction in which the multiple excavation unit support frames are spaced apart from each other, that is, in the direction in which the multiple horizontal frames are spaced apart from each other.

[0093] In an embodiment of the present invention, the excavation unit 400 is arranged in a manner that allows relative movement of the plurality of left-side vertical frames 121, the plurality of right-side vertical frames 122, and the plurality of excavation unit support frames 125.

[0094] Furthermore, the excavation unit 400 is connected to the main frame 100 in a manner that allows or restricts relative movement, and is configured to be able to move relative to the main frame as needed.

[0095] Specifically, the excavation unit 400 includes an upper excavation unit 401 and a lateral excavation unit 402.

[0096] The upper excavation unit 401 is disposed on the upper side of the multiple excavation unit support frames 125, and is configured to be able to move relative to the main frame 100, i.e. the excavation unit support frames 125, in a direction corresponding to the excavation advance direction.

[0097] The lateral excavation unit 402 is disposed on multiple left vertical frames 121 and right vertical frames 122, and is configured to be able to move relative to the main frame 100, i.e., the left vertical frames 121 and right vertical frames 122, in a direction corresponding to the excavation advance direction.

[0098] To further explain, the excavation unit 400 is configured to move relative to the main frame 100 in a forward direction corresponding to the excavation advance direction. Therefore, as... Figure 2 , Figures 8 to 11As shown, separate excavation unit moving pressurization units 700 are respectively provided on multiple left vertical frames 121, right vertical frames 122 and excavation unit support frames 125 to achieve this relative movement.

[0099] That is, in the embodiments of the present invention, when the main frame 100 moves back and forth along the track 200, the excavation unit 400 and the backfilling and compaction module 500 move back and forth together with the main frame 100, and the excavation unit 400 can move relative to the main frame 100 toward the excavation advancement direction, that is, forward.

[0100] In an embodiment of the present invention, a digging unit moving pressurizing unit 700 is respectively provided on a plurality of left vertical frames 121, a plurality of right vertical frames 122 and a plurality of digging unit support frames 125. The digging unit moving pressurizing unit 700 is used to enable the digging unit 400 to move relative to the main frame 100 and to pressurize the digging unit 400 on the inner wall of the tunnel excavation face.

[0101] That is, such as Figures 8 to 11 As shown, the excavation unit 400 includes an excavation drilling section 410, an inner wall support section 420, and a housing 440. The excavation drilling section 410 excavates the soil and sand wall in front to form a borehole 10. The inner wall support section 420 can provide overall or partial pressure support for the inner wall surface of the borehole formed by the excavation drilling section 410 and the inner wall surface of the wider tunnel excavation face formed as the tunnel excavation operation progresses. The housing 440 forms the exterior and is equipped with the excavation drilling section 410 and the inner wall support section 420. In this embodiment, the cross-section of the housing 440 is rectangular as an example. However, unlike this embodiment, the cross-section of the housing 440 can be various shapes such as an I-shaped H-beam or a U-shaped steel beam.

[0102] The excavation drilling section 410 and the inner wall support section 420 are installed on the housing 440.

[0103] The excavation unit moving pressurization unit 700 can move the excavation drill section 410 and the inner wall support section 420, which are installed in the housing 440, forward relative to the main frame 100. Furthermore, the excavation unit moving pressurization unit 700 can move the inner wall support section 420 in a direction away from the main frame 100 (towards the upper inner wall surface of the tunnel excavation face and the left and right inner wall surfaces of the tunnel excavation face), thereby pressurizing and supporting the upper and left and right inner wall surfaces of the tunnel excavation face with a certain pressure, and can also reset in the opposite direction.

[0104] The reason for moving the excavation unit 400 relative to the front of the main frame 100 is not only to excavate the front part of the soil and sand wall continuously and sequentially, but also to move a portion of the front of the excavation unit 400 to the inside of the borehole 10 before further excavation using an excavator, so as to support the inner wall of the borehole 10 and prevent it from collapsing.

[0105] Furthermore, the reason for applying pressure to the excavation unit 400 in the direction of the upper inner wall and the left and right inner walls of the tunnel excavation face is also to provide stable contact support for the tunnel excavation face formed by the excavation, so as to prevent it from collapsing.

[0106] The specific structure of the excavation unit 400, which includes the excavation borehole 410, the inner wall support 420, and the shell 440, will be described later.

[0107] The following is a detailed description of the excavation unit's moving pressurization unit 700.

[0108] In embodiments of the present invention, multiple excavator unit moving pressurization units 700 are provided at predetermined intervals along directions corresponding to the length directions of all excavator units 400. Specifically, the excavator unit moving pressurization units 700 are not only provided on all excavator unit support frames 125, but also multiple units are provided at intervals along the length direction of each excavator unit support frame 125.

[0109] In addition, the excavation unit moving pressurization unit 700 is not only provided on all the left vertical frames 121 and right vertical frames 122, but also has multiple units spaced apart from each other along the length of each left vertical frame 121 and right vertical frame 122.

[0110] That is, multiple excavation unit moving pressurization units 700 are arranged at intervals with each other in the length direction of excavation unit 400. For this purpose, multiple units are arranged at intervals with each other along the length direction of excavation unit support frame 125, left vertical frame 121 and right vertical frame 122.

[0111] Specifically, such as Figures 8 to 11 , Figure 15 As shown, the excavation unit moving pressurization unit 700 includes an excavation unit moving roller 710, an excavation unit moving adjustment drive unit 720, an excavation unit moving roller drive unit 730, and an excavation unit moving adjustment control unit 740.

[0112] The digging unit moving roller 710 is rotatably disposed on the digging unit support frame 125, the left vertical frame 121 and the right vertical frame 122 so as to be able to contact the housing 440 of the digging unit 400.

[0113] The digging unit movement adjustment drive unit 720 moves the digging unit 400 closer to or further away from the digging unit support frame 125, the left vertical frame 121, and the right vertical frame 122, thereby allowing the digging unit moving roller 710 to selectively contact the housing 440 of the digging unit 400. The housing 440 is provided with a structure that contacts the digging unit moving roller 710 and enables the housing 440 to move linearly when the digging unit moving roller 710 rotates, which will be described later.

[0114] To further explain, the excavation unit movement adjustment drive unit 720 moves the excavation unit 400 closer to or further away from the tunnel excavation face (the upper inner wall of the tunnel excavation face, the left and right inner walls of the tunnel excavation face).

[0115] Specifically, the digging unit movement adjustment drive unit 720 is disposed on the digging unit support frame 125, the left vertical frame 121, and the right vertical frame 122. Specifically, it can be arranged in pairs with the digging unit moving roller 710 as the center. However, this is only one embodiment, and the digging unit movement adjustment drive unit 720 can also be provided in two or more.

[0116] The digging unit movement adjustment drive unit 720 can move the lower part of the housing 440 of the digging unit 400 toward the digging unit moving roller 710, thereby bringing the digging unit moving roller 710 into contact with the housing 440. At this time, due to the contact state between the digging unit moving roller 710 and the housing 440, when the digging unit moving roller rotates, the digging unit 400 is in a state where it can move along the digging propulsion direction.

