T-beam structure with reinforcing structure

By arranging UHPC coated steel components and rebar connectors at the bottom and sides of the T-beam, the problem of cracks when the UHPC structure is connected to the T-beam is solved, the bending and shear strength of the T-beam is improved, and a more economical and Efficient reinforcement effect.

CN221855253UActive Publication Date: 2024-10-18GUANGDONG PROVINCIAL ARCHITECTURAL ENG MACHINERY CONSTR
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323462072.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-18
Publication Date
2024-10-18
Estimated Expiration
2033-12-18

AI Technical Summary

Technical Problem

In the existing T-beam reinforcement technology, the UHPC structure and the T-beam are connected through simple connectors, which are prone to cracks when subjected to gravity for a long time, affecting the stress effect of the reinforcement system, and it is difficult to effectively improve the overall bending and resistance of the T-beam. Shear strength.

Method used

The first reinforcement structure and the second reinforcement structure are used, respectively located at the bottom and both sides of the T-beam, and are fixed through the first and second connectors to form a UHPC-coated steel bar assembly to increase the bending and shear strength, and are secured through the rebar and transverse and longitudinal reinforcement components to improve connection strength and structural stability.

Benefits of technology

It effectively improves the flexural and shear strength of the reinforced T-beam, reduces the amount of concrete, improves the durability and construction quality of the structure, avoids cracks between the UHPC structure and the T-beam, and enhances the load-bearing capacity and service life of the bridge.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221855253U_ABST
    Figure CN221855253U_ABST
Patent Text Reader

Abstract

The utility model relates to a T-beam structure with reinforcing structures. The T-beam structure comprises a T-beam body, a first reinforcing structure and two second reinforcing structures, in the length direction of the T-shaped beam body, the two second reinforcing structures are located on the two sides of the T-shaped beam body, and the two second reinforcing structures are used for supporting flanges of the T-shaped beam body; in the height direction of the T-beam body, the first reinforcing structure is located at the bottom of the T-beam body, and the first reinforcing structure is used for supporting a web of the T-beam body; the T-shaped beam further comprises a first connecting piece and a second connecting piece, the first reinforcing structure is fixed to the T-shaped beam body through the first connecting piece, and the second reinforcing structure is fixed to the T-shaped beam body through the second connecting piece. The problems that an existing T-beam and a UHPC structure are simply connected together only through a connecting piece, when the UHPC structure is subjected to the gravity effect for a long time, cracks are generated between the UHPC structure and the T-beam, and the stress of a reinforcing system is affected are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of bridge reinforcement, in particular to a T-beam structure with a reinforcement structure. Background Art

[0002] T-beam structure refers to a beam with a T-shaped cross-section. The protruding parts on both sides are called flanges, and the middle part is called beam ribs (or webs). T-beams have the characteristics of simple appearance, easy manufacturing, prefabrication, and easy installation on site. At the same time, T-beams have a strong steel skeleton, which makes them have good integrity and convenient joints. The beam bridge formed by T-beams is one of the most widely used bridge structures in my country. Over time, under the combined effects of external environment, load, material degradation, construction quality defects and other factors, the mechanical properties and durability of a large number of T-beam bridges have declined to varying degrees, and the beams need to be reinforced.

[0003] UHPC (Ultra-High Performance Concrete) is ultra-high performance concrete. The Chinese patent publication number is CN213448140U. It is a UHPC reinforced T-beam, including a T-beam body, a UHPC structure and a plurality of connectors; the UHPC structure is arranged at the lower end of the T-beam body; a plurality of connectors are arranged at intervals along the longitudinal direction of the T-beam body, and one end of each connector is connected to the lower end of the T-beam body, and the other end is connected to the UHPC structure, so that the UHPC structure is connected to the T-beam body. This patent has the advantages of large bending and shear stiffness, strong bearing capacity, good durability, etc., and can be widely used in T-beam reinforcement projects. However, this patent adds a UHPC beam at the bottom of the T-beam body, and its style only increases the bending strength of the T-beam after reinforcement, but does not improve the shear strength at both ends of the T-beam much, making it difficult to improve the overall strength of the T-beam (bending strength, shear strength), and failing to achieve the best effect; and the UHPC structure is located at the lower end of the original T-beam body, and the original T-beams are simply connected together by connecting parts, and the connecting parts are arranged longitudinally, and the two do not form a combination, and their forces are dealt with separately. The UHPC structure is subjected to the effect of gravity for a long time, and separate cracks will appear between it and the T-beam, which will affect the force of the reinforcement system, and the overall force improvement after reinforcement is limited. Utility Model Content

