Cast-in-situ bored pile reinforcement cage elevation control device
Through the design of the height control device for the reinforced cage of bored cast-in-place piles, and the cooperation of the marks on the hanging bars and the rotation positioning part, the problem of material waste in the control of the top elevation of the reinforced cage piles for bored cast-in-place piles is solved, and the stability of the reinforced cage is achieved. Positioning and efficient construction.
Patent Information
- Application Number
- CN202323287442.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-04
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2033-12-04
AI Technical Summary
In urban construction, there is a large height difference between the top elevation of bored piles, steel cages, and the original ground elevation, which results in the need for long round steel hanging bars, causing a waste of material.
A device for controlling the height of the steel cage of bored piles is designed, which includes a first hoisting device, a second hoisting device and a latch sleeve. Through the cooperation of the marks on the hanging bars and the rotation positioning part, it is ensured that the steel cage can be stable during construction. Position it to a predetermined height to avoid posture rotation during hoisting.
It effectively reduces material waste, improves the stability and construction efficiency of the steel cage, and ensures the accuracy of the pile top elevation and the stability of the hoisting process.
Smart Images

Figure CN221798433U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to a bored cast-in-place pile reinforcement cage elevation control device. Background Art
[0002] When bored cast-in-place piles are being constructed with steel cages, it is necessary to control the elevation of the top of the steel cage. At present, the elevation control of the top of the bored cast-in-place pile steel cage is mainly carried out by welding round steel hangers on the top of the steel cage, leading them out of the hole, and marking the elevation on the hangers to control the elevation. With the advancement of urban construction, internal support systems are widely used in foundation pit support projects. Affected by the internal support structure, pile foundations often need to be constructed on the original ground. In this case, there is a large height difference between the top elevation of the bored pile and the original ground elevation. In this case, the round steel hangers will be very long. The round steel hangers need to be cut off during the earth excavation stage, resulting in serious material waste. Utility Model Content
[0003] The utility model aims to provide a device for controlling the height of a bored pile reinforcement cage.
[0004] The utility model solves the above-mentioned technical problems with a technical solution as follows: a bored pile steel cage elevation control device: the bored pile steel cage comprises a steel ring and vertical steel bars, a plurality of steel rings are coaxially arranged in parallel and at intervals, and the vertical steel bars are fixed on the outer periphery of the steel ring; the elevation control device comprises a first hoisting device, a second hoisting device and a latch sleeve, the number of the latch sleeves is two, which are respectively fixedly connected to the vertical steel bars of the bored pile steel cage, and the two latch sleeves are arranged in relative positions; the first hoisting device and the second hoisting device both comprise a lower hook, a hanging bar and an upper hook connected in sequence, the lower hook can be inserted into the latch sleeve, the hanging bar is provided with a mark for indicating the height, and the upper hook is used to connect the hoisting equipment; the lower hook comprises a bending portion, an insertion portion and a rotation positioning portion connected in sequence, the latch sleeve comprises an insertion portion pin sleeve and a rotation positioning portion pin sleeve, the lower hook can be inserted into the latch sleeve to achieve connection, the insertion portion is located at the insertion portion pin sleeve, and the rotation positioning portion is located at the rotation positioning portion pin sleeve.
[0005] The utility model provides the bored pile reinforcement cage elevation control device as described above, further, the reinforcement cage also includes internal reinforcements, the internal reinforcements are cross-shaped structures, and the internal reinforcements are fixed inside the reinforcement rings.
[0006] The utility model provides the bored cast-in-place pile reinforcement cage elevation control device as described above, further, the rotation positioning part is a triangular pyramid structure or a quadrangular pyramid structure, and the structure of the rotation positioning part pin sleeve is adapted to the structure of the rotation positioning part.
[0007] The utility model provides the bored cast-in-place pile reinforcement cage elevation control device as described above, further, a top cover is provided on the top of the rotation positioning portion.