[0117] Conversely, the digging unit movement adjustment drive unit 720 can move the lower part of the housing 440 of the digging unit 400 away from the digging unit moving roller 710, thereby placing the digging unit moving roller 710 in a non-contact state with the housing 440. At this time, due to the non-contact state between the digging unit moving roller 710 and the housing 440, even if the digging unit moving roller 710 rotates, the digging unit 400 is unable to move along the digging propulsion direction.

[0118] In addition, when the digging unit movement adjustment drive unit 720 drives the housing 440 of the upper digging unit 401, which is located on the upper side of the digging unit support frame 125, to approach the digging unit moving roller 710, the upper digging unit 401 moves downward due to its own weight. At this time, the lower part of the housing 440 of the upper digging unit 401 comes into contact with the digging unit moving roller 710.

[0119] On the other hand, such as Figure 12As shown, elastic members 750 are respectively provided between the left vertical frame 121 and the side digging unit 402, and between the right vertical frame 122 and the side digging unit 402. These elastic members 750 always apply an elastic force in the direction that brings the side digging unit 402 closer to the left vertical frame 121 and the right vertical frame 122. Multiple tension springs can be used for these elastic members 750. Therefore, unless the digging unit movement adjustment drive unit 720 is driven in the direction that moves the side digging unit 402 away from the left and right vertical frames, the housing of the side digging unit 402 and the digging unit moving roller 710 can always remain in contact.

[0120] On the other hand, when the digging unit movement adjustment drive unit 720 drives the side digging unit 402 away from the left vertical frame 121 and the right vertical frame 122, the housing 440 of the side digging unit 402 and the digging unit moving roller 710 can be in a non-contact state. Therefore, the driving force of the digging unit movement adjustment drive unit 720 is preferably greater than the elastic restoring force of the elastic member 750 by a certain degree, and when the driving force of the digging unit movement adjustment drive unit is removed, the side digging unit 402 moves in the direction of contact with the digging unit moving roller 710 by the elastic restoring force of the elastic member 750. One end of the elastic member 750 is fixedly disposed on the left vertical frame 121 or the right vertical frame 122, while the other end of the elastic member 750 can be disposed on the housing 440 in a form that allows it to slide along the digging direction without disengaging in the direction of approaching or moving away from the vertical frames 121 and 122. For example, a structure can be adopted in which a sliding member is attached to the other end of the elastic member 750, and the sliding member is inserted into a guide groove formed in the housing 440 along the digging direction, so that the sliding member can move along the guide groove, while preventing the sliding member from detaching from the guide groove in the direction of approaching or moving away from the vertical frames 121, 122. With this structure, even if the housing 440 moves relative to the vertical frames 121, 122 along the digging direction, the elastic member 750 can apply an elastic force that can pull the housing 440 along the direction of the vertical frames 121, 122 while its one end is fixed to the vertical frames 121, 122.

[0121] On the other hand, unlike this embodiment, the elastic member 750 can be omitted, and the end of the digging unit movement adjustment drive 720 can be disposed in the housing 440 in a form that allows it to slide along the digging direction without disengaging in the direction of approaching or moving away from the vertical frames 121 and 122. For example, the following structure can be adopted: a sliding member is installed at the end of the digging unit movement adjustment drive 720, and the sliding member is inserted into a guide groove formed in the housing 440 along the digging direction, so that the sliding member can move along the guide groove, while preventing the sliding member from disengaging from the guide groove in the direction of approaching or moving away from the vertical frames 121 and 122.

[0122] In embodiments of the present invention, the digging unit movement adjustment drive unit 720 can be a hydraulic jack or the like, for example, it can be arranged on both sides with the digging unit movement roller 710 as the center. Thus, a plurality of assemblies formed by the digging unit movement adjustment drive unit 720, the digging unit movement roller 710, and the digging unit movement adjustment drive unit 720 are arranged at intervals along the length direction of the digging unit support frame 125, the left vertical frame 121, and the right vertical frame 122.

[0123] The excavating unit movement adjustment drive unit 720 includes a hydraulic jack body and a reciprocating rod configured to extend and retract outward from the hydraulic jack body, wherein the reciprocating rod is positioned relatively closer to the housing of the excavating unit 400 than the hydraulic jack body. That is, when the excavating unit movement adjustment drive unit is activated, the reciprocating rod can directly contact the housing of the excavating unit.

[0124] The digging unit moving roller drive unit 730 is used to rotate the digging unit moving roller 710 in both directions. By rotating the digging unit moving roller 710 in both directions, the digging unit 400 can move forward in the digging advance direction or in the opposite direction. The digging unit moving roller drive unit 730 can be, for example, a hydraulic motor.

[0125] In an embodiment of the present invention, multiple excavation unit moving rollers 710 are rotatably disposed on the excavation unit support frame 125, the left vertical frame 121, and the right vertical frame 122, and are rotated by the excavation unit moving roller drive unit 730. Multiple excavation unit moving rollers can be driven simultaneously by one or more excavation unit moving roller drive units.

[0126] like Figures 9 to 11 As shown, a third groove tooth 441 is continuously provided along its length direction on the lower part of the housing 440 of the digging unit 400, which is opposite to the digging unit moving roller 710, and a fourth groove tooth 711 corresponding to and engaging with the third groove tooth 441 is formed on the digging unit moving roller 710 along its circumferential direction.

[0127] Through the meshing structure between the third groove tooth 441 and the fourth groove tooth 711, when the digging unit moving roller drive unit 730 rotates the digging unit moving roller 710, the digging unit 400 can move smoothly along the digging propulsion direction. Of course, at this time, the digging unit moving roller 710 and the housing 440 of the digging unit are in contact with each other through the digging unit movement adjustment drive unit 720, i.e., the hydraulic jack drive, etc.

[0128] The excavating unit movement adjustment control unit 740 controls the driving of the excavating unit movement adjustment drive unit 720 and the excavating unit movement roller drive unit 730. That is, the excavating unit movement adjustment control unit 740 can control the driving of the hydraulic jack, which serves as the excavating unit movement adjustment drive unit, and the hydraulic motor, which serves as the excavating unit movement roller drive unit 730.

[0129] The digging unit movement adjustment control unit 740 transmits a drive signal to the digging unit movement roller drive unit 730, i.e., the hydraulic motor, only when the digging unit movement adjustment drive unit 720 is driven and the lower part of the housing 440 of the digging unit 400 is in contact with the digging unit movement roller 710, so as to make the digging unit movement roller 710 rotate in the forward or reverse direction.

[0130] That is, the digging unit movement adjustment control unit controls the digging unit movement roller 710 so that it does not rotate when it is in a non-contact state with the lower part of the housing 440 of the digging unit 400.

[0131] In this embodiment, the digging unit 400 is described as being moved along the digging direction by the moving roller 710 of the digging unit and the third groove tooth 441 of the housing 440. However, the present invention is not limited to this, and various forms such as hydraulic cylinders and tracks can be used as long as the digging unit 400 can be moved. Furthermore, in this embodiment, a hydraulic jack or the like is described as a means of restricting the movement of the digging unit 400. However, the present invention is not limited to this, and various forms of movement restriction means can be used as long as the movement of the digging unit 400 can be restricted.

