Gluing device for production of multi-layer flame-retardant plate
By integrating the vacuum cleaner system and glue management system in the glue coating device for multi-layer flame retardant board production, the problem of dust on the flame retardant board affecting the glue effect is solved, and a more uniform and efficient glue coating process is achieved.
Patent Information
- Application Number
- CN202420859812.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-24
- Publication Date
- 2024-12-24
- Estimated Expiration
- 2034-04-24
AI Technical Summary
The dust attached to the flame retardant board will affect the subsequent glueing effect, resulting in uneven glue coating.
A multi-layer flame retardant plate production glue device is designed, including a belt conveyor, a vacuum cover, a vacuum tank, a suction fan and a dust collector. The dust collecting and dust removal is carried out through the vacuum tank and the transmission tube to ensure that The surface of the flame retardant plate is clean; at the same time, the rubber delivery box, rubber roller, rubber conveying pump and rubber storage box ensure that the glue liquid is evenly coated.
Through dust removal operations, the glue uniformity of the flame retardant plate is improved, the sufficient supply of glue is ensured, and the effect and efficiency of subsequent glue is improved.
Smart Images

Figure CN222220073U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of multi-layer flame-retardant board production, in particular to a gluing device for the production of multi-layer flame-retardant boards. Background Art
[0002] Flame retardant board, also known as flame-retardant board, flame-retardant plywood, flame-retardant plywood, etc., is a three-layer or multi-layer plywood made by peeling logs into wood chips or planing wood blocks into small wooden blocks, treating the wood chips with flame retardant treatment and then gluing them with adhesives, so that the fiber directions of adjacent layers of wood chips are perpendicular to each other. When gluing manually, the gluing operation is cumbersome, resulting in uneven gluing and waste of glue.
[0003] A Chinese patent application numbered CN201721641757.4 discloses a gluing device for the production of multi-layer flame-retardant panels, which solves the problems of manual gluing. However, the device requires the user to push the gluing mechanism to apply glue to the surface of the flame-retardant panel. Since it is manually pushed, there is inevitably the problem of unstable pushing speed. When the gluing speed remains unchanged, pushing too fast will cause the glue to be too thin, and pushing too slow will cause the glue to be too late, so the device still has the problem of uneven gluing.
[0004] A Chinese patent search shows a gluing device for producing multi-layer flame retardant panels (publication number CN210453090U), which includes two mounting rods, a conveyor belt is installed between the two mounting rods, a support rod is fixedly connected to the upper side of the mounting rod, a gluing mechanism is slidably installed between the two support rods, the gluing mechanism includes a glue storage box and a gluing roller arranged below the glue storage box, both ends of the gluing roller are rotatably connected to a fixed frame, the ends of the two fixed frames away from the gluing roller are fixedly connected to the glue storage box, a cross bar is fixedly connected above the support rod, and a mounting groove is provided inside the cross bar. The utility model sets a mesh plate at the glue outlet to make the glue storage box more uniform in glue discharge, cooperates with the conveyor belt to drive the flame retardant panel to move at a uniform speed, so that the gluing roller evenly applies the glue on the surface of the flame retardant panel, and avoids the relative speed between the glue outlet and the flame retardant panel being too fast, resulting in too thin glue coating, or the relative speed between the two being too slow, resulting in too thick glue coating.
[0005] Although the above patent improves the uniformity of glue coating, the flame retardant board is not dusted before gluing, so that the dust attached to the flame retardant board will affect the subsequent gluing effect.
[0006] Therefore, it is necessary to invent a glue application device for producing multi-layer flame retardant panels to solve the above problems. Utility Model Content
[0007] The utility model aims to provide a gluing device for producing multi-layer flame retardant boards, so as to solve the problem that dust attached to the flame retardant boards will affect the subsequent gluing effect proposed in the above background technology.