[0004] The utility model aims to provide a T-beam structure with a reinforcement structure to solve the problem that the existing T-beam and the UHPC structure are simply connected together by connecting parts, and when the UHPC structure is subjected to gravity for a long time, cracks will be generated between the T-beam and the UHPC structure, affecting the stress of the reinforcement system.

[0005] In order to achieve the above purpose, the technical solution adopted by the utility model is as follows:

[0006] A T-beam structure with a reinforcement structure, comprising a T-beam body, a first reinforcement structure and two second reinforcement structures; in the length direction of the T-beam body, the two second reinforcement structures are located on both sides of the T-beam body, and the two second reinforcement structures are used to support the flange of the T-beam body;

[0007] In the height direction of the T-beam body, the first reinforcement structure is located at the bottom of the T-beam body, and the first reinforcement structure is used to support the web of the T-beam body;

[0008] It also includes a first connecting member and a second connecting member, the first reinforcement structure is fixed to the T-beam body through the first connecting member, and the second reinforcement structure is fixed to the T-beam body through the second connecting member.

[0009] According to the above technical solution, by setting a first reinforcement structure and two second reinforcement structures, the first reinforcement structure is located at the bottom of the T-beam body, and is used to support the web position of the T-beam body, and the second reinforcement structure is located on both sides of the T-beam body. The two second reinforcement structures are respectively used to support the flanges of the T-beam body, which not only increases the bending strength of the reinforced T-beam, but the second reinforcement structure also improves the bending strength and shear strength at both ends of the T-beam. While achieving the effect of improving the bending strength and shear strength, the amount of concrete used is greatly reduced, which is economical and affordable.

[0010] Furthermore, the first reinforcement structure includes a first UHPC body and a first steel bar assembly, and the first UHPC body is coated on the first steel bar assembly.

[0011] According to the above technical solution, by using the first UHPC body to cover the first steel bar assembly, the first UHPC body is reinforced by using UHPC (ultra-high performance concrete) to cover the first steel bar assembly, which has high strength and good structural properties, reduces the adverse effects of the environment on the reinforced components, and ensures construction quality and durability.

[0012] Furthermore, the number of the first connecting members is more than two, each of the first connecting members is distributed at the bottom of the T-beam body, and one end of each of the first connecting members is connected to the T-beam body, and the other end of each of the first connecting members is connected to the first steel bar assembly.

[0013] According to the above technical solution, one end of the first connector is connected to the first steel bar assembly, wherein the other end of some of the first connectors is connected to the bottom of the T-beam body, and the other end of some of the first connectors is also connected to the side wall of the T-beam body, and the first connector tightly connects the first steel bar assembly to the T-beam body. At the same time, the first connector is set in the form of more than two, and multiple first connectors can make the connection between the T-beam body and the first steel bar assembly more stable, and improve the connection strength between the two.

[0014] Furthermore, the first connecting member is a first threaded steel bar, one end of the first threaded steel bar is welded to the first steel bar assembly, and the other end of the first threaded steel bar extends into the interior of the T-beam body and is fixedly connected to the T-beam body.

[0015] According to the above technical solution, by setting the first connecting member in the form of threaded steel, the threaded steel has the characteristics of excellent mechanical properties, high strength and rigidity, ability to withstand large loads and stresses, strong plasticity, convenient construction, and good corrosion resistance.

