Rainwater and sewage pipe structure for old community

By adopting the structure of half-pipe body, middle-partition plate and inner arc plate in the rain and sewage pipe, the direct construction and rapid replacement of the pipe section on the old pipeline are achieved, which solves the problem of low construction efficiency in the existing technology and improves the transformation Efficiency and reduce the impact on residents' lives.

CN222009117UActive Publication Date: 2024-11-15CHONGQING ZHIYIN CONSTRUCTION (GROUP) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420634383.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-29
Publication Date
2024-11-15
Estimated Expiration
2034-03-29

AI Technical Summary

Technical Problem

When renovating rainwater and sewage pipes in old communities, construction workers need to repeatedly suspend and restore the functions of the pipe sections, resulting in large workload and low construction efficiency.

Method used

The structure of half-pipe body, middle-partition plate and inner arc plate is adopted to transform rainwater and sewage pipes by splicing and filling cement slurry, allowing direct construction on old pipes and quick replacement of the pipe sections to reduce the impact on residents' lives and construction personnel. rework.

Benefits of technology

The efficient transformation of rainwater and sewage pipes has been achieved, reducing the workload and construction time of construction workers, and reducing the impact on residents' lives.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222009117U_ABST
    Figure CN222009117U_ABST
Patent Text Reader

Abstract

The utility model discloses an old community rain sewage pipe structure which comprises a plurality of branch pipe sections which are communicated with one another, and each branch pipe section comprises two half pipe bodies which are spliced with one another; the middle division plate is arranged between the two half pipe bodies of the branch pipe section; the inner arc plate is fixed to the middle division plate and located on the inner side of the half pipe body; the half pipe body is in a notch ring shape from the end view; one branch pipe section is provided with two middle division plates, and the two middle division plates are called as a pair; the two middle division plates in the same pair are vertically arranged and correspond to the two splicing faces of the half pipe bodies correspondingly. Inner arc plates are fixed to the two sides of the middle division plate correspondingly, the outer arc faces of the inner arc plates are matched with the inner walls of the half pipe bodies, the inner end of the middle division plate is used for abutting against the outer wall of an old pipeline, and the middle division plate is fixed to the splicing face of the half pipe bodies. The rainwater and sewage pipe renovation device has the effect that workers can renovate and reconstruct rainwater and sewage pipes more conveniently.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of rainwater pipe reconstruction, and in particular to a rainwater and sewage pipe structure for an old residential area. Background Art

[0002] Rainwater and sewage pipes are important facilities for municipal drainage. At present, in addition to demolition and reconstruction, many residential areas in domestic cities will continue to be maintained, and a large part of these residential areas have been built and used for a long time. The previous rainwater and sewage pipes can hardly meet the increasing sewage discharge needs, so they are modified and transformed.

[0003] One way of transformation is: after excavation, suspend the functions of some pipe sections in the community during the designated construction period, wait until the residents enter their home rest time, such as 5 pm, and then temporarily restore the functions of the disabled pipe sections.

[0004] Although the above method can meet the construction needs, for the construction workers, it is necessary to repeatedly pause and resume the corresponding pipe section, which increases the workload and the construction efficiency is relatively low. Therefore, this application proposes a new technical solution. Utility Model Content

[0005] In order to make it more convenient for staff to renovate and transform rainwater and sewage pipes, the present application provides a rainwater and sewage pipe structure for an old residential area.

[0006] This application provides a rainwater and sewage pipe structure for an old residential area, which adopts the following technical solution:

[0007] A rainwater and sewage pipe structure for an old residential area includes a plurality of interconnected branch pipe sections, wherein the branch pipe sections include:

[0008] A half-tube body, which consists of two parts and is spliced ​​to each other;

[0009] A central dividing plate, which is arranged between two half pipe bodies of the branch pipe section; and

[0010] An inner arc plate, which is fixed to the middle dividing plate and is located on the inner side of the half pipe body;

[0011] The half-tube body is in a notched ring shape when viewed from the end, and one branch pipe section has two center dividing plates, and the two center dividing plates are called a pair; the two center dividing plates of the same pair are arranged vertically and correspond to the two joint surfaces of the half-tube body respectively;

[0012] Inner arc plates are fixed on both sides of the center dividing plate, and the outer arc surface of the inner arc plate is adapted to the inner wall of the half pipe body. The inner end of the center dividing plate is used to abut against the outer wall of the old pipe. The center dividing plate is fixed to the joint surface of the half pipe body.