[0132] Furthermore, in this embodiment, the digging unit moving roller 710 is rotated by engaging the third groove tooth 441 of the housing 440 with the fourth groove tooth 711 of the digging unit moving roller 710, causing the housing 400 to move in the rear-to-rear direction. However, unlike this embodiment, the third groove tooth 441 of the housing 400 and the fourth groove tooth 711 of the digging unit moving roller 710 can be removed respectively, so that the digging unit moving roller 710 without the fourth groove tooth 711 directly contacts the bottom surface of the housing 400 without the third groove tooth 441. Then, the housing 400 is driven in the rear-to-rear direction by a drive cylinder or the like, thereby causing the housing 400 to move in the digging direction. In this case, the drive cylinder can be located behind the housing 400.

[0133] like Figure 1 , Figure 2 , Figure 9 , Figure 10 As shown, in an embodiment of the present invention, guide plates 760 are respectively provided on the excavation unit support frame 125, the left vertical frame 121 and the right vertical frame 122. The guide plates 760 are used to guide the excavation unit 400, which moves back and forth along the excavation advancement direction, from the side.

[0134] The guide plates 760 guide the two sides of the housing 440 of the digging unit 400, thereby minimizing the swaying of the digging unit in the left-right and up-down directions when the digging unit moves forward (including backward). A sliding bearing 761 is provided on the inner side of the guide plate 760 opposite to the housing of the digging unit. The sliding bearing 761 contacts the housing 440 of the digging unit 400 to reduce the frictional resistance between them when moving forward.

[0135] The excavation unit 400 will be described in detail below. Since the upper excavation unit 401 located on the upper side of the excavation unit support frame 125 and the side excavation unit 402 located on the left vertical frame 121 and the right vertical frame 122 have essentially the same structure, the upper excavation unit will be used as the focus of the explanation for ease of explanation.

[0136] like Figure 1 , Figure 2 , Figure 9 , Figure 10 , Figure 13 As shown, the excavation unit 400 includes an excavation drilling section 410, an inner wall support section 420, and a housing 440. The excavation drilling section 410 excavates the soil and sand wall in front to form a borehole 10. The inner wall support section 420 can provide overall or partial pressure support for the inner wall surface of the borehole formed by the excavation drilling section 410 and the inner wall surface of the wider tunnel excavation face formed as the tunnel excavation operation progresses. The housing 440 forms the exterior and is equipped with the excavation drilling section 410 and the inner wall support section.

[0137] The excavation drill section 410 and the inner wall support section 420 are installed on the housing 400.

[0138] The excavating drill bit 410 is located in front of the housing 440. It can not only rotate via a separate drive source, but also move relative to the housing 440 along the excavation direction via a separate drive source, thereby excavating the soil and sand wall to be excavated to form a borehole 10. The rotation drive of the excavating drill bit 410 can employ various rotary drive means such as a hydraulic motor, and the linear drive of the excavating drill bit 410 along the excavation direction can also employ various known linear drive means such as ball screws or hydraulic cylinders.

[0139] The excavation drilling section 410 can be equipped not only with an auger for excavating soil and sand by rotation, but also with various tools such as a breaker for breaking rocks or a rock drill for drilling into rocks. Furthermore, in order to use appropriate tools (augmenter, breaker, rock drill, etc.) depending on the geological type of the hole to be drilled, such as soil or rock, the tools can be installed in a replaceable manner in the excavation drilling section 410.

[0140] The drilling section 410 can perform drilling operations while protruding further forward from the housing 440, and is configured to reciprocate in the front-back direction, so that when the drilling operation is completed, it can move backward to restore the protruding state to the initial state.

[0141] like Figure 9 , Figure 10 , Figure 13 As shown, the inner wall support 420 includes a plurality of pressure plates 421 spaced apart from each other along the length of the housing 440, and a pressure plate drive 426 that changes the state of the plurality of pressure plates 421 so that they are tilted relative to the housing 440.

[0142] Multiple pressure plates 421 are disposed on the outside of the housing 440, and the pressure plate drive unit 426 is connected to the multiple pressure plates 421 with at least a portion disposed on the inside of the housing 440.

[0143] In embodiments of the present invention, such as Figure 7 As shown, the pressure plate drive unit 426 connects a pair of pressure plates 421 arranged close to each other and applies pressure to the pressure plates 421 towards the tunnel excavation face, so that the pair of pressure plates 421 are inclined and tightly fitted relative to the housing 440. Further explanation: the pair of pressure plates 421 can be converted to an inclined state relative to the bottom surface of the housing 440.

[0144] That is, the pressure plate drive unit 426 is configured to pressurize all the pressure plates 421 disposed on the tunnel excavation face to make them fit tightly together, and to connect all pairs of pressure plates 421 arranged close to each other.

[0145] In an embodiment of the present invention, an elongated hole 422 is formed on the pressure plate 421 in a direction parallel to the length direction of the housing 440. Specifically, the pressure plate 421 includes a pressure plate body 423 and a plurality of pressure plate supports 424 integrally connected to the lower side of the pressure plate body 423, and the aforementioned elongated hole 422 is formed on the plurality of pressure plate supports 424. The plurality of elongated holes 422 formed on the plurality of pressure plate supports 424 are arranged in a row when viewed from the side, and a steel rod 425 is attached to penetrate the plurality of elongated holes 422.

[0146] At least a portion of the pressure plate drive unit 426 is fixedly installed inside the housing 440, and one side of it is connected to the steel rod 425 to perform the action of pushing the steel rod 425 away from the housing 440 or pulling it in the opposite direction.

[0147] Specifically, such as Figure 7 , Figure 9 , Figure 10 As shown, for example, the pressure plate drive unit 426 may include a pair of lifting rods 427 connected to the steel rod 425 and a rotating body 428 for lifting and driving the pair of lifting rods 427.

[0148] The lifting rod 427 and the rotating body 428 may have a threaded connection structure, and may have a mutually combined structure in which the lifting rod 427 is raised and lowered by rotating the rotating body 428.

[0149] Multiple rotating bodies 428 can be configured and each can be combined with a separate lifting rod 427 so that only one lifting rod 427 can be raised or lowered; otherwise, they can be integrated with a pair of lifting rods 427 so that the pair of lifting rods 427 can be raised or lowered simultaneously.

[0150] In addition, the rotating body 428 can be configured as a single unit and can be integrated with four lifting rods 427 to simultaneously raise and lower the four adjacent lifting rods 427.

[0151] In addition, the pressure plate drive unit 426 can also use various lifting drive sources such as a hydraulic jack that is connected to the steel bar 425 and raises and lowers the steel bar 425.

[0152] In an embodiment of the present invention, the excavation drilling section 410 forms a hole in the front excavation wall, and the excavator excavates around it to form a tunnel excavation surface 40. The pressure plate 421 is pressed against the tunnel excavation surface 40 side by the pressure plate driving section 426, thereby closely fitting the tunnel excavation surface and providing support to prevent it from collapsing.

[0153] In addition, the pressure plate 421 is tightly attached to the tunnel excavation face and supports the earth pressure, which not only prevents eccentric loads from acting on the main frame 100, but also fundamentally prevents the main frame 100 from torsion and local buckling, thereby improving the safety of the entire device.

[0154] At this point, the inner wall of the tunnel excavation face 40 can generally form a smooth plane, but in most cases it forms a curved shape.

[0155] When the inner wall of the tunnel excavation face 40 is formed in the aforementioned curved shape, the present invention as follows: Figure 7As shown, by driving the pressure plate drive unit 426 to rotate multiple pressure plates 421 so that the pressure plates 421 are tilted relative to the housing 440, the tunnel excavation face can be pressurized and supported in a state of stable contact and support with the curved tunnel excavation face.