[0008] The utility model is a bored cast-in-place pile reinforcement cage elevation control device as described above, further, the upper hook includes a base and a rotating part, the rotating part is connected to the base through a rotating shaft, the rotating part is fixed with a hook body, the base is provided with a positioning hole, the rotating part is provided with a pin hole whose position corresponds to the positioning hole, the pin is inserted into the pin hole and the positioning hole to realize the positioning of the base and the rotating part; the base is connected to the upper part of the suspension rod; the hook body is used to connect the lifting equipment.
[0009] The utility model provides the bored cast-in-place pile reinforcement cage elevation control device as described above, further, the positioning holes of the base are arranged in a ring shape, the number of the positioning holes is five to twelve, and the number of the pin holes is at least one.
[0010] In specific applications, the height control device for bored pile steel cage of the utility model can conveniently use the mark for indicating the height provided on the lifting rod to indicate the lifting, so as to position the steel cage to a predetermined height. In addition, due to the cooperation between the rotation positioning part and the rotation positioning part pin sleeve, the lifting rods of the first lifting device and the second lifting device will not rotate axially, thereby ensuring the stability of the posture of the steel cage during the lifting process. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] The above and / or other advantages of the present invention will become clearer and easier to understand through the detailed description made in conjunction with the following drawings, which are only schematic and do not limit the present invention, wherein:
[0012] Figure 1 A schematic diagram of a bored pile reinforcement cage and an elevation control device according to an embodiment;
[0013] Figure 2 This is a schematic diagram of the lower hook of an embodiment of the utility model;
[0014] Figure 3 It is a partial enlarged schematic diagram of the lower hook of an embodiment of the utility model;
[0015] Figure 4 This is a schematic diagram of a latch sleeve according to an embodiment of the utility model;
[0016] Figure 5 A schematic cross-sectional view of a latch sleeve according to an embodiment of the utility model;
[0017] Figure 6 This is a schematic diagram of an upper hook of an embodiment of the utility model;
[0018] Figure 7The figure is a schematic diagram of an upper hook of an embodiment of the utility model.
[0019] In the accompanying drawings, the components represented by the reference numerals are listed as follows:
[0020] 10. Steel cage, 11. Steel ring, 12. Internal steel bars, 13. Vertical steel bars, 20. First lifting device, 21. Lower hook, 211. Bending portion, 212. Inserting portion, 213. Rotational positioning portion, 214. Top cover, 22. Suspension rod, 23. Upper hook, 231. Base, 232. Rotational portion, 233. Latch, 234. Hook body, 235. Positioning hole, 236. Latch hole, 30. Second lifting device, 40. Latch sleeve, 41. Inserting portion pin sleeve, 42. Rotational positioning portion pin sleeve, 43. Inserting portion accommodating cavity, 44. Rotational positioning portion accommodating cavity. DETAILED DESCRIPTION
[0021] Hereinafter, an embodiment of the bored cast-in-place pile reinforcement cage elevation control device of the present invention will be described with reference to the accompanying drawings.
[0022] The embodiments described herein are specific embodiments of the present invention, which are used to illustrate the concept of the present invention, are explanatory and exemplary, and should not be interpreted as limiting the embodiments of the present invention and the scope of the present invention. In addition to the embodiments described herein, those skilled in the art can also adopt other obvious technical solutions based on the claims and the contents disclosed in the specification of this application, including technical solutions that adopt any obvious replacement and modification of the embodiments described herein.
[0023] The drawings of this specification are schematic diagrams, which assist in explaining the concept of the utility model and schematically show the shapes of various parts and their mutual relationships. Please note that in order to clearly show the structure of various components of the embodiments of the utility model, the drawings are not drawn according to the same scale. The same reference numerals are used to represent the same parts.
[0024] Figure 1 A bored pile reinforcement cage elevation control device according to an embodiment of the utility model is shown, wherein the bored pile reinforcement cage 10 comprises reinforcement rings 11 and vertical reinforcements 13, wherein a plurality of reinforcement rings 11 are coaxially and parallelly arranged at intervals, and the vertical reinforcements 13 are fixed to the outer circumference of the reinforcement rings 11; the diameters of the reinforcement rings and the vertical reinforcements can be determined according to the actual needs of the bored piles, for example, the diameters of the reinforcement rings and the vertical reinforcements are 10 mm to 20 mm.
