Integrated rainwater control system for rainwater regulation, storage, purification and utilization
By setting up a water storage area, a transition area, and a clear water area within a pool, and utilizing porous purification materials and booster pumps to purify and utilize rainwater, the problems of space occupation and energy consumption in the process of rainwater collection and treatment are solved, realizing the integration of rainwater control and utilization, which is energy-saving and environmentally friendly.
Patent Information
- Application Number
- CN202420216954.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-25
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2034-01-25
AI Technical Summary
In existing technologies, during the rainwater collection, treatment and reuse process, the water storage tank, treatment unit and clear water tank each occupy space, have a single function, and the purification process requires the consumption of chemicals and energy.
A water storage area, a transition area, a first clear water area, and a second clear water area are set up in a pool. The water is filtered and biologically treated using porous purification materials. Combined with a booster pump, rainwater is purified and utilized, eliminating the need for external power equipment and using waste materials as the purification medium.
It integrates rainwater collection, purification, and utilization, reducing land occupation, saving resources, promoting energy conservation and environmental protection, facilitating the reuse of waste materials, and is easy to operate.
Smart Images

Figure CN221855668U_ABST
Abstract
Description
Technical Field
[0001] When the water level in the second clean water area 13 is lower than the low water level 86 of the second clean water area, water replenishment is started, and when the water level reaches the high water level 87 of the second clean water area, water replenishment is stopped. Background Art
[0002] In summary, in engineering practice, due to the requirements of rainwater collection and rainwater treatment and reuse, conventional technology is often completed through the process of water storage tank → treatment unit → clean water tank. This technology can realize the collection, purification and utilization of rainwater, but the three main units each occupy space and have a single function. The raw water in the water storage tank is pressurized to the treatment unit through a lifting pump, and the treatment process consumes reagents and energy. The present application fills the porous purification material 71 in the water storage area 10, and purifies the raw water through filtration, adsorption and biological treatment of the porous purification material 71, thereby realizing the setting of water storage, treatment and clean water in one pool body, realizing the integration of rainwater control and utilization, reducing the occupied space, and no external power is consumed in the entire purification process, which is energy-saving and environmentally friendly, and promotes the reuse of waste materials. Utility Model Content
[0003] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principle of the present invention. These improvements and substitutions should also be regarded as the protection scope of the present invention.
[0004] The technical solution of the utility model is as follows: a water storage area, a transition area, a first clean water area and a second clean water area are in the same pool body and are separated by partition walls respectively; a porous purification material is arranged in the water storage area; a rainwater pipe is connected to the front end of the water storage area; the rear end of the water storage area is connected with the transition area through a low-level connecting port at the bottom of the partition wall; the first clean water area and the second clean water area are arranged in sequence at the rear end of the transition area; a first lifting pump is arranged in the transition area; the first lifting pump lifts the stored water into the first clean water area, the rainwater pipe network or the sewage system respectively; a second lifting pump is arranged in the first clean water area to lift the clean water to the first water use point or water storage area outside the pool body; the rear end of the first clean water area is connected with the second clean water area through a high-level connecting port on the partition wall; a disinfection tank is arranged at the front end of the second clean water area, near the high-level connecting port; a third lifting pump is arranged in the second clean water area to lift the disinfected clean water to the second water use point outside the pool body.
[0005] Based on the above technical features: inspection ports are set at the top of the water storage area, transition area, first clean water area and second clean water area.
[0006] Based on the above technical features: a support plate is overhead set at the bottom of the water storage area; a porous purification material is placed above the support plate; and the support plate is located on the low-level connecting port.
[0007] Based on the above technical features: a flushing pipe and a flushing nozzle are set at the front end of the water storage area.
[0008] Based on the above technical features: the bottom of the disinfection tank is lower than the high-level connecting port.
[0009] Based on the above technical characteristics: the bottom elevation of the transition zone is lower than the water storage area.
[0010] An operation method of an integrated rainwater control system for rainwater regulation, purification and utilization: in normal working state, the first lifting pump lifts the purified rainwater into the first clean water area; when rainwater control is required and peak discharge is performed, the first lifting pump lifts the rainwater and discharges it to the rainwater pipe network; when flushing the water storage area, the first lifting pump is used to lift and discharge flushing wastewater and empty the wastewater in the pool of the water storage area to the sewage system. The rainwater pipe network and sewage system can be municipal or internal to the building community.