[0013] Optionally, a bottom support plate is fixed to the lower portion of the center dividing plate located below, and the bottom support plate extends laterally.

[0014] Optionally, the center dividing plate includes a component plate and a functional plate, the component plate is a metal plate, a concrete plate or a stone plate, the component plate passes through between two half-tube bodies of the same branch pipe section, the inner end of the component plate is concave to form a card slot, the end of the card slot and one side facing the center of the branch pipe section are open, and the functional plate is a wooden board and is formed with a card block inserted into the card slot.

[0015] Optionally, the contact surface between the center dividing plate and the half-tube body is an edge surface.

[0016] Optionally, the center dividing plate is provided with a grouting hole extending along the height, and the grouting hole is closed at one end facing the center of the branch pipe section. The center dividing plate is also provided with a connecting hole extending along the thickness direction, and the end of the connecting hole is close to the splicing surface of the half pipe body; the grouting hole is used for pouring cement slurry or concrete.

[0017] Optionally, reinforcing blocks are fixed on both sides of the center dividing plate, the reinforcing blocks fit the outer wall of the semi-tube body, and a locking block is fixed on one side of the reinforcing block facing the outer wall of the semi-tube body, and the locking block is inserted into a slot pre-opened on the semi-tube body.

[0018] Optionally, an elastic sheet is fixed to the inner end surface of the center dividing plate.

[0019] To summarize, the present application includes at least one of the following beneficial technical effects: after applying the structure of the present application, construction can be carried out directly on the old pipe, and new rainwater and sewage pipes can be spliced. After completing a section, the old pipe can be pulled out to complete the transformation. Compared with the existing method, it has less impact on the lives of community owners, and construction workers do not need to repeatedly stop and restore the functions of rainwater and sewage pipes in certain areas, which makes it more convenient for staff to renovate and transform rainwater and sewage pipes. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a schematic diagram of the overall structure of this application;

[0021] Figure 2 It is a partial structural diagram of this application.

[0022] Explanation of the reference numerals: 1. half pipe body; 2. center dividing plate; 21. component plate; 22. functional plate; 23. grouting hole; 24. connection hole; 3. inner arc plate; 4. bottom supporting plate; 5. reinforcement block; 51. locking block; 6. elastic sheet. DETAILED DESCRIPTION

[0023] The following is combined with Figure 1-2 This application is described in further detail.

[0024] The embodiment of the present application discloses a rainwater and sewage pipe structure for an old residential area.

[0025] Reference Figure 1-2The structure of the rainwater and sewage pipes in old residential areas includes multiple interconnected branch pipe sections, and the ends of each branch pipe section are connected to each other. An example of the connection method is: a ring with a larger diameter is simultaneously sleeved on two branch pipe sections with their ends spliced ​​to each other, and cement slurry and melted rubber are poured between the ring and the branch pipe section to enhance the sealing.

[0026] In this embodiment, the branch pipe section includes a half pipe body 1 , a middle branch plate 2 and an inner arc plate 3 .

[0027] There are two half-tube bodies 1 which are spliced ​​together. The half-tube body 1 is in a notched ring shape when viewed from the end. Because one branch pipe section is divided into two, the half-tube body 1 is approximately a semicircular ring when viewed from the end. One branch pipe section has two center dividing plates 2 and the two center dividing plates 2 are called a pair; the two center dividing plates 2 of the same pair are arranged vertically and correspond to the two splicing surfaces of the half-tube body 1 respectively, that is, the splicing areas of the two half-tube bodies 1 are separated by the center dividing plate 2.

[0028] Inner arc plates 3 are fixed on both sides of the center dividing plate 2, and the outer arc surface of the inner arc plate 3 is adapted to the inner wall of the half pipe body 1. During the renovation construction, if the old pipe has not been removed, the inner end of the center dividing plate 2 is used to contact the outer wall of the old pipe, and the center dividing plate 2 is fixed to the splicing surface of the half pipe body 1.