[0156] An elongated hole 422 is formed on the pressure plate 421, allowing the steel rod 425 to move along the elongated hole 422 and engage. The pressure plate drive part 426 is connected to the steel rod 425, causing the steel rod 425 to rise and fall, thereby achieving the above-mentioned action.

[0157] In embodiments of the present invention, such as Figure 1 , Figure 2 , Figure 13 As shown, the housing 440 of the excavation unit 400 adjacent to the backfilling and compaction module 500 extends rearward to cover the upper side of the housing 528 of the upper compaction unit 521 of the backfilling and compaction module 500. A roller is provided between the rearwardly extending housing 440 and the housing 528 to allow the excavation unit 400 to move smoothly relative to the main frame 100 when moving forward. This roller can be provided on the upper part of the housing 528 or the lower part of the pressure plate 421, but more preferably it is fixedly installed on the upper part of the housing 528 of the upper compaction unit 521.

[0158] The following is a detailed description of the backfilling and compaction module 500.

[0159] like Figures 16 to 21 As shown, during tunnel excavation, the backfilling and compaction module 500 performs the function of backfilling the excavated soil and sand behind the tunnel structure 30 and firmly compacting it. The tunnel structure 30 extends along the excavation direction to penetrate the inner empty space of the main frame 100 and the inner empty space of the backfilling and compaction module 500.

[0160] Specifically, the backfilling and compaction module 500 does not excavate and backfill soil and sand around the tunnel structure 30 located in the empty space inside the main frame 100, but instead performs operations on the rear part of the tunnel structure 30 located inside the main frame 100, based on the direction of excavation.

[0161] To further explain, the excavation, backfilling, and compaction of the corresponding portion of the tunnel structure 30 located inside the main frame 100 are carried out after further excavation along the excavation direction, allowing the main frame 100 and the backfilling and compaction module 500 to be transported further forward along the excavation direction. This backfilling and compaction operation is repeated, and as the tunnel excavation progresses forward, the tunnel structure 30 is also formed sequentially and continuously in front.

[0162] like Figures 16 to 21 As shown, the backfilling and compaction module 500 is connected and installed on the main frame 100, forming an inner empty space that communicates with the inner area (inner empty space) of the main frame 100, and is configured to backfill excavated soil and sand on the outside of the tunnel structure 30 located behind it, and to compact the backfilled excavated soil and sand.

[0163] In an embodiment of the present invention, the backfilling and compaction module 500 includes a backfilling unit 510 and a compaction unit 520.

[0164] like Figures 16 to 21 As shown, the backfill unit 510 is installed on the main frame 100. It transports the excavated soil and sand excavated in front of the tunnel structure 30 based on the excavation direction to the rear of the main frame 100, so that the excavated soil and sand fall to the outside of the corresponding tunnel structure 30. At the same time, it backfills the area around the tunnel structure (upper side and left and right sides).

[0165] Specifically, the backfill unit 510 includes a conveyor belt 511, a first excavated soil and sand conveying actuator 512, and a second excavated soil and sand conveying actuator 516.

[0166] The conveyor belt 511 transports the excavated soil and sand excavated on the front side of the tunnel structure 30 to the chute 518 installed on the rear side of the main frame 100, where it falls and is disposed of. Further, the conveyor belt 511 can be installed on the lower part of the upper frame 120 of the main frame 100, and multiple conveyor belts 511 can be spaced apart from each other along the width direction of the main frame 100.

[0167] Although not specifically shown in the accompanying drawings, another conveyor belt can be connected to the front side of conveyor belt 511, i.e., the front side based on the excavation advance direction, so that it is inclined relative to the excavation bottom surface, and the excavated soil and sand contained by a separate hopper are simultaneously transported rearward along the conveyor belt and conveyor belt 511 connected to the excavation bottom surface.

[0168] Multiple chutes 518, separated by individual partitions along the width of the main frame 100, are provided behind the main frame 100. Multiple conveyor belts 511 transport excavated soil and sand to the corresponding chute 518 side. First excavated soil and sand conveying actuators 512 are respectively installed in the multiple chutes 518, and cause the excavated soil and sand collected in the chute 518 to rise and move upwards towards the upper side, which is the outer side of the chute 518. The first excavated soil and sand conveying actuator 512 may include a soil and sand support plate 514 and a cylinder for raising and lowering the soil and sand support plate 514, the cylinder may be a hydraulic cylinder or the like.

[0169] The second excavated soil and sand conveying actuator 516 causes the excavated soil and sand, which is moved upward by the first excavated soil and sand conveying actuator 512, to fall onto the outside of the tunnel structure 30 located behind the backfilling and compaction module 500, thereby backfilling the upper and left and right sides of the corresponding tunnel structure.

[0170] The second excavation soil and sand conveying actuator 516 is provided in multiple ways corresponding to the multiple first excavation soil and sand conveying actuators 512. It may include a push plate 517 and a cylinder that moves the push plate 517 back and forth. The cylinder may be a hydraulic cylinder or the like.

[0171] On the other hand, if the excavated soil and sand continues to be conveyed to the chute 518 side via the conveyor belt 511 when the soil and sand support plate 514 has risen to a certain level, the excavated soil and sand may fall to the bottom of the chute 518, thereby causing damage to the cylinder of the first excavated soil and sand conveying actuator.

[0172] For this purpose, the first excavated soil and sand conveying actuator 512 has a baffle 515 that can close the front of the conveyor belt 511, thereby preventing the excavated soil and sand from falling into the chute 518 through the conveyor belt 511 during upward movement. Thus, the excavated soil and sand conveyed along the conveyor belt 511 is blocked by the baffle 515, thereby limiting its fall into the chute.

[0173] Furthermore, the present invention can detect the rising height of the soil and sand support plate 514, and when it is confirmed that the rising movement has reached a certain level, it controls the motor driving the conveyor belt 511 to stop. In this case, when the baffle plate 515 is provided, it can more stably prevent the excavated soil and sand from falling into the chute 518.

[0174] Next, as Figures 16 to 21 As shown, the compaction unit 520 includes an upper compaction unit 521 and left and right compaction units 531.

[0175] The upper compaction unit 521 compacts the backfill soil and sand on the upper side of the tunnel structure 30 relative to the excavation bottom surface. The left and right compaction units 531 are arranged on the left and right sides centered on the tunnel structure 30 to compact the backfill soil and sand on the left and right sides of the tunnel structure 30.

[0176] To further explain, the excavated soil and sand fall through the aforementioned backfilling unit 510 and backfill the upper and left and right sides of the tunnel structure 30. The backfilled soil and sand refers to the soil and sand that falls around the tunnel structure 30, propelled by the second excavated soil and sand conveying actuator 516. The compaction unit 520 pressurizes the backfilled soil and sand laterally, thereby fully compacting it to prevent collapse. In this embodiment, the compaction unit 520 is used as an example of pressurizing and compacting the soil and sand. However, unlike this embodiment, the compaction unit 520 can also compact the soil and sand through vibration. Furthermore, unlike this embodiment, the compaction unit 520 can also simultaneously have the function of pressurizing and vibrating the soil and sand. For this purpose, vibration devices for generating vibration can be additionally provided on the compaction block 526 and the plate 523.