[0011] The second lifting pump is turned on to lift clean water out of the pool for use in greening irrigation, road washing, or flushing of the water storage area. The third lifting pump is turned on to lift the disinfected clean water out of the pool for reuse.
[0012] Control water levels are set in the transition zone, the first clean water zone and the second clean water zone, and the first lift pump, the second lift pump and the third lift pump are started and stopped according to the control water levels; solenoid valves are set on the water outlet pipes of the first lift pump and the second lift pump, and they are automatically switched in combination with the control water levels; an ordinary valve is set on the water outlet pipe of the third lift pump to control the water outlet.
[0013] In the above technical solution: the flow rate and lift of the first lifting pump can simultaneously meet the requirements of lifting into the first clean water area, staggered discharge and flushing discharge for the water storage area. The flow rate and lift of the second lifting pump must meet the water demand of the water use point and can ensure the flushing demand of the water storage area. The flow rate and lift of the third lifting pump must meet the water demand of the water use point. The size of the water storage area is selected according to actual needs. The size of the transition area is set according to the equipment installation and maintenance requirements. The size of the first clean water area and the second clean water area is set according to the water consumption storage requirements of the water use point.
[0014] Compared with the prior art, the present application provides a rainwater control system that integrates rainwater storage, purification and utilization. Compared with the traditional process, the rainwater storage, purification and utilization of the process are completed in one pool, without the need to set up an additional clean water pool and mechanical treatment equipment. The water storage area is filled with porous purification materials produced from waste materials as raw materials as the main treatment medium. After one construction is completed, the entire treatment process does not require additional addition of pharmaceutical consumables and external power supplies. The process saves space, saves resources, saves energy and protects the environment, and promotes the reuse of waste materials. In addition, it controls the water level through the setting of the functional area, automatically adjusts the opening and closing of each lifting pump, is simple and convenient to operate, does not require the addition of external power throughout the process, and is energy-saving and environmentally friendly. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a schematic diagram of the interior plan of the integrated rainwater control system.
[0016] Figure 2 It is a top plan schematic diagram of the integrated stormwater control system.
[0017] Figure 3 It is a cross-sectional schematic diagram of the water storage area and transition zone in the integrated rainwater control system.
[0018] Figure 4 It is a cross-sectional schematic diagram of the transition zone, the first clean water zone and the second clean water zone in the integrated rainwater control system.
[0019] Among them, Figures 1 to 4 The reference numerals are described as follows:
[0020] 10-water storage area; 11-transition area; 12-first clean water area; 13-second clean water area; 20-tank body; 21-first partition wall; 22-second partition wall; 23-third partition wall; 30-water inlet; 31-first connecting port; 32-second connecting port; 33-high-level connecting port; 40-first lifting pump; 41-second lifting pump; 42-third lifting pump; 50-disinfection tank; 60-first inspection well; 61-second inspection well Well; 62-the third inspection well; 63-the fourth inspection well; 70-support plate; 71-porous purification material; 72-flushing pipe; 73-flushing nozzle; 80-low water level in transition zone; 81-high water level in transition zone; 82-low water level in the first clean water zone; 83-middle-low water level in the first clean water zone; 84-middle-high water level in the first clean water zone; 85-high water level in the first clean water zone; 86-low water level in the second clean water zone; 87-high water level in the second clean water zone. DETAILED DESCRIPTION
[0021] To make the purpose, advantages and features of this application more clear, the following Figures 1 to 4 The technology proposed in this application is further described in detail. It should be noted that the drawings are all in a very simplified form and are not in precise proportions, and are only used to conveniently and clearly assist in explaining the purpose of the embodiments of this application.