[0029] Usage process:

[0030] 1) Excavate the old pipeline area to expose the old pipeline;

[0031] 2) Dig out the lower soil layer of the old pipeline, and dig out half of it first, so that a middle dividing plate 2 can be used as support for the lower part of the old pipeline;

[0032] 3) Place another center dividing plate 2 on the upper part of the old pipe and temporarily fix it by hand support or bracket support;

[0033] 4) Place a half pipe 1 from the side and move it toward the center dividing plate 2 until it contacts the center dividing plate 2, and apply cement slurry on the contacting area;

[0034] 5) At this time, the inner arc plate 3 on the upper center dividing plate 2 provides a certain support to prevent the installed half pipe body 1 from falling off; the side of the half pipe body 1 can be supported and reinforced;

[0035] 6) Install another half pipe body 1 and make it contact with the middle dividing plate 2, and splice them together to form a branch pipe section;

[0036] 7) After installing multiple branch pipe sections, cut the old pipes that are not covered to form an empty area, and then pull out the old pipes in the branch pipe sections.

[0037] According to the above settings, this application allows the renovation of rainwater and sewage pipes without having to shut down the pipes for a long time or repeatedly rework and restore the pipes, making it more convenient for staff to renovate and transform rainwater and sewage pipes.

[0038] Because the area where the pipeline is located is a soil foundation after excavation, a bottom support plate 4 is fixed to the lower part of the center dividing plate 2 located below. The bottom support plate 4 extends laterally to expand the contact area and reduce the pressure at a single point to prevent excessive sinking during the support process.

[0039] In one embodiment of the present application, the center dividing plate 2 includes a component plate 21 and a functional plate 22, wherein the component plate 21 is a metal plate, a concrete plate or a stone plate, and in this embodiment, a concrete plate is preferred. The component plate 21 passes through the two half pipe bodies 1 of the same branch pipe section, and a card slot is formed in the inner concave of the component plate 21, and the end of the card slot and one side facing the center of the branch pipe section are open. The functional plate 22 is a wooden board and is formed with a card block inserted into the card slot.

[0040] The reason why the functional board 22 is made of wood is that it is required to provide stable support and withstand repeated disassembly and assembly and collision with little damage.

[0041] When the installation of multiple branch pipe sections is completed and the old pipes in the branch pipe sections need to be removed, the function board 22 can be pulled out first to reduce the obstacles to pulling out the old pipes. It is understandable that nails, metal rods, etc. can be driven on the side of the function board 22 to facilitate the construction workers to pull out the function board 22 through the long rod with a hook.

[0042] After the functional plate 22 is removed, the obstruction to the flow of dirt in the branch pipe section can be reduced.

[0043] In one embodiment of the present application, considering the need to ensure the sealing of the connection between the two half-tube bodies 1 after splicing to reduce rain and sewage seepage, the contact surface between the center dividing plate 2 and the half-tube body 1 is set to an edge surface, that is, a structural surface with multiple edges.

[0044] The half pipe body 1 can be prefabricated with concrete.

[0045] Although the branch pipe section is supported by soil on all sides after the soil foundation is backfilled, the connection stability and sealing are low by simply brushing cement slurry on the joint surface of the half-pipe body 1. Therefore, the present application also provides a grouting hole 23 extending along the height on the center dividing plate 2, and the grouting hole 23 is closed at one end toward the center of the branch pipe section; the center dividing plate 2 also provides a connecting hole 24 extending along the thickness direction, and the end of the connecting hole 24 is close to the joint surface of the half-pipe body 1.

[0046] After the two half-tube bodies 1 are spliced ​​together, cement slurry or concrete is poured into the grouting hole 23 by high-pressure injection. During the process, the cement slurry and concrete enter the connection hole 24 and seep into between the center dividing plate 2 and the half-tube body 1. After the cement slurry and concrete are cured, the half-tube body 1 and the center dividing plate 2 can be more firmly connected.