[0016] Furthermore, the first steel bar assembly includes more than two first transverse steel bars and more than two first longitudinal steel bars, each of the first transverse steel bars is arranged along the length direction of the T-beam body, each of the first longitudinal steel bars is arranged perpendicular to each of the first transverse steel bars, and each of the first transverse steel bars is fixedly connected to the first longitudinal steel bars.

[0017] According to the above technical solution, by arranging each first transverse steel bar vertically with the first longitudinal steel bar and fixing the first transverse steel bar with the first longitudinal steel bar, a steel cage is formed, which facilitates the pouring of UHPC concrete, improves the strength of the overall structure, and plays a role in supporting the T-beam body.

[0018] Furthermore, the second reinforcement structure includes a second UHPC body and a second steel bar assembly, and the second UHPC body is coated on the second steel bar assembly.

[0019] According to the above technical solution, by using the second UHPC body to cover the second steel bar assembly, the second UHPC body is reinforced by using UHPC (ultra-high performance concrete) to cover the second steel bar assembly, which has high strength and good structural properties, reduces the adverse effects of the environment on the reinforced components, and ensures construction quality and durability.

[0020] Further, the second connecting member includes more than two transverse connecting members and more than two vertical connecting members, each of the transverse connecting members passes through the T-beam body, and both ends of the transverse connecting member are respectively connected to the second steel bar assembly;

[0021] One end of each of the vertical connecting members is connected to the T-beam body, and the other end of each of the vertical connecting members is connected to the second steel bar assembly.

[0022] According to the above technical solution, the second reinforcement structure and the T-beam body are connected by the second connecting piece, and the second reinforcement structure supports the T-beam body; since the transverse connecting piece runs through the T-beam body and the two ends of the transverse connecting piece are respectively connected to the second steel bar assembly, the second steel bar assembly can be stably and firmly fixed on both sides of the T-beam body; one end of the vertical connecting piece is connected to the T-beam body, and the other end is connected to the second steel bar assembly, so that the second steel bar assembly located at the bottom of the T-beam body can be fixed on the T-beam body.

[0023] Furthermore, the vertical connecting member is a second threaded steel bar, one end of the second threaded steel bar is welded to the second steel bar assembly, and the other end of the second threaded steel bar extends into the interior of the T-beam body and is fixedly connected to the T-beam body.

[0024] Furthermore, the second steel bar assembly includes more than two second transverse steel bars and more than two second longitudinal steel bars, each of the second transverse steel bars is arranged along the length direction of the T-beam body, each of the second longitudinal steel bars is arranged perpendicular to each of the second transverse steel bars, and each of the second transverse steel bars is fixedly connected to the second longitudinal steel bars.

[0025] According to the above technical solution, by vertically arranging each second transverse steel bar and the second longitudinal steel bar, and fixedly connecting the second transverse steel bar and the second longitudinal steel bar, a second steel bar assembly is formed, which facilitates the pouring of UHPC concrete, improves the strength of the overall structure, and plays a role in stabilizing the support of the T-beam body.

[0026] Furthermore, the cross-section of the second reinforcement structure is a horseshoe-shaped structure, which is used to improve the bending resistance of the T-beam body.

[0027] Beneficial effects of the utility model:

[0028] 1. The utility model forms a first reinforcement structure and a second reinforcement structure by casting and coating the first steel bar assembly and the second steel bar assembly with UHPC. The tensile toughness and resistance to adverse environmental erosion of UHPC are better than those of ordinary concrete. The use of UHPC to reinforce T-beam bridges can effectively enhance the ability of the structure to withstand the live load of the bridge deck, and at the same time, it can prevent erosion by harmful substances such as water and chloride ions to the maximum extent, avoid rusting of steel bars in concrete, and thus extend the service life of the bridge.