[0022] In order to facilitate the understanding of the present application, the present invention is described in more detail below in conjunction with the accompanying drawings and specific embodiments. It should be noted that the terms and similar expressions used in this application are for illustrative purposes only and cannot be understood as indicating relative importance or implicitly indicating the number of technical features indicated. The term "include" and any variation thereof are intended to be non-exclusive inclusions, and one or more other features, integers, steps, operations, units and / or combinations thereof may exist or be added. All technical and scientific terms used in this specification have the same meaning as those commonly understood by technicians in the technical field of this application. The terms used in the specification of this application are only for the purpose of describing specific embodiments and are not used to limit the present invention. The term "and / or" used in this specification includes any and all combinations of one or more related listed items.
[0023] In addition, the technical features involved in the different embodiments of the present application described below can be combined with each other as long as they do not conflict with each other. In addition, in the description of the present utility model, unless otherwise specified, the meaning of "multiple" is two or more.
[0024] See also Figure 1 , combined with Figure 3 and Figure 4 The present application provides an integrated rainwater control system for rainwater regulation, purification and utilization, comprising a water storage area 10, a transition area 11, a first clean water area 12, and a second clean water area 13. Each functional area is in a pool body 20. The water storage area 10 is separated from the transition area 11, the first clean water area 12, and the second clean water area 13 by a first partition wall 21. The transition area 11 and the first clean water area 12 are separated by a second partition wall 22; the first clean water area 12 and the second clean water area 13 are separated by a third partition wall 23. The water storage area 10 and the transition area 11 are connected through a low-level connecting port opened on the first partition wall 21, and the low-level connecting port is set at the bottom of the first partition wall 21. Figure 1 There are two low-level communication ports, namely, a first communication port 31 and a second communication port 32 as a backup. The first clean water area 12 is connected to the second clean water area 13 through a high-level communication port 33 provided on the third partition wall 23, and the high-level communication port 33 is provided on the upper part of the third partition wall 23.
[0025] The first lifting pump 40 is arranged in the transition area 11. In normal working state, the first lifting pump 40 lifts the rainwater purified by the porous purification material 71 in the water storage area into the first clean water area 12; when staggered discharge is required, the first lifting pump 40 lifts the rainwater and discharges it to the rainwater pipe network for direct discharge; when flushing the water storage area 10, the first lifting pump 40 is used to lift and discharge the flushing wastewater, and the bottom elevation of the transition area 11 is lower than the bottom elevation of the water storage area 10.
[0026] A second lifting pump 41 is arranged in the first clean water area 12, and the second lifting pump 41 lifts clean water to the first water point, which can be used for greening irrigation, road washing, etc. When the water storage area 10 is washed, the second lifting pump 41 can also pressurize and output clean water as washing water.
[0027] A disinfection tank 50 is provided in the second clean water area 13, and the outlet water is disinfected by adding disinfectant in the disinfection tank 50. A third lifting pump 42 is provided in the second clean water area 13 to lift the disinfected clean water to the second water point for recycling water needs such as flushing toilets and washing vehicles.
[0028] It should be noted that the pool body 20, the first partition wall 21, the second partition wall 22, and the third partition wall 23 can be made of reinforced concrete or glass fiber reinforced plastic. The size of the water inlet 30 is determined according to the size of the rainwater pipe, and a waterproof sleeve is reserved; the connecting port is combined with the design scale to meet the water flow requirements, and the connecting port can be in the form of a square hole or a round hole.
[0029] See also Figure 2 , combined with Figure 3 and Figure 4 A first inspection well 60 is arranged at the top of the water storage area 10, serving as a passage for construction equipment and materials inside the water storage area 10 and a normal operation inspection and maintenance passage; a second inspection well 61 is arranged at the top of the transition area 11, serving as a passage for installation and normal operation inspection and maintenance of the first lifting pump 40 and supporting pipelines; a third inspection well 62 is arranged at the top of the first clean water area 12, serving as a passage for installation and normal operation inspection and maintenance of the second lifting pump 41 and supporting pipelines; a fourth inspection well 63 is arranged at the top of the second clean water area 13, serving as a passage for installation and normal operation inspection and maintenance of the disinfection tank 50, the third lifting pump 42 and supporting pipelines.
[0030] It should be noted that the size of the first inspection well 60 should meet the requirements for the installation of equipment and materials inside the water storage area 10. The sizes of the second inspection well 61, the third inspection well 62 and the fourth inspection well 63 should meet the installation and maintenance requirements of the first lifting pump 40, the second lifting pump 41 and the third lifting pump 42 respectively.