[0177] like Figures 16 to 21 As shown, the upper compaction unit 521 and the left and right compaction units 531 respectively include a first compaction part 522 and a second compaction part 525, and have roughly similar structures.

[0178] The first compaction section 522 has a flat plate 523 and a first backfill compaction actuator 524 that moves the flat plate 523 forward or backward toward the soil and sand backfilled around the tunnel structure 30. The flat plate 523 has a plurality of through holes spaced apart from each other.

[0179] The second compaction section 525 has multiple compaction blocks 526 and a second backfill compaction actuator 527 that moves the multiple compaction blocks 526 forward or backward toward the soil and sand backfilled around the tunnel structure 30. The multiple compaction blocks 526 are arranged to correspond to and be inserted into multiple through holes formed on the plate 523. The first and second backfill compaction actuators can be hydraulic cylinders, etc.

[0180] In an embodiment of the present invention, the first backfill soil and sand compaction actuator 524 and the second backfill soil and sand compaction actuator 527 cause the plate 523 and the compaction block 526 to reciprocate, while simultaneously applying pressure to the backfill soil and sand in the horizontal direction relative to the excavation bottom surface for compaction.

[0181] In an embodiment of the present invention, the compaction unit 520 further includes a lifting actuator 533 and a third compaction part 535.

[0182] like Figures 16 to 21 As shown, the lifting actuator 533 is fixedly installed at the rear of the main frame 100, and a lifting block 534 is connected to the end of its rod.

[0183] The lifting actuator 533 can be a hydraulic cylinder with a cylinder body and a rod. The cylinder body is fixedly installed at the rear of the main frame 100 by a separate structure, and the rod is configured to protrude downwards from the cylinder body. Therefore, when the rod moves back and forth, i.e., when it performs a lifting action, the lifting block 534 also moves up and down.

[0184] The third compaction part 535 is connected to the lifting block 534, such as Figures 16 to 21 As shown, the device includes a bottommost plate 536 located below the plate 523 of the left and right side compaction units 531, and a third backfill compaction actuator 537 that moves the bottommost plate 536 forward or backward toward the soil and sand backfilled around the tunnel structure 30. The third backfill compaction actuator 537 may be a hydraulic cylinder or the like, and is integrally connected to the lifting block 534 via a separate structure.

[0185] The bottommost plate 536 is used to pressurize and compact the bottommost part of the backfill soil and sand in the horizontal direction, and can be compacted by reciprocating back and forth driven by the third backfill soil and sand compaction actuator.

[0186] Therefore, when the lifting actuator 533 is driven to lift, the lifting block 534 and the third backfill sand compaction actuator 537 can lift simultaneously.

[0187] In an embodiment of the present invention, the lifting actuator 533 moves the lowest side plate 536 and the third backfill soil and sand compaction actuator 537 upward from the excavation bottom surface to a certain extent.

[0188] To further explain, as described below, after the excavator has excavated in front, the main frame 100 is moved forward. At this time, it is necessary to move the main frame forward while supporting the inner wall of the excavation. Therefore, the main frame 100 is moved forward after being raised to a certain level by the lifting unit 140.

[0189] However, since the lifting height achieved by the lifting unit 140 is not large, the lowermost plate 536 and the third backfill sand compaction actuator 537 also rise to a small height when the lifting unit 140 is driven to rise.

[0190] On the other hand, around the lowest plate 536 and the third backfill sand compaction actuator 537, the excavated soil and sand falling from the upper side accumulate to a certain extent. When the main frame 100 moves forward, the lowest plate 536 and the third backfill sand compaction actuator 537 may be interfered with by the soil and sand accumulated around them, thus hindering the main frame 100 from moving forward.

[0191] To prevent this, before the main frame 100 moves forward, the lifting actuator 533 is driven to raise the lowermost plate 536 and the third backfill sand compaction actuator 537, so that they move upward at least to a position higher than the soil and sand arranged around their bottom surface. This prevents interference to the lowermost plate 536 and the third backfill sand compaction actuator 537 during the forward movement of the main frame 100.

[0192] like Figures 16 to 21 As shown, the flat plate 523 of the upper compaction unit 521 is set at an angle, and when viewed from the side, its lower end is relatively closer to the main frame 100 than its upper end.

[0193] In addition, the flat plate 523 of the left and right side compaction unit 531 is set at an angle, and when viewed from the side, its lower end is relatively closer to the main frame 100 than its upper end.

[0194] Therefore, the upper compaction unit 521 and the left and right compaction units 531 can compact the soil and sand on the upper and left and right sides of the tunnel structure 30 at an angle relative to the excavation bottom surface. To further explain, as mentioned above, if the soil and sand are not compacted in the aforementioned inclined state, but rather in a state perpendicular to the excavation bottom surface, the compacted soil and sand may collapse due to loss of shape. Therefore, to stably maintain the compacted state of the soil and sand, inclined compaction is preferable.

[0195] Furthermore, when viewed from the rear, the flat plate 523 of the upper compaction unit 521 and the flat plate 523 of the left and right compaction units 531 can be connected flatly as a whole and can be located on the same virtual plane.

[0196] To further explain, based on the maximum driving state (maximum forward movement state of the cylinder rod) of the hydraulic cylinders in the upper compaction unit 521 and the left and right compaction units 531, as described above, the plate 523 of the upper compaction unit 521 and the plate 523 of the left and right compaction units 531 can be connected flatly as a whole and located on the same virtual plane.

[0197] Therefore, when the initial compaction work is completed, such as Figure 21 As shown, relative to the excavation bottom, the compacted soil and sand surfaces on the upper and left and right sides of the tunnel structure 30 can maintain an overall interconnected inclined state, so that the compacted soil and sand will not collapse and can maintain a stable state as much as possible.

[0198] like Figures 16 to 21 As shown, in an embodiment of the present invention, the upper compaction unit 521 and the left and right compaction units 531 each include a housing 528, the housing 528 forming the exterior and having a first compaction part 522 and a second compaction part 525 installed thereon.

[0199] like Figures 16 to 21As shown, an empty space is formed between the shell 528 of the upper compaction unit 521 and the left and right compaction units 531, so that the tunnel structure 30 can be arranged therein.

[0200] A brush 540 is provided on the side of the shell 528 near the tunnel structure 30 to prevent gaps from forming between it and the tunnel structure 30.

[0201] To further explain, when viewed from the side, with the area where the brush 540 is located as the center, the space on the left is the space where the excavated soil and sand fall from the backfill unit 510. If the fallen soil and sand insert into the gap between the shell 528 and the tunnel structure 30, or more seriously, move and accumulate in the front part of the tunnel structure 30 through such gap, as mentioned above, when it is necessary to move the main frame 100 forward, interference may occur between the main frame 100 and the tunnel structure 30, or the main frame 100 may be unable to move forward normally due to the interference between the soil and sand accumulated on the outer surface of the front part of the tunnel structure 30 and the shell 528.

[0202] To this end, a brush 540 is provided to prevent excavated soil and sand from filling the gap between the shell 528 and the tunnel structure 30, or to prevent excavated soil and sand from accumulating on the outer surface of the front part of the tunnel structure 30 through such gap.

[0203] The outer surface of the front portion of the tunnel structure refers to the outer surface of the tunnel structure near the brush 540 located on the side of the excavation direction, with the brush 540 as the center.