[0029] 2. By setting a first reinforcement structure and two second reinforcement structures, the first reinforcement structure is located at the bottom of the T-beam body, and is used to support the web position of the T-beam body. The second reinforcement structure is located on both sides of the T-beam body. The two second reinforcement structures are respectively used to support the flanges of the T-beam body. Compared with the prior art, the utility model adds a second reinforcement structure, which not only increases the bending strength of the T-beam after reinforcement, but the second reinforcement structure also improves the bending strength and shear strength at both ends of the T-beam. While achieving the effect of improving the bending strength and shear strength, it greatly reduces the amount of concrete used, which is economical and affordable.

[0030] 3. The connecting piece in the prior art is longitudinally arranged, and the two ends of the connecting piece are respectively inserted into the lower end of the T-beam body and the UHPC structure. Compared with the prior art, one end of the first connecting piece of the utility model is connected to the first reinforcement structure, wherein the other end of part of the first connecting piece includes a connection with the bottom of the T-beam body, and the other end of part of the first connecting piece is also connected to the side wall of the T-beam body. The first connecting piece makes the first reinforcement structure and the T-beam body tightly connected together, and the connection strength is higher. When the UHPC structure is subjected to gravity for a long time, no cracks will be generated with the T-beam, thereby improving the stress condition of the reinforcement system. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] Figure 1 It is a schematic diagram of the overall structure of the T-beam structure with a reinforcement structure of the utility model;

[0032] Figure 2 This is a schematic diagram of a half-section structure of a T-beam structure with a reinforcement structure of the utility model;

[0033] Figure 3 In the T-beam structure with a reinforcement structure of the utility model Figure 2 AA structural cross-sectional view;

[0034] Figure 4 In the T-beam structure with a reinforcement structure of the utility model Figure 2 BB structure cross-sectional view.

[0035] Among them, the T-beam body 1, the crack 11, the first reinforcement structure 2, the first UHPC body 21, the first steel bar assembly 22, the first transverse steel bar 221, the first longitudinal steel bar 222, the second reinforcement structure 3, the second UHPC body 31, the second steel bar assembly 32, the second transverse steel bar 321, the second longitudinal steel bar 322, the first connecting piece 4, the second connecting piece 5, the vertical connecting piece 51, and the transverse connecting piece 52. DETAILED DESCRIPTION

[0036] The following will describe the implementation of the present invention with reference to the accompanying drawings and preferred embodiments. Those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification. The present invention can also be implemented or applied through other different specific implementations, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present invention. It should be understood that the preferred embodiments are only for illustrating the present invention, not for limiting the scope of protection of the present invention.

[0037] It should be noted that the illustrations provided in the following embodiments are only schematic illustrations of the basic concept of the present invention, and thus the drawings only show components related to the present invention rather than being drawn according to the number, shape and size of components in actual implementation. In actual implementation, the type, quantity and proportion of each component may be changed at will, and the component layout may also be more complicated.

[0038] It should be noted that the T-beam structure refers to a beam with a T-shaped cross-section. The protruding parts on both sides are called flanges, and the middle part is called the beam rib (or web).

[0039] This embodiment proposes a T-beam structure with a reinforcement structure, such as Figure 1 and Figure 2 As shown, it includes a T-beam body 1, a first reinforcement structure 2 and two second reinforcement structures 3; in the length direction of the T-beam body 1, the two second reinforcement structures 3 are located on both sides of the T-beam body 1, and the two second reinforcement structures 3 are used to support the flanges of the T-beam body 1.

[0040] In the height direction of the T-beam body 1, the first reinforcement structure 2 is located at the bottom of the T-beam body 1, and the first reinforcement structure 2 is used to support the web of the T-beam body 1; Figure 3 and Figure 4 As shown, it also includes a first connecting member 4 and a second connecting member 5 . The first reinforcement structure 2 is fixed to the T-beam body 1 through the first connecting member 4 , and the second reinforcement structure 3 is fixed to the T-beam body 1 through the second connecting member 5 .

