Floor slab deformation dynamic monitoring equipment support

By designing an adjustable floor deformation dynamic monitoring equipment bracket and using prefabricated connecting rods and support structures, the problem of low monitoring efficiency in the existing technology is solved, and rapid assembly and high stability monitoring effects are achieved.

CN221824877UActive Publication Date: 2024-10-11SICHUAN RUIYI ZHUOHENG ELECTRIC POWER ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323575478.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-26
Publication Date
2024-10-11
Estimated Expiration
2033-12-26

AI Technical Summary

Technical Problem

The existing dynamic monitoring equipment for floor deformation requires the erection of steel pipe racks of different heights, resulting in low monitoring efficiency and time-consuming and labor-intensive monitoring.

Method used

Design a floor deformation dynamic monitoring equipment bracket that includes a base and positioning rods. By prefabricating multiple connecting rods of different lengths, the positioning rods are assembled according to the floor height, and combined with structures such as support rods and fixed magnets to improve the stability and firm connection of the bracket. properties, simplifying the installation process.

Benefits of technology

It realizes rapid assembly and fine-tuning of the positioning rod, improves monitoring efficiency, enhances the stability of the bracket and the firmness of the connection, making it easy to transport and use.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221824877U_ABST
    Figure CN221824877U_ABST
Patent Text Reader

Abstract

The utility model discloses a floor deformation dynamic monitoring equipment support, which comprises a base and a positioning rod mounted on the base, the positioning rod comprises a mounting rod, a connecting rod and a fixing rod, the fixing rod is mounted on the base, one end of the connecting rod is connected with a connecting screw rod, and the other end of the connecting rod is connected with a rotating shaft; the upper end of the fixing rod is provided with a connecting hole in threaded connection with the connecting screw rod, the mounting rod is connected with a mounting screw rod, the connecting rod is provided with a mounting hole in threaded connection with the mounting screw rod, and the base is connected with a fixing cylinder allowing the fixing rod to be inserted therein. The connecting rod is a prefabricated part, a plurality of connecting rods with different lengths are prefabricated, people can select the connecting rod with the proper length according to the height of a floor, after the positioning rod is assembled, the mounting rod is rotated, the height of the positioning rod is finely adjusted, the dial indicator is mounted on the mounting rod after adjustment, time and labor are saved in the whole process, and the monitoring efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of building monitoring, and in particular to a floor deformation dynamic monitoring equipment bracket. Background Art

[0002] In recent years, the renovation and reconstruction of existing buildings has become more and more frequent, which has put forward higher requirements for the safety of house structures. As time goes by, the house structure will also age, be damaged or have performance degradation due to various factors. In order to ensure the safe use of the house, the safety of the house needs to be evaluated before the house is renovated or reconstructed. Among them, the bearing capacity of the floor slab is particularly important in the evaluation. The bearing capacity of the floor slab is mainly determined by pre-adding a constant load and dynamically monitoring the deformation of the floor slab. At present, the widely used method is to monitor the floor slab with a dial indicator. After the steel pipe rack is set up on the ground, the dial indicator is installed on the upper end of the steel pipe rack, and the floor slab is dynamically monitored by the dial indicator.

[0003] With respect to the above-mentioned related technologies, the inventors believe that the following defects exist: the heights of the floors are different, and steel pipe racks of different heights need to be erected each time, which is time-consuming and labor-intensive, affects the monitoring efficiency, and therefore needs to be improved. Utility Model Content

[0004] In view of the deficiencies in the prior art, the present application provides a floor deformation dynamic monitoring equipment bracket, aiming to solve the above problems.

[0005] A bracket for dynamic monitoring equipment of floor deformation comprises a base and a positioning rod installed on the base, the positioning rod comprises a mounting rod, a connecting rod and a fixing rod, the fixing rod is installed on the base, one end of the connecting rod is connected to a connecting screw, the upper end of the fixing rod is provided with a connecting hole threadedly connected to the connecting screw, the mounting rod is connected to a mounting screw, the connecting rod is provided with a mounting hole threadedly connected to the mounting screw, and the base is connected to a fixing tube for inserting the fixing rod.

[0006] By adopting the above technical solution, the connecting rod is a prefabricated part, and a plurality of connecting rods of different lengths are prefabricated. People can choose a connecting rod of appropriate length according to the floor height. First, place the base on the ground, then insert the fixing rod into the fixing tube on the base, screw the connecting screw on the connecting rod into the connecting hole, and then screw the mounting screw on the mounting rod into the mounting hole. The positioning rod can be assembled, the mounting rod can be rotated to fine-tune the height of the positioning rod. After adjustment, the dial indicator can be installed on the mounting rod to start monitoring. The whole process saves time and labor and improves monitoring efficiency.

