Pipeline replacement device in complex environment

By designing a pipeline replacement device in a complex environment that includes hangers, generator sets, supporting steel plates, hydraulic jacks, pilot drills, tie rods and hydraulic tractors, the problem that underground pipelines cannot be repaired without excavation is solved and efficient Pipe replacement reduces impact on surrounding environment.

CN221824646UActive Publication Date: 2024-10-11SINOHYDRO BUREAU 14 CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420409544.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-04
Publication Date
2024-10-11
Estimated Expiration
2034-03-04

AI Technical Summary

Technical Problem

In complex environments, underground pipelines cannot be repaired through open excavation due to problems such as blockage, collapse, deformation, and dislocation, and excavation construction cannot be used due to environmental restrictions. There is an urgent need for a pipeline replacement method that does not require excavation.

Method used

A pipeline replacement device including a hanger, a generator set, a supporting steel plate, a hydraulic jack, a pilot drill bit, a pull rod and a hydraulic tractor is designed. Through the linkage of the hydraulic jack and the hydraulic tractor, the pilot drill bit and pull rod are used to realize the short pipe in the pipeline. Pushing and pulling, combined with rubber waterstops and air bags, realize pipe replacement without excavation.

Benefits of technology

It improves the installation efficiency of pipeline replacement, reduces the impact on surrounding traffic, realizes pipeline replacement without excavation construction, has a simple structure and is easy to operate.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221824646U_ABST
    Figure CN221824646U_ABST
Patent Text Reader

Abstract

The utility model discloses a pipeline replacement device in a complex environment, which comprises a hanging bracket, a generator set, a supporting steel plate, a hydraulic jack, a guide drill bit, a pull rod and a hydraulic traction machine, the generator set is placed near a wellhead of the drainage inspection well and electrically connected with the hydraulic jack and the hydraulic traction machine, the supporting steel plate is fixedly connected with a pipeline opening in the bottom of the drainage inspection well, the hydraulic jack is placed at the bottom of the drainage inspection well, and the guide drill bit is in sliding connection with a rod body of the pull rod. The two ends of the pull rod are fixedly connected with the hydraulic jack and the hydraulic traction machine respectively, and the hydraulic traction machine is placed at the bottom of the other adjacent drainage inspection well and connected with the guide drill bit. The pipeline replacement device in the complex environment is simple in structure, convenient to operate and capable of completing pipeline replacement operation without excavation construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of municipal engineering construction, and specifically relates to a pipeline replacement device in a complex environment. Background Art

[0002] With the continuous development of urban municipal pipeline networks, underground pipelines are complex and diverse. In addition, the drainage pipelines built earlier in the city have been blocked, collapsed, deformed, dislocated and other defects due to the baptism of time, the discharge of wastewater, and the failure to dredge and clean them in time for many years. Due to the complex distribution and variety of underground pipelines and the limitations of the surrounding environment, it is impossible to repair defective pipelines by open excavation. Therefore, there is an urgent need for a device that can complete the replacement of pipelines without excavation to solve the above problems. Utility Model Content

[0003] The technical problem to be solved by the utility model is to provide a pipeline replacement device which has a simple structure, is easy to operate and can complete the pipeline replacement operation without excavation construction.

[0004] The technical solution of the utility model is: a pipeline replacement device under complex environment, including: a hanger, a generator set, a support steel plate, a hydraulic jack, a guide drill bit, a pull rod, and a hydraulic traction machine. The hanger is placed at the wellhead of a drainage inspection well, the generator set is placed near the wellhead of the drainage inspection well and is electrically connected to the hydraulic jack and the hydraulic traction machine, the support steel plate is fixedly connected to a pipe opening at the bottom of the drainage inspection well, the hydraulic jack is placed at the bottom of the drainage inspection well and is located on one side of the support steel plate, the guide drill bit is slidably connected to the rod body of the pull rod, and the two ends of the pull rod are respectively fixedly connected to the hydraulic jack and the hydraulic traction machine, and the hydraulic traction machine is placed at the bottom of another adjacent drainage inspection well and is connected to the guide drill bit.