[0041] According to the above technical solution, by setting a first reinforcement structure 2 and two second reinforcement structures 3, the first reinforcement structure 2 is located at the bottom of the T-beam body 1, and is used to support the web position of the T-beam body 1, and the second reinforcement structure 3 is located on both sides of the T-beam body 1. The two second reinforcement structures 3 are respectively used to support the flanges of the T-beam body 1. The first reinforcement structure 2 not only increases the bending strength of the middle part of the T-beam after reinforcement, but the second reinforcement structure 3 also improves the bending strength and shear strength of the two ends of the T-beam, and also greatly reduces the amount of concrete used, which is economical and affordable.

[0042] Furthermore, if Figure 3 As shown, the first reinforcement structure 2 includes a first UHPC body 21 and a first steel bar assembly 22, and the first UHPC body 21 is coated on the first steel bar assembly 22. By using the first UHPC body 21 to coat the first steel bar assembly 22, the first UHPC body 21 is formed by coating the first steel bar assembly 22 with UHPC (ultra-high performance concrete); for example, using UHPC150 (where 150 represents a compressive strength of 150 MPa) to reinforce the T-beam body 1 can effectively enhance the ability of the structure to withstand the bridge deck load, and it has high strength and good structural properties, reduces the adverse effects of the environment on the reinforced components, and ensures the construction quality and durability.

[0043] like Figure 3 As shown, the number of first connectors 4 is more than two, and one end of each first connector 4 is connected to the T beam body 1, and the other end of each first connector 4 is connected to the first steel bar assembly 22. Specifically, one end of a portion of the first connectors 4 is welded to the first steel bar assembly 22, and the other end extends from the bottom of the T beam body 1 and is fixedly connected to the inside of the T beam body 1; one end of another portion of the first connectors 4 is welded to the first steel bar assembly 22, and the other end extends from the side wall of the T beam body 1 and is fixedly connected to the inside of the T beam body 1. The first connector 4 tightly connects the first steel bar assembly 22 and the T beam body 1 together, so that the two are combined into one.

[0044] As a preferred embodiment, the first connecting member 4 is a first threaded steel bar, one end of which is welded to the first steel bar assembly 22, and the other end of which extends into the interior of the T-beam body 1 and is fixedly connected to the T-beam body 1. By setting the first connecting member 4 in the form of a threaded steel bar, the threaded steel bar has the characteristics of excellent mechanical properties, high strength and rigidity, ability to withstand large loads and stresses, strong plasticity, convenient construction, and good corrosion resistance.

[0045] like Figure 3 As shown, the first steel bar assembly 22 includes more than two first transverse steel bars 221 and more than two first longitudinal steel bars 222. Each first transverse steel bar 221 is arranged along the length direction of the T beam body 1, each first longitudinal steel bar 222 is arranged perpendicular to each first transverse steel bar 221, and each first transverse steel bar 221 is fixedly connected to the first longitudinal steel bar 222. By vertically arranging the first transverse steel bar 221 and the first longitudinal steel bar 222, and fixing the first transverse steel bar 221 and the first longitudinal steel bar 222, a steel cage is formed, which facilitates the pouring of UHPC concrete, improves the strength of the overall structure, and plays a role in supporting the T beam body 1.

[0046] Furthermore, if Figure 4As shown, the cross section of the second reinforcement structure 3 is a horseshoe-shaped structure, which is used to improve the bending resistance of the T-beam body 1; wherein the second reinforcement structure 3 includes a second UHPC body 31 and a second steel bar assembly 32, wherein the material of the first UHPC body 21 and the second UHPC body 31 is UHPC150, and is maintained at room temperature and moisturizing; the second UHPC body 31 is coated on the second steel bar assembly 32. By using the second UHPC body 31 to coat the second steel bar assembly 32, the second UHPC body 31 is also reinforced by using UHPC (ultra-high performance concrete) to coat the second steel bar assembly 32, which has high strength and good structural properties, reduces the adverse effects of the environment on the reinforced components, and ensures the construction quality and durability.

