Underground ventilation device
By adopting a height-adjustable installation method in the underground ventilation device, the problem of cumbersome maintenance operations caused by fixed installation is solved, and the overall stability and maintenance efficiency of the ventilation equipment are improved.
Patent Information
- Application Number
- CN202420336921.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-23
- Publication Date
- 2024-10-08
- Estimated Expiration
- 2034-02-23
AI Technical Summary
Due to the fixed installation method of existing underground ventilation devices, maintenance operations are cumbersome and it is difficult to ensure overall maintenance efficiency, requiring frequent movement of lifting equipment.
An underground ventilation device including a fixed plate, connecting pin, installation sleeve, fixed frame, bearing plate, screw rod and ventilation assembly is designed. It is fixed on the underground side wall through a height-adjustable installation method, which simplifies the installation of ventilation equipment. and maintenance processes.
It achieves stable installation and flexible adjustment of ventilation equipment, improves maintenance efficiency, and facilitates maintenance and maintenance operations by staff.
Smart Images

Figure CN221810841U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of ventilation equipment, in particular to an underground ventilation device. Background Art
[0002] Underground ventilation devices for preventing geological disasters play a very important role in underground workplaces such as coal mines. They can effectively improve the safety and production efficiency of workers. Underground ventilation devices usually include main fans, auxiliary fans, dampers, air ducts and other components.
[0003] At present, most underground ventilation devices for preventing geological disasters are installed on the top of the tunnel in a fixed manner. In order to ensure the overall stability of the ventilation device, the ventilation device needs to be maintained regularly. The top fixed installation method requires workers to use lifting equipment to perform maintenance operations. The overall operation is cumbersome and the lifting equipment needs to be moved frequently, which makes it difficult to ensure the overall maintenance efficiency of the ventilation equipment. Utility Model Content
[0004] The utility model aims to provide an underground ventilation device specially used for preventing geological disasters, which is convenient for maintenance and improves the overall stability of the ventilation device.
[0005] To achieve the above objectives, the utility model is implemented through the following technical solutions: an underground ventilation device, comprising a fixing plate and four first connecting pins, wherein the four first connecting pins are respectively embedded at the four corners of the fixing plate, and a ventilation adjustment structure is provided on one side of the fixing plate;
[0006] The regulating ventilation structure comprises two mounting sleeves, a fixing frame, a bearing plate, a screw rod and a ventilation assembly;
[0007] The two mounting sleeves are both installed on the wall surface of one side of the fixed plate, and the two sides of the bottom end of the fixed frame are movably embedded in the two mounting sleeves respectively. The two ends of the bearing plate are respectively connected to the side walls of the two mounting sleeves. One end of the screw rod is movably embedded in the bearing plate, and the other end is movably embedded in the center of the upper end of the fixed frame. The ventilation assembly is movably mounted on the screw rod and the upper end of the fixed frame.
[0008] Preferably, the ventilation assembly comprises a moving block, a ventilation sleeve and two ventilation fans;
[0009] The moving block is movably sleeved on the screw rod and the upper end of the fixed frame, the ventilation sleeve is fixedly installed on a wall surface of one side of the moving block, and the two ventilation fans are respectively installed on both sides of the ventilation sleeve.
[0010] Preferably, an operating handle is provided at the bottom end of the screw rod.
[0011] Preferably, an operation opening is provided at the center of the lower end of the fixing plate.
[0012] Preferably, second connecting pins are provided on both sides of the upper end of the fixing frame.
[0013] Preferably, a fixing bolt is embedded in one side wall of the mounting sleeve.
[0014] The beneficial effects of the utility model are as follows: by setting up multiple first connecting pins and second connecting pins, the device is fixed to the side wall of the well, and a height-adjustable installation method is adopted. According to different usage requirements, the installation height of the ventilation equipment is adjusted to ensure the overall application range of the ventilation equipment, and at the same time, it is convenient for subsequent staff to carry out maintenance on the ventilation equipment, thereby ensuring the overall maintenance efficiency of the ventilation equipment. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a schematic diagram of the main three-dimensional structure of the utility model.
[0016] Figure 2 It is a rear-view stereoscopic structural schematic diagram of the utility model.
[0017] In the figure: 1. fixing plate, 2. first connecting pin, 3. mounting sleeve, 4. fixing frame, 5. bearing plate, 6. screw rod, 7. moving block, 8. ventilation sleeve, 9. ventilation fan, 10. operating handle, 11. operating opening, 12. second connecting pin, 13. fixing bolt. DETAILED DESCRIPTION
[0018] Based on the embodiments of the present utility model, all other embodiments obtained by ordinary technicians in the field without making any creative work shall fall within the scope of protection of the present utility model.
[0019] like Figure 1-2 As shown, an underground ventilation device includes a fixed plate 1 and four first connecting pins 2. The four first connecting pins 2 are respectively embedded in the four corners of the fixed plate 1, and a ventilation adjustment structure is provided on one side of the fixed plate 1.