[0031] See also Figure 3 , combined with Figure 1 A support plate 70 is provided at the bottom of the water storage area 10, and a porous purification material 71 is placed above the support plate 70. The support plate 70 is provided to facilitate maintenance and flushing. A flushing pipe 72 and a flushing nozzle 73 are provided at the front end of the water storage area 10. After working for a period of time, the water storage area 10 is flushed, and the flushing wastewater is discharged to the sewage system by the first lifting pump 40. The sewage system can be a municipal one or inside a building community.
[0032] It should be noted that the support plate 70 can be assembled with finished materials or cast-in-place concrete structure with holes. The strength of the support plate 70 needs to meet the load requirements of the porous purification material 71 placed on the upper part. The openings of the support plate 70 need to be selected in combination with the porous purification material 71. The openings of the support plate 70 need to meet the drainage requirements and ensure that the particles of the porous purification material 71 are not lost. A certain net space is reserved under the support plate 70 for flushing sludge and flushing wastewater; the flushing nozzles 73 are evenly distributed under the support plate 70.
[0033] The porous purification material 71 is a material produced using waste materials as raw materials. The porous purification material has the characteristics of being porous, having a large specific surface area, being lightweight, being water-permeable, retaining water, and being breathable. Rainwater is filtered, adsorbed, and biologically treated while being stored in the water storage area 10.
[0034] See also Figure 4 , combined with Figure 1 A disinfection tank 50 is disposed on the upper portion of the second clean water area 13 , and the bottom of the disinfection tank 50 is lower than the high-position communication port 33 .
[0035] Next Read Figure 4 In one implementation case, water level control is set in the transition zone 11, the first clean water zone 12 and the second clean water zone 13 to control the start and stop of the first lift pump 40, the second lift pump 41 and the third lift pump 42. Solenoid valves are set on the outlet pipes of the first lift pump 40 and the second lift pump 41, and they are automatically switched according to different functional requirements. The third lift pump 42 has only one function of discharging water, and a common valve is set on the outlet pipe, which can be normally open.
[0036] Specifically, the transition zone 11 is provided with a transition zone low water level 80 and a transition zone high water level 81; the first clean water zone 12 is provided with a first clean water zone low water level 82, a first clean water zone medium-low water level 83, a first clean water zone medium-high water level 84, and a first clean water zone high water level 85; the second clean water zone 13 is provided with a second clean water zone low water level 86 and a second clean water zone high water level 87.
[0037] For the first lifting pump 40, specifically, when the water level in the transition zone 11 reaches the high water level 81 of the transition zone, the first lifting pump 40 starts to lift rainwater into the first clear water zone 12; when the water level in the transition zone 11 drops to the low water level 80 of the transition zone or the water level in the first clear water zone 12 reaches the high water level 85 of the first clear water zone, the first lifting pump 40 stops pumping; when the water level in the first clear water zone 12 drops to the middle-high water level 84 of the first clear water zone, and the water level in the transition zone 11 is not less than the high water level 81 of the transition zone, the first lifting pump 40 starts pumping to lift rainwater into the first clear water zone 12. At this time, the valve of the pipeline lifted by the first lifting pump 40 into the first clear water zone 12 is opened, and other valves are closed.
[0038] The first lifting pump 40 is connected to three pipelines, which are used to lift water into the first clean water area 12, the rainwater pipe network and the sewage system. Under different functions, only the corresponding function valve is opened, and other function valves are closed. When the water storage area 10 needs to be emptied, the first lifting pump 40 is started, the pipe valve leading to the rainwater pipe network is opened, and other valves are closed. When the water storage area 10 needs to be flushed and drained, the first lifting pump 40 is started, the pipe valve leading to the sewage system is opened, and other valves are closed.
[0039] The second lifting pump 41 is connected to two pipelines, which are used for watering greenery, road washing and water storage area washing functions respectively. Under different functions, only the corresponding function valve is opened, and other function valves are closed. When water is used for outdoor greening watering, road washing, etc., the second lifting pump 41 is turned on, the corresponding pipeline valve leading to the first water point is opened, and other valves are closed. When the water storage area 10 needs to be flushed, the second lifting pump 41 is turned on, the pipeline valve leading to the water storage area is opened, and other valves are closed.
