Blasting device for blasting open-air thin-layer ore body

By using cross-distributed cuttings and civilian explosives in the open-pit thin-layer ore body blasting device, and electrically connecting the detonator pins to the electric detonator, the problem of excessive rock crushing around the blasthole is solved and the rock blockiness is achieved. The improvement and reduction of aggregate powder content reduces the use of explosives and mining costs, and improves the economic benefits of engineering blasting.

CN221802671UActive Publication Date: 2024-10-01ANHUI TONGLING CONCH CEMENT
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202322195036.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-08-16
Publication Date
2024-10-01
Estimated Expiration
2033-08-16

AI Technical Summary

Technical Problem

During blasting operations in open-pit thin-layer ore body limestone mines, the rocks around the blast holes are excessively crushed, resulting in a high powdered ore rate in aggregate production, and some varieties are unqualified, which increases the cost of explosives and affects economic benefits.

Method used

A blasting device including detonator pins, rock cuttings, electric detonators and civilian explosives is designed. Rock cuttings and civilian explosives are cross-distributed in the shell. The electric detonator is connected to the external power supply through the detonator pins. The detonator pins and The number of electric detonators corresponds to that of civilian explosives, and the detonator pins penetrate the cuttings and are electrically connected to the electric detonators.

Benefits of technology

After blasting, the rock mass is increased, the aggregate powder content is reduced, and the crushing degree is uniform, which reduces the use of explosives, reduces the cost of ore mining, and improves the economic benefits of engineering blasting.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221802671U_ABST
    Figure CN221802671U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of blasting, in particular to a blasting device for blasting an open-air thin-layer ore body. According to the technical scheme, the blasting device for blasting the open-air thin-layer ore body comprises detonator leg wires, rock debris, electric detonators, civil explosives and a shell, the rock debris and the civil explosives are arranged in the shell and distributed in a crossed mode in the shell, the electric detonators are arranged in the civil explosives, and the electric detonators are arranged in the shell. And the electric detonator is communicated with an external power supply through a detonator leg wire. According to the utility model, after the thin-layer ore body is blasted, the rock lumpiness is obviously improved, the powder content of aggregate is obviously reduced, the crushing degree is uniform, no obvious large blocks or low blocks are generated, meanwhile, the use of explosives is reduced, the unit consumption of the explosives is reduced, the ore mining cost is directly reduced, and the economic benefit of engineering blasting is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of blasting, in particular to a blasting device for blasting an open-air thin-layer ore body. Background Art

[0002] Engineering blasting has a wide range of uses in national economic construction. In industrial fields such as coal mines, metal mines, and building materials mines, blasting methods are the main means of crushing ore rocks. At the same time, engineering blasting also has specific engineering objects and target requirements such as quality, safety, and economic and technical indicators. The project is closely combined with reality. The blasting effect must be tested through practical evaluation. The design and construction of engineering blasting must be technically feasible, economically reasonable, safe and reliable. In the process of blasting operations in open-pit thin-layer limestone mines, blasting operations are carried out according to conventional blasting designs. There will be excessive crushing of rocks around the blastholes, small particle size of materials in the blasting area, resulting in a high powder ore rate in aggregate production, and some varieties of aggregates are unqualified. This will not only cause excessive consumption of explosive energy and increase the cost of explosive use, but also seriously affect the economic benefits of finished aggregate products. Utility Model Content

[0003] The utility model provides a blasting device for blasting an open-air thin-layer ore body, which solves the above-mentioned technical problems.

[0004] The utility model solves the above-mentioned technical problems as follows:

[0005] A blasting device for blasting an open-air thin-layer ore body comprises a detonator leg wire, rock cuttings, an electric detonator, civilian explosives and an outer shell, wherein the rock cuttings and civilian explosives are arranged in the outer shell, and the rock cuttings and civilian explosives are cross-distributed in the outer shell, and the civilian explosives are arranged in the electric detonator, and the electric detonator is connected to an external power supply through the detonator leg wire.

[0006] On the basis of the above technical solution, the present invention can also be improved as follows.

[0007] Furthermore, the number of the detonator leg wires and electric detonators corresponds to that of civilian explosives.

[0008] Furthermore, two rock cuttings and civil explosives are respectively arranged in the shell, and the length of the upper rock cuttings in the shell is greater than the length of the lower rock cuttings, and the length of the upper civil explosives in the shell is less than the length of the lower civil explosives.

[0009] Furthermore, the detonator leg wire penetrates the rock cuttings and is electrically connected to the electric detonator.

