Electric construction platform buffering device

By designing a height-adjustable electric construction platform buffer device, the problem of existing buffer devices being unable to adapt to changing sites and inconvenient installation is solved, thereby improving safety and efficiency.

CN221857419UActive Publication Date: 2024-10-18SHANGHAI PUDONG NEW AREA CONSTR GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420561282.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-21
Publication Date
2024-10-18
Estimated Expiration
2034-03-21

AI Technical Summary

Technical Problem

The existing buffer device cannot adapt to the changing needs of the site where the electric construction platform foundation is located, and it is inconvenient to install and disassemble, and cannot effectively protect the safety of construction workers.

Method used

An electric construction platform buffer device including a square base, a sleeve, a return spring and an impact head is designed. The height adjustment is achieved through the combination of the central axis and the return spring, and the locking of high-strength connecting bolts and L-shaped grounding connectors , easy to install and disassemble.

Benefits of technology

The device can adjust the height according to the needs of sites with different height differences, and is easy to install and disassemble, significantly improving construction safety and efficiency and reducing costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221857419U_ABST
    Figure CN221857419U_ABST
Patent Text Reader

Abstract

The utility model discloses an electric construction platform buffering device which comprises at least one square base, a sleeve is arranged on the uppermost square base, a middle shaft is arranged in the sleeve, the upper end and the lower end of the middle shaft are respectively provided with a reset spring, one end of the middle shaft and one reset spring stretch into the sleeve together, and the other end of the middle shaft and the other reset spring stretch into the sleeve together. And the other end of the middle shaft is connected with an impact head. According to the electric construction platform buffering device, the effective height of the electric construction platform buffering device can be conveniently adjusted, and the requirements of sites with different height differences can be met; the device is convenient to mount and dismount, can be recycled for multiple times, and can greatly protect the safety of constructors.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to a buffer device, in particular to a buffer device for an electric construction platform. Background Art

[0002] Traditional facade repair methods mainly use scaffolding or hanging baskets. However, these two construction techniques have high safety risks, long erection time, low construction efficiency, and difficult quality inspection, and cannot fully meet the growing requirements of urban renewal and safe and civilized construction. In response to the many pain points of traditional construction methods, alternative products to scaffolding and hanging baskets, namely attached electric construction platforms, have also begun to be used. Attached electric construction platforms are a new type of work platform. They are raised and lowered by gears and racks, and have very reliable electrical and mechanical safety systems. The platform can rise automatically as the building rises, and can be lengthened or shortened as needed.

[0003] Electric construction platforms can be divided into single-column and double-column types according to the number of foundations. Figure 1 , according to the layout form, it can be divided into linear type and special type. The buffer devices currently used by attached construction machinery on construction sites cannot adapt to the changing needs of the site where the electric construction platform foundation is located. Two of the four legs of the existing base are placed on the natural ground, while the other two legs are placed on the steps, and they are not at the same horizontal position. When installing the buffer device, the effective extension height of the buffer device needs to exceed the base of the construction platform chassis, and the existing buffer devices on the market do not meet the requirements. Therefore, it is necessary to provide a new type of electric construction platform buffer device. Utility Model Content

[0004] The technical problem to be solved by the utility model is to provide an electric construction platform buffer device, which can conveniently adjust its effective height to meet the needs of sites with different height differences; it is easy to install and disassemble, can be recycled for many times, and can greatly protect the safety of construction workers.

[0005] The technical solution adopted by the utility model to solve the above-mentioned technical problems is to provide an electric construction platform buffer device, including at least one square base, a sleeve is arranged on the uppermost square base, a central axis is arranged in the sleeve, a return spring is arranged at each of the upper and lower ends of the central axis, one end of the central axis extends into the sleeve together with a return spring, and the other end of the central axis is connected to an impact head.

[0006] The above-mentioned electric construction platform buffer device, wherein a first return spring is arranged at one end of the central axis, the diameter of the first return spring is less than or equal to the diameter of the central axis, and one end of the central axis extends into the sleeve together with the first return spring; the other end of the central axis is an impact head and a second return spring is arranged, the second return spring is sleeved outside the central axis, one end of the second return spring is abutted against the sleeve, and the other end of the second return spring is abutted against the impact head.

[0007] The above-mentioned electric construction platform buffer device, wherein the first return spring is YA type 14×95×60, the second return spring is YA type 14×65×20, the diameter of the central axis is 80mm, and the length is 120mm.

[0008] The above-mentioned electric construction platform buffer device, wherein the number of the square bases is multiple, and the multiple square bases are stacked together in sequence and locked together by high-strength connecting bolts and L-shaped grounding connectors.

[0009] The above-mentioned electric construction platform buffer device, wherein the impact head and the central axis are welded and connected.

[0010] Compared with the prior art, the utility model has the following beneficial effects: the electric construction platform buffer device provided by the utility model has the following advantages: (1) The base height of the buffer device developed for the electric construction platform is adjustable, which is suitable for sites with different height differences. (2) The buffer device developed for the electric construction platform is easy to disassemble and install, which can speed up the construction progress and reduce costs. (3) The buffer device developed for the electric construction platform can greatly protect the safety of construction personnel. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 This is a schematic diagram of the structure of the buffer device of the electric construction platform of the utility model;

[0012] Figure 2 It is a schematic diagram of the explosion structure of the buffer device of the electric construction platform of the utility model.