[0204] The brush 540 can be made of any material selected from metal, rubber, and plastic, and preferably has densely packed bristles to fundamentally prevent gaps that could allow soil and sand to enter between the shell 528 and the tunnel structure 30. Thus, the brush 540 prevents interference between the shell 528, which moves along the excavation direction with the main frame 100, and the tunnel structure 30, while also preventing soil and sand from getting trapped between the shell 528 and the tunnel structure 30 in front of the shell 528.

[0205] The following describes in detail a method for excavating a tunnel using a mobile backfilling and compaction device based on an excavation system according to an embodiment of the present invention.

[0206] First, such as Figure 22 As shown, a vertical shaft 50 is formed from the ground near the starting point around the excavation area where the tunnel is to be formed.

[0207] Subsequently, as Figure 23As shown, with the main frame 100 mounted and installed with the excavation unit 400 and the backfilling and compaction module 500, the excavation unit 400 is driven to form multiple boreholes 10 on the soil and sand wall in front of the main frame 100 when the main frame 100 is in a stationary state.

[0208] The borehole 10 is formed by the excavation drilling section 410 of the excavation unit 400, and the excavation drilling section 410 forms the borehole 10 while protruding forward towards the housing 440 of the excavation unit 400. After the borehole forming operation is completed, it moves backward and returns to the initial position.

[0209] In this configuration, boreholes 10 are formed in multiple ways, spaced apart from each other, corresponding to the cross-sectional shape of the tunnel structure 30 to be installed. For example, as... Figure 29 As shown, when the cross-sectional shape of the tunnel structure 30 to be installed is rectangular or arched, the multiple boreholes are also formed into corresponding rectangular or arched shapes.

[0210] On the other hand, the main frame 100 has a fairly large size corresponding to the excavation area where the tunnel is to be formed, and an empty space is formed on its inner side, in which excavation equipment such as excavators can be arranged.

[0211] On the other hand, multiple excavation units 400 are provided. For the convenience of the following explanation, the relevant drawings are based on the case where five upper excavation units 401 are provided on the upper side of the main frame 100, and five side excavation units 402 are provided on the left and right sides of the main frame 100 respectively.

[0212] In embodiments of the present invention, the main frame 100, excavation unit 400, backfilling and compaction module 500, and main frame movement adjustment unit 300 are supplied to the ground through a shaft 50 and can be assembled in the ground, or assembled on the ground and then lowered below the shaft by a crane for placement. Furthermore, excavators and the like are placed in the empty space inside the main frame 100 placed in the ground.

[0213] Subsequently, as Figure 24 , Figure 25 As shown, before further excavating the soil and sand wall ahead using an excavator, the excavation unit 400 is moved forward relative to the main frame 100, and the front part of the excavation unit 400 is inserted into the inside of the borehole 10 to support the inner walls of the multiple boreholes 10. The inner wall surface of the borehole 10, broadly speaking, also constitutes part of the tunnel excavation face.

[0214] This is to prevent the collapse of the soil and sand wall in front during the following excavation operation. The excavation unit 400 stably supports the inner wall of the tunnel excavation face during the excavation operation.

[0215] Specifically, such as Figure 26 As shown, among the five upper excavation units 401, the first, third, and fifth upper excavation units are moved forward first. Similarly, among the five side excavation units 402 on the left and right sides, the first, third, and fifth side excavation units 402 are moved forward.

[0216] At this time, the digging unit movement adjustment drive unit 720 drives the digging unit movement roller 710 to contact the housing 440 of the digging unit 400, and the digging unit movement roller drive unit 730 rotates the digging unit movement roller 710 so that the digging unit 400 moves forward relative to the main frame 100.

[0217] When the excavating unit 400 completes its forward movement, the excavating unit movement adjustment drive unit 720 drives the excavating unit movement roller 710 to prevent it from contacting the housing 440. That is, the excavating unit movement adjustment drive unit 720 applies pressure to the excavating unit 400 upwards and to the left and right, causing the excavating unit 400 to move towards the inner wall of the excavation surface to be excavated (away from the main frame). At this time, the pressure plate 421 of the excavating unit 400, arranged inside the borehole 10, can pressurize and support the inner wall of the borehole, i.e., the inner wall of the tunnel excavation surface.

[0218] To further explain, the inner wall of the borehole 10 and the inner wall of the tunnel excavation face 40 formed by the excavation of the excavator described below are supported by moving the excavation unit 400 from the main frame 100 toward the inner wall of the tunnel excavation face 40.

[0219] On the other hand, such as Figure 7 As shown, to address the unevenness of the borehole's inner wall, the pressure plate drive unit 426 is driven so that the pressure plate 421, arranged inside the borehole 10, can stably apply pressure to support the uneven and inclined inner wall of the borehole. At this time, the pressure plate 421, inserted inside the borehole 10, rotates at an angle relative to the housing 440, thereby making overall contact with the uneven and inclined inner wall of the borehole and providing stable support.

[0220] To further explain, when the inner wall of the borehole 10 and the inner wall of the tunnel excavation face 40 are uneven and concave, the excavation unit 400 deforms and supports the inner wall of the borehole 10 and the tunnel excavation face 40.

[0221] Subsequently, in the five upper excavation units 401, the second and fourth upper excavation units 401 are moved forward. Similarly, in the five side excavation units 402 on the left and right sides, the second and fourth side excavation units 402 are moved forward. Then, the same operation as described above is repeated.

[0222] Subsequently, as Figure 27 As shown, using an excavator or similar device positioned inside the main frame 100, the excavation is carried out on the front sand wall surrounding multiple excavation holes 20, thereby expanding the excavation area forward. At this time, the excavation unit 400 can be driven forward at a position set before its operation, and the excavation can proceed approximately 30-60 cm along the excavation direction.

[0223] Subsequently, as Figure 28 , Figure 29 As shown, the main frame 100 is moved forward by about 30 to 60 cm. At this time, the backfilling and compaction module 500 installed on the main frame 100 also moves forward together with the main frame 100.

[0224] Specifically, workers further install rails 200 in front of the main frame 100, and the forward movement of the main frame 100 is carried out while the excavation unit 400, i.e., the pressure plate 421, is in stable contact with the tunnel excavation face.

[0225] That is, the main frame 100 moves forward while the excavation unit 400 applies pressure support to the inner wall of the borehole 10 and the inner wall of the tunnel excavation face 40 formed by the excavator.

[0226] To further explain, before the main frame 100 moves forward, the pressure plate 421 of the upper excavation unit 401 remains in contact with and supports the upper inner wall of the tunnel excavation face, and the pressure plate 421 of the side excavation unit 402 remains in contact with and supports the left and right inner walls of the tunnel excavation face.

[0227] In order to move the main frame 100 forward while keeping the pressure plate 421 of the excavation unit 400 in contact with the tunnel excavation face, the excavation unit movement adjustment drive unit 720 installed on the excavation unit support frame 125 is first driven, so that the upper excavation unit 401 descends due to its own weight, thereby causing the excavation unit movement roller 710 to come into contact with the housing 440 of the upper excavation unit 401.

[0228] At the same time, such as Figure 28 As shown, the lifting unit 140 drives the main frame 100 to move the upper frame 120 of the main frame 100 upward.