[0010] The beneficial effects of the utility model are: it can achieve that the rock block size of the thin layer ore body is significantly improved after blasting, the powder content of the aggregate is significantly reduced, the crushing degree is uniform without the generation of obvious large pieces and low heels, and at the same time, the use of explosives is reduced, the unit consumption of explosives is reduced, the cost of ore mining is directly reduced, and the economic benefits of engineering blasting are improved.

[0011] The above description is only an overview of the technical solution of the utility model. In order to more clearly understand the technical means of the utility model and implement it according to the contents of the specification, the following is a detailed description of the preferred embodiment of the utility model with the accompanying drawings. The specific implementation method of the utility model is given in detail by the following embodiments and their drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] The drawings described herein are used to provide a further understanding of the present invention and constitute a part of the present application. The illustrative embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation on the present invention.

[0013] In the attached picture:

[0014] Figure 1 It is a structural schematic diagram of the utility model.

[0015] In the accompanying drawings, the components represented by the reference numerals are listed as follows:

[0016] 1. Detonator leg wire; 2. Rock cuttings; 3. Electric detonator; 4. Civilian explosives; 5. Casing. DETAILED DESCRIPTION

[0017] The principles and features of the present invention are described below in conjunction with the accompanying drawings. The examples given are only used to explain the present invention and are not used to limit the scope of the present invention. The present invention is described in more detail in the following paragraphs by way of example with reference to the accompanying drawings. The advantages and features of the present invention will become clearer according to the following description and claims. It should be noted that the drawings are all in a very simplified form and are not in precise proportions, and are only used to conveniently and clearly assist in explaining the purpose of the embodiments of the present invention.

[0018] See also Figure 1 As shown, the embodiments provided by the utility model:

[0019] Embodiment 1

[0020] A blasting device for blasting an open-air thin-layer ore body comprises a detonator leg line 1, rock cuttings 2, electric detonators 3, civilian explosives 4 and an outer shell 5. The rock cuttings 2 and the civilian explosives 4 are arranged in the outer shell 5, and the rock cuttings 2 and the civilian explosives 4 are cross-distributed in the outer shell 5. Two rock cuttings 2 and two civilian explosives 4 are arranged in the outer shell 5 respectively, and the length of the upper rock cuttings 2 in the outer shell 5 is greater than the length of the lower rock cuttings 2.

[0021] The length of the upper civilian explosive 4 in the shell 5 is smaller than the length of the lower civilian explosive 4. An electric detonator 3 is arranged in the civilian explosive 4. The electric detonator 3 is connected to an external power supply through a detonator leg wire 1, so that the rock blockiness of the thin layer ore body can be significantly improved after blasting, the aggregate powder content can be significantly reduced, the crushing degree is uniform without the production of obvious large blocks and low heels, and at the same time, the use of explosives is reduced, the unit consumption of explosives is reduced, the cost of ore mining is directly reduced, and the economic benefits of engineering blasting are improved. The number of detonator leg wires 1 and electric detonators 3 corresponds to the civilian explosive 4, and the detonator leg wire 1 passes through the rock cuttings 2 and is electrically connected to the electric detonator 3.

[0022] When used, a blasting device for blasting an open-pit thin-layer ore body based on Example 1 can achieve the following: the rock blockiness of the thin-layer ore body can be significantly improved after blasting, the powder content of the aggregate can be significantly reduced, the crushing degree is uniform without the production of obvious large pieces and low heels, and at the same time, the use of explosives is reduced, the unit consumption of explosives is reduced, the cost of ore mining is directly reduced, and the economic benefits of engineering blasting are improved.

[0023] Embodiment 2

[0024] A method for using a blasting device for blasting an open-pit thin-layer ore body. Compared with the first embodiment, this embodiment also includes: (1) determining the length and width of the blasting area of ​​the open-pit thin-layer ore body; (2) designing blasting parameters; (3) on-site hole position layout; (4) drilling and hole inspection by a drilling rig; (5) blasting operation; (6) ore mining and transportation; (7) determination of the powder content of finished aggregate products. The scope of the blasting area is determined by the size of the mine and the production capacity requirements. The width of the blasting area does not exceed 4 rows to ensure the effect of the blasting pile throwing after the blasting. The platform within the blasting area must be cleaned so that the drilling rig has safe drilling conditions. The blasting hole positions are arranged in a plum blossom pattern, with a hole spacing of 9 meters, a row spacing of 5.5 meters, a minimum resistance line of 5 meters, and the hole positions are regular and orderly and marked and numbered.

[0025] In this embodiment:

[0026] Step (1) Determine the length and width of the blasting zone of the open-pit thin-layer ore body: Determine the length and width of the blasting zone according to the size of the mine and the production capacity requirements, and conduct on-site measurement and platform cleaning to ensure that the drilling rig has the conditions for drilling operations. The open-pit thin-layer ore body is composed of a thin layer of rock with a thickness of 8-15 cm. The diameter of the drill hole is 203 mm, and the width of the blasting zone does not exceed 4 rows of blast holes.