[0025] The elevation control device includes a first hoisting device 20, a second hoisting device 30 and a latch sleeve 40. The number of the latch sleeves 40 is two, which are respectively fixedly connected to the vertical steel bars 13 of the bored pile steel cage 10. The two latch sleeves 40 are arranged in relative positions. Figure 1 In the embodiment shown, the line connecting the two fixing positions of the latch sleeves is the diameter of the steel ring, which can ensure the stability of the steel cage during hoisting; the first hoisting device 20 and the second hoisting device 30 both include a lower hook 21, a hanging rod 22 and an upper hook 23 connected in sequence, the lower hook 21 can be inserted into the latch sleeve 40, the hanging rod 22 is provided with a mark for indicating the height, and the upper hook 23 is used to connect the hoisting equipment; in a specific embodiment, the mark for indicating the height can be a scale line, such as a large scale is set for every meter of the hanging rod, and a small scale is set for every 25 cm, which is used for controlling and checking the pile top elevation; Figure 2 and Figure 3 As shown, the lower hook 21 includes a bending portion 211, an inserting portion 212 and a rotation positioning portion 213 connected in sequence. Figure 4 and Figure 5 As shown, the latch sleeve 40 includes an insertion portion sleeve 41 and a rotational positioning portion sleeve 42. The lower hook 21 can be inserted into the latch sleeve 40 to achieve connection. The insertion portion 212 is located at the insertion portion sleeve 41, and the rotational positioning portion 213 is located at the rotational positioning portion sleeve 42. In an embodiment of a bored pile reinforcement cage elevation control device, the rotational positioning portion 213 is a triangular pyramid structure or a quadrangular pyramid structure, and the structure of the rotational positioning portion sleeve 42 is compatible with the structure of the rotational positioning portion 213. Figure 2 and 3 In the embodiment of the height control device for bored pile reinforcement cage shown in the figure, the rotation positioning part 213 is a triangular pyramid structure. Figure 3 The structure of the pin sleeve of the middle insertion part is a circular tube structure (with the insertion part receiving cavity 43 inside; for example, a seamless hollow steel tube with a wall thickness of DN20 and a thickness of 10mm can be used as the pin sleeve, and the insertion part pin sleeve is 250mm long), and the rotation positioning part pin sleeve is a hollow triangular pyramid structure (with the rotation positioning part receiving cavity 44 inside). The triangular pyramid cooperates with the rotation positioning part pin sleeve to realize the positioning of the hoisting device and prevent it from rotating during the hoisting process. Figure 3 In the preferred embodiment, a top cover 214 is provided on the top of the rotation positioning portion 213 .
[0026] When the height control device for bored cast-in-place pile reinforcement cage of the above embodiment of the utility model is used in a specific application, the first lifting device and the second lifting device can be rotated to the appropriate height in advance according to the construction scene; before lifting, the first lifting device and the second lifting device are respectively inserted into the corresponding latch sleeves, and then the upper hook of the lifting device is connected to the lifting equipment. During lifting, the mark for indicating the height provided on the lifting rod can be conveniently used for lifting instructions, and the lowering depth of the reinforcement cage can be checked and controlled, so as to position the reinforcement cage to a predetermined height. In addition, due to the cooperation between the rotation positioning part and the rotation positioning part pin sleeve, the lifting rods of the first lifting device and the second lifting device will not rotate axially, thereby ensuring the stability of the posture of the reinforcement cage during the lifting process. After the lifting is completed, tap the device to separate the lifting device from the latch sleeve and it can be recycled and reused.
[0027] In such Figure 1 In the embodiment of the elevation control device for bored pile steel cage shown, the steel cage 10 further includes internal steel bars 12, which are cross-shaped structures and are fixed inside the steel ring 11. By providing the internal steel bars, the stability of the steel cage can be improved, and deformation of the steel cage during the hoisting process or concrete pouring can be avoided, thereby improving the construction effect of bored piles.