[0007] Optionally, the circumferential outer side wall of the fixing rod is provided with at least three supporting grooves spaced equidistantly around its own axial center line direction, and a supporting rod is hinged on the inner side wall of each supporting groove.

[0008] By adopting the above technical solution, the support rod is rotated out of the support groove, and then the fixing rod is inserted into the fixing tube, and the end of the support rod is fixed on the ground. The support rod can provide supporting force for the fixing rod, thereby improving the stability of the bracket.

[0009] Optionally, a fixing block is connected to the outer wall of each support rod, and the fixing tube is provided with fixing grooves with the same number as the support rods for the fixing blocks to snap into and slide, and an elastic fastening pad is connected to the inner wall of the fixing groove, and the fastening pad presses against the outer wall of the fixing block.

[0010] By adopting the above technical solution, after the support rod is stored in the support groove, the fixing rod is then inserted into the fixing tube, so that the fixing block on the support rod is inserted into the fixing groove, and the fastening pad clamps the fixing block, thereby limiting the fixing rod from accidentally detaching from the fixing tube, thereby improving the connection firmness between the fixing rod and the base, and facilitating the transportation of the fixing rod and the base.

[0011] Optionally, a fixed magnet is connected to the support rod, a clearance groove for the fixed magnet to be inserted into is formed on the inner side wall of the support groove, and a metal block for the fixed magnet to be adsorbed is connected to the bottom wall of the clearance groove.

[0012] By adopting the above technical solution, the support rod is received into the support groove, the fixed magnet on the support rod is inserted into the clearance groove, and the fixed magnet is adsorbed on the metal block, thereby preventing the support rod from accidentally falling out of the support groove.

[0013] Optionally, a fastening spring is connected to the bottom wall of the connecting hole, and one end of the fastening spring is connected to a fastening plate for tightening the connecting screw.

[0014] By adopting the above technical solution, after the connecting screw is screwed into the connecting hole, the fastening plate presses against the connecting screw, thereby applying a pressing force to the connecting screw to prevent the connecting screw from rotating.

[0015] Optionally, a non-slip pad is connected to the lower end surface of the base.

[0016] By adopting the above technical solution, the anti-skid pad can improve the anti-skid performance of the base, thereby preventing the base from slipping as much as possible.

[0017] In summary, the present application includes at least one of the following beneficial technical effects:

[0018] 1. The connecting rod is a prefabricated part. Multiple connecting rods of different lengths are prefabricated. People can choose the appropriate length of connecting rod according to the floor height. First, place the base on the ground, then insert the fixing rod into the fixing tube on the base, screw the connecting screw on the connecting rod into the connecting hole, and then screw the mounting screw on the mounting rod into the mounting hole. The positioning rod can be assembled. Turn the mounting rod to fine-tune the height of the positioning rod. After adjustment, install the dial indicator on the mounting rod to start monitoring. The whole process saves time and effort and improves monitoring efficiency.

[0019] 2. Turn the support rod out of the support groove, then insert the fixing rod into the fixing tube, and fix the end of the support rod on the ground. The support rod can provide supporting force to the fixing rod, thereby improving the stability of the bracket.

[0020] 3. After storing the support rod in the support groove, insert the fixing rod into the fixing tube so that the fixing block on the support rod is inserted into the fixing groove and the fastening pad clamps the fixing block, thereby limiting the fixing rod from accidentally detaching from the fixing tube, thereby improving the connection firmness between the fixing rod and the base, and facilitating the transportation of the fixing rod and the base. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 It is a schematic diagram of the structure of an embodiment of the present application.

[0022] Figure 2 It is a schematic diagram of the structure of the embodiment of the present application in the storage state.

[0023] Figure 3 It is an exploded schematic diagram of an embodiment of the present application.

[0024] Figure 4 yes Figure 3 A magnified schematic diagram of area A in the middle.