[0005] Furthermore, a gasket is provided on the hydraulic jack, and the pull rod passes through the gasket.

[0006] Furthermore, a plurality of rubber water stop rings are arranged on the pull rod, and the plurality of rubber water stop rings are located between the hydraulic jack and the tail of the guide drill bit, and the front and back sides of the rubber water stop rings are respectively connected to the ends of adjacent short pipes.

[0007] Furthermore, an air bag and a blocking wall are provided on the other side of the supporting steel plate, and the air bag is attached to the blocking wall.

[0008] Beneficial effects of the utility model: a pipe replacement device under a complex environment of the utility model places a hydraulic jack and a hydraulic traction machine in two adjacent drainage inspection wells respectively and connects them with a pull rod, and a guide drill bit is arranged on the pull rod to achieve the technical effect of pushing one end of the short pipe in the pipe in the drainage inspection well and pulling the other end, which effectively improves the replacement and installation efficiency of the pipe and does not require excavation construction, with little impact on surrounding traffic. In summary, a pipe replacement device under a complex environment of the utility model has a simple structure and is easy to operate, and the pipe replacement operation can be completed without excavation construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0009] In order to more clearly illustrate the technical solutions in the embodiments of the utility model or the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0010] Figure 1 It is a structural schematic diagram of a pipeline replacement device in a complex environment according to the utility model.

[0011] In the figure: 1- switch, 2- hanger, 3- generator set, 4- supporting steel plate, 5- hydraulic jack, 6- short pipe, 7- gasket, 8- rubber water stop ring, 9- guide drill bit, 10- pull rod, 11- hydraulic traction machine, 12- air bag, 13- blocking wall, 14- drainage inspection well. DETAILED DESCRIPTION

[0012] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the term "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection, a direct connection, an indirect connection through an intermediate medium, or the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0013] like Figure 1As shown, a pipeline replacement device for a complex environment includes: a hanger 2, a generator set 3, a support steel plate 4, a hydraulic jack 5, a guide drill bit 9, a pull rod 10, and a hydraulic traction machine 11. The hanger 2 is placed at the wellhead of a drainage inspection well 14, the generator set 3 is placed near the wellhead of the drainage inspection well 14 and is electrically connected to the hydraulic jack 5 and the hydraulic traction machine 11, the support steel plate 4 is fixedly connected to a pipe opening at the bottom of the drainage inspection well 14, the hydraulic jack 5 is placed at the bottom of the drainage inspection well 14 and is located on one side of the support steel plate 4, the guide drill bit 9 is slidably connected to the rod body of the pull rod 10, and the two ends of the pull rod 10 are respectively fixedly connected to the hydraulic jack 5 and the hydraulic traction machine 11, and the hydraulic traction machine 11 is placed at the bottom of another adjacent drainage inspection well 14 and is connected to the guide drill bit 9.

[0014] Preferably, a gasket 7 is provided on the hydraulic jack 5 , and the pull rod 10 passes through the gasket 7 .

[0015] Preferably, a plurality of rubber water stop rings 8 are provided on the pull rod 10 , and the plurality of rubber water stop rings 8 are located between the hydraulic jack 5 and the tail of the guide drill bit 9 , and the front and back sides of the rubber water stop rings 8 are respectively connected to the ends of the adjacent short tubes 6 .

[0016] Preferably, an air bag 12 and a blocking wall 13 are provided on the other side of the supporting steel plate 4 , and the air bag 12 is in contact with the blocking wall 13 .

[0017] When in use, the hydraulic jack 5 is pushed into the conical guide drill bit 9 into the drainage inspection well 14 pipeline. The operator goes down the well to install the hydraulic jack 5 back support steel plate 4, and fixes the support steel plate 4 in the inspection well. The hydraulic jack 5 is firmly fixed to ensure that the equipment will not move during operation. The assembly process needs to be completed in the drainage inspection well 14. First, the conical guide drill bit 9 is connected to the pull rod 10, and the first section of the short tube 6 is inserted into the tail of the guide drill bit 9. The pad 7 with the same diameter as the outer diameter of the short tube 6 is fixed to the piston of the hydraulic jack 5, and then connected to the short tube 6. The pull rod 10 passes through the guide drill bit 9, the short tube 6, and the pad 7, and is fixed to the hydraulic jack 5 with a pin to form an overall force. After the assembly is completed, the jacking operation can be started.