[0008] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a gluing device for the production of multi-layer flame-retardant panels, comprising a belt conveyor, a first support frame is provided on one side of the belt conveyor, a dust hood is slidably connected to the first support frame, a dust suction groove is provided at the bottom of the dust hood, a first transmission pipe is connected to the interior of the dust hood, a suction fan is provided at one end of the first transmission pipe, a second transmission pipe is connected to the suction fan, a second support frame is provided on the other side of the belt conveyor, a glue delivery box is slidably connected to the second support frame, a glue delivery groove is provided on the glue delivery box, two groups of bearing seats are fixedly connected to the bottom of the glue delivery box, the two groups of bearing seats are internally rotatably connected with gluing rollers, the glue delivery box is internally connected with a third transmission pipe, a glue delivery pump is provided at one end of the third transmission pipe, and a fourth transmission pipe is connected to the glue delivery pump.
[0009] Preferably, a dust collecting box is provided at one end of the second transmission pipe away from the suction fan, and a first box cover is installed on the dust collecting box.
[0010] Preferably, a visual glass is installed on the side wall of the glue delivery box.
[0011] Preferably, a glue storage box is provided at one end of the fourth transmission pipe away from the glue delivery pump, and a second box cover is provided on the top of the glue storage box.
[0012] Preferably, a bottom plate is provided at the bottom of the belt conveyor.
[0013] Preferably, a first self-locking electric cylinder is mounted on the first support frame, and an output shaft of the first self-locking electric cylinder is connected to the dust hood.
[0014] Preferably, a second self-locking electric cylinder is installed on the second support frame, and an output shaft of the second self-locking electric cylinder is connected to the glue delivery box.
[0015] Technical effects and advantages of the utility model:
[0016] 1. By setting the first support frame, the suction fan, the dust suction groove, the dust hood, the first transmission pipe, the second transmission pipe and the dust collection box, the first self-locking electric cylinder and the second self-locking electric cylinder can be started first when gluing, and the dust suction hood and the glue delivery box can be adjusted to the thickness suitable for the corresponding flame retardant board respectively, and then the flame retardant board to be glued is placed on the belt conveyor. The belt conveyor first conveys the flame retardant board through the first support frame. During the conveying process, the suction fan will start to suck the dust on the flame retardant board into the dust suction hood through the dust suction groove. The dust hood conveys the dust to the dust collection box through the first transmission pipe and the second transmission pipe for collection. Dust removal operation is performed before gluing the flame retardant board to improve the subsequent gluing effect of the flame retardant board;
[0017] 2. By setting up a second support frame, a glue delivery box, a glue delivery trough, a glue roller, a visual glass, a glue delivery pump, a fourth transmission pipe, a third transmission pipe and a glue storage box, the belt conveyor then delivers the flame retardant board through the second support frame, and the glue liquid inside the glue delivery box is delivered to the glue roller through the glue delivery trough. When the flame retardant board passes through the glue roller, it drives the glue roller to rotate, thereby completing the gluing of the flame retardant board. In addition, when the staff observes through the visual glass that the glue liquid inside the glue delivery box is insufficient, the glue delivery pump can be started. The glue delivery pump delivers the glue liquid inside the glue storage box to the inside of the glue delivery box through the fourth transmission pipe and the third transmission pipe, which is convenient for the staff to add glue liquid. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] In order to more clearly illustrate the technical solutions of the embodiments of the utility model, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the utility model and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other relevant drawings can be obtained based on these drawings without paying creative work.
[0019] Figure 1 The utility model is a bottom view of the assembly structure of a gluing device for producing multi-layer flame retardant panels.
[0020] Figure 2 The utility model is a front view of the assembly structure of a gluing device for producing multi-layer flame retardant panels.
[0021] Figure 3 It is a rear view of the assembly structure of a gluing device for producing a multi-layer flame retardant board according to the utility model.
[0022] Figure 4 The utility model is a side view of the assembly structure of a gluing device for producing multi-layer flame retardant panels.