[0047] Furthermore, if Figure 4 As shown, the second connector 5 includes more than two transverse connectors 52 and more than two vertical connectors 51, each transverse connector 52 passes through the T beam body 1, and the two ends of the transverse connector 52 are respectively connected to the second steel bar assembly 32; one end of each vertical connector 51 is connected to the T beam body 1, and the other end of each vertical connector 51 is connected to the second steel bar assembly 32. The second reinforcement structure 3 and the T beam body 1 are connected by the second connector 5, and the second reinforcement structure 3 supports the T beam body 1; because the transverse connector 52 passes through the T beam body 1 and the two ends of the transverse connector 52 are respectively connected to the second steel bar assembly 32, the second steel bar assembly 32 can be stably and firmly fixed on both sides of the T beam body 1; one end of the vertical connector 51 is connected to the T beam body 1, and the other end is connected to the second steel bar assembly 32, so that the second steel bar assembly 32 located at the bottom and side of the T beam body 1 can be fixed on the T beam body 1.

[0048] Furthermore, the vertical connector 51 is a second threaded steel bar, one end of which is welded to the second steel bar assembly 32, and the other end of which extends into the interior of the T-beam body 1 and is fixedly connected to the T-beam body 1. The second steel bar assembly 32 includes more than two second transverse steel bars 321 and more than two second longitudinal steel bars 322, each second transverse steel bar 321 is arranged along the length direction of the T-beam body 1, each second longitudinal steel bar 322 is arranged perpendicular to each second transverse steel bar 321, and each second transverse steel bar 321 is fixedly connected to the second longitudinal steel bar 322. By vertically arranging each second transverse steel bar 321 and the second longitudinal steel bar 322, and fixing the second transverse steel bar 321 and the second longitudinal steel bar 322, the second steel bar assembly 32 is formed, which facilitates the pouring of UHPC concrete, improves the strength of the overall structure, and plays a role in stabilizing the support of the T-beam body 1.

[0049] During the implementation of the utility model, the surface of the original T-beam body 1 needs to be processed, and the processing requirements and steps are as follows:

[0050] Step 1: Clean the concrete surface on the T-beam body 1

[0051] 1. In the damaged concrete part of the original T-beam body 1 to be reinforced (i.e., the first reinforcement structure 2 and the second reinforcement structure 3 to be installed), the loose, damaged and stained concrete shall be removed by manual chiseling, pneumatic tool chiseling or high-speed water jetting until a hard and dense base surface is exposed. The surface shall be chiseled into a rough surface with a concave-convex difference of not less than 6mm. At the same time, care shall be taken to ensure that there is no oil, grease, wax, dust and attachments in this part.

[0052] 2. For defects with a depth of ≥10cm and an area of ​​≥(10cm×10cm), the surface should be chiseled into a square wave and serrated shape and chiseled to the solid layer. The criterion for judgment is whether the coarse aggregate of the concrete can be seen.

[0053] 3. Use a steel brush to remove the rust on the surface of the exposed steel bars of the T-beam body 1 to expose the smooth part.

[0054] 4. Wipe clean the surface of the reinforced area structure with acetone.

[0055] 5. When cleaning the concrete defective parts on the T-beam body 1, be careful not to damage the original steel bars of the beam body (especially the main bars or prestressed steel strands).

[0056] 6. After the surface of the T-beam body 1 is cleaned, the exposed rusted steel bars must be derusted and rust-proofed, the existing concrete damage on the beam body must be repaired, and the excessive cracks 11 must be grouted.

[0057] like Figure 1 As shown, Figure 1 A crack 11 appears in the middle T-beam body 1 , and the first reinforcement structure 2 and the second reinforcement structure 3 are required to support the T-beam body 1 .