[0229] That is, the main frame 100 is in a state where it can move relative to the upper excavation unit 401, while the pressure plate 421 of the upper excavation unit 401 can maintain contact support while applying pressure to the excavation face. The above explains the relationship between the upper excavation unit 401 and the main frame 100.

[0230] Regarding the relationship between the lateral excavation unit 402 and the main frame 100, as follows: Figure 22 As shown, the digging unit movement adjustment drive unit 720, which is installed on the left vertical frame 121 and the right vertical frame 122, is driven to make the digging unit movement roller 710 contact with the housing 440 of the side digging unit 402.

[0231] As described above, when the digging unit movement adjustment drive unit 720 is driven to offset or reduce the force exerted by the side digging unit 402 on the sidewall of the tunnel excavation face to a certain extent, the digging unit moving roller 710 and the housing 440 of the side digging unit 402 come into contact with each other due to the elastic restoring force of the elastic member 750. Alternatively, according to another embodiment, the end of the digging unit movement adjustment drive unit 720 can be engaged with the housing 440 of the digging unit 402 in a way that allows it to slide without disengaging laterally. In this case, by retracting the movement adjustment drive unit 720, the digging unit moving roller 710 can be brought into contact with the housing 440 of the side digging unit 402.

[0232] At this time, when the pressure plate 421 of the side excavation unit 402 applies pressure support to the inner walls of the left and right sides of the tunnel excavation face with a certain degree of pressure, its pressure support force may be weaker than that of the pressure plate 421 of the upper excavation unit 401 when applying pressure support to the upper inner wall of the tunnel excavation face with a certain degree of pressure.

[0233] However, even if the pressure support of the pressure plate on the left and right inner walls of the tunnel excavation face is weaker than that on the upper inner wall of the tunnel excavation face, the risk of collapse is also smaller. Therefore, in order to move the main frame 100 forward, even if the pressure force of the pressure plate 421 of the side excavation unit 402 on the left and right inner walls of the tunnel excavation face is reduced to a certain extent, it will not cause problems in maintaining the tunnel excavation face.

[0234] In this state, the main frame movement adjustment drive unit 320 is driven to bring the main frame movement roller 310 into contact with the track 200, and then the main frame movement roller 310 is rotated to move the main frame 100 forward.

[0235] like Figure 28 As shown, after the main frame 100 completes its forward movement, in order to perform the next drilling operation 10, the excavation unit movement adjustment drive unit 720 is driven to separate the excavation unit movement roller 710 from the housing 440 of the upper excavation unit 401, and the pressure plate 421 of the upper excavation unit 401 applies pressure support to the upper inner wall of the tunnel excavation face. At this time, the lifting unit 140 lowers the main frame 100 to a level corresponding to the aforementioned rising height.

[0236] In addition, such as Figure 29 As shown, similarly, in order to carry out the next drilling operation 10, the excavation unit is driven to move the adjustment drive unit 720, so that the excavation unit moving roller 710 is separated from the housing 440 of the side excavation unit 402, and while pressurizing the housing 440 of the side excavation unit 402, the pressure plate 421 of the side excavation unit 402 pressurizes and supports the inner walls of the left and right sides of the tunnel excavation face.

[0237] Subsequently, the process of drilling, moving the excavation unit forward and closely fitting it to the tunnel face, excavating the soil and sand wall in front using an excavator, and moving the main frame forward is repeated multiple times until the desired result is achieved. Figure 30 The state shown.

[0238] In an embodiment of the present invention, the tunnel structure 30 to be installed can be arranged inside the main frame 100, and the inner area where the tunnel structure 30 is arranged is formed to be open to the outside along the excavation direction. The tunnel structure 30 is installed in the empty space inside the main frame 100 by concrete curing or the like.

[0239] The installation of the tunnel structure 30 can be carried out in at least one of the following operations: forming multiple boreholes 10, inserting an excavation unit into the borehole after the borehole is formed to support the borehole wall, excavating the front of the tunnel by an excavator, and moving the main frame forward after the excavator has excavated.

[0240] Furthermore, the installation of the tunnel structure 30 can be carried out independently of the aforementioned various operations. In embodiments of the present invention, such as... Figure 30 As shown, the state of installing the tunnel structure 30 in the empty space inside the main frame 100 after a certain degree of forward excavation work is disclosed. This is only an example, and as mentioned above, it can be carried out in various work procedures.

[0241] In an embodiment of the present invention, an empty space is formed on the inner side of the backfill and compaction module 500 so that the tunnel structure 30 can pass through its inner side. However, in the aforementioned steps, the tunnel structure 30 is currently only installed in the empty space inside the main frame 100.

[0242] The tunnel structure 30 at this point is the initial tunnel structure installed to form the entire tunnel structure by continuously installing tunnel structures as described below.

[0243] Subsequently, as described above, when the operations of forming multiple boreholes 10, inserting the excavation unit into the borehole after forming the borehole to support the borehole wall, excavating the front by the excavator, and moving the main frame forward after the excavator has excavated, as the main frame moves forward, the tunnel structure 30 is not only located inside the main frame 100, but also simultaneously arranged in the empty space inside the main frame 100 and the backfill and compaction module 500.

[0244] Furthermore, the tunnel structure 30 penetrates the inner empty space of the backfill and compaction module 500 along its side, and protrudes further behind the backfill and compaction module 500 based on the tunnel excavation direction. Additionally, as the main frame moves forward relative to the tunnel structure, the inner empty space of the main frame 100 increases, and this empty space can be used for the continuous installation of tunnel structures.

[0245] Subsequently, as Figure 31 , Figure 32 As shown, the space between the tunnel excavation face 40 and the initially installed tunnel structure 30 is filled to form a supporting concrete wall 800.

[0246] In an embodiment of the present invention, after the main frame 100 is conveyed forward, as... Figure 33 As shown, another tunnel structure is installed to connect it to the tunnel structure 30 previously installed inside the main frame 100.

[0247] When the main frame 100 is being transported forward, the present invention, as follows: Figure 32 As shown, the excavated soil and sand generated by expanding the excavation area through the excavation of the front soil and sand wall are transported to the side of the backfilling and compaction module 500, and compaction is carried out while backfilling the excavated soil and sand around the tunnel structure 30. The tunnel structure 30, which is compacted around the tunnel structure by excavating soil and sand, is not an additional tunnel structure as mentioned above, but refers to the previously installed tunnel structure.

[0248] The steps of backfilling and compacting excavated soil and sand around the tunnel structure 30 include: the step of causing the excavated soil and sand to fall and accumulate on the upper and left and right sides of the tunnel structure 30; and the step of compacting the accumulated excavated soil and sand so that the compacted soil and sand surface on the upper and left and right sides of the tunnel structure 30 remains inclined relative to the excavation bottom surface.

[0249] The process of excavating, backfilling, and compacting the soil and sand has already been explained above, so specific details will be omitted below.

[0250] However, when compacting the excavated soil and sand, the first compaction is to move the plate 523 of the upper compaction unit 521 and the left and right compaction units 531 and the multiple compaction blocks 526 back and forth repeatedly in the direction of the compaction surface. Then, only the multiple compaction blocks 526 are moved back and forth to perform the second compaction. Finally, only the plate 523 is moved back and forth repeatedly to complete the compaction.