[0023] In the figure: 1. belt conveyor; 2. first support frame; 3. dust hood; 4. dust suction trough; 5. first transmission pipe; 6. suction fan; 7. second transmission pipe; 8. dust collecting box; 9. first box cover; 10. second support frame; 11. glue delivery box; 12. seat bearing; 13. glue roller; 14. glue delivery trough; 15. sight glass; 16. third transmission pipe; 17. glue delivery pump; 18. fourth transmission pipe; 19. glue storage box; 20. second box cover; 21. bottom plate; 22. first self-locking electric cylinder; 23. second self-locking electric cylinder. DETAILED DESCRIPTION
[0024] In order to make the purpose, technical scheme and advantages of the embodiments of the utility model clearer, the technical scheme in the embodiments of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiments of the utility model. Therefore, the following detailed description of the embodiments of the utility model provided in the drawings is not intended to limit the scope of the utility model claimed for protection, but merely represents the selected embodiments of the utility model. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the utility model.
[0025] The utility model provides Figure 1-4 A gluing device for producing a multi-layer flame-retardant board shown in the figure comprises a belt conveyor 1, wherein the belt conveyor 1 can convey the flame-retardant board, a first support frame 2 is arranged on one side of the belt conveyor 1, wherein the first support frame 2 plays a supporting role, a dust hood 3 is slidably connected to the first support frame 2, a dust suction groove 4 is provided at the bottom of the dust hood 3, a first transmission pipe 5 is connected to the inside of the dust hood 3, a suction fan 6 is arranged at one end of the first transmission pipe 5, and a second transmission pipe 7 is connected to the suction fan 6, and a second support frame 10 is arranged on the other side of the belt conveyor 1, wherein the second support frame 10 plays a supporting role. The second support frame 10 has a supporting function, and a glue delivery box 11 is slidably connected to the second support frame 10, and a glue delivery groove 14 is provided on the glue delivery box 11, wherein the glue delivery box 11 stores glue liquid and transports it to the glue roller 13 through the glue delivery groove 14 at the bottom, and two groups of bearings with seats 12 are fixedly connected to the bottom of the glue delivery box 11, and the two groups of bearings with seats are internally rotatably connected to the glue roller 13, wherein the bearings with seats 12 are used to install the glue roller 13, and the interior of the glue delivery box 11 is connected to a third transmission pipe 16, and a glue delivery pump 17 is provided at one end of the third transmission pipe 16, and the glue delivery pump 17 is connected to a fourth transmission pipe 18.
[0026] A dust box 8 is provided at one end of the second transmission pipe 7 away from the suction fan 6, wherein the dust after dust removal is collected inside the dust box 8, and a first box cover 9 is installed on the dust box 8, wherein the first box cover 9 can be disassembled from the dust box 8, so as to facilitate the staff to clean the filter inside the dust box 8.
[0027] A visual glass 15 is installed on the side wall of the glue delivery box 11 , wherein the visual glass 15 allows a user to conveniently observe the glue content inside the glue delivery box 11 .
[0028] A glue storage box 19 is provided at one end of the fourth transmission pipe 18 away from the glue delivery pump 17, wherein the glue storage box 19 stores glue liquid, and a second box cover 20 is provided on the top of the glue storage box 19, wherein the second box cover 20 can be removed from the glue storage box 19 to facilitate the staff to transport glue liquid into the glue storage box 19.
[0029] A bottom plate 21 is provided at the bottom of the belt conveyor 1, wherein the bottom plate 21 can start the function of stable support, so that the gluing device for producing the multi-layer flame retardant board can operate stably.
[0030] A first self-locking electric cylinder 22 is installed on the first support frame 2, and the output shaft of the first self-locking electric cylinder 22 is connected to the dust hood 3. When the first self-locking electric cylinder 22 is started, the output shaft of the first self-locking electric cylinder 22 will drive the dust hood 3 to slide on the first support frame 2 to adapt to flame retardant panels of different thicknesses.
[0031] A second self-locking electric cylinder 23 is installed on the second support frame 10, and the output shaft of the second self-locking electric cylinder 23 is connected to the glue delivery box 11. When the second self-locking electric cylinder 23 is started, the output shaft of the second self-locking electric cylinder 23 will drive the glue delivery box 11 to slide on the second support frame 10 to adapt to flame-retardant panels of different thicknesses.