[0025] Description of reference numerals:

[0026] 1. Base; 11. Fixing tube; 111. Fixing groove; 112. Fastening pad; 2. Positioning rod; 3. Mounting rod; 31. Mounting screw; 4. Connecting rod; 41. Connecting screw; 42. Mounting hole; 5. Fixing rod; 51. Supporting groove; 511. Giving groove; 512. Metal block; 52. Supporting rod; 521. Fixing block; 522. Fixing magnet; 53. Connecting hole; 6. Fastening spring; 61. Fastening plate; 7. Anti-slip pad. DETAILED DESCRIPTION

[0027] In order to facilitate the understanding of the present application, the present application is described in more detail below in conjunction with the accompanying drawings and specific embodiments. It should be noted that when an element is described as "fixed to" another element, it can be directly on the other element, or there can be one or more centered elements therebetween. When an element is described as "connected to" another element, it can be directly connected to the other element, or there can be one or more centered elements therebetween. The terms "vertical", "horizontal", "left", "right" and similar expressions used in this specification are for illustrative purposes only.

[0028] Unless otherwise defined, all technical and scientific terms used in this specification have the same meaning as those commonly understood by those skilled in the art to which this application belongs. The terms used in the specification of this application are only for the purpose of describing specific embodiments and are not intended to limit this application. The term "and / or" used in this specification includes any and all combinations of one or more of the related listed items.

[0029] The present application embodiment discloses a floor deformation dynamic monitoring equipment bracket. Figure 1 and Figure 2 , including a base 1 and a positioning rod 2 installed on the base 1.

[0030] Reference Figure 2 The lower end surface of the base 1 is fixedly connected with an anti-skid pad 7, which is made of rubber material. The anti-skid pad 7 can improve the anti-skid performance of the base 1, thereby preventing the base 1 from slipping as much as possible.

[0031] Reference Figure 2 and Figure 3The positioning rod 2 includes a mounting rod 3, a connecting rod 4 and a fixing rod 5, and the fixing rod 5 is detachably connected to the base 1. A connecting screw 41 is fixedly connected to one end of the connecting rod 4, and a connecting hole 53 threadedly connected to the connecting screw 41 is provided at the upper end of the fixing rod 5. A mounting screw 31 is fixedly connected to the mounting rod 3, and a mounting hole 42 threadedly connected to the mounting screw 31 is provided on the connecting rod 4. A fixing tube 11 for inserting the fixing rod 5 is fixedly connected to the base 1, and the cross sections of the fixing rod 5 and the fixing tube 11 are both rectangular. The fixing rod 5 is inserted into the fixing tube 11, and the circumferential outer wall of the fixing rod 5 is in close contact with the circumferential inner wall of the fixing tube 11. The connecting rod 4 is a prefabricated part, and the connecting rods 4 of 0.5 meters, 1 meter and 1.5 meters are prefabricated. People can choose the connecting rod 4 of appropriate length according to the floor height. First, place the base 1 on the ground, then insert the fixing rod 5 into the fixing tube 11 on the base 1, screw the connecting screw 41 on the connecting rod 4 into the connecting hole 53, and then screw the mounting screw 31 on the mounting rod 3 into the mounting hole 42, and the positioning rod 2 can be assembled. Turn the mounting rod 3 to fine-tune the height of the positioning rod 2. After adjustment, install the dial indicator on the mounting rod 3 to start monitoring. The whole process saves time and effort and improves monitoring efficiency.

[0032] Reference Figure 2 and Figure 3 The outer circumferential wall of the fixing rod 5 is provided with four support grooves 51 at equal intervals around its own axis direction, each support groove 51 is arranged along the length direction of the fixing rod 5, and a support rod 52 is hinged on the inner wall of each support groove 51. The support rod 52 is rotated out of the support groove 51, and then the fixing rod 5 is inserted into the fixing tube 11, so that one end of the support rod 52 is fixed on the ground, and the support rod 52 can provide support force to the fixing rod 5, thereby improving the stability of the bracket.

[0033] Reference Figure 3 and Figure 4 The support rod 52 is fixedly connected with a fixed magnet 522, and the inner side wall of the support groove 51 is provided with a clearance groove 511 for the fixed magnet 522 to be inserted into. The bottom wall of the clearance groove 511 is fixedly connected with a metal block 512 for the fixed magnet 522 to be adsorbed. The metal block 512 is an iron block. The support rod 52 is put into the support groove 51, and the fixed magnet 522 on the support rod 52 is inserted into the clearance groove 511, and the fixed magnet 522 is adsorbed on the metal block 512, thereby preventing the support rod 52 from accidentally falling out of the support groove 51.