[0013] The markings in the figure are:

[0014] 1 Square base 2 Sleeve 3 Middle axis

[0015] 4First return spring 5Second return spring 6Impact head

[0016] 7 High-strength connecting bolts 8 L-type grounding connector. DETAILED DESCRIPTION

[0017] The utility model is further described below in conjunction with the accompanying drawings and embodiments.

[0018] Figure 1This is a schematic diagram of the structure of the buffer device of the electric construction platform of the utility model; Figure 2 It is a schematic diagram of the explosion structure of the buffer device of the electric construction platform of the utility model.

[0019] See also Figure 1 and Figure 2 The electric construction platform buffer device provided by the utility model comprises at least one square base 1, on which a sleeve 2 is arranged on the topmost square base, a central axis 3 is arranged in the sleeve 2, a return spring is arranged at each of the upper and lower ends of the central axis 3, one end of the central axis 3 together with a return spring extends into the sleeve 2, and the other end of the central axis 3 is connected to an impact head. Specifically, a first return spring 4 is arranged at one end of the central axis 1, the diameter of the first return spring 4 is less than or equal to the diameter of the central axis 3, one end of the central axis 3 together with the first return spring 4 as a core shaft extends into the sleeve 2; the other end of the central axis 3 is an impact head 6 and a second return spring 5 is arranged, the second return spring 5 is sleeved outside the central axis 3, one end of the second return spring 5 abuts against the sleeve 2, and the other end abuts against the impact head 6; the impact head 6 and the central axis 3 can be welded and connected.

[0020] The electric construction platform buffer device provided by the utility model, wherein the diameter of the central axis 3 is 80 mm and the length is 120 mm; the specification parameters of the return spring are as follows:

[0021] First return spring: YA type 14×95×60 (GB / T 2089)

[0022] Second return spring: YA type 14×65×20 (GB / T 2089)

[0023] The utility model provides an electric construction platform buffer device, wherein the number of the square bases 1 is multiple, and the multiple square bases 1 are stacked together in sequence and locked and connected by high-strength connecting bolts 7 and L-shaped grounding connectors 8.

[0024] The electric construction platform buffer device provided by the utility model comprises an impact head 6, a central axis 3, two return springs, several square bases 1, an L-shaped grounding connector 8 and several high-strength connecting bolts 7; it is easy to install and disassemble, and the installation and use process is as follows:

[0025] 1) Position and lay out according to the construction plan, determine the specific location of the buffer device, and mark it with white chalk.

[0026] 2) Calculate the height of the buffer device so that the height of the impact head of the buffer device is greater than the elevation of the chassis of the construction platform base.

[0027] 3) Weld the sleeve 2 to the first square base 1.

[0028] 4) Assemble the main components of the buffer device, including the impact head 6 and the middle shaft assembly (the impact head 6 and the middle shaft 3 are welded), two return springs, the sleeve 2 and other square bases.

[0029] 5) Stack the square base 1 to the specified height.

[0030] 6) Use high-strength connecting bolts 7 to connect the L-shaped grounding connector 8 and the steel base to form a whole.

[0031] Repeat steps 3 to 6 to complete the assembly of the four buffers. Fix the buffers to the ground marks of the chassis clearance positioning line, which is the projection position of the four corner points of the lifting device. The removal order is the opposite of the above order.

[0032] Although the present invention has been disclosed as above with preferred embodiments, it is not intended to limit the present invention. Any person skilled in the art may make some modifications and improvements without departing from the spirit and scope of the present invention. Therefore, the scope of protection of the present invention shall be based on the definition of the claims.

Claims

1. A buffer device for an electric construction platform, characterized in that: It comprises at least one square base, a sleeve is arranged on the uppermost square base, a central axis is arranged in the sleeve, a return spring is arranged at each of the upper and lower ends of the central axis, one end of the central axis extends into the sleeve together with the return spring, and the other end of the central axis is connected to an impact head.

2. The electric construction platform buffer device according to claim 1, characterized in that: A first return spring is arranged at one end of the central axis, and the diameter of the first return spring is less than or equal to the diameter of the central axis. One end of the central axis extends into the sleeve together with the first return spring; the other end of the central axis is an impact head and a second return spring is arranged thereon, and the second return spring is sleeved outside the central axis, one end of the second return spring abuts against the sleeve, and the other end of the second return spring abuts against the impact head.

3. The electric construction platform buffer device according to claim 2, characterized in that: The first return spring is YA type 14×95×60, the second return spring is YA type 14×65×20, the diameter of the central axis is 80 mm, and the length is 120 mm.

4. The electric construction platform buffer device according to claim 1, characterized in that: There are multiple square bases, which are stacked one on top of the other and are locked together by high-strength connecting bolts and L-shaped grounding connectors.

5. The electric construction platform buffer device according to claim 1, characterized in that: The impact head is connected to the center shaft by welding.