[0032] Working principle: When gluing, the first self-locking electric cylinder 22 and the second self-locking electric cylinder 23 can be started first, and the dust hood 3 and the glue delivery box 11 can be adjusted to the thickness suitable for the corresponding flame-retardant board respectively, and then the flame-retardant board to be glued can be placed on the belt conveyor 1. The belt conveyor 1 first conveys the flame-retardant board through the first support frame 2. During the conveying process, the suction fan 6 will start and suck the dust on the flame-retardant board into the dust hood 3 through the dust suction groove 4. The dust hood 3 conveys the dust to the dust box 8 through the first transmission pipe 5 and the second transmission pipe 7 for collection. Dust removal operation is performed before gluing the flame-retardant board, which provides The subsequent gluing effect of the flame retardant board is high; then the belt conveyor 1 transports the flame retardant board through the second support frame 10, and the glue in the glue delivery box 11 is transported to the glue roller 13 through the glue delivery groove 14. When the flame retardant board passes through the glue roller 13, it will drive the glue roller 13 to rotate, and then complete the gluing of the flame retardant board. In addition, when the staff observes through the visual glass 15 that the glue in the glue delivery box 11 is insufficient, the glue delivery pump 17 can be started. The glue delivery pump 17 transports the glue in the glue storage box 19 to the inside of the glue delivery box 11 through the fourth transmission pipe 18 and the third transmission pipe 16, which is convenient for the staff to add glue.
[0033] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, the present invention may be subject to various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A gluing device for producing a multi-layer flame retardant board, comprising a belt conveyor (1), characterized in that: A first support frame (2) is provided on one side of the belt conveyor (1), a dust hood (3) is slidably connected to the first support frame (2), a dust suction groove (4) is provided at the bottom of the dust hood (3), a first transmission pipe (5) is connected to the inside of the dust hood (3), a suction fan (6) is provided at one end of the first transmission pipe (5), a second transmission pipe (7) is connected to the suction fan (6), and a second support frame (10) is provided on the other side of the belt conveyor (1), and the second support frame (11) is provided on the other side of the belt conveyor (1), and the second support frame (12) is provided on the other side of the belt conveyor (1). A glue delivery box (11) is slidably connected to the frame (10), and a glue delivery groove (14) is provided on the glue delivery box (11). Two groups of seat bearings (12) are fixedly connected to the bottom of the glue delivery box (11), and the two groups of seat bearings (12) are rotatably connected to glue rollers (13) inside. The inside of the glue delivery box (11) is connected to a third transmission pipe (16), and a glue delivery pump (17) is provided at one end of the third transmission pipe (16), and a fourth transmission pipe (18) is connected to the glue delivery pump (17).
2. The gluing device for producing a multi-layer flame retardant board according to claim 1, characterized in that: A dust collecting box (8) is provided at one end of the second transmission pipe (7) away from the suction fan (6), and a first box cover (9) is installed on the dust collecting box (8).
3. The gluing device for producing a multi-layer flame retardant board according to claim 1, characterized in that: A visual glass (15) is installed on the side wall of the glue delivery box (11).
4. The gluing device for producing a multi-layer flame retardant board according to claim 1, characterized in that: A glue storage box (19) is arranged at one end of the fourth transmission pipe (18) away from the glue delivery pump (17), and a second box cover (20) is arranged on the top of the glue storage box (19).
5. The gluing device for producing a multi-layer flame retardant board according to claim 1, characterized in that: A bottom plate (21) is provided at the bottom of the belt conveyor (1).
6. The gluing device for producing a multi-layer flame retardant board according to claim 1, characterized in that: A first self-locking electric cylinder (22) is mounted on the first support frame (2), and an output shaft of the first self-locking electric cylinder (22) is connected to the dust hood (3).
7. The gluing device for producing a multi-layer flame retardant board according to claim 1, characterized in that: A second self-locking electric cylinder (23) is installed on the second support frame (10), and an output shaft of the second self-locking electric cylinder (23) is connected to the glue delivery box (11).