[0020] The adjustable ventilation structure is mainly composed of two mounting sleeves 3, a fixing frame 4, a bearing plate 5, a screw rod 6 and a ventilation assembly.
[0021] The two mounting sleeves 3 are both installed on the wall surface of one side of the fixed plate 1, and the two sides of the bottom end of the fixed frame 4 are movably embedded in the two mounting sleeves 3 respectively. The two ends of the bearing plate 5 are respectively connected to the side walls of the two mounting sleeves 3. One end of the screw rod 6 is movably embedded in the bearing plate 5, and the other end is movably embedded in the center of the upper end of the fixed frame 4. The ventilation component is movably mounted on the screw rod 6 and the upper end of the fixed frame 4.
[0022] The ventilation assembly is mainly composed of a moving block 7 , a ventilation sleeve 8 and two ventilation fans 9 .
[0023] The moving block 7 is movably sleeved on the screw rod 6 and the upper end of the fixed frame 4 , the ventilation sleeve 8 is fixedly installed on a wall surface of one side of the moving block 7 , and two ventilation fans 9 are respectively installed on both sides of the ventilation sleeve 8 .
[0024] In order to ensure the ventilation effect underground and ensure the stability of use and scope of application of the ventilation equipment, an adjustable ventilation structure is set. The specific working principle is as follows: during installation, the staff first fixes the fixed plate 1 at the specified position of the underground side wall through the first connecting pin 2 according to the use requirements, and then embeds the fixed frame 4 into the two installation sleeves 3, and fixes the fixed frame 4 through the fixing bolts 13 to ensure the installation stability of the fixed frame 4; then, the upper end of the fixed frame 4 is connected to the underground side wall through the second connecting pin 12 to further ensure the stability of the fixed frame 4, and then the bearing plate 5 and the screw rod 6 in the fixed frame 4 are screwed to change the overall height of the moving block 7 by rotating the screw rod 6, and the height of the ventilation sleeve 8 is adjusted. The two ventilation fans 9 in the ventilation sleeve 8 work synchronously to achieve the purpose of ventilation underground; when the ventilation equipment is subsequently maintained, the staff changes the overall height of the ventilation sleeve 8 by screwing the screw rod 6 to facilitate the maintenance of the ventilation equipment.
[0025] In the specific implementation process, an operating handle 10 is provided at the bottom end of the screw rod 6; an operating opening 11 is provided at the center of the lower end of the fixing plate 1; second connecting pins 12 are provided on both sides of the upper end of the fixing frame 4; and a fixing bolt 13 is embedded in the wall of one side of the mounting sleeve 3.
[0026] The screw rod 6 can be quickly operated through the opened operation opening 11 and the operation handle 10. The operation space of the operation handle 10 is increased through the opened operation opening 11. The bottom end of the screw rod 6 is provided with an operation handle 10, the center of the lower end of the fixing plate 1 is provided with an operation opening 11, second connecting pins 12 are provided on both sides of the upper end of the fixing frame 4, and a fixing bolt 13 is embedded in the wall of one side of the mounting sleeve 3.
[0027] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A downhole ventilation device, comprising a fixing plate (1) and four first connecting pins (2), characterized in that: The four first connecting pins (2) are respectively embedded at the four corners of the fixing plate (1), and a ventilation adjustment structure is provided on one side of the fixing plate (1); The adjustable ventilation structure comprises two mounting sleeves (3), a fixing frame (4), a bearing plate (5), a screw rod (6) and a ventilation assembly; The two mounting sleeves (3) are both mounted on a side wall of the fixing plate (1); the two sides of the bottom end of the fixing frame (4) are movably embedded in the two mounting sleeves (3); the two ends of the bearing plate (5) are respectively connected to the side walls of the two mounting sleeves (3); one end of the screw rod (6) is movably embedded in the bearing plate (5); the other end is movably embedded in the center of the upper end of the fixing frame (4); and the ventilation component is movably sleeved on the screw rod (6) and the upper end of the fixing frame (4).
2. The underground ventilation device according to claim 1, characterized in that: The ventilation assembly comprises a moving block (7), a ventilation sleeve (8) and two ventilation fans (9); The movable block (7) is movably sleeved on the screw rod (6) and the upper end of the fixed frame (4); the ventilation sleeve (8) is fixedly mounted on a wall surface on one side of the movable block (7); and the two ventilation fans (9) are respectively mounted on both sides of the ventilation sleeve (8).
3. The underground ventilation device according to claim 1, characterized in that: An operating handle (10) is provided at the bottom end of the screw rod (6).
4. The underground ventilation device according to claim 1, characterized in that: An operating opening (11) is provided at the center of the lower end of the fixing plate (1).
5. The underground ventilation device according to claim 1, characterized in that: Second connecting pins (12) are provided on both sides of the upper end of the fixed frame (4).
6. The underground ventilation device according to claim 1, characterized in that: A fixing bolt (13) is embedded in a wall surface on one side of the installation sleeve (3).