[0018] When the short pipe 6 starts to be pushed forward, the guide drill bit 9 is pulled by the traction machine, and the short pipe 6 is slowly pushed forward by the hydraulic jack 5, and the operation is carried out slowly and synchronously. It is not advisable to operate too fast to avoid deviation in the pushing process;

[0019] When the tail of the first short pipe 6 is pushed into the position of the pipe mouth, stop pushing, remove the tie rod 10 pin and the pad 7, retract the pushing end of the hydraulic jack 5, and then assemble the second short pipe 6, retract the traction end of the hydraulic traction machine 11, remove the first tie rod 10, and start the pushing operation of the second short pipe 6 according to the operation process of the first short pipe 6, and repeat the operation by analogy; when splicing the short pipe 6, pay attention to the rubber water stop ring 8 to be installed in place to avoid water seepage after falling off;

[0020] At the connection position of each section of the short pipe 6, a rubber water stop ring 8 is inserted into the inner diameter of the short pipe 6, and then spliced ​​together. At the same time, the first section of the pull rod 10 in the downstream drainage inspection well 14 is removed, and so on; when the conical guide drill bit 9 in the downstream drainage inspection well 13 pushes out of the pipe mouth, the guide drill bit 9 is removed and lifted out of the drainage inspection well 14, and the last section of the jacking operation is continued. After the jacking operation is completed, the pull rods 10 are first removed one by one, and then the pad 7 and the remaining equipment are removed; after the short pipe 6 is installed, cement slurry is used to fill the gap between the new and old pipes, and chemical grouting is used to carry out anti-seepage treatment on the docking joint to ensure that the new and old pipes work together to achieve double protection.

[0021] The embodiments of the present invention are described in detail above with reference to the accompanying drawings, but the present invention is not limited to the above embodiments and various changes can be made thereto within the knowledge scope of those skilled in the art.

Claims

1. A pipeline replacement device in a complex environment, characterized in that: include: A hanger (2), a generator set (3), a support steel plate (4), a hydraulic jack (5), a guide drill bit (9), a pull rod (10), and a hydraulic traction machine (11). The hanger (2) is placed at the wellhead of a drainage inspection well (14). The generator set (3) is placed near the wellhead of the drainage inspection well (14) and is electrically connected to the hydraulic jack (5) and the hydraulic traction machine (11). The support steel plate (4) is fixedly connected to a pipe opening at the bottom of the drainage inspection well (14). The hydraulic jack (5) is placed at the bottom of the drainage inspection well (14) and is located on one side of the support steel plate (4). The guide drill bit (9) is slidably connected to the rod body of the pull rod (10). The two ends of the pull rod (10) are respectively fixedly connected to the hydraulic jack (5) and the hydraulic traction machine (11). The hydraulic traction machine (11) is placed at the bottom of another adjacent drainage inspection well (14) and is connected to the guide drill bit (9).

2. The pipeline replacement device in complex environment according to claim 1, characterized in that: A gasket (7) is provided on the hydraulic jack (5), and the pull rod (10) passes through the gasket (7).

3. The pipeline replacement device in complex environment according to claim 1 is characterized in that: A plurality of rubber water stop rings (8) are provided on the pull rod (10), and the plurality of rubber water stop rings (8) are located between the hydraulic jack (5) and the tail of the guide drill bit (9), and the front and back surfaces of the rubber water stop rings (8) are respectively connected to the ends of adjacent short tubes (6).

4. The pipeline replacement device in complex environment according to claim 1, characterized in that: An air bag (12) and a blocking wall (13) are provided on the other side of the supporting steel plate (4), and the air bag (12) is in contact with the blocking wall (13).