[0058] Step 2: Planting the tendons

[0059] 1. Plant the first transverse reinforcement 221, the first longitudinal reinforcement 222, the second transverse reinforcement 321, the second longitudinal reinforcement 322, the first connector 4, the second connector 5, the vertical connector 51 and the transverse connector 52. Before construction, the on-site trial reinforcement planting method should be used to test the bonding strength of the structural adhesive. Only after ensuring that the bonding strength meets the requirements of the construction design and specifications can the reinforcement planting construction be formally carried out.

[0060] 2. Before drilling, it is necessary to determine the position of the steel bars inside the original T-beam body 1 to avoid damage to the internal structural steel bars of the original T-beam body 1 during the drilling process.

[0061] 3. The holes for anchoring reinforcement need to be cleaned.

[0062] 4. Before or after the construction of embedded reinforcement, a pull-out test should be carried out on the site or on a concrete structure of the same grade as the original structure to detect the rationality of the embedded reinforcement process and the bonding performance of the structural adhesive.

[0063] Step 3: Casting with UHPC concrete

[0064] 1. The supply of concrete must ensure the continuous pouring demand within the specified construction section; 2. The free fall height of concrete should not exceed 2m; in the case of no stratification and segregation, the maximum fall height should be controlled within 4m; 3. The pipes for pumping concrete should be reasonably arranged according to the site conditions. 4. Concrete should be pumped within 120 minutes after mixing to prevent the loss of slump from affecting pumping.

[0065] Step 4: UHPC maintenance

[0066] High-performance concrete must be strengthened with moisture-retaining maintenance. After pouring and forming the first reinforcement structure 2 and the second reinforcement structure 3, it should be immediately covered with plastic film. During the second vibration and surface pressing, the covering material can be rolled up and then covered in time. After the concrete is finally set, it can be cured with water. When water curing is used, the temperature of the water should be adapted to the temperature of the concrete to avoid cracks in the concrete due to excessive temperature difference 11. The moisture-retaining maintenance period should not be less than 14 days. When the amount of cementitious materials in high-performance concrete is large, covering and heat preservation measures should be taken. During the heat preservation maintenance period, the internal temperature of the concrete should be controlled not to exceed 75°C; measures should be taken to ensure that the temperature difference between the inside and outside of the concrete does not exceed 25°C. The maximum temperature inside the concrete structure can be controlled by controlling the mold temperature, and the temperature difference between the inside and outside of the structure can be controlled by moisture-retaining heat storage maintenance; the surface temperature of the concrete should also be prevented from changing dramatically due to environmental influences (such as exposure to the sun, sudden drop in temperature, etc.).

[0067] The utility model forms the first reinforcement structure 2 and the second reinforcement structure 3 by pouring and coating the first steel bar assembly 22 and the second steel bar assembly 32 with UHPC respectively. The tensile toughness and resistance to adverse environmental erosion of UHPC concrete are better than those of ordinary concrete. The use of UHPC to reinforce T-beam bridges can effectively enhance the ability of the structure to withstand the live load of the bridge deck, and at the same time can prevent erosion by harmful substances such as water and chloride ions to the greatest extent, avoid rusting of steel bars in concrete, and thus extend the service life of the bridge. The first reinforcement structure 2 is located at the bottom of the T-beam body 1, and is used to support the web position of the T-beam body 1. The second reinforcement structure 3 is located on both sides of the T-beam body 1. The two second reinforcement structures 3 are respectively used to support the flanges of the T-beam body 1. Compared with the prior art, the utility model adds the second reinforcement structure 3, which not only increases the bending strength of the T-beam after reinforcement, but also improves the bending strength and shear strength at both ends of the T-beam. While achieving the effect of improving the bending strength and shear strength, the amount of concrete used is greatly reduced. When the UHPC structure is subjected to gravity for a long time, cracks 11 will not be generated with the T-beam, which solves the problem that when the UHPC structure is subjected to gravity for a long time, cracks 11 will be generated with the T-beam, affecting the stress of the reinforcement system.