[0034] Reference Figure 2 and Figure 3, a fixing block 521 is fixedly connected to the outer wall of each support rod 52, and four fixing grooves 111 are provided on the fixing tube 11 for the fixing block 521 to be inserted and slided, and an elastic fastening pad 112 is fixedly connected to the inner wall of the fixing groove 111, and the fastening pad 112 is made of rubber material, and the fastening pad 112 is pressed against the outer wall of the fixing block 521. After the support rod 52 is stored in the support groove 51, the fixing rod 5 is then inserted into the fixing tube 11, so that the fixing block 521 on the support rod 52 is inserted into the fixing groove 111, and the fastening pad 112 clamps the fixing block 521, thereby preventing the fixing rod 5 from accidentally detaching from the fixing tube 11, thereby improving the connection firmness between the fixing rod 5 and the base 1, and facilitating the transportation of the fixing rod 5 and the base 1.

[0035] Reference Figure 2 and Figure 3 A tightening spring 6 is fixedly connected to the bottom wall of the connecting hole 53, and a tightening plate 61 for tightening the connecting screw 41 is fixedly connected to one end of the tightening spring 6. After the connecting screw 41 is screwed into the connecting hole 53, the tightening plate 61 tightens the connecting screw 41, thereby applying a tightening force to the connecting screw 41 to prevent the connecting screw 41 from rotating.

[0036] The implementation principle of a floor deformation dynamic monitoring equipment bracket according to an embodiment of the present application is as follows: the connecting rod 4 is a prefabricated part, and a plurality of connecting rods 4 of different lengths are prefabricated. People can choose the connecting rod 4 of appropriate length according to the floor height. First, place the base 1 on the ground, then rotate the support rod 52 out of the support groove 51, and then insert the fixing rod 5 into the fixing tube 11 on the base 1, fix one end of the support rod 52 on the ground, and then screw the connecting screw 41 on the connecting rod 4 into the connecting hole 53, and then screw the mounting screw 31 on the mounting rod 3 into the mounting hole 42, and the positioning rod 2 can be assembled, rotate the mounting rod 3, fine-tune the height of the positioning rod 2, and after adjustment, install the dial indicator on the mounting rod 3 to start monitoring. The whole process saves time and effort and improves the monitoring efficiency.

[0037] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A floor deformation dynamic monitoring equipment bracket, comprising a base (1) and a positioning rod (2) mounted on the base (1), characterized in that: The positioning rod (2) comprises a mounting rod (3), a connecting rod (4) and a fixing rod (5); the fixing rod (5) is mounted on the base (1); one end of the connecting rod (4) is connected to a connecting screw (41); the upper end of the fixing rod (5) is provided with a connecting hole (53) threadedly connected to the connecting screw (41); the mounting rod (3) is connected to the mounting screw (31); the connecting rod (4) is provided with a mounting hole (42) threadedly connected to the mounting screw (31); and the base (1) is connected to a fixing tube (11) for inserting the fixing rod (5).

2. A floor deformation dynamic monitoring equipment bracket according to claim 1, characterized in that: The circumferential outer side wall of the fixing rod (5) is provided with at least three supporting grooves (51) spaced equidistantly around its own axial center line direction, and a supporting rod (52) is hingedly connected to the inner side wall of each supporting groove (51).

3. A floor deformation dynamic monitoring equipment bracket according to claim 2, characterized in that: A fixing block (521) is connected to the outer side wall of each support rod (52), and the fixing tube (11) is provided with fixing grooves (111) which are the same in number as the support rods (52) for the fixing blocks (521) to be inserted and slide, and an elastic fastening pad (112) is connected to the inner side wall of the fixing groove (111), and the fastening pad (112) is pressed against the outer side wall of the fixing block (521).

4. A floor deformation dynamic monitoring equipment bracket according to claim 3, characterized in that: The support rod (52) is connected to a fixed magnet (522), the inner side wall of the support groove (51) is provided with a clearance groove (511) for the fixed magnet (522) to be inserted into, and the bottom wall of the clearance groove (511) is connected to a metal block (512) for the fixed magnet (522) to be adsorbed.

5. The floor deformation dynamic monitoring equipment bracket according to claim 1, characterized in that: A fastening spring (6) is connected to the bottom wall of the connecting hole (53), and one end of the fastening spring (6) is connected to a fastening plate (61) for tightening the connecting screw rod (41).

6. The floor deformation dynamic monitoring equipment bracket according to claim 1, characterized in that: The lower end surface of the base (1) is connected with an anti-slip pad (7).