[0040] As for the third lift pump 42 , specifically, when water is needed for flushing toilets, washing vehicles, etc., the third lift pump 42 is turned on.
[0041] It should be noted that the first clean water area 12 and the second clean water area 13 give priority to the use of rainwater. When there is no rainfall or it is the dry season, water replenishment is used to enter the first clean water area 12 and the second clean water area 13. When the water level in the first clean water area 12 is lower than the low water level 82 of the first clean water area, water replenishment is started. When the water level reaches the middle and low water level 83 of the first clean water area, water replenishment is stopped. When the water level in the second clean water area 12 is lower than the low water level 86 of the second clean water area, water replenishment is started. When the water level reaches the high water level 87 of the second clean water area, water replenishment is stopped.
[0042] In summary, in engineering practice, due to the requirements of rainwater collection and rainwater treatment and reuse, conventional technology is often completed through the process of water storage tank → treatment unit → clean water tank. This technology can realize the collection, purification and utilization of rainwater, but the three main units each occupy space and have a single function. The raw water in the water storage tank is pressurized to the treatment unit through a lifting pump, and the treatment process consumes reagents and energy. The present application fills the porous purification material 71 in the water storage area 10, and purifies the raw water through filtration, adsorption and biological treatment of the porous purification material 71, thereby realizing the setting of water storage, treatment and clean water in one pool body, realizing the integration of rainwater control and utilization, reducing the occupied space, and no external power is consumed in the entire purification process, which is energy-saving and environmentally friendly, and promotes the reuse of waste materials.
[0043] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principle of the present invention. These improvements and substitutions should also be regarded as the protection scope of the present invention.
Claims
1. An integrated rainwater control system for rainwater storage, purification and utilization, characterized by: The water storage area (10), the transition area (11), the first clean water area (12) and the second clean water area (13) are in the same pool body (20) and are separated by partition walls. A porous purification material (71) is arranged in the water storage area (10). A rainwater pipe is connected to the front end of the water storage area (10). The rear end of the water storage area (10) is connected to the transition area (11) through a low-position communication port at the bottom of the partition wall. The first clean water area (12) and the second clean water area (13) are arranged in sequence at the rear end of the transition area (11). A first lifting pump (40) is arranged in the transition area (11). The first lifting pump (40) lifts the water in the water storage area (10) and the second clean water area (13) in turn. The stored water enters the first clean water area (12) or the rainwater pipe network or the sewage system; a second lifting pump (41) is arranged in the first clean water area (12) to lift the clean water to the first water point outside the pool body (20) or the water storage area (10); the rear end of the first clean water area (12) is connected with the second clean water area (13) through the high-position connecting port (33) on the partition wall; a disinfection tank (50) is arranged at the front end of the second clean water area (13) near the high-position connecting port (33); a third lifting pump (42) is arranged in the second clean water area (13) to lift the disinfected clean water to the second water point outside the pool body (20).
2. The integrated rainwater control system for rainwater storage, purification and utilization according to claim 1 is characterized by: Inspection ports are provided at the tops of the water storage area (10), the transition area (11), the first clean water area (12) and the second clean water area (13).
3. The integrated rainwater control system for rainwater storage, purification and utilization according to claim 1 is characterized by: A support plate (70) with openings is suspended at the bottom of the water storage area (10); the porous purification material (71) is placed above the support plate (70); and the support plate (70) is located on the low-position communication port.
4. The integrated rainwater control system for rainwater storage, purification and utilization according to claim 1 is characterized in that: A flushing pipe (72) and a flushing nozzle (73) are arranged at the front end of the water storage area (10).
5. The integrated rainwater control system for rainwater storage, purification and utilization according to claim 1 is characterized by: The bottom of the disinfection tank (50) is lower than the high-position communication port (33).
6. The integrated rainwater control system for rainwater storage, purification and utilization according to claim 1 is characterized by: The bottom elevation of the transition zone (11) is lower than that of the water storage zone (10).