[0068] The above embodiments are only preferred embodiments for fully illustrating the present invention, and the protection scope of the present invention is not limited thereto. Any equivalent substitution or modification made by a person skilled in the art based on the present invention is within the protection scope of the present invention.

Claims

1. A T-beam structure with a reinforcement structure, characterized in that: include: A T-beam body (1), a first reinforcement structure (2) and two second reinforcement structures (3); in the length direction of the T-beam body (1), the two second reinforcement structures (3) are located at two ends of the T-beam body (1), and the two second reinforcement structures (3) are used to support the flange of the T-beam body (1); In the height direction of the T-beam body (1), the first reinforcement structure (2) is located at the bottom of the T-beam body (1), and the first reinforcement structure (2) is used to support the web of the T-beam body (1); It also comprises a first connecting member (4) and a second connecting member (5), wherein the first reinforcement structure (2) is fixed to the T-beam body (1) via the first connecting member (4), and the second reinforcement structure (3) is fixed to the T-beam body (1) via the second connecting member (5).

2. The T-beam structure with a reinforcement structure according to claim 1, characterized in that: The first reinforcement structure (2) comprises a first UHPC body (21) and a first steel bar assembly (22), wherein the first UHPC body (21) is coated on the first steel bar assembly (22).

3. The T-beam structure with a reinforcement structure according to claim 2, characterized in that: The number of the first connecting members (4) is more than two, one end of each of the first connecting members (4) is connected to the T-beam body (1), and the other end of each of the first connecting members (4) is connected to the first steel bar assembly (22).

4. The T-beam structure with a reinforcement structure according to claim 3, characterized in that: The first connecting member (4) is a first threaded steel bar, one end of which is welded to the first steel bar assembly (22), and the other end of which extends into the interior of the T-beam body (1) and is fixedly connected to the T-beam body (1).

5. The T-beam structure with a reinforcement structure according to claim 2, characterized in that: The first steel bar assembly (22) comprises more than two first transverse steel bars (221) and more than two first longitudinal steel bars (222), each of the first transverse steel bars (221) being arranged along the length direction of the T-beam body (1), each of the first longitudinal steel bars (222) being arranged perpendicular to each of the first transverse steel bars (221), and each of the first transverse steel bars (221) being fixedly connected to the first longitudinal steel bars (222).

6. The T-beam structure with a reinforcement structure according to claim 1, characterized in that: The second reinforcement structure (3) comprises a second UHPC body (31) and a second steel bar assembly (32), wherein the second UHPC body (31) is coated on the second steel bar assembly (32).

7. The T-beam structure with a reinforcement structure according to claim 6, characterized in that: The second connecting member (5) comprises more than two transverse connecting members (52) and more than two vertical connecting members (51), each of the transverse connecting members (52) passes through the T-beam body (1), and both ends of the transverse connecting member (52) are respectively connected to the second steel bar assembly (32); One end of each of the vertical connecting members (51) is connected to the T-beam body (1), and the other end of each of the vertical connecting members (51) is connected to the second steel bar assembly (32).

8. The T-beam structure with a reinforcement structure according to claim 7, characterized in that: The vertical connecting member (51) is a second threaded steel bar, one end of which is welded to the second steel bar assembly (32), and the other end of which extends into the interior of the T-beam body (1) and is fixedly connected to the T-beam body (1).

9. The T-beam structure with a reinforcement structure according to claim 6, characterized in that: The second steel bar assembly (32) comprises more than two second transverse steel bars (321) and more than two second longitudinal steel bars (322), each of the second transverse steel bars (321) being arranged along the length direction of the T-beam body (1), each of the second longitudinal steel bars (322) being arranged perpendicular to each of the second transverse steel bars (321), and each of the second transverse steel bars (321) being fixedly connected to the second longitudinal steel bars (322).

10. The T-beam structure with a reinforcement structure according to any one of claims 1 to 9, characterized in that: The cross section of the second reinforcement structure (3) is a horseshoe-shaped structure, and is used to improve the bending resistance of the T-beam body (1).