[0027] Step (2) Design blasting parameters: Determine blasting parameters based on the mine bench height, slope angle, geological characteristics of rock, conditions of different mining machinery and equipment, and other constraints. Blasting parameters include: hole diameter, hole depth, over-depth, chassis resistance line, minimum resistance line, hole spacing, row spacing, filling length, and explosive unit consumption. The mine bench height H is 15 meters, the slope angle is 75°, the over-depth is 2.0 meters, the blasthole depth is 17.5 meters, the hole spacing is 9 meters, the row spacing is 5.5 meters, and the minimum resistance line is 5 meters.

[0028] Step (3) On-site hole layout: The hole layout must be strictly determined in accordance with the requirements of the minimum resistance line, hole spacing, and row spacing design values. The holes must be arranged in an orderly manner and marked and numbered. The number of rows of holes should not exceed four.

[0029] Step (4) Drilling and hole inspection: The blastholes must be drilled strictly according to the designed hole position, drilling angle and depth, and shall not be changed at will. After the drilling is completed, the blastholes are inspected and checked, and the blastholes that do not meet the design requirements are recorded and reprocessed, and special holes such as caves and fissures are marked.

[0030] Step (5) Blasting operation: During the blasting operation, the inspection of pyrotechnic materials, blasthole charging, blasthole filling, blasthole delay time setting, network connection, blasting initiation and post-blasting inspection operations shall be carried out in accordance with the design requirements. The charging height of the first and second rows of blastholes is 11.5 meters, and the filling height is 6 meters; the charging height of the third and fourth rows is 10 meters, and the filling height is 7.5 meters. The material used for filling is blasthole rock cuttings. The blasting initiation is multi-point initiation in the hole. The first initiation point is 2 meters above the bottom of the hole, and the second initiation point is 9.5 meters above the bottom of the hole. The detonator selected for the network connection is a digital electronic detonator. The blastholes are initiated hole by hole. The delay time between the first row of blastholes is 17 ms, the delay time between the second row of blastholes is 42 ms, and the delay time between the third and fourth rows of blastholes is 65 ms.

[0031] Step (6) Ore mining and transportation: After the explosion inspection to confirm that there are no safety issues, arrange for shoveling and transportation equipment to carry out the mine and transportation.

[0032] Step (7) Determination of powder content of finished aggregate: After crushing and screening, the ore enters the finished product warehouse with different particle sizes. The powder content of the finished aggregate is calculated by the mass ratio of the different particle sizes entering the warehouse. The crushing and screening particle sizes are 0-6mm, 6-15mm, and 15-22mm.

[0033] The above description is only a preferred embodiment of the utility model and does not impose any form of limitation on the utility model. Any ordinary technician in the industry can smoothly implement the utility model as shown in the drawings of the specification and described above. However, any equivalent changes, modifications and evolutions made by technicians familiar with the profession without departing from the scope of the technical solution of the utility model using the technical content disclosed above are all equivalent embodiments of the utility model. At the same time, any equivalent changes, modifications and evolutions made to the above embodiments based on the essential technology of the utility model are still within the protection scope of the technical solution of the utility model.

Claims

1. A blasting device for blasting thin-layer ore bodies in an open air, characterized in that: The utility model comprises a detonator leg wire (1), rock cuttings (2), an electric detonator (3), civil explosives (4) and an outer shell (5); the rock cuttings (2) and the civil explosives (4) are arranged in the outer shell (5), and the rock cuttings (2) and the civil explosives (4) are cross-distributed in the outer shell (5); the civil explosives (4) are arranged in the electric detonator (3), and the electric detonator (3) is connected to an external power supply through the detonator leg wire (1).

2. The blasting device for blasting thin-layer ore bodies in an open-pit according to claim 1, characterized in that: The number of the detonator leg wires (1) and the electric detonators (3) corresponds to the number of the civilian explosives (4).

3. The blasting device for blasting thin-layer ore bodies in an open-pit according to claim 1, characterized in that: Two rock cuttings (2) and civil explosives (4) are respectively arranged in the shell (5), and the length of the upper rock cuttings (2) in the shell (5) is greater than the length of the lower rock cuttings (2), and the length of the upper civil explosives (4) in the shell (5) is less than the length of the lower civil explosives (4).

4. The blasting device for blasting thin-layer ore bodies in an open-pit according to claim 1, characterized in that: The detonator leg wire (1) penetrates the rock cuttings (2) and is electrically connected to the electric detonator (3).