[0251] To further explain, in the initial state where excavated soil and sand have fallen and accumulated in an irregular manner, even if the slab 523 and multiple compaction blocks 526 are moved simultaneously for compaction, the compacted surface of the soil and sand may still be uneven and irregular. Therefore, only multiple compaction blocks 526 are subsequently moved to level the uneven and irregular compacted surface of the soil and sand as much as possible while compacting. Afterwards, the slab 523 is used for compaction to make the overall compacted surface of the soil and sand flat.

[0252] In an embodiment of the present invention, when the excavated soil and sand are compacted for the first time by the backfilling and compaction module 500, that is, when the soil and sand on the end side of the initially installed tunnel structure 30 are compacted for the first time, the compaction is carried out while the excavated soil and sand are supported by the supporting concrete wall 800 behind them.

[0253] The supporting concrete wall 800 is formed through concrete curing, just like the tunnel structure 30, and is integrally connected with the tunnel structure 30. Therefore, during the initial compaction of excavated soil and sand, it can firmly support the back of the compacted excavated soil and sand, thereby improving the compaction strength.

[0254] After that, as Figure 33 and Figure 24 As shown and as explained above, while repeatedly performing the drilling operation → moving the excavation unit forward and closely fitting it against the tunnel excavation face → using an excavator to excavate the soil and sand wall in front, additional tunnel structure installation work and excavated soil and sand backfilling and compaction work are carried out. Therefore, tunnel excavation and tunnel structure installation work can be carried out simultaneously and continuously.

[0255] As described above, when carrying out tunnel engineering operations such as setting up subway operating sections and underground lanes in the ground, the present invention differs from the currently used open-cut method. It only involves excavation work in the ground without damaging the ground surface (road), thus minimizing traffic congestion and avoiding a large amount of construction costs, such as the cost of large-scale soil and sand excavation, external soil and sand removal and transportation costs, and the cost of transporting the removed soil and sand to the construction site for backfilling after the structure is completed.

[0256] Furthermore, while the present invention sequentially forms excavation holes for tunnel formation in the ground, the installation of tunnel structures that substantially form the tunnel, the backfilling of soil and sand around the tunnel structures, and the formation of tunnel excavation holes can be carried out simultaneously and continuously, thereby significantly shortening the time required for the entire construction operation and greatly reducing the required costs.

[0257] In this summary, although the present invention has been illustrated and described in conjunction with preferred embodiments to illustrate the principles of the invention, the invention is not limited to the structures and operations shown in the above illustrations and descriptions. Rather, those skilled in the art will fully understand that various changes and modifications can be made to the invention without departing from the spirit and scope of the appended claims.

[0258] Industrial applicability

[0259] This invention allows the installation of tunnel structures that actually form the tunnel, the backfilling of soil and sand around the tunnel structures, and the tunnel excavation to be carried out simultaneously and continuously, which can significantly shorten the time required for the entire construction operation and greatly reduce the required cost, thus having industrial applicability.

Claims

1. A mobile backfill and tamping device for an excavation system, characterized in that, include: The main frame has a tunnel structure that can be arranged inside it, and the inner area where the tunnel structure is arranged is open to the outside along the excavation direction. as well as The backfilling and compaction module is installed on the main frame, forming an inner empty space that communicates with the inner area of ​​the main frame. It backfills the excavated soil and sand on the outer side of the tunnel structure located behind it, and simultaneously compacts the backfilled excavated soil and sand. The backfilling and compaction module includes: The backfill unit, installed on the main frame, transports the excavated soil and sand excavated in front of the tunnel structure with the excavation direction as the reference to the rear of the main frame, so as to backfill the excavated soil and sand to the corresponding outside of the tunnel structure. as well as The compaction unit is installed behind the main frame with the excavation direction as the reference, and compacts the soil and sand backfilled by the backfill unit in a horizontal direction relative to the excavation bottom surface.

2. The mobile backfilling and compaction device for the excavation system according to claim 1, characterized in that, The backfill unit includes: The conveyor belt transports the excavated soil and sand excavated on the front side of the tunnel structure and dumps it into the chute installed on the rear side of the main frame. A first excavated soil and sand conveying actuator, installed in the chute, causes the excavated soil and sand, which is dumped into and collected in the chute, to rise upwards towards the upper side, which is the outer side of the chute; and The second excavated soil and sand conveying actuator causes the excavated soil and sand, which has been moved upward by the first excavated soil and sand conveying actuator, to fall onto the outside of the tunnel structure located behind the backfilling and compaction module for backfilling.

3. The mobile backfilling and compaction device for the excavation system according to claim 2, characterized in that, The first excavated soil and sand conveying actuator has a baffle plate that can close the front of the conveyor belt to prevent excavated soil and sand from being dumped into the chute through the conveyor belt during upward movement.

4. The mobile backfilling and compaction device for the excavation system according to claim 1, characterized in that, The compaction unit includes: The upper compaction unit compacts the backfill soil and sand located above the tunnel structure relative to the excavation bottom surface; and The left and right side compaction units are arranged on the left and right sides with the tunnel structure as the center, and compact the backfill soil and sand located on the left and right sides of the tunnel structure. The upper compaction unit and the left and right compaction units respectively include: The first compaction section includes a flat plate and a first backfill compaction actuator that moves the flat plate forward or backward toward the backfilled soil and sand surrounding the tunnel structure; and The second compaction section has multiple compaction blocks that correspond to and are inserted into multiple through holes formed on the plate, and a second backfill soil and sand compaction actuator that causes the multiple compaction blocks to move forward or backward toward the backfill soil and sand around the tunnel structure.

5. The mobile backfilling and compaction device for the excavation system according to claim 4, characterized in that, The backfilling and compaction module also includes: A lifting actuator is fixedly installed at the rear of the main frame, and a lifting block is connected to its rod end; and The third compaction unit, connected to the lifting block, has a bottommost plate located below the plate of the left and right compaction units and a third backfill soil and sand compaction actuator that moves the bottommost plate forward or backward toward the backfill soil and sand around the tunnel structure.

6. The mobile backfilling and compaction device for the excavation system according to claim 5, characterized in that, The lifting actuator causes the lowest side plate and the third backfill soil and sand compaction actuator to rise and move a certain distance from the excavation bottom surface.

7. The mobile backfilling and compaction device for the excavation system according to claim 4, characterized in that, The upper compaction unit is inclined, and when viewed from the side, its lower end is closer to the main frame than its upper end. The flat plates of the left and right side compaction units are tilted, and when viewed from the side, their lower ends are relatively closer to the main frame than their upper ends.

8. The mobile backfilling and compaction device for the excavation system according to claim 7, characterized in that, When viewed from the side, the flat plate of the upper compaction unit and the flat plates of the left and right compaction units can be connected flatly as a whole and located on a virtual plane.

9. The mobile backfilling and compaction device for the excavation system according to claim 4, characterized in that, The upper compaction unit and the left and right compaction units each include a shell that forms the exterior and on which the first compaction part and the second compaction part are installed. An empty space is formed between the shells of the upper compaction unit and the left and right compaction units for arranging the tunnel structure. A brush is provided on one side of the housing near the tunnel structure to prevent gaps from forming between the brush and the tunnel structure.

10. The mobile backfilling and compaction device for the excavation system according to claim 9, characterized in that, The brush is made of any one of the following materials: metal, rubber, or plastic.