[0028] Figure 1 The upper hook shown in the figure is a Q-shaped structure. When the hoisting equipment is connected, it cannot be rotated in an azimuth to connect with the hoisting equipment (such as the hook of the hoisting equipment) because it is an integrated structure with the hanging rod. At this time, it is necessary to adjust the direction of the hook of the hoisting equipment (sometimes it is difficult and the overall position of the hoisting equipment needs to be moved). In another embodiment, the upper hook 23 includes a base 231 and a rotating part 232, the rotating part 232 is connected to the base 231 through a rotating shaft, the rotating part 232 is fixed with a hook body 234, the base is provided with a positioning hole 235, the rotating part 232 is provided with a latch hole 236 corresponding to the positioning hole 235, and the latch 233 is inserted into the latch hole 236 and the positioning hole 235 to realize the positioning of the base and the rotating part 232; the base 231 is connected to the upper part of the hanging rod 22; the hook body 234 is used to connect the hoisting equipment. In a preferred embodiment, the positioning holes 235 of the base are arranged in a ring, the number of the positioning holes 235 is five to twelve, and the number of the latch hole 236 is at least one.
[0029] When the height control device for bored cast-in-place pile reinforcement cage of the utility model is used, if the direction position of the upper hook needs to be adjusted, the pin is pulled out of the pin hole, and the rotating part can rotate relative to the base, and then the direction position of the hook body connected to the rotating part moves to a suitable direction position, so as to be conveniently connected to the lifting equipment, and then the pin is inserted into the pin hole and deep into the positioning hole to fix the base and the rotating part.
[0030] The technical features disclosed above are not limited to the disclosed combinations with other features. Those skilled in the art may also make other combinations between the technical features according to the purpose of the utility model to achieve the purpose of the utility model.
Claims
1. A bored pile reinforcement cage elevation control device, Features: The bored pile reinforcement cage (10) comprises reinforcement rings (11) and vertical reinforcements (13), wherein a plurality of reinforcement rings (11) are coaxially arranged in parallel and spaced relation, and the vertical reinforcements (13) are fixed to the outer periphery of the reinforcement rings (11); the elevation control device comprises a first hoisting device (20), a second hoisting device (30) and a latch sleeve (40), wherein the number of the latch sleeves (40) is two and they are respectively fixedly connected to the vertical reinforcements (13) of the bored pile reinforcement cage (10), and the two latch sleeves (40) are arranged in opposite positions; the first hoisting device (20) and the second hoisting device (30) both comprise a lower hook (21), a hanging bar (22) and a The upper hook (23) is provided with a mark for indicating the height on the suspension rod (22). The upper hook (23) is used to connect the lifting equipment. The lower hook (21) comprises a bending part (211), an insertion part (212) and a rotational positioning part (213) which are connected in sequence. The latch sleeve (40) comprises an insertion part pin sleeve (41) and a rotational positioning part pin sleeve (42). The lower hook (21) can be inserted into the latch sleeve (40) to realize the connection. The insertion part (212) is located in the insertion part pin sleeve (41), and the rotational positioning part (213) is located in the rotational positioning part pin sleeve (42).
2. The bored pile reinforcement cage elevation control device according to claim 1, It is characterized in that The steel cage (10) further comprises internal steel bars (12), wherein the internal steel bars (12) are of a cross-shaped structure and are fixed inside the steel ring (11).
3. The bored pile reinforcement cage elevation control device according to claim 1, It is characterized in that The rotation positioning portion (213) is a triangular pyramid structure or a quadrangular pyramid structure, and the structure of the rotation positioning portion pin sleeve (42) is compatible with the structure of the rotation positioning portion (213).
4. The bored pile reinforcement cage elevation control device according to claim 3, It is characterized in that A top cover (214) is provided on the top of the rotation positioning portion (213).