[0047] Furthermore, reinforcing blocks 5 are fixed on both sides of the center dividing plate 2. The reinforcing blocks 5 are triangular in shape when viewed from the end with the hypotenuse of the triangle facing outward, and the reinforcing blocks 5 fit the outer wall of the semi-tube body 1. A locking block 51 is fixed on one side of the reinforcing block 5 facing the outer wall of the semi-tube body 1, and the locking block 51 is inserted into a slot 11 pre-opened on the semi-tube body 1.

[0048] If the reinforcing block 5 and the locking block 51 are prefabricated, they can be used to prevent the two half pipe bodies 1 from separating during the installation process, and after cement slurry is laid on the contact surface, the structural sealing of the branch pipe section can be increased to a certain extent.

[0049] If the reinforcement block 5 and the locking block 51 are used for casting after the half-tube bodies 1 are spliced ​​together, the splicing stability and sealing effect of the two half-tube bodies 1 can be effectively enhanced.

[0050] In one embodiment of the present application, an elastic sheet 6 is fixed to the inner end surface of the center dividing plate 2, and the elastic sheet 6 can be supported by a rubber material.

[0051] The elastic sheet 6 can be used to enhance the fit between the center dividing plate 2 and the old pipe, reduce the force imbalance, and increase the probability of single-point bursting of the old pipe in advance, thus ensuring smooth reconstruction of the rainwater and sewage pipes.

[0052] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A rainwater and sewage pipe structure for an old residential area, characterized by: It comprises a plurality of interconnected branch sections, wherein the branch sections include: A half-tube body (1), which consists of two parts and are spliced ​​together; a middle dividing plate (2), which is arranged between the two half pipe bodies (1) of the pipe section; and An inner arc plate (3) fixed to the middle dividing plate (2) and located on the inner side of the half-tube body (1); The half-tube body (1) is in the shape of a notched ring when viewed from the end, one branch pipe section has two center dividing plates (2), and the two center dividing plates (2) are called a pair; the two center dividing plates (2) in the same pair are arranged vertically and correspond to the two joint surfaces of the half-tube body (1) respectively; Inner arc plates (3) are fixed to both sides of the center dividing plate (2), and the outer arc surface of the inner arc plate (3) is adapted to the inner wall of the half pipe body (1). The inner end of the center dividing plate (2) is used to abut against the outer wall of the old pipe. The center dividing plate (2) is fixed to the joint surface of the half pipe body (1).

2. The rainwater and sewage pipe structure for old residential areas according to claim 1 is characterized by: A bottom support plate (4) is fixed to the lower part of the middle dividing plate (2) located at the bottom, and the bottom support plate (4) extends transversely.

3. The rainwater and sewage pipe structure for old residential areas according to claim 1 is characterized by: The center dividing plate (2) comprises a component plate (21) and a functional plate (22); the component plate (21) is a metal plate, a concrete plate or a stone plate; the component plate (21) passes between two half pipe bodies (1) of the same branch pipe section; the inner end of the component plate (21) is concave to form a card slot; the end of the card slot and one side facing the center of the branch pipe section are open; the functional plate (22) is a wooden board and is formed with a card block inserted into the card slot.

4. The rainwater and sewage pipe structure for old residential areas according to claim 1 is characterized by: The contact surface between the center dividing plate (2) and the half tube body (1) is an edge surface.

5. The rainwater and sewage pipe structure for old residential areas according to claim 1 is characterized by: The center dividing plate (2) is provided with a grouting hole (23) extending along the height, and one end of the grouting hole (23) facing the center of the branch pipe section is closed. The center dividing plate (2) is also provided with a connecting hole (24) extending along the thickness direction, and the end of the connecting hole (24) is close to the joint surface of the half pipe body (1); the grouting hole (23) is used for pouring cement slurry or concrete.

6. The rainwater and sewage pipe structure for old residential areas according to claim 1 is characterized by: Reinforcement blocks (5) are fixed on both sides of the center dividing plate (2), the reinforcement blocks (5) are in contact with the outer wall of the half-tube body (1), and a locking block (51) is fixed on one side of the reinforcement block (5) facing the outer wall of the half-tube body (1), and the locking block (51) is inserted into a slot pre-opened on the half-tube body (1).

7. The rainwater and sewage pipe structure for old residential areas according to claim 1 is characterized by: An elastic sheet (6) is fixed to the inner end surface of the center dividing plate (2).